HomeMy WebLinkAboutA000 Cover SheetGENERAL PROJECT NOTES
I. EACH CONTRACTOR SHALL BECOME COMPLETELY FAMILIAR WITH ALL ASPECTS
OF THE WORK, EVEN THOSE AREAS DESIGNATED TO BE PROVIDED BY OTHERS, THIS
FAMILIARIZATION INCLUDES FULL AND COMPLETE UNDERSTANDING OF THE WORK
DESCRIBED ON ALL SHEETS OF THE DRAWINGS. FAILURE BY THE CONTRACTOR TO
BECOME COMPLETELY FAMILIAR OF ALL ASPECTS OF THE WORK SHALL NOT RELIEVE
THE CONTRACTOR OF THE RESPONSIBILITY TO PROVIDE MATERIALS, ASSEMBLIES, OR
SERVICES INDICATED IN THE CONTRACT DOCUMENTS.
2. ALL WORK SHALL COMPLY WITH THE REQUIREMENTS OF ALL APPLICABLE STATE
AND LOCAL BUILDING CODES. CONTRACTORS ARE RESPONSIBLE FOR VERIFYING
THE CURRENT APPLICABLE BUILDING CODES) FOR THEIR RESPECTIVE SCOPE OF
WORK. ALWAYS ABIDE BY THE MOST RESTRICTIVE CODE.
3. FIELD VERIFY ALL EXISTING CONDITIONS AND MEASUREMENTS INDICATED ON THE
DRAWINGS AND REPORT ANY DISCREPANCY THROUGH THE GENERAL CONTRACTOR
TO PARALLEL DESIGN GROUP BEFORE BEGINNING ANY CONSTRUCTION.
4. THE GENERAL CONTRACTOR SHALL COORDINATE WITH THE OWNER REGARDING
ALL ON -SITE ACTIVITIES: SUCH AS, BUT NOT LIMITED TO, WORK SCHEDULE, MATERIALS
STORAGE AND HANDLING, DELIVERIES, ACCESS TO THE WORKSITE, TRAFFIC
CONTROL, AND BUILDING/PUBLIC SAFETY PROCEDURES DURING CONSTRUCTION.
THE CONTRACTOR SHALL ALSO COORDINATE WORK BY OTHERS" WITH HIS/HER OWN
ACTIVITIES AS NECESSARY TO EXECUTE THE OVERALL PROJECT SCOPE.
5. GENERAL CONTRACTOR TO REVIEW DOCUMENTS IN DETAIL AN D COMMUNICATE
ANY ITEMS THAT MAY REQUIRE LEAD TIMES. CONTRACTOR TO COORDINATE
PROJECT SCHEDULE ACCORDINGLY AND COMMUNICATE TO TEAM ANY DECISIONS
THAT NEED TO BE MADE TO KEEP PROJECTSCHEDULE ON TRACK. CONTRACTOR IS
RESPONSIBLE FOR DELAYS WHEN LEAD TIMES ARE NOT PROPERLY COMMUNICATED
TO OWNER AND PARALLEL DESIGN GROUP.
6. NO SUBSTITUTIONS FOR SPECIFICALLY NAMED PRODUCTS/MATERIALS WILL BE
ALLOWED WITHOUT PRIOR APPROVAL FROM PARALLEL DESIGN GROUP. PRODUCT
CHANGE SUBMITTALS SHOULD BE COMMUNICATED TO PARALLEL DESIGN GROUP
ALLOWING ADEQUATE TIME TO RESPOND.
7. CONTACT THE DESIGNER IMMEDIATELY IF, IN THE FIELD, CONFLICTS ARE
DISCOVERED BETWEEN COMPONENTS OF DIFFERENT SYSTEMS THAT PREVENT THE
INSTALLATION OF THOSE COMPONENTS AS INDICATED ON THE DRAWINGS. (I.E.
WHERE EXISTING MECHANICAL DUCTWORK MAY PREVENT THE INSTALLATION OF
LIGHTING FIXTURES AS INDICATED ON THE CEILING PLAN).
8. SHOP DRAWINGS OR CATALOG CUTS MUST BE SUBMITTED TO PARALLEL DESIGN
GROUP FOR APPROVAL ON ALL MATERIALS/PRODUCTS IF THE DRAWINGS DO NOT
INDICATE A SPECIFIC MANUFACTURER OR MODEL N UMBER.
9. PROVIDE SUBMITTAL SHOP DRAWINGS INA TIMELY FASHION TO ALLOW SUFFICIENT
TIME FOR CHECKING, APPROVAL, ORDERING, FABRICATION, AND DELIVERY OF
MATERIALS AND EQUIPMENT.
10. ALL MATERIAL AND EQUIPMENT OF INDUSTRY STANDARD QUALITY SPECIFIED OR
NOT, AND WITH THE LIMITATION OF THE CONTRACT DOCUMENTS TO CAUSE THE
INSTALLATION TO FUNCTION IN ACCORDANCE WITH THE INTENTION AND OBJECTIVE
OF THE FINISHED PROJECT.
11. EACH CONTRACTOR SHALL FULLY REVIEW DRAWING SHEETS TO FULLY
UNDERSTAND NEW WORK AND EXISTING CONDITIONS TO DETERMINE FULL EXTENT OF
RESPONSIBILITIES FOR EACH RESPECTIVE TRADE IN ADDITION TO COORDINATING FULL
EXTENT OF RESPONSIBILITIES WITH ALL OTHER TRADES. FIELD WORK ORDERS &
CHANGE ORDERS WILL NOT BE APPROVED FOR ANY CONDITIONS OR CONFLICTS
THAT COULD HAVE BEEN ACCOUNTED FOR BY THE BIDDER DURING PRE -BID FIELD
INSPECTION AND AFTER AWARD OF CONTRACT.
12. THE GENERAL CONTRACTOR IS REQUIRED TO PATCH AND REPAIR ANY
DAMAGED EXISTING SURFACES TO MATCH NEW.
13. WHEN REQUIRED BY STATE BUILDING CODE, THE CONTRACTOR(S) SHALL
PROVIDE DESIGN/BUILD DRAWINGS FOR MECHANICAL, PLUMBING, ELECTRICAL, OR
FIRE SUPPRESSION. DRAWINGS SHALL BE CERTIFIED BY A LICENSED ENGINEER AND
SUBMITTED BY THE CONTRACTOR FOR STATE DESIGN REVIEW.
14. ALL EQUIPMENT, MATERIALS AND/OR FIXTURES SHALL BE INSTALLED IN STRICT
ACCORDANCE WITH THE MANUFACTURER'S RECOMMENDATIONS OR INSTRUCTIONS.
15. EXECUTE A THOROUGH FINAL CLEAN AND INSPECTION OF THE SPACE UPON
COMPLETION OF THE PROJECT. ALL SURFACES, FIXTURES, AND EQUIPMENTSHALL BE
CLEAN, AND THE SPACE SHALL BE TURNED OVER TO THE OWNER IN A CONDITION
THAT REPRESENTS THE HIGHEST LEVEL OF CARE AND PROFESSIONALISM. ENSURE ALL
GENERAL CONTRACTOR INSTALLED APPLIANCES WORK & DO NOT LEAK.
16, PROVIDE TO THE OWNER ALL OPERATION AND/OR MAINTENANCE MANUALS, OR
INSTRUCTIONS FOR ALL EQUIPMENT AND SYSTEMS AT THE COMPLETION OF THE
PROJECT.
17. DO NOT SCALE DRAWINGS. DIMENSIONS GOVERN. ALL DIMENSIONS ARE FROM
FINISHED FACE OF WALL TO FINISHED FACE OF WALL.
18. CONTRACTOR TO PROVIDE AN ALLOWANCE FOR CLEANING EXISTING WINDOW
BLINDS,
19. THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING THE
REQUIREMENTS REGARDING LOCAL PLAN REVIEW, PERMITS, INSPECTIONS, AND FEES
THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR SUBMITTING ALL REQUIRED
DRAWINGS AND SUPPORTING DOCUMENTS TO THE LOCAL BUILDING OFFICIAL
AND/OR PERMIT DEPARTMENT. ALL REQUIRED LOCAL PERMIT FEES SHALL BE PAID BY
THE GENERAL CONTRACTOR UNLESS STIPULATED OTHERWISE IN THE
OWNER/CONTRACTOR AGREEMENT.
20. NOTE REGARDING PROJECTS WITHIN MARION COUNTY: LOCAL ORDINANCE
REQUIRES ONE SET OF CONSTRUCTION DRAWINGS FOR CLASS I STRUCTURES, THAT
ARE DESIGNED WITH A FIRE PROTECTION AND LIFE SAFETY SYSTEMS (I.E. FIRE ALARMS),
BE SUBMITTED TO THE INDIANAPOLIS FIRE DEPARTMENT (ED) FOR THE PURPOSE OF
CONDUCTING A FIRE DEPARTMENT PLAN REVIEW AND ONSITEINSPECTIONS,
DRAWING SET SHOULD INCLUDE ARCH, STRUCT, MECH, ELEC, SPRINKLER, FIRE
ALARM, AND SITE/CIVIL(WHERE APPLICABLE). DRAWINGS MAYBE DELIVERED OR
MAILED TO THE ED PLAN REVIEW DIVISION (1200 MADISON AVENUE, INDIANAPOLIS,
IN 46225, ATTENTION: T.J. BURNS). INCLUDE THE DMD STRUCTURAL PERMIT NUMBER
(STR-XXXXXX) WITH THE DRAWING SET. THE GENERAL CONTRACTOR SHALL BE
RESPONSIBLE FOR COORDINATING THE SUBMISSION OF THESE DRAWINGS AND THE
REQUIRED FEE TO THE ED PLAN REVIEW DIVISION. CONTACT THE ED WITH QUESTIONS
REGARDING THIS REQUIREMENT (317-327-5529).
RELEASED FOR CONSTRUCTION
Subject to compliance with all regulations
of State and Local Codes
City Df Camel
DATE: 06/25/19
FINISH NOTES
I. ALL MATERIALS TO BE DELIVERED IN THEIR ORIGINAL PACKAGING WITH
MANUFACTURER'S LABELS. CONTRACTOR WILL BE RESPONSIBLE FOR RECEIVING,
STORING AND PROTECTING MATERIALS FROM ANY DAMAGE BY MOISTURE, WIND.
SUN ABUSE, OR ANY HARMFUL EFFECTS, DAMAGED MATERIALS WILL BE REJECTED
AND MUST BE REPLACED BY THE CONTRACTOR.
2. REMOVE ALL PLATES AND SWITCHES BEFORE PAINTING AND REATTACH
AFTERWARDS.
3. ALL REMAINING PAINT (I GALLON MINIMUM) TO BE LEFT WITH THE OWNER
4. WALLCOVERING SHALL BE FROM THE SAME PRODUCTION RUN.
5. DO NOT LOCATE WALLCOVERING SEAMS ON CORNERS. WRAP 6"BEYOND INSIDE
OR OUTSIDE CORNERS AS INDICATED ON THE FINISH PLAN WHERE CHANGE OF
WALLCOVERING LOCATION OCCURS.
6. CONTRACTOR TO REMOVE EXCESS ADHESIVE IMMEDIATEDLY FROM SURFACE OR
WALLCOVERING AS EACH JOINT OR SEAM 15 MADE AND BEFORE PROCEEDING TO
THE NEXT JOINT OR SEAM.
7. ALL WALLCOVERING SEAMS ARE TO BE CUT STRAIGHT. ASSURE INSTALLATION IS
SECURE, SMOOTH, CLEAN, AND WITHOUT WRINKLES, BUBBLES, GAPS, AND/OR
OVERLAPS.
S. FOR ALL NEW DRYWALL INSTALLATIONS, INSTALL AS RECOMMENDED BY THE
GYPSUM ASSOCIATION. (SUCH AS, CONTROL JOINTS, FINISH LEVELS, FASTENERS
TAPING DETAILS, CORNER BEADS, ETC.(
9. TRANSITION OF DIFFERENT FLOORING MATERIALS SHALL OCCUR AT THE
CENTERLINE OF THE DOOR.
10. CONTRACTOR TO PROVIDE AND INSTALL TRANSITION STRIP BETWEEN DISSIMILAR
FLOORING MATERIALS. TRANSITION STRIP IS TO BE SCHLUTER OR EQUAL WITH
BRUSHED ALUMINUM FINISH OR IS TO BE VINYL AND MATCH VINYL BASE COLOR (I.E.:
WHERE VCi MEETS CARPET). CONTRACTOR TO DETERMINE TYPE OF SCHLUTER STRIP
BASED ON DISSIMILAR FLOORING MATERIALS. CONTRACTOR TO VERIFY TYPE OF
TRANSITION WITH PARALLEL DESIGN, IF NOT NOTED, PRIOR TO PLACING ORDER.
11. SUBFLOOR MUST BE LEVEL SOUND. RIGID, CLEAN/FREE OF ANY DEBRIS, AND
PERMANENTLY DRY PRI OR TO INSTALLATION. THE INSTALLATION OF FINISH FLOORING
MATERIALS SHALL SERVE AS ACCEPTANCE OF SLAB CONDITION.
12. FLOORING MATERIALS SHALL BE FROM THE SAME PRODUCTION RUN.
13. CONTRACTOR SHALL REPAIR, REF) NISH OR TOUCH-UP 5U RFACES DAMAGED BY
SUBSEQUENT WORK. (EXAMPLE: WHERE NEW OUTLETS/FIXTURES HAVE BEEN
INSTALLED.)
14. LOW VOC CONTENT PAINT AND ADHESIVES TO BE USED THROUGHOUT PROJECT
15. REVIEW AND ABIDE BY ALL MANUFACTURER INSTALLATION INSTRUCTIONS PRIOR
TO INSTALLATION OF FINISH MATERIALS, MANUFACTURER RECOMMENDED
ADHESIVES/SEALANTS TO BE USED.
16. UPON COMPLETION OF ALL FINISH APPLICATIONS, ALL MATERIALS AND
EQUIPMENT SHALL BE REMOVED. CONTRACTOR SHALL INSURE THAT ALL AREAS ARE
LEFT CLEAN AND DAMAGE FREE.
17. ANY VARIATION IN PATTERN, TEXTURE, COLOR OR ANY OTHER DEFECT SHOULD
BE BROUGHT TO THE ATTENTION OF PARALLEL DESIGN GROUP FOR DIRECTION AND
APPROVAL.
MECHANICAL &
ELECTRICAL NOTES
I. POWER AND COMMUNICATION PLAN IS TO SHOW ELECTRICAL, VOICE/DATA
RECEPTACLES AND TV LOCATIONS. ELECTRICAL CONTRACTOR TO FIELD VERIFY
LOAD CAPACITIES AND AVAILABILITY. PARALLEL DESIGN GROUP AND THEIR
ARCHITECT ARE NOT RESPONSIBLE FOR ANY MECHANICAL OR ELECTRICAL
ENGINEERING.
2. REFLECTED CEILING PLAN IS TO SHOW LIGHT FIXTURE, DIFFUSER AND SWITCH
LOCATIONSONLY. PARALLEL DESIGN GROUP AND THEIR ARCHITECT ARE NOT
RESPONSIBLE FOR ANY MECHANICAL OR ELECTRICAL ENGINEERING.
3. ELECTRICAL CONTRACTOR RESPONSIBLE FOR RELOCATION AND/OR ADDITION OF
HORN STROBES, FIRE ALARM STATIONS AND EXIST SIGNS AS REQUIRED BY CODE.
4. VERIFY IF ANY SPECIAL EQUIPMENT WILL REQUIRE ADDITIONAL AIR FLOW.
PROVIDE ADDITIONAL HVAC REQUIREMENTS AFTER APPROVAL FROM TENANT.
REVISE ZONING AS NEEDED.
5. PLUMBING, FIRE SUPPRESSION, AND FIRE ALARM SYSTEMS SHALL BE DESIGNED
AND INSTALLED BY THE RESPECTIVE DESIGN/BUILD CONTRACTORS PER AGREEMENT
W ITHTHEOWNER. ALL TRADES SHALL DESIGN AND INSTALL THEIR RESPECTIVE
SYSTEMS IN ACCORDANCE WITH ALL APPLICABLE STATE AND LOCAL BUILDING
CODES. COORDINATE WITH THE ARCHITECT IF ADDITIONAL INFORMATION IS
REQUIRED IN ORDER TO DO THE WORK IN THE FIELD, PARALLEL DESIGN GROUP AND
THEIR ARCHITECT ARE NOT RESPONSIBLE FOR ANY ENGINEERING OF THESE SYSTEMS.
6. COORDINATE CIRCUITRY REQUIREMENTS FOR FURNITURE SYSTEMS WITH TENANT,
BEFORE RUNNING WIRING TO JUNCTION BOXES,
7. CENTER I N CEI LI NG TI LES RECESS ED DOWN LIGHTS, SMO KE DETECTORS, S PRI N KLER
HEADS. AND EXIT SI GNS, UNLESS OTHERWISE NOTED.
8. REVIEW FIRE DETECTION DEVICE LOCATIONS WITH TENANT PRIOR TO
INSTALLATION.
9. THE DESIGN/BUILD CONTRACTOR SHALL COMPLY WITH THE INDIANA BUILDING
CODE, THE IN DIANA FIRE CODE, AND ALL OTHER APPLICABLE LAWS, CODES, RULES
AND REGULATIONS THAT APPLY TO DESIGN AN D INSTALLATION OF FIRE
SPRIN KLER/FIRE SUPPRESSION SYSTEMS.
10. PROVIDE NEW OR RELOCATE EXISTING SPRINKLER HEADS AS REQUIRED. PROVIDE
MISSING COVER/ESCUTCHEON PLATES FOR SPRINKLER HEADS WHERE APPLICABLE.
FIELD VERIFY EXISTING CONDITIONS PRIOR TO THE START OF WORK.
11. THE FIRE PROTECTION CONTRACTOR SHALL GENERATE ALL REQUIRED
DRAWINGS, AND SHALL FILE THOSE DRAWINGS, AND RELATED DOCUMENTS, WITH
THE STATE AN D LOCAL AUTHORITIES HAVING JURISDICTION OVER THE PROJECT.
DEMOLITION NOTES
I. ALL EXISTING EQUIPMENT. FIXTURES. ETC. SHALL REMAIN PROPERTY OF THE OWNER
ALL REUSABLE ITEMS SALVAGED DURING DEMOLITION SHALL BE RETAINED FOR THE
OWNER'S INSPECTION. ONLY ITEMS SO INSPECTED AND REJECTED BY THE OWNER
SHALL BE DISPOSED.
2. CONTRACTOR TO VISIT SITE TO BECOME FAMILIAR WITH EXISTING CONDITIONS,
DEMOLITION DRAWINGS ARE A REFERENCE TO AID CONTRACTOR IN EVALUATION
OF THE EXTENT OF THE DEMOLITION, BUT SHALL NOT BE CONSIDERED ALL INCLUSIVE.
CONTRACTOR TO FIELD VERIFY ALL EXISTING CONDITIONS, DIMENSIONS, ETC.
REFERENCE NEW CONSTRUCTION DRAWINGS TO DETERMINE THE FULL EXTENT OF
NECESSARY DEMOLITION.
3. NO STRUCTURAL OR LOAD -BEARING CONSTRUCTION SHALL BE REMOVED,
DEMOLISHED, OR DAMAGED AS A RESULT OF THIS PROJECT UNLESS SPECIFICALLY
NOTED OTHERWISE ON THE DRAWINGS. THE CONTRACTOR SHALL VERIFY IN THE
FIELD, PRIOR TO DEMOLITION, THAT ALL ITEMS NOTED TO BE DEMOLISHED ARE NOT
STRUCTURAL, CONTACT PARALLEL DESIGN GROUP IMMEDIATELY IF THE
CONTRACTORS) IN THE FIELD SUSPECTTHAT AN ITEM NOTED FOR DEMOLITION
APPEARS TO BE STRUCTURAL OR OTHERWISE LOAD -BEARING. THE CONTRACTOR IS
SOLELY RESPONSIBLE FOR INADVERTENT DAMAGE TO THE BUILDING STRUCTURAL
SYSTEM.
4. EACH TRADE CONTRACTOR IS RESPONSIBLE FOR ALL DEMOLITION WORK
REQUIRED OR NOTED FOR THE INSTALLATION OF THE NEW WORK,
5. EACH TRADE CONTRACTOR IS RESPONSIBLE TO REFER TO NEW CONSTRUCTION
DRAWINGS FOR ADDITIONAL PATCHING AND PREPARATION WORK RELATED TO THE
DEMOLITION ITEMS.
6. WHERE EQUIPMENT,FIXTURES, OR FINISHES ARE MOVED FROM ANY OTHER PART
OF THE BUILDING TO BE REUSED IN THE PROJECT AREA, THE CONTRACTOR SHALL
INCLUDE IN THEIR SCOPE OF WORK ANY NECESSARY PATCHING OR REPAIRING OF
THE REMAINING AREAS FROM WHERE THE ITEMS WERE RELOCATED, UNLESS
OTHERWISE DIRECTED BY OWNER.
7. CHECK EXISTING FLOOR LEVEL BEFORE INSTALLATION OF NEW FLOORING.
PREPARE FLOOR WITH CEMENTITIOUS LEVELING COMPOUND PRIOR TO INSTALLATION
OF NEW FLOOR FINISH AS REQUIRED TO MAINTAIN LEVEL.
S. REMOVE ALL ITEMS ASSOCTIATED WITH DEMOLISHED WALL IF NOT NOTED OR
SHOWN OTHERWISE. SALVAGE ANY ITEMS IS GOOD CONDITION FOR REUSE IN NEW
CONSTRUCTION, e.g., OUTLETS.
9. THE CONTRACTOR IS RESPONSIBLE FOR THE PROTECTION OF ALL EXISTING
SURFACES, MATERIALS, COMPONENTS, ETC. TO REMAIN OR BE RELOCATED. ANY
DAMAGE TO THESE RESULTING FROM PERFORMANCE OF WORK SHALL BE REPAIRED
BY THE CONTRACTOR TO THE SATISFACTION OF THE OWNER AND PARALLEL DESIGN
GROUP AT NO ADDITIONAL EXPENSE TO THE OWNER.
10. COMPLY WITH ALL APPLICABLE LOCAL, STATE AND FEDERAL CODES AND
REGULATIONS. ALWAYS ABIDE BY THE MOST RESTRICTIVE CODE.
11. THE CONTRACTOR SHALL PROVIDE TEMPORARY DUST PROTECTION AS REQUIRED
BY THE OWNER TO PREVENT CONSTRUCTION DEBRIS AN D DUST FROM MIGRATING
OUT OF THE PROJECT AREA. THE OWNER SHALL CONFIRM ALL DUST PREVENTION
MEASURES/LOCATIONS, AN D SHALL DETERMINE ANY CHANGES TO THESE MEASURES.
12. REMOVE DUST AND DEBRIS FROM NEWLY EXPOSED SURFACES
13. CONTRACTOR TO PROVIDE AN "AS-BUILTSET INDICATING THE LOCATION OF ALL
PERMANENTLY ABANDONED SYSTEMS.
14. GENERAL CONTRACTOR TO PROVIDE RECYCLING COSTS TO THE BUILDING
OWNER/LANDLORD ON ALL ITEMS BEING DEMOLISHED, SUCH A5, METAL STUDS,
DRYWALL, CARPEL CEILING TILES, DOORS,GLASS, AND CABINETRY.
L.M. HENDERSON
CONSTRUCTION DOCUMENTS
450 EAST 96TH STREET, SUITE 200
INDIANAPOLIS, INDIANA 46240
KEY PLAN
NOT TO SCALE
DRAWING INDEX
COVER SHEET A000
DEMOLITION PLAN DI00
FLOOR PLAN AI00
DIMENSION PLAN
DOOR SCHEDULE
POWER IF DATA PLAN A200
FINISH SPECIFICATIONS MOO
FINISH PLAN
INTERIOR ELEVATIONS
PROJECT TEAM
INTERIOR DESIGNER
PARALLEL DESIGN GROUP
BRIANA DUNKIN
8801 RIVER CROSSING BLVD.
SUITE 140
INDIANAPOLIS, IN 46240
PH 317.308.9617
bricnc@perclleldg.com
APPROVAL FOR CONSTRUCTION
THE TENANT I CLIENT AGREES THAT THESE DRAWINGS AN D SPECIFICATIONS REPRESENT
THE ENTIRE SCOPE OF WORK FOR THE IMPROVEMENTS TO BE PROVIDED. THE
TENANT I CLIENT'S SIGNATURE BELOW REPRESENTS ACCEPTANCE OF THE FINAL
DESIGN. ANY CHANGES TO THIS SCOPE OF WORK INITIATED BY THE TENANT I CLIENT
WILL CAUSE CHANGES IN THE TOTAL COST TO THE TENANT I CLIENT AND IN THE
COMPLETION DATE FOR THE PROJECT.
TENANT I CLIENT REPRESENTATIVE SIGNATURE DATE
TENANT CLIENT REPRESENTATIVE NAME PRINTED
<"s
a1uzru St S
G
a""
a
°navLama
�.
Rx..v
LIZ
TRAY 4i
LOS
�Vammund llRU 1465
wcu R scan
BE
E WAR D
f
f
S ? D
_ 'a
a
l'
Y
=
p
E915F 51 E91561
VICINITY MAP
NOT TO SCALE
I
0
ce o
j}p -v3
B
W
S
z
O
z
O
w
U
3
AnED
U
WO
O
❑
U
m
W
W
N
h
0
MOOR
N
m
m
m
z N
r R,
GC DO
W p
G
Ca N
LAL
V f0
w p
N
CDO
Z
0
0
Net
N
�
`
LU
QInf6
0 mRRRR
Y
tovC
Z
LU
(d �n O
= WLm
0 l{{
c!f
w:RMID
5•
C
J
COVER SHEET
A000
ALL DESIGNS CONCERTS,ARRAnGEMENTSM) PUNS
INDICATED OR REPRESENTED BYTxESE DRAWINGS ARE
OWNED BY PARALLEL DESIGN GROUP INC AND SHALL
NOT BE USED BY OR DISCLOSED TO ANY PERSON, FIRM
OR CORP. FOR ANY REASON WHATSOEVER WHOUTTHE
WR17EN CONSENT OF PARALLEL DESIGN GROUP INC.
CONTRACTORS SHALL VERRYANO BE RESPONSIBLE FOR
ALL DIMENSIONS ON THE FOR SITE PARALLEL DESIGN
GROUPING MUST BE NOTIFIED OF MY DISCREPANCIES
OR VARIANTIOINS FROM THE DIMENSIONS SHOWN ON THE
PUN