HomeMy WebLinkAboutRieth-Riley/Eng/CO #1/25,747.36/Shelborne Road Multi-Use Path – Project #16-ENG-69 City of Carmel Project 16-ENG-69
Shelborne Road Multi-Use Path
CHANGE ORDER#1 bet`
Extra work at the Snyder property and at Sedgemoor Circle due to agreements between The City of
Carmel,James Snyder, and Bridlebourne Subdivision.Additional change order items for Bridlebourne
subdivision include the removal of 7 dead/dying trees, installation of a new R13 inlet at approximate
Sta. 12+25"P" on the east side of the center island at Sedgemoor Circle, installing 10" HDPE instead of
the planned 8" HDPE for Str. No. 10 and 11, and removing and salvaging existing bricks at Sedgemoor
Circle from the existing asphalt to the east edge of the path.Additional change order items of
mobilization/demobilization, construction engineering, and maintaining traffic are needed to complete
the work for placement of two new asphalt driveways at the Snyder property and for the additional
work for Bridlebourne Subdivision.Additional change order items for asphalt are also needed due to an
increase in the PG asphalt binder index from the bid price to the current price in September.Additional
change order item for geogrid will be added to help stabilize soils for the path subgrade where needed.
Additional change order item for material that is not needed and non-returnable due to a change order
revision from an unforeseen condition. 166 days will be added for time it took for all right-of-way to be
obtained in order for Rieth-Riley to work on all of the project to finish the project this year per
their updated schedule from 10/10/18 and 138 days will be added due to not being able to pave HMA
surface until the spring of 2019 due to heavy rain and cold temperatures in the fall/winter of 2018.
Contract Price prior to this Change Order $563,174.84
Contract Price will be increased/decreased by this Change Order $25,747.36
New Contract Price including this Change Order $588,922.20
Amount Adjusted Contract Cumulative%Change
Price from Original Contract
Original Contract $563,174.84 $563,174.84 N/A
CO1 $25,747.36 $588,922.20 4.57%
CITY OF CARMEL
TO: CONTRACT CHANGE ORDER NO.: I
DATE: 1/31/2019
Rieth-Riley Construction Co. PROJECT NAME: Shelbome Road Multi-Use Path
1751 W.Minnesota St. CITY REQ.NO.:
Indianapolis,IN 46206 CITY PO NO.:
ATTN:Gary Davis CITY PO DATE:
I. You are directed to make the following changes in this Contract:
1. This change order will add eleven new items for this contract for extra work.Seven new items will be added for work at
the Snyder property and at Sedgemoor Circle due to agreements between the City of Carmel, James Snyder, and
Bridlebourne Subdivision and design changes.One item will be added for geogrid to help stabilize the subgrade.One item
will be added for non-returnable material due to a design change at Sedgemoor Circle.Two new items will be added for
an increase to the PG asphalt binder index price from the bid price to the current price in September.
2. Quantities will be changed due to Items 24 and 27 not needing to be used.
3. 166 days will be added for time until all right-of-way has been cleared for Rieth-Riley to complete their work and 138
days will be added due to not being able to pave HMA surface until the spring of 2019 due to heavy rain and cold
temperatures in the fall/winter of 2018.
ITEM AMOUNT SCHEDULED ADJUSTMENT(+)OR(-1 DAYS
41-51 New Items S65,471.60 304 Days
24,27 Quantity Changes -S39,724.24
II. The following referenced Documents further describe the changes outlined in Paragraph I,and are to be considered a part of this
Change Order:R.F.P.: W.D.C.No.:
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $ 563,174.84
Contract Price will be increased/deer-ease€1 by this Change Order $ 25.747.36
New Contract Price including this Change Order $ 588,922.20
Contract Time Prior to this Change Order 92 Days 7/1/2018 Substantial Completion Date
Contract Time Prior to this Change Order 123 Days 8/1/2018 Final Completion Date
Net increased/deereased-resulting from this Change Order 304 Days
Current Contract Time including this Change Order 396 Days 5/1/2019 Substantial Completion Date
Current Contract Time including this Change Order 427 Days 6/1/2019 Final Completion Date
This Change Order is for full and final settlement of all direct,indirect,impact costs and time extensions incurred at any time resulting
from the performance of the changed work.
The Above Changes Are Recommended: The Above Changes Are Accepted: Approved:
USI Consultants,Inc. Rieth-Riley Construction Co. Je y .Kashm ,City Engineer
ENGINEER CONTRACTOR
t?5k° Ar
Jam Brainard a or
or
8415 East 56'''Street 1751 W.Minnesota St.
Indianapolis,IN 46216 Indianapolis,IN 46206
Mary An Burk , ember
City/State/Zip City/State/Zip
L i ats n,Member
By: Kevin Harris By:17,Q.) ^1 1i ATTEST:
Phone: 317-363-9360 Phone: s�6:47
a4/( Christine S.Pauley,Clerk-Treasure( .114-01-11--/'
/
Date: 2/5/2019 Date: 13 I kt� !
Date: 7/'c,�//
•
USI Consultants, Inc
Change Order Details
consultants Carmel Shelbourne Path
Description City of Carmel Project I6-ENG-69-Shelboume Road Path from 106th Street to 116th Street
Prime Contractor Rieth-Riley Construction Co.
1751 W.Minnesota St.
Indianapolis,IN 46206
Change Order 1
Status Pending
Date Created 10/26/2018
Type Changed Conditions
Summary Extra work at the Snyder property,Bridleboume Subdivision,and Sedgemoor Circle.Additional items will be added for an increase in asphalt
pricing,geogrid for soil stabilization,and non-returnable material not needed.Time will be added as well.
Change Order Description Extra work at the Snyder property and at Sedgemoor Circle due to agreements between The City of Cannel,James Snyder,and Bridleboume
Subdivision.Additional change order items for Bridleboume subdivision include the removal of 7 dead/dying trees,installation of a new R13
inlet at approximate Sta. 12+25"P"on the east side of the center island at Sedgemoor Circle,installing 10"HDPE instead of the planned 8"
HDPE for Str.No.10 and 11,and removing and salvaging existing bricks at Sedgemoor Circle from the existing asphalt to the east edge of the
path.Additional change order items of mobilization/demobilization,construction engineering,and maintaining traffic are needed to complete the
work for placement of two new asphalt driveways at the Snyder property and for the additional work for Bridleboume Subdivision.Additional
change order items for asphalt are also needed due to an increase in the PG asphalt binder index from the bid price to the current price in
September.Additional change order item for geogrid will be added to help stabilize soils for the path suhgrade where needed.Additional change
order item for material that is not needed and non-returnable due to a change order revision from an unforeseen condition.166 days will be added
for time it took for all the right-of-way to be obtained in order for Rieith-Riley to work on all the project per their updated schedule from 10/10/
18 and 138 days will be added due to not being able to pave HMA surface until the spring of 2019 due to heavy rain and cold temperatures in the
fall/winter of 2018.
Awarded Project Amount $563,174.84
Change Order Details: 02/05/2019
Carmel Shelboume Path Page 1 of 5
Authorized Project Amount $563,174.84
Change Order Amount $25,747.36
Revised Project Amount $588,922.20
Increases/Decreases
Line. 'audit
Section:2-Description
0024 Shelbourne Path Item 24 SYS $133 600 244.000 $32,598.40 -244.000 -$32,598.40 0.000 $0.00
ARTICULATED CONCRETE BLOCK
Reason:No longer needed due to a design change of the drainage at Sedgemoor Circle from an unforeseen condition.The ditch will not need to be cut deep where this item was
required.
0027 Shelboume Path Item 27 LFT $32.990 216.000 $7,125.84 -216.000 -$7,125.84 0.000 $0.00
HDPE,8 IN
Reason:No longer needed due to a design change of the drainage at Sedgemoor Circle from an unforeseen condition. 10"HDPE will be installed in place of this item as added to
this change order.
2 items Totals $39 724 24 1. -$39,72424 $0.00
Change Order Details: 02/05/2019
Carmel Shelbourne Path Page 2 of 5
New Items
Line Number Item ID I nit
Section: 1 -Description
OU41 Shelbourne Path Item 41 LS 1 000 $1.870.000 $1,870 00
CONSTRUCTION ENGINEERING:Additional
Reason:For added work per agreement with property owner James Snyder and Bridleboume Subdivision.
0042 Shelbourne Path Item 42 LS 1.000 $3,500 000 $3,500 00
MOBILIZATION AND DEMOBILIZATION:Additional
Reason:For added work per agreement with property owner James Snyder and Bridleboume Subdivision.
0043 Shelboume Path Item 43 LS 1.000 $8.115.000 $8,115.00
TREE REMOVAL:
Reason:For added work per agreement with Bridleboume Subdivision to remove 7 dead/dying trees
0044 Shelboume Path Item 44 LS 1.000 $5,909.000 $5,909.00
MAINTAINING TRAFFIC:Additional
Reason:For added work per agreement with property owner James Snyder and Bridleboume Subdivision.
0045 Shelbounie Path Item 45 SYS 88 uuo $69 u90 $6,079 92
REMOVE AND SALVAGE BRICK PAVERS
Reason:Existing brick pavers removed at Sedgemoor Circle to fix drainage issues.
Change Order Details: 02/05/2019
Carmel Shelbourne Path Page 3 of 5
f s
unit Quantity Unit Price Ex
0046 Shelboume Path Item 46 EACH 1.000 $3,694.560 $3,694.56
INLET,R13
Reason:New inlet installed at Sedgemoor Circle to replace existing slotted drain to fix drainage issues.
0047 Shelboume Path Item 47 TON 1,349.000 $2.400 $3,237.60
HMA FOR MULTI-USE PATH:Price Increase
Reason:Increase in PG asphalt binder index from the bid price to the current price in September
0048 Shelboume Path Item 48 TON 240.000 $2.850 $684.00
HMA FOR APPROACHES,TYPE C:Price Increase
Reason:Increase in PG asphalt binder index from the bid price to the current price in September.
0049 Shelboume Path Item 49 LFT 216.000 $34.090 $7,363.44
HDPE,LOIN
Reason:Replaces the planned 8"HDPE for Str.10 and 11 in order to increase the pipe size due to being able to lower the pipe inverts at the new R13 inlet at Sedgemoor Circle.
0050 Shelboume Path Item 50 SYS 1,400 000 $5.460 $7,644.00
Geogrid
Reason:To help stabilize soils where needed.
0051 Shelboume Path Item 51 LS 1.000 $17,374.080 $17,374.08
NON-RETURNABLE MATERIAL:City Purchased
Reason:Due to a design change to the drainage plan from an unforeseen condition at Sedgemoor Circle,Item No.24(Articulated Concrete Block)and Item No.27(HDPE,8 IN)
Change Order Details 02/05/2019
Carmel Shelbourne Path
Page 4 of 5
Line Number Item ID t nit Oaantit% Unit Price Exien,i[
are no longer needed.Since the items were made or delivered before the design change and are non-returnable,the City of Carmel has agreed to purchase them.
11 items Total:$65,471.60
New Time Limits
lie Pending Deadline Pending Cost per 17rrs
Completion Date l 'i 19
Substantial Completion
Completion Date 06/01/2019 $1,000.00
Final Completion
Ztn e�111R1tS `'y ✓� aFr f s
Change Order Details. 02/05/2019
Carmel Shelbourne Path Page 5 of 5
Cost Report
Rieth Riley Construction Co., Inc. 15 Gary Vandergriff Page 1 of 7
22.0143C 16-ENG-69 Shelborne Rd. -Snyder Parcel 09/26/2018 2:29 PM
Biditem CONSTRUCTION ENGINEERING
1 Takeoff Qty: 1.000 LS
Bid Qty: 1.000 LS
Activity: 670001 Construction Engineering-SUB Quantity: 1 Unit: LS
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
4ENG ENGINEERING SUB 1.00 1.00 LS 500.00 100.00 500.00 500.00
Biditem MOBILIZATION AND DEMOBILIZATION
2 Takeoff Qty: 1.000 LS
Bid Qty: 1.000 LS
Base Labor Burden Total Labor Equipment Perm Matls Const Math Sub Trucking Bridge Asphalt Total
U.Cost 492.31 273.02 765.33 486.38 0.00 688.00 0.00 0.00 0.00 0.00 1,939.71
Total 492.31 273.02 765.33 486.38 0.00 688.00 0.00 0.00 0.00 0.00 1,939.71
Manhours Unit/MH MH/Unit 5/MN Base Labor/MH Total Labor/MH Unit/CH
14.0000 0.0714 14.0000 138.5507 35.1650 54.6664 0.0714
Activity: 00801 Mob/Demob Quantity: 1 Unit: LS
Base Labor Burden Total Labor Equipment Perm Math Const Math Sub Trucking Bridge Asphalt Total
U.Cost 136.55 78.87 215.42 288.75 0.00 0.00 0.00 0.00 0.00 0.00 504.17
Total 136.55 78.87 215.42 288.75 0.00 0.00 0.00 0.00 0.00 0.00 504.17
Crew 5/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit 5/Shift
504.1700 4.0000 0.2500 126.0425 0.4000 2.5000 0.4000 1,260.4250
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
4.0000 0.2500 4.0000 53.8550 136.5500
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0069 LOWBOY &TEAMSTER Prod: 0 Eff: 100.00 Crew Hrs: 4.00 Labor Pcs: 1.00 Equipment Pcs:1.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8TTTRT IRKS TRACTOR W/TRL 1.00 4.00 FIR 70.77 100.00 72.19 288.75
TM TEAMSTER 1.00 4.00 MH 28.41 116.67 53.86 215.42
Activity: 00811 Supervision Quantity: 1 Unit: LS
Base Labor Burden Total Labor Equipment Perm Mats Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 163.40 76.32 239.72 61.20 0.00 0.00 0.00 0.00 0.00 0.00 300.92
Total 163.40 76.32 239.72 61.20 0.00 0.00 0.00 0.00 0.00 0.00 300.92
Crew 5/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit S/Shift
300.9200 4.0000 0.2500 75.2300 0.5000 2.0000 0.5000 601.8400
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
4.0000 0.2500 4.0000 59.9300 163.4000
Calendar:040 5 DAYS Q 8 HRS/EA Hrs/Shift:8 WC: 1 WC/GL
Crew: AA0099 SUPERINTENDENT Prod: 0 Eff: 100.00 Crew Hrs: 4.00 Labor Pcs: 1.00 Equipment Pcs:1.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8TPU1 TRKS SUPERINTENDENT 1.00 4.00 HR 15.00 100.00 15.30 61.20
SUPT SUPERINTENDENT 1.00 4.00 MH 39.66 100.00 59.93 239.72
22-0143C 16-ENG-69 Shelborne Rd. - Snyder Parcel 09/26/2018 2:29 PM Page 2 of 7
Activity: 00826 Water/Fuel Quantity: 1 Unit: 13
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 136.55 78.87 215.42 111.79 0.00 0.00 0.00 0.00 0.00 0.00 327.21
Total 136.55 78.87 215.42 111,79 0.00 0.00 0.00 0.00 0.00 0.00 327.21
Crew$Knit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit $/Shift
327.2100 4.0000 0.2500 81.8025 0.4000 2.5000 0.4000 818.0250
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
4.0000 0.2500 4.0000 53.8550 136.5500
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0039 WATER TRUCK a TEAMSTER Prod: 0 Eff: 100.00 Crew Hrs: 4.00 Labor Pcs: 1.00 Equipment Pcs: 1.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8TWFT TRKS WATER/FUEL T/A 1.00 4.00 HR 27.40 100.00 27.95 111.79
TM TEAMSTER 1.00 4.00 MH 28.41 116.67 53.86 215.42
Activity: 00828 Show-Up Quantity: 1 Unit: LS
Base Labor Burden Total Labor Equipment Perm Matis Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 55.81 38.96 94.77 24.64 0.00 0.00 0.00 0.00 0.00 0.00 119.41
Total 55.81 38.96 94.77 24.64 0.00 0.00 0.00 0.00 0.00 0.00 119,41
Crew$/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit 5/Shift
119.4100 2.0000 0.5000 59.7050 0.2000 5.0000 0.2000 597.0500
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
2.0000 0.5000 2.0000 47.3850 55.8100
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0019 QA TECHNICIAN Prod: 0 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 1.00 Equipment Pcs:1.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 2.00 HR 12.08 100.00 12.32 24.64
QA QA TECH 1.00 2.00 MH 23.22 116.67 47.39 94.77
Activity: 00831 Bonds Quantity: 1 Unit: LS
Base Labor Burden Total Labor Equipment Perm Matls Const Malls Sub Trucking Bridge Asphalt Total
U.Cost 0.00 0.00 0.00 0.00 0.00 138.00 0.00 0.00 0.00 0.00 138,00
Total 0.00 0.00 0.00 0.00 0.00 138.00 0.00 0.00 0.00 0.00 138.00
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
30BON01 MAINTAINANCE/WARRANTY 1.00 30.00 THOU 1.00 100.00 1.00 30.00
30BON07 NEW RD. FIRST$2.5 MIL 1.00 30.00 THOU 3.60 100.00 3.60 108.00
Activity: 00855 Small Tool Supplies Quantity: 1 Unit: LS
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
3J JOB EXPENSE 1.00 1.00 LS 50.00 100.00 50.00 50.00
Activity: 00871 Potholing Quantity: 1 Unit: LS
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
3J JOB EXPENSE 1.00 1.00 LS 500.00 100.00 500.00 500.00
Biditem EXCAVATION, COMMON
1
I
22-0143C 16-ENG-69 Shelborne Rd. -Snyder Parcel 09/26/2018 2:29 PM Page 3 of 7 1
4 Takeoff Qty: 19.000 CYS
Bid Qty: 19.000 CYS
i
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking
Bridge Asphalt Total
U.Cost 40.78 26.04 66.82 25.19 0.00 0.00 0.00 10.68 0.00 0.00 102.69
Total 774.86 494.67 1,269.53 478.58 0.00 0.00 0.00 203.00 0.00 0.00 1,951.11
Manhours Unit/MH MH/Unit $/MH Base Labor/MH Total Labor/MH Unit/CH
22.0000 0.8636 1.1579 88.6868 35.2209 57.7059 4.7500
Activity: 06120 Cut-to-Waste Quantity: 19 Unit: CYS
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 18.92 11.99 30.91 13.76 0.00 0.00 0.00 10.68 0.00 0.00 55.36
Total 359.53 227.85 587.38 261.39 0.00 0.00 0.00 203.00 0.00 0.00 1,051.77
Crew$/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit S/Shift
44.6721 0.1053 9.5000 424.3850 0.2000 95.0000 0.0105 5,258.8500
Manhours Unit/MH MH/Unit Total labor/MH Base Labor/Unit
10.0000 1.9000 0.5263 58.7380 18.9226
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0083 CUT TO WASTE CREW Prod: 0 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 5.00 Equipment Pcs:3.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
5HTR10 TRUCKING 10 HOURS 1.00 2.00 HR 101.50 100.00 101.50 203.00
8D-4 DOZER 85 HP(D4) 1.00 2.00 HR 36.15 100.00 36.88 73.75
8EX314 EXCAVATOR 314 1.00 2.00 HR 79.90 100.00 81.50 163.00
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 2.00 HR 12.08 100.00 12.32 24.64
FOR FOREMAN 1.00 2.00 MH 35.05 116.67 67.24 134.48
LAB LABORER 2.00 4.00 MH 23.22 116.67 47.39 189.55
OPER OPERATOR(103) 2.00 4.00 MH 34.05 116.67 65.84 263.35
Activity: 06194 FG Seed ft Sod Quantity: 59.32 Unit: SYS
Base Labor Burden Total Labor Equipment Perm Matls Const Math Sub Trucking Bridge Asphalt Total
U.Cost 7.00 4.50 11.50 3.66 0.00 0.00 0.00 0.00 0.00 0.00 15.16
Total 415.33 266.82 682.15 217.19 0.00 0.00 0.00 0.00 0.00 0.00 899.34
Crew S/Unit Crew Hrs/Unit Units/Crew Hr S/Crew Hour Shifts Units/Shift Shifts/Unit $/Shift
15.1608 0.0337 29.6600 449.6700 0.2000 296.6000 0.0034 4,496.7000
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
12.0000 4.9433 0.2023 56.8458 7.0015
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0086 DOZER CREW Prod: UH 29.66 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 6.00 Equipment Pcs:3.00
Notes: ,-'4 _ ,,
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8D-4 DOZER 85 HP(D4) 1.00 2.00 HR 36.15 100.00 36.88 73.75
8LSKD85 SKID STEER 85 HP 1.00 2.00 HR 58.23 100.00 59.40 118.80
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 2.00 HR 12.08 100.00 12.32 24.64
FOR FOREMAN 1.00 2.00 MH 35.05 116.67 67.24 134.48
LAB LABORER 3.00 6.00 MH 23.22 116.67 47.39 284.32
OPER OPERATOR(103) 2.00 4.00 MH 34.05 116.67 65.84 263.35
Biditem TEMPORARY INLET PROTECTION
6 Takeoff Qty: 1.000 EACH
Bid Qty: 1.000 EACH
22-0143C 16-ENG-69 Shelborne Rd. -Snyder Parcel 09/26/2018 2:29 PM Page 4 of 7
Activity: 57050 Temp Ditch Inlet Protection Quantity: 1 Unit: EACH
Calendar:061 6 DAYS C 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
4EROS EROSION CONTROL SUB 1.00 1.00 EACH 100.00 100.00 100.00 100.00
Notes: Str.1- 9 cys St:.11-3i. / Str.1S-3.7 cys . Str.19-v-1 cys / Str.20-0.5 cys I
y
Str-21 cys / Str.22-15.5 cys /
.2_--2.4 cys / Str.24-1 rys , Str. :i •••r.26-4._ cya •« TOTAL - 11 Structures
Biditem STRUCTURE BACKFILL, TYPE I
11 Takeoff Qty: 20.000 CYS
Bid Qty: 20.000 CYS
Activity: 10220 Str Backfitt,Type 1 Quantity: 20 Unit: CYS
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
2AB1005 B-BORROW 1.00 40.00 TON 15.05 100.00 15.05 602.00
Notes: 6-0• Subbase for Path
Biditem COMPACTED AGGREGATE NO. 53
13 Takeoff Qty: 30.000 TON
Bid Qty: 30.000 TON
Base Labor Burden Total Labor Equipment Perm Malls Const Matis Sub Trucking Bridge Asphalt Total
U.Cost 19.66 12.61 32.27 4.10 11.00 0.00 0.00 13.53 0.00 0.00 60.91
Total 589.87 378.30 968.17 123.12 330.00 0.00 0,00 406.00 0.00 0.00 1,827.29
Manhours Unit/MH MH/Unit $/MH Base Labor/MH Total Labor/MH Unit/CH
18.0000 1.6667 0.6000 101.5161 32.7706 53.7872 15.0000
Activity: 29420 Camp Agg No 53 Base Quantity: 30 Unit: TON
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 19.66 12.61 32.27 4.10 11.00 0.00 0.00 13.53 0.00 0.00 60.91
Total 589.87 378.30 968.17 123.12 330.00 0.00 0.00 406.00 0.00 0.00 1,827.29
Crew$/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit $/Shift
36.3763 0.0667 15.0000 545.6450 0.2000 150.0000 0.0067 9,136.4500
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
18.0000 1.6667 0.6000 53.7872 19.6623
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0041 CONCRETE CREW,FLATWORK Prod: UH 15 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 9.00 Equipment Pcs:3.00
Notes: TRUCKING BY THE Ton (Long Method)
INPUT COMPUTED
Total Tons 2326.00
TonsiHr 55.15 40.00 Total Hours
Hours/Shift 10.00 4.00 Total Shifts
5,11.50 Tons/Shift
One Way Distance'Miles) 10.00 2:.00 MtlesfP.ourd Trip
Average Speed MPH 20.00 6ct.00 HaulTiaie/BndTr :i4in)
Load Tim? - . Mir. 10.00 20.64 ['optima- 20 Tons%Lcad
Dump Time Min 20.64 90.64 Tc.tTineikndTr Odin%
Usable -:,;Hr. 50.00 0.55 EnriTr,Loada/Er/T:uck
Tans%Tru_ .load 19.00 129.22 Total Truckloads
5,66 Theor. No. of Trucks
Use This Mo. of : 5.96 234.40 Tctal Truck Hours
trice:Hr f:-:. -...,,ks 0.00 !). 5 To. Price - Trucking
FriceiTcr, for Trtckinn
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT96 Actual UC Total
22-0143C 16•ENG-69 Shelborne Rd. -Snyder Parcel 09/26/2018 2:29 PM Page 5 of 7
2AL2053M TYPE"0"#53(MO) 1.00 30.00 TON 11.00 100.00 11.00 330.00
5HTR10 TRUCKING 10 HOURS 1.00 4.00 HR 101.50 100.00 101.50 406.00
8L580 BACKHOE 580 1.00 2.00 HR 32.34 100.00 32.99 65.97
8TPU1.5T TRKS 1.5 TON 1.00 2.00 HR 15.93 100.00 16.26 32.51
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 2.00 HR 12.08 100.00 12.32 24.64
COMB COMBINATION 1.00 2.00 MH 29.01 116.67 55.49 110.98
FIN FINISHER 4.00 8.00 MH 25.22 116.67 50.19 401.48
FOR FOREMAN 1.00 2.00 MH 35.05 116.67 67.24 134.48
LAB LABORER 2.00 4.00 MH 23.22 116.67 47.39 189.55
OPER OPERATOR(103) 1.00 2.00 MH 34.05 116.67 65.84 131.68
Notes: - -
Biditem RCP, 18 IN
Takeoff Qty: 43.000 LFT
3 2 Bid Qty: 43.000 LFT
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 19.37 12.42 31.79 13.09 17.92 0.00 0.00 20.30 0.00 0.00 83.11
Total 833.07 534.05 1,367.12 562.93 770.66 0.00 0.00 872.90 0.00 0.00 3,573.61
Manhours Unit/MH MH/Unit S/MH Base Labor/MH Total Labor/MH Unit/CH
24.0000 1.7917 0.5581 148.9004 34.7113 56.9633 7.1667
Activity: 11106 18IN Type 2 Circ Pipe Quantity: 43 Unit: LFT
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 19.37 12.42 31.79 13.09 17.92 0.00 0.00 20.30 0.00 0.00 83.11
Total 833.07 534.05 1,367.12 562.93 770.66 0.00 0.00 872.90 0.00 0.00 3,573.61
Crew S/Unit Crew Hrs/Unit UnIts/Crew Hr S/Crew Hour Shifts Units/Shift Shifts/Unit S/Shift
44.8849 0.1395 7.1667 321.6750 0.6000 71.6667 0.0140 5,956.0167
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
24.0000 1.7917 0.5581 56.9633 19.3737
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0061 PIPE CREW,SMALL/CAT 314 Prod: UH 7.1667 Eff: 100.00 Crew Hrs: 6.00 Labor Pcs: 4.00 Equipment Pcs:2.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
2AL1008 LIMESTONE#8 1.00 5.38 TON 20.00 100.00 20.00 107.60
2DP1018 PIPE, RCP, 18•' 1.00 43.00 LFT 15.42 100.00 15.42 663.06
5HTR10 TRUCKING 10 HOURS 1.00 8.60 HR 101.50 100.00 101.50 872.90
8EX314 EXCAVATOR 314 1.00 6.00 HR 79.90 100.00 81.50 488.99
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 6.00 HR 12.08 100.00 12.32 73.94
FOR FOREMAN 1.00 6.00 MH 35.05 116.67 67.24 403.43
LAB LABORER 2.00 12.00 MH 23.22 116.67 47.39 568.65
OPER OPERATOR(103) 1.00 6.00 MN 34.05 116.67 65.84 395.04
Notes: Str.19 l 2.76' depth / Str.20 4 4.35' depth / Srr.34 @ 4."-' depth / _tr.25 4 4.45' depth / S:_._. @ 3.F,5' aecth
'' ' TOTAL e 5 ea:A, @ 3.95' average deerh
Biditem INLET, E7
35 Takeoff Qty: 1.000 EACH
Bid Qty: 1.000 EACH
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 719.04 455.72 1,174.76 723.35 799.25 0.00 0.00 0.00 0.00 0.00 2,697.36
Total 719.04 455.72 1,174.76 723.35 799.25 0.00 0.00 0.00 0.00 0.00 2,697.36
Manhours Unit/MH MR/Unit S/MH Base Labor/MH Total Labor/MH Unit/CH i
22-0143C 16•ENG-69 Shelborne Rd. •Snyder Parcel 09/26/2018 2:29 PM Page 6 of 7
20.0000 0.0500 20.0000 134.8680 35.9520 58.7380 0.2500
Activity: 10325 E7 Inlet Quantity: 1 Unit: EACH
Base Labor Burden Total Labor Equipment Perm Matis Const Mails Sub Trucking Bridge Asphalt Total
U.Cost 719.04 455.72 1,174.76 723.35 799.25 0.00 0.00 0.00 0.00 0.00 2,697.36
Total 719.04 455.72 1,174.76 723.35 799.25 0.00 0.00 0.00 0.00 0.00 2,697.36
Crew 5/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit 5/Shift
1,898.1100 4.0000 0.2500 474.5275 0.4000 2.5000 0.4000 6,743.4000
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
20.0000 0.0500 20.0000 58.7380 719.0400
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0062 PIPE CREW,MEDIUM/CAT 320 Prod: HU 4 Eff: 100.00 Crew Hrs: 4.00 Labor Pcs: 5.00 Equipment Pcs:4.00
Notes: : s)" -, . - '.as _•<c
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
2AB1005 B- BORROW 1.00 5.00 TON 15.05 100.00 15.05 75.25
2CA CONCRETE CLASS"A" 1.00 1.00 CYS 103.00 100.00 103.00 103.00
2DC1007 CASTING TYPE 7(R-4215-C) 1.00 1.00 EACH 225.00 100.00 225.00 225.00
2DSI-E INLET TYPE E 1.00 1.00 EACH 396.00 100.00 396.00 396.00
8EX320 EXCAVATOR 320/ 325 1.00 4.00 FIR 76.91 100.00 78.45 313.80
8L938 LOADER 938 1.00 4.00 HR 63.30 100.00 64.57 258.26
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 4.00 HR 12.08 100.00 12.32 49.29
8TXBOX TRENCH BOX FOR PIPE 1.00 4.00 HR 25.00 100.00 25.50 102.00
FOR FOREMAN 1.00 4.00 MH 35.05 116.67 67.24 268.95
LAB LABORER 2.00 8.00 MH 23.22 116.67 47.39 379.10
OPER OPERATOR(103) 2.00 8.00 MH 34.05 116.67 65.84 526.71
Biditem MAINTAINING TRAFFIC
38 Takeoff Qty: 1.000 LS
Bid Qty: 1.000 LS
Manhours Unit/MH MH/Unit $/MH Base Labor/MH Total Labor/MH Untt/CH
64.0000 0.0156 64.0000 47.3873 27.9034 47.3873 0.0313
Activity: 52615 Flagging/ Quantity: t Unit: LS
Crew 5/Unit Crew Hrs/Unit Units/Crew Hr 5/Crew Hour Shifts Units/Shift Shifts/Unit 5/Shift
3,032.7900 32.0000 0.0313 94.7747 3.2000 0.3125 3.2000 947.7469
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
64.0000 0.0156 64.0000 47.3873 1,785.8200
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0031 FLAGGING CREW Prod: 0 Eff: 100.00 Crew Hrs: 32.00 Labor Pcs: 2.00 Equipment Pcs:0.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
LAB LABORER 2.00 64.00 MH 23.22 116.67 47.39 3,032.79
Biditem RESIDENTIAL DRIVEWAY, CONCRETE
43 Takeoff Qty:Bid Qty: 82.000 SYS
82.000 SYS
Base Labor Burden Total Labor Equipment Penn Matls Const Matis Sub Trucking Bridge Asphalt Total
U.Cost 57.55 36.91 94.46 12.01 19.32 1.00 0.00 0.00 0.00 0.00 126.78
Total 4,718.94 3,026.45 7,745.39 984.96 1,583.96 82.00 0.00 0.00 0.00 0.00 10,396.31
22-0143C 16-ENG-69 Shelborne Rd. -Snyder Parcel 09/26/2018 2:29 PM Page 7 of 7
Manhours Unit/MH MH/Unit $/MH Base Labor/MH Total Labor/MH Unit/CH
144.0000 0.5694 1.7561 72.1966 32.7704 53.7874 5.1250
Activity: 42530 PCCP App 6 IN Quantity: 82 Unit: SYS
Base Labor Burden Total Labor Equipment Penn Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 57.55 36.91 94.46 12.01 19.32 1.00 0.00 0.00 0.00 0.00 126.78
Total 4,718.94 3,026.45 7,745.39 984.96 1,583.96 82.00 0.00 0.00 0.00 0.00 10,396.31
Crew 5/Unit Crew Hrs/Unit Units/Crew Hr 5/Crew Hour Shifts Units/Shift Shifts/Unit $/Shift
106.4677 0.1951 5.1250 545.6469 1.6000 51.2500 0.0195 6,497.6938
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
144.0000 0.5694 1.7561 53.7874 57.5480
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0041 CONCRETE CREW,FLATWORK Prod: UH 5.125 Eff: 100.00 Crew Hrs: 16.00 Labor Pcs: 9.00 Equipment Pcs:3.00
Notes: EC? App 6 IN
0.5' X 9 / ' - .1666 IL.k = .1632 CYS PER SYS
0.5' v 9 / _ _ .166E X PA = .1915 Cis PER SYS
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
2CA CONCRETE CLASS"A" 1.00 15.02 CYS 103.00 100.00 103.00 1,547.06
2CXCURE CURING COMPOUND(55 GAL) 1.00 6.15 GAL 6.00 100.00 6.00 36.90
3JCXFS CONCRETE FORMS BY SYS 1.00 82.00 SYS 1.00 100.00 1.00 82.00
8L580 BACKHOE 580 1.00 16.00 HR 32.34 100.00 32.99 527.76
8TPU1.5T IRKS 1.5 TON 1.00 16.00 HR 15.93 100.00 16.25 260.03 I
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 16.00 HR 12.08 100.00 12.32 197.17
COMB COMBINATION 1.00 16.00 MH 29.01 116.67 55.49 887.84
FIN FINISHER 4.00 64.00 MH 25.22 116.67 50.19 3,211.92
FOR FOREMAN 1.00 16.00 MH 35.05 116.67 67.24 1,075.81
LAB LABORER 2.00 32.00 MN 23.22 116.67 47.39 1,516,40
OPER OPERATOR(103) 1.00 16.00 MH 34.05 116.67 65.84 1,053.42
Report Summary
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
Total 9,914 6,409 16,323 3,359 4,086 770 600 1,482 0 0 26,620
Calendars Used In Estimate
061 6 DAYS @ 10 HRS/EA
040 5 DAYS® 8 HRS/EA
Cost Report
Rieth Riley Construction Co., Inc. 15 Gary Vandergriff Page 1 of 8
22-0143B to-ENG-69 Shelborne Rd. -Sedgemoor Circ 09/26/2018 2:23 PM
Biditem CONSTRUCTION ENGINEERING
1 Takeoff Qty: 1.000 LS
Bid Qty: 1.000 LS
Activity: 670001 Construction Engineering-SUB Quantity: 1 Unit: LS
Calendar:061 6 DAYS @ 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
4ENG ENGINEERING SUB 1.00 1.00 LS 200.00 100.00 200.00 200.00
Biditem MOBILIZATION AND DEMOBILIZATION
2 Takeoff Qty: 1.000 LS
Bid Qty: 1.000 LS
Base Labor Burden Total Labor Equipment Perm Matis Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 274.07 156.00 430.07 255.52 0.00 342.00 0.00 0.00 0.00 0.00 1,027.59
Total 274.07 156.00 430.07 255.52 0.00 342.00 0.00 0.00 0.00 0.00 1,027.59
Manhours Unit/MH MH/Unit S/MH Base Labor/MH Total Labor/MH Unit/CH
8.0000 0.1250 8.0000 128.4488 34.2588 53.7588 0.1250
Activity:, 00801 Mob/Demob Quantity: 1 Unit: LS
Base Labor Burden Total Labor Equipment Perm Matis Const Mats Sub Trucking Bridge Asphalt Total
U.Cost 68.28 39.44 107.72 144.38 0.00 0.00 0.00 0.00 0.00 0.00 252.10
Total 68.28 39.44 107.72 144.38 0.00 0.00 0.00 0.00 0.00 0.00 252.10
Crew S/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit S/Shift
252.1000 2.0000 0.5000 126.0500 0.2000 5.0000 0.2000 1,260.5000
Manhours Unit/MH NH/Unit Total Labor/MH Base Labor/Unit
2.0000 0.5000 2.0000 53.8600 68.2800
Calendar:061 6 DAYS @ 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0069 LOWBOY &TEAMSTER Prod: 0 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 1.00 Equipment Pcs:1.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8 i I i RT TRKS TRACTOR W/TRL 1.00 2.00 HR 70.77 100.00 72.19 144.38
TM TEAMSTER 1.00 2.00 MH 28.41 116.67 53.86 107.72
Activity: 00811 Supervision Quantity: 1 Unit: LS
Base Labor Burden Total Labor Equipment Perm Mats Const Matis Sub Trucking Bridge Asphalt Total
U.Cost 81.70 38.16 119.86 30.60 0.00 0.00 0.00 0.00 0.00 0.00 150.46
Total 81.70 38.16 119.86 30.60 0.00 0.00 0.00 0.00 0.00 0.00 150.46
Crew$/Unit Crew Hrs/Unit Units/Crew Hr S/Crew Hour Shifts Units/Shift Shifts/Unit S/Shift
150.4600 2.0000 0.5000 75.2300 0.2500 4.0000 0.2500 601.8400
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
2.0000 0.5000 2.0000 59.9300 81.7000
Calendar:040 5 DAYS @ 8 HRS/EA Hrs/Shift:8 WC: 1 WC/GL
Crew: AAA SUPERINTENDENT Prod: 0 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 1.00 Equipment Pcs:1.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8TPU1 TRKS SUPERINTENDENT 1.00 2.00 HR 15.00 100.00 15.30 30.60
SUPT SUPERINTENDENT 1.00 2.00 MH 39.66 100.00 59.93 119.86
i
.i
22-0143B 16-ENG-69 Shelborne Rd. -Sedgemoor Circ 09/26/2018 2:23 PM Page 2 of 8
Activity: 00826 Water/Fuel Quantity: 1 Unit: LS
Base Labor Burden Total Labor Equipment Perm Malls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 68.28 39.44 107.72 55.90 0.00 0.00 0.00 0.00 0.00 0.00 163.62
Total 68.28 39.44 107.72 55.90 0.00 0.00 0.00 0.00 0.00 0.00 163.62
Crew S/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit $/Shift
163.6200 2.0000 0.5000 81.8100 0.2000 5.0000 0.2000 818.1000
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
2.0000 0.5000 2.0000 53.8600 68.2800
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0039 WATER TRUCK&TEAMSTER Prod: 0 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 1.00 Equipment Pcs:1.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8TWFT TRKS WATER/FUEL T/A 1.00 2.00 HR 27.40 100.00 27,95 55.90
TM TEAMSTER 1.00 2.00 MH 28.41 116.67 53.86 107.72
Activity: 00828 Show-Up Quantity: 1 Unit: LS
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 55.81 38.96 94.77 24.64 0.00 0.00 0.00 0.00 0.00 0.00 119.41
Total 55.81 38.96 94.77 24.64 0.00 0.00 0.00 0.00 0.00 0.00 119.41
Crew 5/Unit Crew Hrs/Unit Units/Crew Hr S/Crew Hour Shifts Units/Shift Shifts/Unit $/Shift
119.4100 2.0000 0.5000 59.7050 0.2000 5.0000 0.2000 597.0500
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
2.0000 0.5000 2.0000 47.3850 55.8100
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AAO0i9 QA TECHNICIAN Prod: 0 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 1.00 Equipment Pcs: 1.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 2.00 HR 12.08 100.00 12.32 24.64 j
QA QA TECH 1.00 2.00 MH 23.22 116.67 47.39 94.77
Activity: 00831 Bonds Quantity: 1 Unit: LS
Base Labor Burden Total Labor Equipment Perm Matls Const Malls Sub Trucking Bridge Asphalt Total
U.Cost 0.00 0.00 0.00 0.00 0.00 92.00 0.00 0.00 0.00 0.00 92.00
Total 0.00 0.00 0.00 0.00 0.00 92.00 0.00 0.00 0.00 0.00 92.00
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
30BON01 MAINTAINANCE/WARRANTY 1.00 20.00 THOU 1.00 100.00 1.00 20.00
30B0N07 NEW RD. FIRST$2.5 MIL 1.00 20.00 THOU 3.60 100.00 3.60 72.00
Activity: 00855 Small Tool Supplies Quantity: 1 Unit: LS
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
3J JOB EXPENSE 1.00 1.00 LS 50.00 100.00 50.00 50.00
Activity: 00871 Potholing Quantity: 1 Unit: LS
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
3J JOB EXPENSE 1.00 1.00 LS 200.00 100.00 200.00 200.00
Biditem EXCAVATION, COMMON
22-0143B 16-ENG-69 Shelborne Rd. -Sedgemoor Circ 09/26/2018 2:23 PM Page 3 of 8
4 Takeoff Qty: 15.000 CYS
Bid Qty: 15.000 CYS
Base Labor Burden Total Labor Equipment Perm Matls Const Malls Sub Trucking Bridge Asphalt Total
U.Cost 25.83 16.49 42.32 17.45 0.00 0.00 0.00 6.77 0.00 0.00 66.54
Total 387.44 247.33 634.77 261.77 0.00 0.00 0.00 101.50 0.00 0.00 998.04
Manhours Unit/MH MH/Unit $/MH Base Labor/MH Total Labor/MH Unit/CH
11.0000 1.3636 0.7333 90.7309 35.2218 57.7064 7.5000
Activity: 06120 Cut-to-Waste Quantity: 15 Unit: CYS
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 11.98 7.59 19.58 10.21 0.00 0.00 0.00 6.77 0.00 0.00 36.56
Total 179.77 113.92 293.69 153.19 0.00 0.00 0.00 101.50 0.00 0.00 548.38
Crew$/Unit Crew Hrs/Unit Units/Crew Hr 5/Crew Hour Shifts Units/Shift Shifts/Unit $/Shift
29.7920 0.0667 15.0000 446.8800 0.1000 150.0000 0.0067 5,483.8000
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
5.0000 3.0000 0.3333 58.7380 11.9847
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0083 CUT TO WASTE CREW Prod: UH 15 Eff: 100.00 Crew Hrs: 1.00 Labor Pcs: 5.00 Equipment Pcs:3.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
5HTR10 TRUCKING 10 HOURS 1.00 1.00 HR 101.50 100.00 101.50 101.50
8D-4 DOZER 85 HP(D4) 1.00 1.00 HR 36.15 100.00 36.87 36.87
8EX330 EXCAVATOR 330/ 336 1.00 1.00 HR 101.96 100.00 104.00 104.00
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 1.00 HR 12.08 100.00 12.32 12.32
FOR FOREMAN 1.00 1.00 MN 35.05 116.67 67.24 67.24
LAB LABORER 2.00 2.00 MH 23.22 116.67 47.39 94.77
OPER OPERATOR(103) 2.00 2.00 MH 34.05 116.67 65.84 131.68
Activity: 06194 FG Seed>:t Sod Quantity: 46.83 Unit: SYS
Base Labor Burden Total Labor Equipment Perm Matis Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 4.43 2.85 7.28 2.32 0.00 0.00 0.00 0.00 0.00 0.00 9.60
Total 207.67 133.41 341.08 108.58 0.00 0.00 0.00 0.00 0.00 0.00 449.66
Crew$/Unit Crew Hrs/Unit Units/Crew Hr 5/Crew Hour Shifts Units/Shift Shifts/Unit 5/Shift
9.6020 0.0214 46.8300 449.6600 0.1000 468.3000 0.0021 4,496.6000
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
6.0000 7.8050 0.1281 56.8467 4.4346
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
it
Crew: AA0086 DOZER CREW Prod: UN 46.83 Eff: 100.00 Crew Hrs: 1.00 Labor Pcs: 6.00 Equipment Pcs:3.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8D-4 DOZER 85 HP(D4) 1.00 1.00 HR 36.15 100.00 36.87 36.87
8LSKD85 SKID STEER 85 HP 1.00 1.00 HR 58.23 100.00 59.39 59.39
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 1.00 HR 12.08 100.00 12.32 12.32
FOR FOREMAN 1.00 1.00 MN 35.05 116.67 67.24 67.24
LAB LABORER 3.00 3.00 MN 23.22 116.67 47.39 142.16
OPER OPERATOR(103) 2.00 2.00 MH 34.05 116.67 65.84 131.68
Biditem TEMPORARY INLET PROTECTION
6 Takeoff Qty:Bid Qty: 1.000 EACH
1.000 EACH
Activity: 57050 Temp Ditch Inlet Protection Quantity: i Unit: EACH
I
22.01436 16-ENG-69 Shelborne Rd. -Sedgemoor Circ 09/26/2018 2:23 PM Page 4 of 8
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
4EROS EROSION CONTROL SUB 1.00 1.00 EACH 100.00 100.00 100.00 100.00
Biditem SUBGRADE TREATMENT TYPE II
7 Takeoff Qty:Bid Qty: 88.000 SYS
88.000 SYS
Base Labor Burden Total Labor Equipment Perm Matls Const Malls Sub Trucking Bridge Asphalt Total
U.Cost 8.17 5.18 13.35 5.46 4.61 1.48 0.00 2.31 0.00 0.00 27.21
Total 719.06 455.70 1,174.76 480.43 406.00 130.00 0.00 203.00 0.00 0.00 2,394.19
Manhours Unit/MH MH/Unit $/MH Base Labor/MH Total Labor/MH Unit/CH
20.0000 4.4000 0.2273 119.7095 35.9530 58.7380 22.0000
Activity: 06641 SGT Type II /Excav 6" Quantity: 14.66 Unit: CYS
Base Labor Burden Total Labor Equipment Perm Malls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 24.52 15.54 40.07 17.41 0.00 8.87 0.00 13.85 0.00 0.00 80.20
Total 359.53 227.85 587.38 255.30 0.00 130.00 0.00 203.00 0.00 0.00 1,175.68
Crew S/Unit Crew Hrs/Unit Units/Crew Hr S/Crew Hour Shifts Units/Shift Shifts/Unit $/Shift
57.4816 0.1364 7.3300 421.3400 0.2000 73.3000 0.0136 5,878.4000
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
10.0000 1.4660 0.6821 58.7380 24.5246
Calendar:061 6 DAYS @ 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0083 CUT TO WASTE CREW Prod: UH 7.33 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 5.00 Equipment Pcs:3.00
Notes: Type I - 24 in. of soil compacted to density and moisture requirements.
Type TB - 14 in. chemical soil modification.
Type IC - 1_ in. of the suhgrade excavated and replaced with coarse aggregate. Na. 53.
Type II - 6 in. of the subgrade excavated and replaced with coarse aggregate Na. 53.
Type IIA - 8 in. chemical soil modification. 1
Type III - 6 in. of soil compacted to the density and moisture requirements.
Type IV - 12 in. of the subgrede excavated and replaced with coarse aggregate No. 53 on Type I3 geogrid.
Type v - 3 in. of subgrada excavated and replaced with 3 in. coarse aggregate No. 53.
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
3JDF01 DUMP FEE/TRI-AXLE#1 1.00 2.00 LOAD 65.00 100.00 65.00 130.00
5HTR10 TRUCKING 10 HOURS 1.00 2.00 HR 101.50 100.00 101.50 203.00
8D•4 DOZER 85 HP(D4) 1.00 2.00 HR 36.15 100.00 36.88 73.75
8EX320 EXCAVATOR 320/ 325 1.00 2.00 HR 76.91 100.00 78.46 156.91
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 2.00 HR 12.08 100.00 12.32 24.64
FOR FOREMAN 1.00 2.00 MH 35.05 116.67 67.24 134.48
LAB LABORER 2.00 4.00 MH 23.22 116.67 47.39 189.55
OPER OPERATOR(103) 2.00 4.00 MH 34.05 116.67 65.84 263.35
Activity: 06642 SGT Type II /Stone 6' Quantity: 29 Unit: TON
i
Base Labor Burden Total Labor Equipment Perm Matls Const Malls Sub Trucking Bridge Asphalt Total
U.Cost 12.40 7.86 20.25 7.76 14.00 0.00 0.00 0.00 0.00 0.00 42.02
Total 359.53 227.85 587.38 225.13 406.00 0.00 0.00 0.00 0.00 0.00 1,218.51
Crew S/Unit Crew Hrs/Unit Units/Crew Hr S/Crew Hour Shifts Units/Shift Shifts/Unit $/Shift
28.0176 0.0690 14.5000 406.2550 0.2000 145.0000 0.0069 6,092.5500
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
10.0000 2.9000 0.3448 58.7380 12.3976
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0084 GRADER CREW Prod: UH 14.5 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 5.00 Equipment Pcs: 3.00
Notes: r;pe I - 24 -... of call c<r;:.c=:c...ra t.. de,si:.; •er-.i MO is r i:te requiremenr .
.
22.0143B 16-ENG-69 Shelborne Rd. -Sedgemoor Circ 09/26/2018 2:23 PM Page 5 of 8
_....... Type ID - 14 in. chemical e,:ii modification.
Type IC - 12 in. of the subgrade excavated and replaced with coarse aggregate No. 5-
Type II - 6 in. of the subgrade excavated and replaced with coarse aggregate No. 51.
Type I<A - in. chemical soil modification.
Type III - in. of soil compacted to the density and moisture requirements.
Type IV - 12 in. of the subgrade excavated and replaced with coarse aggregate No. 53 on Type IS geogrid.
Type V - ., in. of subgrade excavated and repa.a:i 3 in. coarse aggrega7e Nc,. 53.
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
2AL2053 TYPE"0"tt53 1.00 29.00 TON 14.00 100.00 14.00 406.00
8D-4 DOZER 85 HP(D4) 1.00 2.00 HR 36.15 100.00 36.88 73.75
8RVG66 ROLLER VIBR GRADE 66" 1.00 2.00 HR 62.13 100.00 63.37 126.74
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 2.00 HR 12.08 100.00 12.32 24.64
FOR FOREMAN 1.00 2.00 MH 35.05 116.67 67.24 134.48
LAB LABORER 2.00 4.00 MH 23.22 116.67 47.39 189.55
OPER OPERATOR(103) 2.00 4.00 MH 34.05 116.67 65.84 263.35
Biditem STRUCTURE BACKFILL, TYPE I
11 Takeoff Qty: 9.000 CYS
Bid Qty: 9.000 CYS
Activity: 10220 Str Backfill,Type 1 Quantity: 9 Unit: CYS
Calendar:061 6 DAYS® 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
2AB1005 B-BORROW 1.00 18.00 TON 15.05 100.00 15.05 270.90
Biditem ASPHALT FOR TACK COAT
14 Takeoff Qty: 0.003 TON
Bid Qty: 0.003 TON
Activity: 33710 Tack Coat Quantity: 0.01 Unit: TON
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
ZLAE-T/T AE-T(TON) 1.00 0.01 TON 465.00 100.00 465.00 4.65
Notes: - ..
Biditem HMA FOR APPROACHES, TYPE C
1 6 Takeoff Qty:Bid Qty: 25.000 TON
25.000 TON
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 19.35 12.25 31.60 20.61 0.00 0.00 0.00 16.24 0.00 53.58 122.03
Total 483.64 306.24 789.88 515.28 0.00 0.00 0.00 406.00 0.00 1,339.47 3,050.63
Manhours Unit/MH MH/Unit S/MH Base Labor/MH Total Labor/MH Unit/CH
14.0000 1.7857 0.5600 217.9021 34.5457 56.4200 12.5000
Activity: 32392 HMA Int Type C 19.0 Quantity: 17 Unit: TON
Base Labor Burden Total Labor Equipment Penn Mats Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 14.22 9.01 23.23 15.16 0.00 0.00 0.00 11.94 0.00 49.63 99.96
Total 241.82 153.12 394.94 257.64 0.00 0.00 0.00 203.00 0.00 843.71 1,699.29
Crew 5/Unit Crew Hrs/Unit Units/Crew Hr S/Crew Hour Shifts Units/Shift Shifts/Unit 5/Shift
38.3871 0.0588 17.0000 652.5800 0.1000 170.0000 0.0059 16,992.9000
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
7.0000 2.4286 0.4118 56.4200 14.2247
22.0143B 16-ENG-69 Shelborne Rd. -Sedgemoor Circ 09/26/2018 2:23 PM Page 6 of 8
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0001 PAVING CREW W/1 ROLLER Prod: UH 17 Eff: 100.00 Crew Hrs: 1.00 Labor Pcs: 7.00 Equipment Pcs:4.00
Notes: TRUCKING by THE Ton (Long Methodl
INPUT COMPUTED
Total. Tons 66.00
Tons/Hr 17.00 4.00 Total Hours
Hours/Shift 10.00 0.40 Total Shifts
170.00 Tons/Shift
One Way Distance(Miles) 10.00 20.00 Miles/Round Trip
Average Speed in MPH 10.00 60.00 NaulTime!RndTr (Min)
Load Time in Min 10.00 70.59 rnnptlme- 20 Tons/Load
Dump Time in Min 70.59 140.53 TotTime/RndTr (Min)
Usable Min:Hr 50.00 0.36 RndTr,Loads/Hr/Truck
Tons/Truckload 20.00 3.40 Total Truckloads
2.39 Theor. No. of Trucks
Use Th1s Mc. of Trucks 2.39 9.56 Total Truck Hours
Price/Hr for Truck: 0..00 0.00 Tot Price - Trucking
Unit Price/Ton for Trucking
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
1A326116 HMA INTER,TYPE C, 19.0MM 1.00 17.00 TON 49.63 100.00 49.63 843.71
5HTR10 TRUCKING 10 HOURS 1.00 2.00 HR 101.50 100.00 101.50 203.00
8PAT10 PAVER ASPHALT 10'TRACK 1.00 1.00 HR 154.08 100.00 157.16 157.16
8R66H ROLLER VIBR 66"HF 1.00 1.00 HR 45.13 100.00 46.03 46.03
8TDSS TRKS DISTRIBUTOR 1.00 1.00 HR 41.30 100.00 42.13 42.13
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 1.00 HR 12.08 100.00 12.32 12.32
FOR FOREMAN 1.00 1.00 MH 35.05 116.67 67.24 67.24
LAB LABORER 3.00 3.00 MH 23.22 116.67 47.39 142.16
OPER OPERATOR(103) 2.00 2.00 MH 34.05 116.67 65.84 131.68
TM TEAMSTER 1.00 1.00 MH 28.41 116.67 53.86 53.86
Activity: 32592 HMA Surf Type C 9.5 Quantity: 8 Unit: TON
Base Labor Burden Total Labor Equipment Penn Matis Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 30.23 19.14 49.37 32.21 0.00 0.00 0.00 25.38 0.00 61.97 168.92
Total 241.82 153.12 394.94 257.64 0.00 0.00 0.00 203.00 0.00 495.76 1,351.34
Crew$/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit 5/Shift
81.5725 0.1250 8.0000 652.5800 0.1000 80.0000 0.0125 13,513.4000
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
7.0000 1.1429 0.8750 56.4200 30.2275
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0001 PAVING CREW W/t ROLLER Prod: UH 8 Eff: 100.00 Crew Hrs: 1.00 Labor Pcs: 7.00 Equipment Pcs:4.00
Notes: T0UCNING by THE Ton (Long MethedI
INPUT COMPUTED
Total Tons 37.00
Tons/Hr 9.25 4.00 Total Hours
Hours/Shift 10.00 0.40 Total Shifts
92.50 Tens/Ehift.
One Way Distance(Miles) 10.00 20.00 Miles/Round Trip
Average Speed in MPH _0.00 60.0+7 HaulTime/RndTr (Min)
Load Time in Min 10.30 1 7.7_ t5tptime- 20 Tens/Load
Dump Time in Mir: 127.73 3 TotTime/RndTr (Min)
Usable Mli.Hr. 50.VJ RndTr,Loads/HriTruck
Tons/Truckload 20.C2 Total Truckloads
Theot. Ho. of Trucks
Use This Nc. of Trucks 1.75 Total Truck Hours
Price/)ir for Trucks 0.00 .:'0 Tot Price - Trucking
..3 Unit Price/Ton for Truckinu
Resource Description PcsiWste Quantity Unit Unit Cost Tax/OT% Actual UC Total
1A326113 HMA SURF, TYPE C, 9.5MM 1.00 8.00 TON 61.97 100.00 61.97 495.76
5HTR10 TRUCKING 10 HOURS 1.00 2.00 HR 101.50 100.00 101.50 203.00
8PAT10 PAVER ASPHALT 10'TRACK 1.00 1.00 HR 154.08 100.00 157.16 157.16
8R66H ROLLER VIBR 66"HF 1.00 1.00 HR 45.13 100.00 46.03 46.03
8TDSS TRKS DISTRIBUTOR 1.00 1.00 HR 41.30 100.00 42.13 42.13
22.0143E 16-ENG-69 She(borne Rd. -Sedgemoor Circ 09/26/2018 2:23 PM Page 7 of 8
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 1.00 HR 12.08 100.00 12.32 12.32
FOR FOREMAN 1.00 1.00 MH 35.05 116.67 67.24 67.24
LAB LABORER 3.00 3.00 MH 23.22 116.67 47.39 142.16
OPER OPERATOR(103) 2.00 2.00 MH 34.05 116.67 65.84 131.68
TM TEAMSTER 1.00 1.00 MH 28.41 116.67 53.86 53.86
Biditem MAINTAINING TRAFFIC
38 Takeoff Qty: 1.000 LS
{}�[j Bid Qty: 1.000 LS
Manhours Unit/MH MH/Unit 5/MH Base Labor/MH Total Labor/MH Unit/CH
48.0000 0.0208 48.0000 47.3875 27.9035 47.3875 0.0417
Activity: 52615 Flagging I Quantity: 1 Unit: LS
Crew 5/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit 5/Shift
2,274.6000 24.0000 0.0417 94.7750 2.4000 0.4167 2.4000 947.7500
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
48.0000 0.0208 48.0000 47.3875 1,339.3700
Calendar:061 6 DAYS @ 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0031 FLAGGING CREW Prod: 0 Eff: 100.00 Crew Hrs: 24.00 Labor Pcs: 2.00 Equipment Pcs:0.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
LAB LABORER 2.00 48.00 MH 23.22 116.67 47.39 2,274.60
Biditem REMOVE Et SALVAGE BRICK PAVERS
41 Takeoff Qty: 88.000 SYS
Bid Qty: 88.000 SYS
Base Labor Burden Total Labor Equipment Perm Matis Const Matis Sub Trucking Bridge Asphalt Total
U.Cost 25.24 16.18 41.43 8.24 0.00 0.00 0.00 0.00 0.00 0.00 49.67
Total 2,221.51 1,424.12 3,645.63 724.93 0.00 0.00 0.00 0.00 0.00 0.00 4,370.56
Manhours Unit/MH MH/Unit 5/MH Base Labor/MH Total Labor/MH Unit/CH
64.0000 1.3750 0.7273 68.2900 34.7111 56.9630 5.5000
Activity: 05902 Remove a Salvage Brick Pavers Quantity: 88 Unit: SYS
Base Labor Burden Total Labor Equipment Perm Matis Const Matis Sub Trucking Bridge Asphalt Total
U.Cost 25.24 16.18 41.43 8.24 0.00 0.00 0.00 0.00 0.00 0.00 49.67
Total 2,221.51 1,424.12 3,645.63 724.93 0.00 0.00 0.00 0.00 0.00 0.00 4,370.56
Crew 5/Unit Crew Hrs/Unit Units/Crew Hr S/Crew Hour Shifts Units/Shift Shifts/Unit 5/Shift
49.6655 0.1818 5.5000 273.1600 1.6000 55.0000 0.0182 2,731.6000
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
64.0000 1.3750 0.7273 56.9630 25.2444
Calendar:061 6 DAYS®10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0091 REMOVAL CREW,SMALL Prod: UH 5.5 Eff: 100.00 Crew Hrs: 16.00 Labor Pcs: 4.00 Equipment Pcs:2.00
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
8L580 BACKHOE 580 1.00 16.00 HR 32.34 100.00 32.99 527.76
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 16.00 HR 12.08 100.00 12.32 197.17
FOR FOREMAN 1.00 16.00 MH 35.05 116.67 67.24 1,075.81
LAB LABORER 2.00 32.00 MH 23.22 116.67 47.39 1,516.40
OPER OPERATOR(103) 1.00 16.00 MH 34.05 116.67 65.84 1,053.42
22-0143B 16-ENG-69 Shelborne Rd. -Sedgemoor Circ 09/26/2018 2:23 PM Page 8 of 8
Biditem INLET, R13
42 Takeoff Qty: 1.000 EACH
Bid Qty: 1.000 EACH
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 539.29 341.79 881.08 542.51 2,570.00 0.00 0.00 0.00 0.00 0.00 3,993.59
Total 539.29 341.79 881.08 542.51 2.570.00 0.00 0.00 0.00 0.00 0.00 3,993.59
Manhours Unit/MH MH/Unit $/MH Base Labor/MH Total labor/MH Unit/CH
15.0000 0.0667 15.0000 266.2393 35.9527 58.7387 0.3333
Activity: 10390 R13 Inlet Quantity: 1 Unit: EACH
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
U.Cost 539.29 341.79 881.08 542.51 2,570.00 0.00 0.00 0.00 0.00 0.00 3,993.59
Total 539.29 341.79 881.08 542.51 2,570.00 0.00 0.00 0.00 0.00 0.00 3,993.59
Crew$/Unit Crew Hrs/Unit Units/Crew Hr $/Crew Hour Shifts Units/Shift Shifts/Unit 5/Shift
1,423.5900 3.0000 0.3333 474.5300 0.3000 3.3333 0.3000 13,311.9667
Manhours Unit/MH MH/Unit Total Labor/MH Base Labor/Unit
15.0000 0.0667 15.0000 58.7387 539.2900
Calendar:061 6 DAYS @ 10 HRS/EA Hrs/Shift:10 WC: 1 WC/GL
Crew: AA0062 PIPE CREW.MEDIUM!CAT 320 Prod: HU 3 Eff: 100.00 Crew Hrs: 3.00 Labor Pcs: 5.00 Equipment Pcs:4.00
Notes: Y. li" / TYPE 13 ASTIl
Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total
2AB1005 B-BORROW 1.00 5.00 TON 10.00 100.00 10.00 50.00
2CA CONCRETE CLASS"A" 1.00 2.00 CYS 110.00 100.00 110.00 220.00
2DC1013 CASTING TYPE 13(R-3360-A) 1.00 1.00 EACH 1,500.00 100.00 1,500.00 1,500.00
2DSI-R INLET TYPE R 1.00 1.00 EACH 800.00 100.00 800.00 800.00
8EX320 EXCAVATOR 320/ 325 1.00 3.00 HR 76.91 100.00 78.45 235.35
8L938 LOADER 938 1.00 3.00 HR 63.30 100.00 64.57 193.70
8TPU3/4 TRKS PICKUP 3/4 TON 1.00 3.00 HR 12.08 100.00 12.32 36.96
8TXBOX TRENCH BOX FOR PIPE 1.00 3.00 HR 25.00 100.00 25.50 76.50
FOR FOREMAN 1.00 3.00 MH 35.05 116.67 67.24 201.72
LAB LABORER 2.00 6.00 MH 23.22 116.67 47.39 284.32
OPER OPERATOR(103) 2.00 6.00 MH 34.05 116.67 65.84 395.04
Report Summary
Base Labor Burden Total Labor Equipment Perm Matls Const Matls Sub Trucking Bridge Asphalt Total
Total 5,964 3,866 9,831 2,780 3,252 472 300 711 0 1,339 18,685
Calendars Used In Estimate
061 6 DAYS @ 10 HRS/EA
040 5 DAYS @ 8 HRS/EA
MATERIAL 109.05(b)(3)
Purchased or
Manufactured Description Quantity Unit Unit Price Extension
S S -
S S -
S - S -
S S
$ S
$ S -
MATERIALS PURCHASED $0.00 (18)
MATERIALS MANUFACTURED $0.00 (19)
TOTAL: LINE(18)+(19) $0.00 (20)
12%x LINE(20) $0.00 (21)
GRAND TOTAL FOR MATERIALS:LINE(20)+(21) $0.00 (22)
EQUIPMENT 109.05(b)(4)
Equipment# CONTRACTOR OWNED EQUIPMENT FHWA HOURLY RATE HOURS EXTENSION
50.00 $0.00
30.00 S0.00
50.00 $0.00
S0.00 S0.00
50.00 $0.00
$0.00 $0.00
50.00 S0.00
50.00 $0.00
30.00 S0.00
Trucking-Strieghl Time S0.00 $0.00
Trucking-Over Time $0.00 $0.00
Trucking-Double Time $0.00 $0.00
TOTAL EQUIPMENT $0.00 (23)
TOTAL TRUCKING $0.00 (24)
FUEL,LUBRICANTS AND TRANSPORTATION COSTS $0.00 (25)
TOTAL LINES(23)•(24)+(25) $0.00 (26)
12%x LINE(26) $0.00 (27)
GRAND TOTAL FOR EQUIPMENT:LINES(26)+(27) $0.00 (28)
SUBCONTRACTORS 109.05(b)(6)
DESCRIPTION AMOUNT
Tri-State Forestry Services S7,500.00
TOTAL SUBCONTRACT WEEK ENDING $7,500.00 (29)
10%x LINE(30)S3,000.00ORLESS 8300.00 (31)
7%x LINE(30)OVER S3,003.00 $315.00 (32)
GRAND TOTAL FOR SUBCONTRACTORS:LINES(30)+(31)+(32) S8,115.00 (33)
TOTAL OF WORK COMPLETED FOR THE WEEK
TOTAL LINES(12).(17),(22).(28)8(33) $8,115.00 (34)
%OF BOND RATE BASED UPON LINE(34) $0.00 (35)
10%x LINE(35) $0.00 (36)
TOTAL EXTRA WORK LINES:(34)+(35)•(36) $8.115.00 (37)
Page 2 of 2
MATERIAL 109.05(b)(3)
Purchased or
Manufactured Description Quantity Unit Unit Price Extenstion
$ - $
$ - $
$ - s -
$
$ - S
$ $
MATERIALS PURCHASED $0.00 (IS)
MATERIALS MANUFACTURED $0.00 (19)
TOTAL: LINE(18)•(19) $0.00 (20)
12%x LINE(20) $0.00 (21)
GRAND TOTAL FOR MATERIALS:LINE(20)+(21) $0.00 (22)
EQUIPMENT 109.05(b)(4)
Equipment p CONTRACTOR OWNED EQUIPMENT FHWA HOURLY RATE HOURS EXTENSION
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 S0.00
$0.00 $0.00
$0.00 $0.00
$0.00 S0.00
Trucking-Striaght Time $0.00 $0.00
Trucking-Over Time $0.00 $0.00
Trucking-Double Time $0.00 MOO
TOTAL EQUIPMENT $0.00 (23)
TOTAL TRUCKING 50.00 (24)
FUEL.LUBRICANTS AND TRANSPORTATION COSTS $0.00 (25)
TOTAL LINES(23)•(24)+(25) $0.00 (26)
12%x LINE(26) $0.00 (27)
GRAND TOTAL FOR EQUIPMENT:LINES(28)+(27) $0.00 (28)
SUBCONTRACTORS 109.05(b)(6)
DESCRIPTION AMOUNT
CES Const Engineering 51,700.00
TOTAL SUBCONTRACT WEEK ENDING $1,700.00 (29)
10%x LINE(30)53.000.00 OR LESS $170.00 (31)
7%x LINE(30)OVER$3,000.00 $0.00 (32)
GRAND TOTAL FOR SUBCONTRACTORS:LINES(30)+(31)+(32) $1,870.00 (33)
TOTAL OF WORK COMPLETED FOR THE WEEK
TOTAL LINES(12).(17),(22),(28)8(33) $1,870.00 (34)
%OF BOND RATE BASED UPON LINE(34) $0.00 (35)
10%x LINE(35) $0.00 (36)
TOTAL EXTRA WORK LINES:(34)+(35)•(36) $1.870.00 (37)
Page 2 of 2
INDIANA DEPARTMENT OF TRANSPORTATION
PG 64-22 AVERAGE MONTHLY PRICE
* Binder Index (BI) * Binder Index (BI)
Year/Month Year/Month
(per ton or Mg) (per ton or Mg)
2013 2016
January $540.00 January $355.00
February $526.00 February $335.00
March $531.00 March $313.00
April $534.00 April $309.00
May $537.00 May $305.00
June $535.00 June $298.00
July $535.00 July $303.00
August $539.00 August $293.00
September $537.00 September $285.00
October $532.00 October $284.00
November $523.00 November _ $284.00
December $521.00 December $284.00
2014 2017
January $521.00 January $288.00
February $521.00 February $303.00
March $526.00 March $322.00
April $525.00 April $330.00
May $537.00 May $332.00
June $551.00 June $330.00
July $565.00 July $329.00
August $575.00 August $327.00
September $579.00 September $327.00
October $576.00 October $327.00
November $559.00 November $327.00 Bid price
December $547.00 December $330.00
2015 2018
January $517.00 January $340.00
February $481.00 February $347.00
March $456.00 March $364.00
April $446.00 April $379.00
May $443.00 May $405.00
June $442.00 June $444.00
July $442.00 July $480.00
August $440.00 August $510.00
September $430.00 September $512.00 Current Price
October $401.00 October
November $373.00 November
December $365.00 December
* The monthly PG asphalt binder index (BI) is determined by averaging the weekly selling
prices in Indiana as listed in the Poten &Partners Asphalt Weekly Monitor publication.
RIETH-RILEY CONSTRUCTION
EXTRA WORK AGREEMENT
DATE: 10/17/18 Work Performed: Add geogrid as needed
CONTRACT: 16-ENG-69 Shelborne Rd Multi. PROJECT: RR#--3200736
r-ORCE ACCOUNT/EXTRA WORK FOR:
Add geogrid as needed in areas where subgrade is soft.
LABOR 109.05(b)(1)
HOURS
EMPLOYEE Regular Overtime Doubletime TOTAL RATE EXTENSION
CARPENTER 0.00 $27.51 $0.00
CARPENTER FOREMAN 0.00 $29.01 $0.00
COMBINATION 0.00 $30.51 $0.00
FINISHER 0.00 $26.22 $0.00
FOREMAN 0.00 $35.80 $0.00
LABORER 2.00 2.00 $25.22 $50.44
MECHANIC 0.00 $35.80 $0.00
OPERATOR(103) 0.00 $34.80 $0.00
OPERATOR(841) 0.00 $33.25 $0.00
OPERATOR OILER(103) 0.00 $30.66 $0.00
OA TECH 0.00 $25.22 $0.00
SUPERINTENDENT/PROJECT MANAGER 0.00 $44.80 $0.00
TEAMSTER 0.00 $28.41 $0.00
TOTAL LABOR $50.44 (2)
FICA _ _ tt % x LINE(2) $3.78 (3)
FRINGES
EMPLOYEE HOURS RATE EXTENSION
CARPENTER 0.00 X $22.32 = $0.00
CARPENTER FOREMAN 0.00 X $22.32 = $0.00
COMBINATION 0.00 X $15.16 = $0.00
FINISHER 0.00 X $15.16 = $0.00
FOREMAN 0.00 x $18.41 = $0.00
LABORER 2.00 x $15.16 = $30.32
MECHANIC 0.00 X $18.41 = $0.00
OPERATOR(103) 0.00 X $18.41 = $0.00
OPERATOR(841) 0.00 X $21.36 = $0.00
OPERATOR OILER(103) 0.00 X $17.66 = $0.00
QA TECH 0.00 X $15.16 = $0.00
SUPERINTENDENT/PROJECT MAN 0.00 X $18.41 = $0.00
TEAMSTER 0.00 X $14.91 = $0.00
TOTAL FRINGES $30.32 (4)
WORKERS COMPENSATION % X LINE(2) $2.89 (5)
BODILY INJURY/PROPERTY DAMAGE INSURANCE ':'i"` % X LINE(2) $2.93 (6)
STATE UNEMPLOYMENT ' % X LINE(2) $1.94 (7)
FEDERAL UNEMPLOYMENT % X LINE(2) $0.20 (8)
TRAVEL ALLOWANCE OR SUBSISTENCE(NOTE#3) $0.00 (9)
TOTAL LINES 2,3.4,5,6,7,8&9 $92.50(10)
20%xLINE(10) $18.50(11)
GRAND TOTAL LABOR LINES(10)+(11) $111.00(12)
Page 1 of 2
10/17/2018 Add geogr)d as needed
MATERIAL 109.05(b)(3) RR#-3200736
FORGE-ACCOUN-T/EXTRA WORK FOR:
Add geogrid as needed
In areas where
subgrade is soft. Description Quantify Unit Unit Price Extenslan
P 72.00 SYS S 3.50 S 252.00
S - S -
S - S
S - S
S - S
S - S
MATERIALS PURCHASED $252.00 (18)
MATERIALS MANUFACTURED $0.00 (19)
TOTAL:LINE(18)•(19) $252.00 (20)
12%x LINE(20) $30.24 (21)
GRAND TOTAL FOR MATERIALS:LINE(20)•(21) $282.24 (22)
EQUIPMENT 109.05(b)(4)
Equipment 8 CONTRACTOR OWNED EQUIPMENT FHWA HOURLY RATE HOURS EXTENSION
50.00 $0.00
50.00 $0.00
S0.00 $0.00
S0.00 $0.00
$0.00 $0.00
S0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
Trucking-Striaght Time 50.00 $0.00
Trucking-Over Time $0.00 $0.00
Trucking-Double Time 50.00 $0.00
TOTAL EQUIPMENT $0.00 (23)
TOTAL TRUCKING $0.00 (24)
FUEL,LUBRICANTS AND TRANSPORTATION COSTS $0.00 (25)
TOTAL LINES(23)a(24)•(25) $0.00 (26)
12%x LINE(26) $0.00 (27)
GRAND TOTAL FOR EQUIPMENT:LINES(26)•(27) $0.00 (28)
SUBCONTRACTORS 109.05(b)(6)
DESCRIPTION AMOUNT
TOTAL SUBCONTRACT WEEK ENDING $0.00 (29)
10%x LINE(30)53,000.00 OR LESS $0.00 (31)
7%x LINE(30)OVER 53,000.00 $0.00 (32)
GRAND TOTAL FOR SUBCONTRACTORS:LINES(30)•(31)•(32) $0.00 (33)
TOTAL OF WORK COMPLETED FOR THE WEEK
TOTAL LINES(12),(17),(22).(28)&(33) S393.24 (34)
% BOND RATE BASED UPON LINE(34) $0.00 (35)
10%a LINE(35) $0.00 (36)
TOTAL EXTRA WORK LINES:(34)•(35)+(36) $393.24 (37)
Page 2 of 2
D2 D2 Land & Water Resource, Inc. INVOICE
2600 Bloyd Ave
Date Invoice#
Indianapolis, IN
Land 6 Water 10/29/2018 62048
Resource
Bill To Ship To
Rieth-Riley Construction-I Rieth-Riley Construction-I
1751 West Minnesota Gary Davis 317-402-8373
P.O. Box 276 On Shelbourne Road between 106th and 116
Indianapolis, IN 46206 Carmel, IN
USA USA
P.O. Number Terms Rep Ship Via S.O. No. Due Date
3205170 Net 30 JMB 10/29/2018 Direct-Ship 40450 11/28/2018
Quantity Item Code Description Price Each Amount
2,163 FB_Item CON-AF400-Contech Armorflex Class 40 Block,Open Cell- 7.62556 16,494.08T
Note:Articulated Concrete Block-ArmorFlex 40 MAT-Cable
Type:Polyester,Armortec Fabric Included,Shipped to Site,
Spreader Bar Rental included for 1 Week
Build per approved drawings
Sales Tax 0.00% 0.00
Returns of inventory items are subject to a Restock Fee of up to 50%.
Custom and Non-inventory items may not be returned for credit.Payment Total $16,494.08
is due on receipt unless a credit account has been previously established.
Remit To: Payments/Credits $0.00
D2 Land&Water Resource,Inc Phone:317-917-2180
PO Box 20792 Fax:317-917-2181
Indianapolis,IN 46220 Email:accounting@d2lwr.com Balance Due $16,494.08
i UTILITY PIPE SALES OF IN, INC. Invoice
11° 'U`JTILITY 11802 N Green River Road
Evansville IN 47725
317)
—11 PEIP SALES (317)224 230100fax
Number IN072829
"Providing Tho Flow. abovo& Below" Website: www.utilitypipesales.com
Page . 1
Date 06/28/2018
• „Bill Rieth-Riley Construction,Co.` .;`Ship SHELBORNE RD MULTI USE PATH
To PO Box 276 •.'To 16-ENG-69
RRCONST Indianapolis IN 46206 RRCONST 106TH ST TO 116TH ST
CARMEL, IN
Customer PO# 'Ship Date •Salesperson Terms Tax Code " •
16-ENG-69 06/20/2018 VINCE REDDING Net 30 Days INGOV
Document# : , ; •' Warehouse . Freight Ship Via
00069684 UTILITY PIPE SALES OF IN, INC. Prepaid BEST WAY
Item/Description • Ordered Shipped i ,Backorder uM Price Per Extension
N-CAR4984 36 36 0 EA 100.00 EA 3,600.00
24"X 24" DET. WARNING PLATE
TRUNCATED DOME PLATE
TX801 P 1 1 0 EA 486.91 EA 486.91
80Z NW RIPRAP FABRIC
INDOT, 500 SQ YD, 15'X300'
DP8N 220 220 0 FT 4.00 FT 880.00
8"DUAL WALL SOLID X 20'
CMPES8 4 4 0 EA 100.00 EA 400.00
8"CMP END SECTION
CMP121620 20 20 0 EA 8.95 EA 179.00
12" 16GA CORR METAL PIPE X 20'
CMPESI2 1 1 0 EA 85.00 EA 85.00
12"CMP END SECTION
CMESI2TP 1 1 0 EA 40.00 EA 40.00
12"CMP TOE PLATE INDOT
CAR4215C 5 5 0 EA 225.00 EA 1,125.00
R-4215-C CONVEX GRATE
INDOT TYPE 7
•
06f01115-INVOICES WILL NO LONGER BE MAILED.
PROVIDE PAYABLES EMAIL ADDRESS TO
�1111I11�!H�!��1111 I III!II!I!HI!I II!H 11111 HI I! II 11111 II! III
IN IN072829
Customer Copy Continued on next page ...