HomeMy WebLinkAbout19020071 Sewer Permit10701 N. College Avenue Suite A Indianapolis, Indiana 46280 phone 317-8449200 fax 317-8449203 www.tdco.eco
Residential SANITARY SEWER PERMIT 999913145
Permit Type Final Subdivision Clay Corner
Project WO 2017-1335 Section Number
Project Name
Clay Comer
Project Developer
0.00
Lift Station
19 Village of Westclay Station
Treatment Plant
MIX
Parcel Acreage
0.18
EDU in Gallons
310
Local Sewer Charge - District Contribution
0.00
Plan Review and Inspection
0.00
Application Fee
..........
150.00
EDU Fee
1908.00
Interceptor Fee
0.00
Other Fees
0.00
Fees Due
2058.00
Invoice Number
PAW C
mw
Lot Number 22
Address Number 1546
Address 2
Street
Jensen Drive
City
Carmel
Zip Code
46032
County
Hamilton
Builder
CalAtlantic Homes of Indiana
Phone Number
317-344-0097
Owner
Phone Number
Occupant
I Phone Number
PLEASE NOTE: Installation of building sewer shall be per the specifications of the TriCo Regional Sewer Utility (see
reverse) and any conditions noted below. All installations shall be inspected by TriCo personnel during "open trench"
phase and before backfilling with stone to twelve inches above the pipe. NO footing or foundation drains, or other
sources of ground or stormwater, shall be permitted to enter TriCo's sanitary sewer system. TriCo will assume no
liability for drains which are below the grade level of the nearest downstream manhole nor for laterals which are
extended beneath driveways or sidewalks. The permit holder (property owner, developer or builder) will be
responsible for damages to TriCo's sewer system. This includes damages to manholes, castings, manhole lids and
the like; caused by construction activity on the building site which is the subject of this permit.
Inspections by TriCo are MANDATORY and shall be arranged by contacting TriCo's office at 844-9200 24 hours in
advance. All new construction will be placed on billing two months after connection has been made or when water is
connected, whichever comes first.
The building has: - Main ID: CC118-CC117
Grease Trap Slab Foundation
Grease Interceptor Crawl Space Manhole IDs USMH CC -118 CC -117 DSMH
Grit Interceptor Basement YES Lid Elevation 886.02-/ 885.13 ✓
Grinder Station First Floor Elevation 888,97!/ 888' 97/
Water Service City of Carmel Basement Elevation 8801 ✓ 880.10 ✓
Calculation is based on both Manhole Lid Elevations and the elevation of the First Floor
2.951 11 3.841 Ft.:
Per Ordinance 9-13-99 and the elevations provided, the substructure shall be plumbed by: Ejector Pump Only
TriCo currently requires that an I&I inspection is performed and a Certificate of Compliance is issued prior to occupancy I
sale of a properrty. Please review attached III Permit.
Manholes shall remain accessible at all times. Buried manholes will be corrected by the Developer/Owner.
The proper class of cleanout must be installed every 100 feet of lateral pipe measured from sewer main to structure.
liv
e terms of the conditional permit, if any, are listed below.
Plans have been submitted. �»
All fees have been paid.��.�,,`�
No certificate of insurance required.
'� I VA
No additional permits required.
L 1 uIr
No manhole core permit required.
1 1_ f `; 4i?
The facility is not classified as a FOG facility.
(Notes)
PAW C
mw
By signing below, I attest the mil'
ons and agree to accept responsibility far all work done under emit.
7
Builder/ Owner Signature
Phone Number '
Printed Name
Approved By
Ryan
Permit is valid for
trict Engineer 01/31/2019
from the date issued. Permit valid only with Trico seal in red ink