A. GENERAL CONTRACTOR SHALL SCHEDULE DEMOLITION ACTIVITIES WITH THE CONSTRUCTION/PROJECT
MANAGER AND BUILIDNG MANAGER INCLUDING THE FOLLOWING: 1) DETAILED SEQUENCE OF DEMOLITION
AND REMOVAL WORK, WITH STARTING AND ENDING DATES FOR EACH ACTIVITY. 2) DATES FOR SHUTOFF,
AND CONTINUATION OF UTILITY SERVICES. 3) IDENTIFY AND ACCURATELY LOCATE UTILITIES AND OTHER
SUBSURFACE AND/OR ABOVE CEILING STRUCTURAL, ELECTRICAL, OR MECHANICAL CONDITIONS.
B. DO NOT START DEMOLITION WORK UNTIL UTILITY DISCONNECTING AND SEALING HAVE BEEN COMPLETED
AND VERIFIED IN WRITING.
C. REMOVE: REMOVE AND LEGALLY DISPOSE OF ITEMS EXCEPT THOSE INDICATED TO BE REINSTALLED,
SALVAGED, OR TO REMAIN.
D. REMOVE, REINSTALL, AND RELOCATE: REMOVE ITEMS INDICATED; CLEAN, SERVICE, AND OTHERWISE
PREPARE THEM FOR REUSE; STORE AND PROTECT AGAINST DAMAGE. REINSTALL ITEMS IN LOCATIONS
INDICATED.
E. REMOVE AND TRANSPORT DEBRIS IN A MANNER THAT WILL PREVENT SPILLAGE ON ADJACENT SURFACES
AND AREAS.
F. EXISTING TO REMAIN: PROTECT ITEMS INDICATED TO REMAIN AGAINST DAMAGE AND SOILING DURING
DEMOLITION. WHEN PERMITTED BY THE ENGINEER, ITEMS MAY BE REMOVED TO A SUITABLE, PROTECTED
STORAGE LOCATION DURING DEMOLITION AND THEN CLEANED AND REINSTALLED IN THEIR ORIGINAL
LOCATIONS.
G. REGULATORY REQUIREMENTS: COMPLY WITH GOVERNING EPA NOTIFICATION REGULATIONS BEFORE
STARTING DEMOLITION. COMPLY WITH HAULING AND DISPOSAL REGULATIONS OF AUTHORITIES HAVING
JURISDICTION.
H. MAINTAIN EXISTING UTILITIES INDICATED TO REMAIN IN SERVICE AND PROTECT THEM AGAINST DAMAGE
DURING DEMOLITION OPERATIONS. DO NOT INTERRUPT EXISTING UTILITIES SERVING OCCUPIED OR
OPERATING FACILITIES, EXCEPT WHEN AUTHORIZED IN WRITING BY ENGINEER AND AUTHORITIES HAVING
JURISDICTION. PROVIDE TEMPORARY SERVICES DURING INTERRUPTIONS TO EXISTING UTILITIES, AS
ACCEPTABLE TO OWNER AND TO GOVERNING AUTHORITIES.
I. ASBESTOS: IT IS NOT EXPECTED THAT ASBESTOS WILL BE ENCOUNTERED IN THE COURSE OF THIS
CONTRACT. IF ANY MATERIALS SUSPECTED OF CONTAINING ASBESTOS ARE ENCOUNTERED, DO NOT
DISTURB THE MATERIALS. IMMEDIATELY NOTIFY THE TENANT AND THE LANDLORD/BUILDING OWNER.
J. SURVEY THE CONDITION OF THE BUILDING TO DETERMINE WHETHER REMOVING ANY ELEMENT MIGHT
RESULT IN A STRUCTURAL DEFICIENCY OR UNPLANNED COLLAPSE OF ANY PORTION OF THE STRUCTURE
OR ADJACENT STRUCTURES DURING DEMOLITION.
K. CONDUCT DEMOLITION OPERATIONS TO PREVENT INJURY TO PEOPLE AND DAMAGE TO ADJACENT
BUILDINGS AND FACILITIES TO REMAIN. ENSURE SAFE PASSAGE OF PEOPLE AROUND DEMOLITION AREA.
L. ERECT TEMPORARY PROTECTION, BARRICADES AS PER LOCAL GOVERNING AUTHORITIES.
M. DO NOT CLOSE OR OBSTRUCT STREETS, WALKS, OR OTHER ADJACENT OCCUPIED OR USED FACILITIES
WITHOUT PERMISSION FROM OWNER AND AUTHORITIES HAVING JURISDICTION. PROVIDE ALTERNATE
ROUTES AROUND CLOSED OR OBSTRUCTED TRAFFIC WAYS IF REQUIRED BY GOVERNING REGULATIONS.
N. PROTECT EXISTING SITE IMPROVEMENTS AND APPURTENANCES TO REMAIN.
O. CLEAN ADJACENT BUILDINGS AND IMPROVEMENT OF DUST, DIRT, AND DEBRIS CAUSED BY DEMOLITION
OPERATIONS. RETURN ADJACENT AREAS TO CONDITION EXISTING BEFORE START OF DEMOLITION.
P. DAMAGES: PROMPTLY REPAIR DAMAGES TO ADJACENT FACILITIES CAUSED BY DEMOLITION OPERATIONS
AT THE GENERAL CONTRACTORS COST.
A. ALL DEVICES REMOVED DURING DEMOLITION SHALL HAVE ALL ASSOCIATED CONDUIT, WIRING, AND CONTROLS
REMOVED BACK TO SOURCE.
GENERAL NOTES
GENERAL ELECTRICAL NOTES
LEGEND
FIXTURE
SYMBOL DESCRIPTION
CEILING TO BE REMOVED
LIGHTING FIXTURES TO
BE REMOVED
MECHANICAL
EQUIPMENT TO BE
REMOVED
NO WORK IN THIS AREA.
N MATCH LINE - SEE 1/D-110.1
REV. DATE DESCRIPTIONDESIGNERPROJECT MANAGER Drawing Name: O:\2019\2019190\32 Carmel (Penn) Office IN\dwg\ConstructionDocuments\Architectural\002_201919032_D-110.dwg
June 19, 2019 - ecurryD-110.1DEMOLITION REFLECTEDCEILING PLANMAR EBC2
1
1 1
1
1
3
4
5
3
4
5
1
1 3
4 5
2
1
1 3 4 52
1
1 3 4 52
1
1 3
4 5
2
1
1 3
4 5
2
1
1 3 4 52
1
1 3 4 52
1
1 3 4 52
PLAN KEYNOTES ELECTRICAL PLAN KEYNOTES --
1. EXISTING LAY-IN CEILING SYSTEM TO BE REMOVED IN IT'S ENTIRETY. COORDINATE W/ MECHANICAL AND
ELECTRICAL DRAWINGS FOR EXTENTS OF DEMOLITION. PREPARE FOR INSTALLATION OF NEW CEILING
PER PLAN. REFER TO A-110 FOR NEW CONSTRUCTION.
1. EXISTING LIGHT FIXTURES, ASSOCIATED BRANCH CIRCUIT WIRING AND
CONTROLS TO BE REMOVED.
2. REMOVE EXISTING LIGHT FIXTURE(S), ASSOCIATED CONTROLS AND BRANCH
CIRCUIT WIRING COMPLETE BACK TO SOURCE.
3. THE E.C. SHALL RECORD THE LOCATIONS OF EXISTING CEILING MOUNTED
SPEAKERS, SECURITY EQUIPMENT AND FIRE ALARM DEVICES PRIOR TO
DEMOLITION OF CEILING. REMOVE THESE DEVICES SO THAT CEILING CAN BE
REMOVED. REINSTALL DEVICES AS CLOSE TO THE EXISTING LOCATION AS
POSSIBLE AFTER NEW CEILING HAS BEEN INSTALLED. ENSURE THAT
REINSTALLED DEVICES ARE FUNCTIONING IN THE SAME MANNER AS THEY WERE
PRIOR TO REMOVAL.