Loading...
HomeMy WebLinkAboutGN1Community & Home Site Construction Manager Frame Check Garage FC CM Attic Access location correct per Print, access has 14 inch sides if an insulated attic. Check size of Gables Access. FC CM Post plumb and strapped to beam at top FC CM Garage beam will be sealed to prevent air infiltration to floor space after Drywall is hung FC CM Walls in Attic have sheathing installed FC CM All panels are taped in Attic & Verticals Taped. FC CM House band board in garage attic has insulated sheathing installed FC CM House wrap installed at Band system in Garage and pulled down FC CM Truss bracing installed if required FC CM 2x Framing for trusses/girders nailed directly house to framing without foam sheathing between frame members FC CM Truss hanger’s nailed completely with required nails FC CM Garage door opening correct size and location FC CM Smart trim at bottom of door at concrete is ¼ inch off of concrete FC CM Anchor bolts in garage plate installed 12 inches from each plate end at foundation and not more than 6 foot on center and 12 inches from corner. Garage Portal frame 2x2 square washers in place at door. Nuts tight. FC CM Garage steps are of equal rise to top of door threshold from garage floor. Not more than 8 ¼ rise FC CM Sill sealer installed under wall or floor system between house and garage FC CM Garage door bucks installed floor to ceiling in 1 piece 2x6 minimum. Buck is not to be in contact with concrete Nailed 12 inches on center FC CM Garage door buck installed above door 1 piece 2x6. 2x10 installed above center of door to ceiling for garage door opener nailed 12 inches on center FC CM Estate/Side load electrical panel walls build if required. Note these walls may not be on print. FC CM OSB is cut back 2 inches on each side of ridge, Ripper row no less than 2' at Peak. FC CM Bowed studs are marked. Note these markings may be visible to customer if garage in not finished FC CM Garage to house door set with 3 shims on each side and/or Exerior Service Door. FC CM Drywall nailer in place on ceiling and corners/check for insulation access. FC CM Garage door Portal framing correct per IRC 2008 Indiana amendments. Truss to girder connection 1/4" or less Solid Bearing. FC CM Truss Drawings and print hung in Garage FC CM Girder truss bearing is complete to foundation Frame, House Interior FC CM Garage to house door set with correct reveal 6 shims total FC CM Bowed studs checked and marked in orange on the stud and floor with a B FC CM Check each room per print for wall and door opening placement FC CM Check each room for window placement. FC CM Check walls for plumpness mark correction using OOP OOL FC CM Windows centered in the opening shim sides if needed window to sit on sill with 1/8 bumper on bottom. Does the window operate smoothly FC CM Mark each doorway with correct door size and swing Example of how to mark… 2/6 RH with an arrow. FC CM Mark in writing if an opening wraps in drywall wright the word out Drywall wrap or do not drywall or Wood wrap. FC CM Add cabinet dimensions to verify correct wall length FC CM Layout CL of range hood location vertical and horizontal. FC CM Layout cabinet locations in kitchens and baths. Verify correct space for cabinets FC CM Think about outlet/switch location in kitchen. Are all location either under cabinets or outside of cabinets? This has to do with backsplash tile FC CM Think about the locations for the outlets in bathrooms, no outlets in side splashed or behind mirrors. FC CM Check ½ wall height to be certain it is tall enough to allow casing and vanity side splash to not interfere same applies in home office area FC CM Check to be sure toilet and shower drains do not interfere it the Joist locations FC CM Verify correct walls or no walls are installed at stairway, walls vs rails. FC CM Check floor joist layout for correct placement FC CM Check roof truss layout for correctness FC CM Check for correct truss bracing, note you will need truss drawings for this. Additionally correct overlapping is required at brace connections FC CM Shower pan blocking is in place FC CM Stud placement in a shower location is to be no more than 16 inches O.C FC CM Drywall nailers are in place in corners all locations FC CM Drywall nailers are in place at ceilings. Parallel wall to trusses should be cross blocked 2 foot OC laid out for drywall placement FC CM Floor decking nailed and glued Nails 4 in the field 6 on the seams missed nails need pulled FC CM Floor joist are nailed and glue is present in hangers FC CM Air sealing in dead cavities is complete FC CM Stairs are secures with 2-16d nails from back of stringer. No visible nails from the top. FC CM Roof decking is gapped on 4 foot ends 1/8 to ¼ inch. Nailed 4 in the field 6 on the edge FC CM Exterior doors are to be shimmed with 3 places each side for a 6/8 door 4 each for a taller door or a door with a transom. FC CM Ensure finish width of Halls, landings will be 36 inches. FC CM Nailers for Tub Flange (32 inches for tub shower & 34 inches for fiberglass shower) Frame Checklist Frame Business Partner 03/14/19 Adam Schriner