HomeMy WebLinkAboutSmock Fansler/Eng/CO #3/3,270/Gray Road Improvements – Project #16-ENG-16 CITY OF CARMEL
TO: Jeremy Kashman CONTRACT CHANGE ORDER NO: 3
City Engineer DATE: 5-6-19
City of Carmel PROJECT NAME:Gray Rd 16-ENG-16.54,55
One Civic Square CITY REQ. NO:
Carmel, IN 46032 CITY PO NO:
CITY PO DATE:
I. You are directed to make the following changes in this Contract: 4qR°tit,
Additional large tree removal and stump grinding at easternmost property along new
Masonry wall at 1260'& Gray �C1t
ITEM AMOUNT SCHEDULED ADJUSTMENT
f+)OR(-)DAYS
II. The following referenced documents further describe the changes outlined in paragraph I,
and are to be considered a part of this Change Order R.F.P.: W.D.C. NO:
Other: See contract change request No.003
The changes result in the following adjustment of Contract Price and Contract Time:
Contract price prior to this change order $861..360.50
Contract price will be increased/decreased by this Change Order $3.270.00
New Contract Price including this Change Order $864,630.50
Contract Time prior to this Change Order Days Completion Date
Net increased/decreased resulting from this Change Order Days
Current Contract Time including this Change Order Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and
Time extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are The Above Changes Are Approved
Recommended Accepted L
Dan Greskamp Smock Fansler 61 4 1 - V `ll —
ENGINEER CONTRACTOR ames Brainard, Mayor
One Civic Square 2910 W. Minnesota St.
ADDRESS ADDRESS ere • - •:n, gine
Carmel, IN 46032 Indpls, IN 46241 //______ ir
City/Stat /Zip City/State/Zip Ma • Burke, r. ber
By: By: �
Dan Gre m e Davee V.P. tori Wat-:(, Member
Phone: 3/7--7/4- ✓6 Phone: 3t7`tyi.'-s31 f . -61i •
/ • �Date: 5 9//9 Date: ���( ��q Ch stine Pauley,Clerk-Treasurer
I?-OQc
CITY OF CARMEL
TO: City of Carmel CONTRACT CHANGE REQUEST NO.: 003
Engineering Department DATE: April 25, 2018
One Civic square PROJECT NAME: 16-ENG-16,54,55 Gray Road Roundabouts
Carmel, IN 46032
FROM:
IT IS REQUESTED THAT A CONTRACT CHANGE BE MADE TO THE ABOVE
REFERENCED CONTRACT.
I. SCOPE OF WORK(USE ADDITIONAL PAGES IF REQUIRED. ALSO LIST OTHER
CONTRACTS INVOLVED.)
Additional large tree removal and stump grinding at easternmost
property along new Masonry Wall at 126th & Gray
2. REASON FOR CHANGE:
Resident at this property made arrangements with the City to remove one large pine
tree and grind down the stump.
3. APPROXIMATE COST CHANGE TO CONTRACT PRICE: Add $3,270.00
4. WILL THE CONTRACT NEED ADDITIONAL CONTRACT TIME TO COMPLETE
THE CHANGE IN WORK SCOPE? -YES X -NO -(CALENDAR
DAYS)
5. WILL THE CONTRACTOR NEED ADDITIONAL PERSONNEL TO COMPLETE THE
CHANGE IN WORK SCOPE? x -YES -NO
IF NO,TRADE(S): Tree Removal Subcontractor
NO. OF PERSONNEL: 3
DURATION: 1 day each for removal and stump grinding
6. IDENTIFICATION OF ATTACHMENTS:
DATE: DATE:
PREPARED
REVIEWED BY: Smock Fansler REVIEWED BY:
ENGINEER
Comments and Recommendation:
AR-5