HomeMy WebLinkAboutRieth-Riley/Eng/CO 34/25,702.57/96th and Gray Road RAB – Project #16-ENG-34 City of Carmel Project 16-ENG-34 96th Street and Gray Road RAB41-z t CHANGE ORDER #4- CONSTRUCTION CHANGE 2 The changes included as part of Construction Change#2 Revision#2 are to revise the Maintenance of Traffic to add left turn access in Phase 1 B to properties west of Gray Road and right turn access in Phase 2A to properties east of Gray Road. Sign locations have been revised to be outside the limits of the future multi-use path/sidewalk as well. Pavement markings have been revised to not conflict with future crosswalk markings for multi-use path/sidewalk. No new items were added due to this change only adjustments to existing pay items. This Change Order#4 will result in an increase of$25,702.57 to the project. Contract Price prior to this Change Order $1,600,645.22 Contract Price will be increased/decreased by this Change Order $25,702,57 New Contract Price including this Change Order $1,626,347.79 Amount Adjusted Contract Cumulative%Change Price from Original Contract Original Contract $1,597,055.37 $1,597,055.37 N/A CO1—MM Add Insured $0.00 $1,597,055.37 (0.0%) General Oblig. Bond CO 2—In-Line BMP $2,580.00 $1,599,635.37 0.16% Storm Water Bond CO3—Const. Change 1 $1,009.85 $1,600,645.22 0.22% Storm Water Bond CO 4—Const. Change 2 $25,702.57 $1,626,347.79 1.83% General Oblig. Bond CITY OF CARMEL TO: CONTRACT CHANGE ORDER NO.: 4 Chris Ogg DATE: 4/21/19 One Civic Square PROJECT NAME: 16-ENG-34 Carmel, IN 46032 CITY REQ.NO.: N/A CITY PO NO.: 100520—2016 General Oblig. Bond CITY PO DATE: 6/22/2017 I. You are directed to make the following changes in this Contract: (Brief Description) The changes included as part of Construction Change#2 Revision#2 are to revise the Maintenance of Traffic to add left turn access in Phase 1 B to properties west of Gray Road and right turn access in Phase 2A to properties east of Gray Road. Sign locations have been revised to be outside the limits of the future multi-use path/sidewalk as well. Pavement markings have been revised to not conflict with future crosswalk markings for multi-use path/sidewalk. No new items were added due to this change only adjustments to existing pay items. This Change Order #4 will result in an increase of$25,702.57 to the project. SCHEDULED ADJUSTMENT ITEM AMOUNT (+) OR(-) DAYS 05 —Excavation, Common 125 CYD x $24.12=$3,015.00 0 06—Borrow 13 CYD x $0.01 =$0.13 0 14—Temporary Seed Mixture 13 LBS x$1.30= $16.90 0 17—Subgrade Treatment, Type IC 225 SYS x$17.83 = $4,011.75 0 18—B Borrow, Undistributed 15 CYD x$46.69=$700.35 0 21 —Compacted Aggregate No. 53 6 TON x$28.89= $173.34 0 27—HMA for Temp. Pvmt, D 124 TON x$77.06=$9,555.44 0 28—Asphalt for Tack Coat 1 TON x $0.01 =$0.01 0 35 —Curb, Concrete, modified 291 LFT x$23.44= $6,821.04 0 46—Fertilizer 0.1 TON x $500.00=$50.00 0 47—Mulched Seeding U 200 SYS x $0.45 = $90.00 0 48—Topsoil 17 CYD x$55.93 = $950.81 0 72—Temp. Pvmt Marking, 273 LFT x$0.95 = $259.35 0 Removable, 4 In. 75 —Construction Sign, B 1 EA x $85.00= $85.00 0 92—Line, Remove (59 LFT x $0.45 =$26.55) 0 AR-6 Version 2016-08-31 II. The following referenced Documents further describe the changes outlined in Paragraph I.and are to be considered a part of this Change Order: R.F.P.: N/A W.D.C.No.: N/A Other: The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $ 1,600,645.22 Contract Price will be increased/decreased by this Change Order $_25,702.57 New Contract Price including this Change Order $ 1.626.347.79 _ Contract Time Prior to this Change Order 81 Days 10/13/17 Completion Date Net increased/decreased resulting from this Change Order 0 Days Current Contract Time including this Change Order 81 Days 10/13/17 Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are The Above Changes Are Approved: � � �t— Recommended Accepted: (��/�f��j�.d!�i CHA Rieth-Riley Construction ENGINEER CONTRACTOR ./-( s Bray e. 300 S. Meridian Street 1751 W. Minnesota Street Address Address Mar &B> Member Indianapolis. IN 46225 Indianapolis, IN 46221 j Lo't(' ►4ember City/State/Zip City/State/Zip Jer- y Kashma ,PE,City gineer By: •U _ icier `� y A E Phone: 317-407-3760 Phone:.N7 -634-556/ Ar; ristine S. P iley,Clerk- 4/26/19 Treasurer Date: Date: 4-2;-Za Date: AR—6 Version 2016-08-31