HomeMy WebLinkAboutErosion Control Cost OpinionEngineer's Cost Opinion - Erosion Control
Project: Belle Tire Store #138
Location: Carmel, IN
Date: 9/12/18
Item Quantity Unit Unit Cost Cost
Erosion Control - during construction
Silt Fence 1050 LF $2.00 $2,100.00
Dewatering 1 LS $10,000.00 $10,000.00
Concrete Washout 1 EA $500.00 $500.00
Temporary Construction Entrance 150 TON $35.00 $5,250.00
Erosion Control Blanket 1225 SY $2.00 $2,450.00
Temporary Seeding 2700 SY $1.00 $2,700.00
Permanent Sod 2700 SY $5.50 $14,850.00
Rock Donut 1 EA $1,500.00 $1,500.00
Rip Rap 3 SY $150.00 $450.00
Sediment Log 70 LF $2.00 $140.00
Inlet Protection 9 EA $210.00 $1,890.00
Subtotal for Erosion Control during construction $41,830.00
Erosion Control - Post Construction
Water Quality Unit - Aqua-Swirl AS-5 1 EA $16,500.00 $16,500.00
Native Vegetation 250 SF $10.00 $2,500.00
Isolator Rows - 44 ADS SC-740 StormTech chambers 1 LS $20,000.00 $20,000.00
Sumped Manhole (72-inch dia.)1 EA $5,000.00 $5,000.00
Subtotal for Erosion Control - Post Construction $44,000.00
Total:$85,830.00