HomeMy WebLinkAboutRieth-Riley/Eng/CO #4/-447.98/96th and Delegates Row RAB – Project #16-ENG-33 City of Carmel Project 16- ENG-33 96th Street and Delegate Row RAB 01 CHANGE ORDER #4- CONSTRUCTION CHANGE 1 With future sidewalk to be constructed on the south side of the RAB at Delegates Row as part of the Keystone project.Construction Change 1 -Revision 2 was released to incorporate a drainage revision that installs a trench drain at the curb turn out location Sta. 36+01, with a pedestrian suited grate crossing the sidewalk. It was determined that the costs associated with the trench drain, Geotextiles, and Riprap Revetment items will be tracked as Time&Material and included in a separate change order once the work is completed. Also,as part of Construction Change 1, Str 111 a Mod. C7 Manhole is being replaced with an E7 Inlet.There are also some minor quantity adjustments to existing pay items included with this change. This Change Order 4 will result in a decrease of-$447.98 to the project. Contract Price prior to this Change Order $1,483,378.49 Contract Price will be increased/decreased by this Change Order ($447.98) New Contract Price including this Change Order $1,483,378.49 Amount Adjusted Contract Cumulative%Change Price from Original Contract Original Contract $1,480,798.49 $1,480,798.49 N/A CO1— In-Line BMP $2,580.00 $1,483,378.49 0.17% Storm Water Bond CO2—Wood Mortgage $0.00 $1,483,378.49 0.17 % Add Insured General Oblig. Bond CO3—CDG & $0.00 $1,483,378.49 0.17 % Precedent Add Insured General Oblig. Bond C04—Const. Chng. 1 ($447.98) $1,482,930.51 0.14% Storm Water Bond CITY OF CARMEL TO: CONTRACT CHANGE ORDER NO.: 4 Chris Ogg DATE: 3/24/2019 One Civic Square PROJECT NAME: 16-ENG-33 Cannel, IN 46032 CITY REQ.NO.: N/A CITY PO NO.: 100569—2016 Storm Water Bond CITY PO DATE: 7/15/17 I. You are directed to make the following changes in this Contract: (Brief Description) With future sidewalk to be constructed on the south side of the RAB at Delegates Row as part of the Keystone project. Construction Change 1 —Revision 2 was released to incorporate a drainage revision that installs a trench drain at the curb turn out location Sta.36+01,with a pedestrian suited grate crossing the sidewalk. It was determined that the costs associated with the trench drain, Geotextiles, and Riprap Revetment items will be tracked as Time & Material and included in a separate change order once the work is completed. Also, a's part of Construction Change 1, Str 111 a Mod. C7 Manhole is being replaced with an E7 Inlet. There are also some minor quantity adjustments to existing pay items included with this change. This Change Order 4 will result in a decrease of-$447.98 to the project. SCHEDULED ADJUSTMENT ITEM AMOUNT (+) OR(-) DAYS 56—Structure Backfill ,Type 1 6 CYD x $25.74= $154.44 0 47—Pipe, Type 4, Circ. , 6 IN 3 LFT x$5.50= $ 16.50 0 48—Pipe, Type 2, Circ. , 12 IN 1 LFT x $50.59 = $50.59 0 52—Video Inspection For Pipe 1 LFT x$1.28=$1.28 0 56—Aggregate for Underdrains (4 CYD x$45.10=$180.40) 0 57—Geotextile for Underdrains (21 SYS x$1.75 =$36.75) 0 111 —Manhole, C7,Mod (1.0 EA x$ $2,738.75 =$2,738.75) 0 112—Inlet, E7 1.0 EA x$2,285.11 =$2,285.11 0 II. The following referenced Documents further describe the changes outlined in Paragraph I,and are to be considered a part of this Change Order: R.F.P.: N/A W.D.C. No.: N/A Other: The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $ 1,483,378.49 Contract Price will be increased/decreased by this Change Order $_ -447.98 AR-6 Version 2016-08-31 New Contract Price including this Change Order $ 1.482.930.51 Contract Time Prior to this Change Order 74 Days 10/13/17 Completion Date Net increased/decreased resulting from this Change Order 0 Days Current Contract Time including this Change Order 74 Days 10/13/17 Completion Date This Change Order is for full and final settlement of all direct. indirect. impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are The Above Changes Are A proved: Recommended Accepted: CHA Rieth-Riley Construction ri 17,n ` ENGINEER CONTRACTOR jets Br ard, i yor 300 S. Meridian Street 1751 W. Minnesota Street Address Address Nlar n u•- er Indianapolis, IN 46225 Indianapolis, IN 46221 Lori n. Mertlber City/State/Zip City/State/Zip Jere sh an. City ineer r . Byro - C1 y.__ v v l , a Phone: ' i7-401 • 31tr0 Nene•. ' ' 6/ Kristine S. P-auley, Clerk- Treasurer . /�j,7hr Date: 4iZi 1 Date: c_.5 e Date: �f AR-6 Version 2016-08-3I RjETHRILEY CONSTRUCTION CO. INC. 100% Quality • 100% Employee Owned • Over 100 Years March 4`h, 2019 Brian Andres CHA Consulting, Inc. Sent Via Email: bandres@chacompanies.com 300 S. Meridian Street Union Station Indianapolis, IN 46225 RE: 96th Street at Delegates Row Construction Change No.1-REV(3/18/2019) Brian, The following documentation is for Construction Change No.1,this proposal includes pricing for Items 112 & 113. Included in this pricing is all the labor, equipment, and materials necessary to complete the work.The following is a pricing breakdown: ITEM NO. ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST 11 LFT $ 674:50 $ 7,419.49 112 113 Inlet, E7 1 EA $ 2,285.11 $ 2,285.11 If you have any questions regarding this change order proposal, please let me know. Thanks, Note: (Tyler Oeeph The added Trench Drain item associated with Construction Tyler Joseph Change 1 was agreed to be tracked as T&M due to pricing Project Manager differences and will not be included in this change order. An Rieth-Riley Construction Co., Inc. additional change order for the Trench Drain will be generated Cell: (419)-966-4890 when the work is completed. P.O. Box 276 •1751 W. Minnesota St.•Indianapolis, IN 46206 / Phone: (317) 634-5561 • www.rieth-riley.com RIETH-RILEY CONSTRUCTION EXTRA WORK AGREEMENT DATE: 3/4/19 Work Performed: Construction Change#1 CONTRACT: 16-ENG-33 PROJECT: 96th Street @ Delegates Row FORCE ACCOU T/EXTRA WORK FOR: Item 112:Trench Drain LABOR 109.05(b)(1) HOURS EMPLOYEE Regular Overtime Doubletime TOTAL RATE EXTENSION CARPENTER 0.00 $2 . 1 $0.00 CARPENTER FOREMAN 0.00 '9.01 $0.00 COMBINATION 0.00 $31.26 $0.00 FINISHER 0.00 $26.77 $0.00 FOREMAN 0.00 $37.80 $0.00 LABORER 0.00 $25.77 $0.00 MECHANIC 0.00 $37.80 $0.00 OPERATOR(103) 0..4 $36.80 $0.00 OPERATOR(841) '.00 _ $34.00 $0.00 OPERATOR OILER(103) 0.00 $31.91 $0.00 QA TECH 0.00 $25.77 $0.00 SUPERINTENDENT/PROJECT MANAGER 0.00 $46.80 $0.00 TEAMSTER 0.00 $29.96 $0.00 TOTAL LABOR $0.00 (2) FICA 7.50 % x LINE(2) $0.00 (3) FRINGES EMPLOYEE •URS RATE EXTENSION CARPENTER 0.00 x $22.32 = $0.00 CARPENTER FOREMAN 0.00 X $22.32 = $0.00 COMBINATION 0.00 X $16.14 = $0.00 FINISHER 0.00 X '.15.86 = $0.00 FOREMAN 0.00 X I. :.71 = $0.00 LABORER 0.00 X $1' :• = $0.00 MECHANIC 0.00 X $18. = $0.00 OPERATOR(103) 0.00 X $18.71 = $0.00 OPERATOR(84 0.00 X $21.36 = $0.00 OPERATOR• ER(103) 0.00 X $18.71 = $0.00 QA TECH 0.00 x $15.86 $0.00 SUPERI ENDENT/PROJECT MAN 0.00 X $18.71 = $0.00 TEAM- ER 0.00 X $15.62 = $0.00 TOTAL FRINGES $0.00 (4) WORKERS OMPENSATION 5.72 % X LINE(2) $0.00 (5) BODILY 'JURY/PROPERTY DAMAGE INSURANCE 5.80 % X LINE(2) $0.00 (6) STAT" UNEMPLOYMENT 3.55 % X LINE(2) $0.00 (7) F-FERAL UNEMPLOYMENT 0.4O % X LINE(2) $0.00 (8) TRAVEL ALLOWANCE OR SUBSISTENCE(NOTE#3) $0.10 (9) TOTAL LINES 2,3,4,5,6,7,8&9 $0.09 10) 20%x LINE(10) $0.00 GRAND TOTAL LABOR LINES(10)+(11) $0.00 (12) Page 1 of 2 MATERIAL 109.05(b)(3) Purcha •or Manufact -d Descnption Quantity Unit Unit Pnce Extenstion $ - $ $ - $ $ - $ $ - $ $ - $ $ - $ MATERIALS PURCHASED $0.•• (18) MATERIALS MANUFACTURED $0.00 (19) TOTAL LINE(18)+(19) $0.00 (20) 12%xLINE(20) $0.00 (21) GRAND TOTAL FOR MATERIALS:LINE(20)+(21) $0.00 (22) EQUIPMENT 109.05(b)(4) Equipment# CONTRACTOR OWNED EQUIPMEN FHWA HOURLY RATE HOURS EXTENSION $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 5.00 $0.00 $0.•9 $0.00 $0.00 $0.00 Trucking-Stnaght Time $0.00 $0.00 Trucking-Over Time $0.00 $0.00 Trucking-Double Time $0.00 $0.00 TOTAL EQUIPMENT $0.00 (23) TOTAL TRUCKIN• $0.00 (24) FUEL LUBRIC• 'TS AND TRANSPOR ION COSTS $0.00 (25) TOTAL LINE' 23)+(24)+(25) $0.00 (26) 12%x LI .(26) $0.00 (27) GRAND •TAL FOR EQUIPMENT LINES(26) 7) $0.00 (28) SUBCONTRACTORS 109.05(b)(6) DESCRIPTION • OUNT Item 112:Trench Dr. $6,767.09 TOTAL SUBCO '•CT WEEK ENDING $6,767.09 9) 10%x LINE( • $3,000.00 OR LESS $300.00 (3 7%x LINE •r)OVER$3,000.00 $263.70 (32) GRAND •TAL FOR SUBCONTRACTORS:LINES(30)+(31)+(32) $7,330.79 (33) TOTAL OF WORK COMPLETED FOR THE WEEK TOTAL LINES(12),(17),(22),(28)&(33) $7,330.79 (34) 1.1 %OF BOND RATE BASED UPON LINE(34) $80.64 (35) 10%x LINE(35) $8.06 (36) TOTAL EXTRA WORK LINES:(34)+(35)+(36) $7,419.49 (37) Page 2 of 2 RIETH-RILEY CONSTRUCTION EXTRA WORK AGREEMENT DATE: 3/4/19 Work Performed: Construction Change#1 CONTRACT: 16-ENG-33 PROJECT: 96th Street @ Delegates Row FORCE ACCOUNT/EXTRA WORK FOR: Item 113: Inlet, E7 LABOR 109.05(b)(1) HOURS EMPLOYEE Regular Overtime Doubletime TOTAL RATE EXTENSION CARPENTER 0.00 $27.51 $0.00 CARPENTER FOREMAN 0.00 $29.01 $0.00 COMBINATION 0.00 $31.26 $0.00 FINISHER 0.00 $26.77 $0.00 FOREMAN 0.00 $37.80 $0.00 LABORER 0.00 $25.77 $0.00 MECHANIC 0.00 $37.80 $0.00 OPERATOR(103) 0.00 $36.80 $0.00 OPERATOR(841) 0.00 $34.00 $0.00 OPERATOR OILER(103) 0.00 $31.91 $0.00 QA TECH 0.00 $25.77 $0.00 SUPERINTENDENT/PROJECT MANAGER 0.00 $46.80 $0.00 TEAMSTER 0.00 $29.96 $0.00 TOTAL LABOR $0.00 (2) FICA 7.50 % x LINE(2) $0.00 (3) FRINGES EMPLOYEE HOURS RATE EXTENSION CARPENTER 0.00 X $22.32 = $0.00 CARPENTER FOREMAN 0.00 X $22.32 = $0.00 COMBINATION 0.00 X $16.14 = $0.00 FINISHER 0.00 X $15.86 = $0.00 FOREMAN 0.00 X $18.71 = $0.00 LABORER 0.00 X $15.86 = $0.00 MECHANIC 0.00 X $18.71 = $0.00 OPERATOR(103) 0.00 X $18.71 = $0.00 OPERATOR(841) 0.00 X $21.36 = $0.00 OPERATOR OILER(103) 0.00 X $18.71 = $0.00 QA TECH 0.00 x $15.86 = $0.00 SUPERINTENDENT/PROJECT MAN 0.00 X $18.71 = $0.00 TEAMSTER 0.00 X $15.62 = $0.00 TOTAL FRINGES $0.00 (4) WORKERS COMPENSATION 5.72 % X LINE(2) $0.00 (5) BODILY INJURY/PROPERTY DAMAGE INSURANCE 5.80 % X LINE(2) $0.00 (6) STATE UNEMPLOYMENT 3.85 % X LINE(2) $0.00 (7) FEDERAL UNEMPLOYMENT 0.40 % X LINE(2) $0.00 (8) TRAVEL ALLOWANCE OR SUBSISTENCE(NOTE#3) $0.00 (9) TOTAL LINES 2,3,4,5,6,7,8&9 $0.00 (10) 20%x LINE(10) $0.00 (11) GRAND TOTAL LABOR LINES(10)+(11) $0.00 (12) Page 1 of 2 MATERIAL 109.05(b)(3) Purchased or Manufactured Descnption Quantity Unit Unit Price Extenstion $ - $ $ - $ $ - $ $ - $ $ - $ $ - $ MATERIALS PURCHASED $0.00 (18) MATERIALS MANUFACTURED $0.00 (19) TOTAL: LINE(18)+(19) $0.00 (20) 12%x LINE(20) $0.00 (21) GRAND TOTAL FOR MATERIALS:LINE(20)+(21) $0.00 (22) EQUIPMENT 109.05(b)(4) Equipment# CONTRACTOR OWNED EQUIPMENT FHWA HOURLY RATE HOURS EXTENSION $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 S0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Trucking-Stnaght Time $0.00 $0.00 Trucking-Over Time $0.00 $0.00 Trucking-Double Time $0.00 $0.00 TOTAL EQUIPMENT $0.00 (23) TOTAL TRUCKING $0.00 (24) FUEL LUBRICANTS AND TRANSPORTATION COSTS $0.00 (25) TOTAL LINES(23)+(24)+(25) $0.00 (26) 12%x LINE(26) $0.00 (27) GRAND TOTAL FOR EQUIPMENT:LINES(26)+(27) $0.00 (28) SUBCONTRACTORS 109.05(b)(6) DESCRIPTION AMOUNT Item 113:Inlet,E7 $2,052.54 4 TOTAL SUBCONTRACT WEEK ENDING $2,052.54 (29) 10%x LINE(30)$3,000.00 OR LESS $205.25 (31) 7%x LINE(30)OVER$3,000.00 $0.00 (32) GRAND TOTAL FOR SUBCONTRACTORS:LINES(30)+(31)+(32) $2,257.79 (33) TOTAL OF WORK COMPLETED FOR THE WEEK TOTAL LINES(12),(17),(22).(28)8(33) $2,257.79 (34) 1.1 %OF BOND RATE BASED UPON LINE(34) $24.84 (35) 10%x LINE(35) $2.48 (36) TOTAL EXTRA WORK LINES:(34)+(35)+(36) $2,285.11 (37) Page 2 of 2 (,,EGRADIDC 3/18/2019 9:40 AM FAMILY OWNED SINCE 1973 16-ENG-33 96TH&DELEGATES ROW Rieth-Riley Recapitulation of Costs Construction Change#1 Added Items Description Quantity Units Labor Total Equipment Total Materials Total Subs Total 113-Inlet,E7(REV 3.18.19) 1.00 EA $ 333.92 $ 167.35 $ 1,307.50 Subtotal $ 333.92 $ 167.35 $ 1,307.50 $- - Allowable Markup 20% $ 66.78 12% $ 20.08 12% $ 156.90 10% $ - Subtotal $ 400.70 $ 187.43 $ 1,464.40 $ - Unit Cost 2,052.54 /EA 1 of 1 41 o% tal dV*—X FAMILY OWNED SINCE 1973 3/4/2019 8:OlAM 16-ENG-33 96T• : DELEGATES ROW Rieth-Riley Recapitulation of Costs Construction Change#1 Added Item Description Quantity Units Labor Total Equipment Total terials Total Subs Total 112-Trench Drain 11.00 LF $ 1,836.57 $ 921.55 $ 3,152.79 Subtotal $ 1,836.57 $ 1.55 $ 3,152.79 $ - Allowable Markup 20% $ 367.31 12% $ 110.59 12% $ 378.33 10% $ - Subtotal $ 2,203.88 $ 1,032.14 $ 3,531.12 $ - Unit Cost $ 615.19 /LF 1 of 2 Cost Report Gradex Inc. 7 Mark Wilson Page 1 of 2 231-1 CC#1 Added Items 03/04/2019 7: ' AM Bidite • TRENCH DRAIN 112 Takeoff Qty: 11.000 LF Clien -: 720-07309 Bid Qty: 11.000 LF Base Burden Total Labor Equipment Perm Mats Canst Mats Sub rucking Total U.Cost 101.47 65.49 166.96 83.78 286.62 0.00 0.00 0.00 537.36 Total 1,116.13 '8.44 1,836.57 921.55 3,152.79 0.00 a.11 0.00 5,910.91 Manhours Unit/ 1 MHNnk SAW Base •• Total Labor/MH Unit/CH 33.0000 0.3333 3.0000 179.1185 .8221 55.6536 2.0000 Activity: 067971 Trench Drain (Unreviewed) Quantity: 11 Unit: LF Base Labor Burden Total Labor Equipment Perm Mats Canst Mats Sub Trucking Total U.Cost 101.47 65.49 166.96 83.78 28. • 0.00 0.00 0.00 537.36 Total 1,116.13 720.44 1,836.57 9 55 3 .79 0.00 0.00 0.00 5,910.91 Crew Stink Crew Firs/Unit Units/Crwv Hr S/Crew : Shifts Units/Shift Shifts/Unit S/Shift 250.7382 0.5000 2.0000 50 .476- 0.5500 20.0000 0.0500 10,747.1091 Manhours Unit/MH k Total Labor/MH Base Labor/Link 33.0000 0.3 3.:100 55.6536 101.4664 Calendar:60 10 HR 6 DAY Hrs/ ift: 10 WC: N6306 Sewer Construction Crew: PC50 PIPE-336 EXCAVATOR -rod: US 20 Eff: 100.00 Crew Hrs: 5.50 Labor Pcs: 6.00 Equipment Pcs:2.00 Resource Description Pcs/Wste Quantity Unit Unit Cast Tax/OT% Actual UC Total 2CCLA Class A Concr= - 1.00 1.65 CY 125.00 1 b' 00 125.00 206.25 2SXTD Trench D n 1.00 6.00 EA 491.09 100.t. 491.09 2,946.54 8E40 336 avator 1.00 5.50 HR 92.40 100.00 92.40 508.20 8EHP Pac 0.25 1.38 HR 182.00 100.00 82.00 251.16 8LW4 930 Loader 0.75 4.13 HR 39.27 100.00 3. 7 162.19 FM Foreman 1.00 5.50 MH 35.65 116.67 67.4 370.79 LG General Laborer 2.00 11.00 MH 23.92 116.67 45.95 505.45 Pipe Laborer 1.00 5.50 MH 24.95 116.67 47.29 260.09 OP Operator 2.00 11.00 MH 32.75 116.67 63.66 00.24 Biditem INLET, E7 113 Takeoff Qty: 1.000 EA Client#: 720-45030 Bid Qty: 1.000 EA Base Labor Burden Total Labor Equipment Perm Mats Const Mats Sub Trucking Total U.Cost 405.86 261.98 667.84 334.71 1,307.50 0.00 0.00 0.00 2,310.05 Total 405.86 261.98 667.84 334.71 1,307.50 0.00 0.00 0.00 2,310.05 Manhours Unit/MH MH/Unit S/MH Base Labor/MH Total Labor/MH Unit/CH 12.0000 0.0833 12.0000 192.5042 33.8217 55.6533 0.5000 Activity: 067211 Inlet. 0-6' IUnreviewedl Quantity: 1 Unit: EA Base Labor Burden Total Labor Equipment Perm Mats Cant Mats Sub Trucking Total u.Cost 405.86 261.98 667.84 334.71 1,307.50 0.00 0.00 0.00 2,310.05 Total 405.86 261.98 667.84 334.71 1,307.50 0.00 0.00 0.00 2,310.05 Crew S/Unit Crew Hrs Unit Units/Crew Hr S/Crew Hour Shifts Units/Shift Shifts/Unit S/Shift 1,002.5500 2.0000 0.5000 501.2750 0.2000 5.0000 0.2000 11,550.2500 Manhours Unit/MH Ai/Unit Total Labor/MH Base Labor/Unit 12.0000 0.0833 12.0000 55.6533 405.8600 17231-1 CC#1 Added Items 03/04/2019 7:50 AM Page 2 of 2 Calendar:60 10 HR 6 DAY Hrs/Shift:10 WC: IN6306 Sewer Construction Crew: PC50 PIPE-336 EXCAVATOR Prod: HU 2 Eff: 100.00 Crew Hrs: 2.00 Labor Pcs: 6.00 Equipment Pcs:2.00 Resource Description Pcs/Wste Quantity Unit Unit Cost Tax/OT% Actual UC Total 2AGG08 No. 8 Stone 1.00 1.00 TN 20.00 100.00 20.00 20.00 2CCLA Class A Concrete 1.00 1.50 CY 125.00 100.00 125.00 187.50 2SCSTM Storm Casting 1.00 1.00 EA 500.00 100.00 500.00 500.00 2SXIN Inlet 1.00 1.00 EA 600.00 100.00 600.00 600.00 8E40 336 Excavator 1.00 2.00 HR 92.40 100.00 92.40 184.80 8EHP Hoe Pac 0.25 0.50 HR 182.00 100.00 182.00 91.00 8LW4 930 Loader 0.75 1.50 HR 39.27 100.00 39.27 58.91 FM Foreman 1.00 2.00 MH 35.65 116.67 67.42 134.83 LG General Laborer 2.00 4.00 MH 23.92 116.67 45.95 183.80 LP Pipe Laborer 1.00 2.00 MH 24.95 116.67 47.29 94.58 OP Operator 2.00 4.00 MH 32.75 116.67 63.66 254.63 Report Summary Base Labor Burden Total Labor Equipment Perm Math Const MatIs Sub Trucking Total Total 1,522 982 2,504 1,256 4,460 0 0 0 8,221 Job Notes Estimate created on:03/04/2019 by User#: 7-Mark Wilson Source estimate used:T:\HEAVYBID\EST\GRADEX Calendars Used In Estimate 60 10 HR 6 DAY