HomeMy WebLinkAboutGN2Frame Check Basement FC CM Post plumb and tabs wrapped around the top FC CM Post locations are correct, point loads from above in floor system installed FC CM Beam is bearing in pocket at least 3 inches FC CM Squash block are in place from over beam if there is a load bearing wall above. FC CM No visible gaps in basement rim board FC CM Floor joist laid out per print, LVL beans if needed are located in correct location. FC CM Look for nails that have missed the joist and remove them FC CM Joist hangers are secure with correct nails and joist are glued FC CM Straps at bottom plate secured with 2 nails each strap on top and spaced 12 inches from plate ends and corners 6 feet on center. FC CM Basement is clean no debris FC CM Basement stairs are shimmed ½ inch from wall. There are no visible nails from top through stringer. All nails are driven through 2x from under stairs. 3 Nails per step. FC CM Stair Head height is correct. At minimum 6’8 inches in a plane diagonal line to stair header plumb. FC CM Nosing not at top of stairs at first floor but is present and basement landing if stair case has a landing FC CM Basement wall at basement landing is furred out with 2x material and wall is covered with insulation board or house wrap. This depends on the space available. FC CM Unfinished basement stair walls have 2x4 stud’s 16 inch OC on all 3 sides to close accessibility FC CM Basement wall secured to floor with concrete nails and walls are plumb. Finished Basement FC CM Door opening plumb and marked with 2 inch over call size of door 2 inches taller FC CM 2x4 studs 16 inches OC treated bottom plate FC CM Drywall nailers present in in corners and at ceiling FC CM All unfinished space must have a door opening into the area. FC CM Bulkheads build shall be no lower than 7’ 1 inch from concrete floor. FC CM Fire block weed cap above framed wall filling gap to bottom of joists. Daylight Walkout Basement FC CM To the bottom of a daylight window there in not more than 42 inches to the opening. FC CM 100% braced sheathing used. Wall must meet bracing requirements of 2008 IRC. This means consideration for full 4 foot sheets. Wall cannot be all windows. Proper nailing pattern of braced sheathing. FC CM Sill sealer is located under exterior walls. Walls are bolted per the 2008 IRC 12” plate ends 6 ‘OC FC CM Any stud distance from concerate wall & each step wall face will need to have concrete wall insulation installed. Exterior FC CM All horizontal seams flashed with house wrap a minimum of 6 inches hanging out FC CM Holes and cuts in sheathing repair by tape or damaged sheathing replaced FC CM Window tape install on 3 sides, 2 sides first and top last. Top must be even past the sides. No tape or sealer on bottom. FC CM Over hangs on home correct per print. Eyebrows installed per print FC CM Windows correct per print and are in alignment FC CM Exterior trim to be installed no closer to a shingled roof than 1 inch. Account for shingle thickness FC CM All trim installed has the vertical ran past the horizontal at the intersections. FC CM All horizontal smart trim used in board and batten style application must be installed prior to MDF board and have drip cap installed over the horizontal 5/4 trim board. Board batten panel is to be installed between the horizontals with ¾ trim over MDF to create the vertical. FC CM Azeck trim installed at under doors on basement homes FC CM 1x2 trim installed at horizontal brick transitions FC CM Window mantles install with Ice and water behind. Ice and water to extend 6 inches past sides and top and is taped at top FC CM House wrap install with overlaps of 6 inches horizontal and vertical FC CM Vertical seams of house wrap need taped with correct brand seathing tape FC CM House warp install on all inside & outside corners FC CM House wrap install with cap nails no more that 32inch square FC CM Raptor roof paper installed professionally verticle laps are to be a minimum of 4 inches, horizontal laps 6 inches, cap nails at seams 12 inches OC 24 inch cap nails on seams. FC CM Raptor paper to be installed to create a valley that sheds water by laps FC CM Roofer to install roof edge under raptor at eaves and over paper gables. Plan nail placement accordingly FC CM Roof less than 4/12 must have 2 layers of felt. FC CM Exterior door trim to be taped as windows. FC CM Exterior doors to be sat on rubber membrane that drapes to the exterior FC CM Rubber membrane to be installed so after concrete is poured it will be between the concrete and the house FC CM Gutter overhang or porch tiding back to verticle wall should have Ice & Water installed @ transition. Notes: 04/17/19 Adam Schriner