City of Carmel Project 16- ENG- 108
3rd Avenue SW and City Center Drive
Roundabout
CHANGE ORDER #3 S-11°
o�
Scope changes to the contract for barrier arms,automatic bollards and a decorative seatwall. There is
also some additional costs for electrical conduit repairs adjacent the Center Green and the Palladium.
Contract Price prior to this Change Order $3,345,566.60
Contract Price will be increased by this Change Order $219,362.72
New Contract Price including this Change Order $3,564,929.32
Amount Adjusted Contract Cumulative%Change
Price from Original Contract
Original Contract $3,288,270.00 $3,288,270.00 N/A
CO1 $27,431.20 $3,315,701.20 0.8%
CO2 $29,865.40 $3,345,566.60 1.7%
CO3 $219,362.72 $3,564,929.32 8.4%
Page 2/23
CITY OF CARMEL
TO: Jeremy Kashman CONTRACT CHANGE ORDER NO.: 3
City Engineer DATE: July11,2019
City of Cannel Indiana PROJECT NAME: 3rd Ave SW and City Center RAB
One Civic Square CITY REQ. NO.:
Cannel, IN 46032 CITY PO NO.: 16-ENG-108
CITY PO DATE:
1. You are directed to make the following changes in this Contract:
Item 0150-Deletion of existing pay Item for barrier arm.
Item 0195-Addition of pay item for revised automatic bollard package.
Item 0196-Addition of pay item for manual barrier arm.
Item 0197-Addition of pay item for decorative seat wall on East side of 3rd Avenue.
Item 0198-Addition of pay item for repairs to Palladium lighting by Enrico.
Item 0199-Addition of pay item for conduit repairs at Center Green by Fredericks.
Item 0200-Addition of pay item for labor costs by ITS.
Item 0201 -Addition of pay item for lighting repairs for Palladium by Fredericks.
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+)OR(-1 DAYS
II. The following referenced Documents further describe the changes outlined in Paragraph I,
and are to be considered a part of this Change Order R.F.P.: W.D.C.NO.:
Other:
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order S 3,345,566.60
Contract Price will be increased by this Change Order S 219,362.72
New Contract Price including this Change Order $ 3,564,929.32
Contract Time prior to this Change Order 0 Days 7/1/2018 Completion Date
Net increased/decreased resulting from this Change Order 61 Days
Current Contract Time including this Change Order 0 Days 9/1/2018 Completion Date
This Change Order is for full and final settlement of all direct,indirect,impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are The Above Changes Are Accepted A.. .ved
Recommended
American Structurepoint,Inc. White Construction
ENGINEER CONTRACTOR J Bran,:f d,Ma
7260 Shadeland Station 3900 East White Ave.,PO Box 249 it/
Address ,werea+ ary Amr
r B ems.' ..bet
Indianapolis.L's 46256 Clinton.IN 47842
C1ry/Sute/7sv atytsw p Lori a .,,, em. •
• J- ,i` Ilan,City Engineer
By: L1J1 By
A •
Phone: 311-Z$1-S S(23 Phone: 3 1?'3bZ-6!'217 �.
stine S.Paulcy Jerk-Treasurer
Date:?_L f(q Date: Z/t 1/ k)19 Date: l7`I/,
American Structurepoint, Inc.
Change Order Details
16-ENG-108 - City Center Drive and 3rd Avenue SW RAB
Description The existing signalized intersection will be reconstructed to a multi-lane roundabout. The project construction will include reconstructing the
median and outside curb lines for a multi-lane roundabout. The asphalt pavement will be milled and reconstructed as needed for the roundabout
intersection. Additionally the pedestrian facilities adjacent to the vehicular travel lanes will be altered to improve pedestrian safety and mobility.
The existing storm water system will be reconstructed as needed for the intersection improvements. Additional lighting will be installed for the
roundabout intersection. The private drives located within the limits of the intersection reconstruction will be replaced. Streetscape
improvements along 3rd Avenue SW and around the roundabout will be constructed. Access to properties within the project limits will be
maintained during construction.
Prime Contractor White Construction
3900 East Whilte Avenue, PO Box 249
Clinton, IN 47842
Change Order 3
Status Pending
Date Created 07/11/2019
Type Changed Conditions
Summary Change Order#3
Change Order Description Change Order#3 is being created to remove the original pay items for the barrier arms and automatic bollards. The change order is adding new
pay items for manual barrier arms,revised automatic bollards,decorative seat walls on the East side of 3rd Avenue,conduit and lighting repairs
adjacent the Palladium and labor costs for an added road closure mobilization.
Awarded Project Amount $3,288,270.00
ua
Authorized Project Amount $3,345,566.60 CD
Change Order Amount $219,362.72 w
Revised Project Amount $3,564,929.32
Change Order Details: 07/11/2019
16-ENG-108-City Center Drive and 3rd Avenue SW RAB Page 1 of 3
Increases/Decreases
Line Number' Item ID Unit Unit Price Current Change ''evised
.
Quantity Amount Quantity Amount Quantity Amount
am,
Section: I - Description
0150 0150 EACH $36,000.000 4.000 $144,000.00 -4.000 -$144,000.00 0.000 $0.00
BARRIER ARM
Reason: Revised barrier arm.
1 item Totals $144,000.00 -$144,000.00 $0.00
New Items
Line Number Item ID Unit Quantity Unit Price Extension
Section: 1 -Description
0195 CO-LS 1. I.o u i S 144,807.500 $144,807.50
Change Order Item "LS":Automatic Bollard Package
0196 CO-LS LS 1.000 $104,950.000 $104,950.00
Change Order Item "LS": Decorative Barrier Arm,Manual
0197 CO-LFT LFT 80.000 $1,315.000 $105,200.00
Change Order Item"LFT": East side of 3rd Avenue
0198 CO-LS LS 1.000 $l,214.400 $1,214.40
Change Order Item "LS": Palladium Lighting(Ermco)
.-o
w
Change Order Details. w 07/11/2019
16-ENG-108-City Center Drive and 3rd Avenue SW RAB Page 2 of 3
Line Number Unit Quantity Unit Price Extensi
0199 CO-LS LS 1.000 $2,227.500 $2,227.50
Change Order Item "LS":Conduit Repair(Fredericks)
Reason: At Center Green
0200 CO-LS LS 1.000 $831.420 $831.42
Change Order Item "LS": ITS Labor
Reason: Additional Closure of RAB
0201 CO-LS LS 1.000 $4,131.900 $4,131.90
Change Order Item "LS": Lighting Repair(Fredericks)
Reason: Street Light and Palladium ground lights
7 items Total: $363,362.72
CD
N
Change Order Details: 07/11/2019
16-ENG-108-City Center Drive and 3rd Avenue SW RAB Page 3 of 3
Change Order#3-3rd Avenue SW and City Center Drive RAB(City of Carmel 16-ENG-108)
Item No. Description Unit Cost Quantity Unit Total Cost Deducts Addition Work Performed
01 0 _ Barrier Ar 361000100 EA _ 1 i,000100 V
019: Auto: ati: Bollard Pa,1 age 1 :I 1807 '0 1 S 1 i 8071:0 V
0196 _ De orative Barrier Ar 1 anual _ 10119 0 00 1 S -10i'i9i 0:00 V
0197 De orative Seat Wall East 1 31 ll00 80 111 : 110 n200 00
0198 Palladiu. Ighting Er of 1:21 III:0 1 S I 1:21:fll0 _ V _
0199 Conduit Re air at Center Green'1 rederi::s 2:227110 1 :S :2'2271',10 . V _
0200 S a or 831112 1 S 831112 V
0201 Ighting Re air irederi: s : :131190 1 S 1131 90
otal Dedu tions: 11 n 1000:00
otal Additions: 363 362 72
Net otal: 219 362 72
"ti7
P
On
ry
ti
w
Item#0195 Page 7/23
WHITE °OWER 3900 East White Avenue
FORWARD P.O.Box 249
Clinton,IN 47842
4.0I E,
Tel(800)355 9401
Fax(765)832 2075
www.whiteconstruction.com
July 9,2019
David Machala
American Structurepoint Inc.
Cell:(317)281-9563
Email:dmachala@structurepoint.com
Regarding: Automatic Bollards
Project No. 16-ENG-108
Gentlemen:
We respectfully request a change order in the amount of$144,807.50 to fabricate and install
automatic bollards as described in the attached document.
Please feel free to contact me with any questions or concerns.
Marc Waltermann
White Constru tlonL�Im
Pro e t anager
Cell: 317-362- 217
ar alter ann hite onstru tion o
An Equal Opportunity Employer.
Page 8/23
MORPHEY CONSTRUCTION, INC.
1499 NORTH SHERMAN DR.
INDIANAPOLIS, IN 46201-1515
(317)356-9250
FAX(317)356-9253
QUOTE
CONTRACT.' CITY OF C4RMEL
DESCRIPTION: CITY CENTER&3RD AVE SW 16-ENG-108
LOCATION: HAMILTON CO
BID DATE: 10/30/18
ITEM DESCRIPTION QTY.. BID UNIT BID TOTAL
1 4"PVC CONDUIT 1300.00 LET 0.00 0.00
2 2"PVC CONDUIT 500.00 LFT 0.00 0.00
3 QUAZITE HANDHOLE 4.00 EA 0.00 0.00
4 SECURE USA (MAT ONLY) 1.00 EA 118950.00 118950.00
5 EPU ENCLOSURE 1.00 EA 1500.00 1500.00
6 EPU ENCLOSURE FOUNDATION 1.00 EA 1700.00 1700.00
7 2/0 CABLE-SERVICE TO EPU 900.00 LET 11.00 9900.00
8 MOTOR&BRAKE CABLE 2000.00 LET 3.40 6800.00
9 HEATER CABLE 2000.00 LFT 2.30 4600.00
10 CONTROL CABLE 2000.00 LET 2.00 4000.00
11 CONDUIT BOLLARDS TO HH 2.00 EA 900.00 1800.00
12 BOLLARD CONCRETE FOUNDATION 2.00 EA 24000.00 48000.00
13 SETUP& TESTING BOLLARDS 1.00 LS 3500.00 3500.00
14 BOLLARD DRAINS 1.00 IS 0.00 0.00
15 PAVER& CURB REPAIR 1.00 LS 0.00 0.00
16 MOB&MOT 1.00 LS 1500.00 1500.00
17 DEDUCT ITEM#149 1.00 LS -67000.00 -67000.00
TOTAL 135,250.00
DOUG SEURING
PROJECT MANAGER
317-716-0882
'EQUAL OPPORTUNITY EMPLOYER'
Page 9/23
MORPHEY CONSTRUCTION, INC.
1499 NORTH SHERMAN DR.
INDIANAPOLIS, IN 46201-1515
(317)356-9250
FAX(317)356-9253
'EQUAL OPPORTUNITY EMPLOYER'
Item#0196 Page 10/23
WHITE POWER 3900 East White Avenue
FORWARD P.O.Box 249
Clinton,IN 47842
.in GDIEA,orr-1 -v
Tel(800)355 9401
Fax(765)832 2075
www.whiteconstruction.com
January 9, 2019
David Machala
American Structurepoint Inc.
Cell: (317)281-9563
Email: dmachala@:structurepoint.com
Regarding: Barrier Arms
Project No. 16-ENG-108
Gentlemen:
We respectfully request a change order in the amount of$104,950.00 to fabricate and install (4
ea.)decorative metal barrier arms on Project No. 16-ENG-108. In addition, we request the
project completion date be revised to April 1, 2019 for all work excluding seasonal plantings.
Please see the attached backup for your records.
Please feel free to contact me with any questions or concerns.
Marc Waltermann
White Construction, Inc.
Project Manager
Cell: 317-362-4217
m a rc.wa l term a n n(aiwh iteco n stru ction.com
An Equal Opportunity Employer.
Page 11/23
2910 West Minnesota Street
Indianapolis,IN 46241.4541
Smock 1Fansler 317.248.8371 Tel
C O R RATION ION 317.244.4507 Fax
i rtcel Contractors•ErtLava.Communion Kwwn
Quotation
DATE: 1/8/2019
Quote# B18-0028A2
TO: Marc Waltermann, White Construction
FROM: Joe Davee
REGARDING: Carmel 3rd Ave Roundabout-Barrier Arms
Final Confirmed Pricing
We Propose to Provide the following Scope of Work:
Fabricate and install decorative metal barrier arms (4 ea)at 3rd avenue street crossing near Palladium.
Base Bid: $98,000.00
Project Deadline extension to April 1, 2019 is requested in conjunction with this work.
INCLUDES:
Excavate, form and place 4 each concrete foundations 30" Dia x 6'deep. Fabricate and install 4 each
decorative metal barrier arms, manually operated with locking pins for both up and down positions. Barrier arms
to be fabricated of laser cut steel plates with a combination of mechanical fasteners and welded connections as
needed. All units to be constructed of a combination of powder coated steel and powder coated aluminum.
Locking mechanism to be keyless digital pad with backup deadbott per Carmel Street Department. Operation of
the arm will be free of pinch points for manual operation and have final appearance based upon latest details and
correspondence between Structurepoint and Smock Fansler on 11/15/2018.
EXCLUDES:
Bonds, Permits or Related Fees
Premium Time for shift work,weekends or holidays.
No electrical components, operators or lights included in above price.
SALES TAX No INCLUDES ADDENDA n/a THROUGH n/a
NOTES:
Please call if you have any questions.
Thanks For The Opportunity To Serve You!
QUOTE -Barrier Arms Final Carmel City Center& 3rd Avenue
Item#0197 Page 12/23
W11VHITE POWER 3900 East White Avenue
FORWARD P.O.Box 249
Clinton,IN 47842
an G'JIEA company
Tel(800)355 9401
Fax(765)832 2075
www.whiteconstruction.com
November 30, 2018
David Machala
American Structurepoint Inc.
Cell: (317)281-9563
Email: dmachalaCstructurepoint.com
Regarding: Additional Seatwall
Project No. 16-ENG-108
Gentlemen: •
We respectfully request a change order in the amount of$1,315.00[LFT for the additional seat
wall at City Center Drive and 3`d Avenue. Please see the attached backup for your records.
Please feel free to contact me with any questions or concerns.
Marc Waltermann
White Construction, Inc.
Project Manager
Cell: 317-362-4217
marc.waltermann(a�whiteconstruction.com
An Equal Opportunity Employer.
Page 13/23
Waltermann, Marc
From: Machala, Dave <DMachala@structurepoint.corn>
Sent: Thursday, November 29,2018 4:01 PM
To: Joe Davee;Waltermann, Marc
Subject: Re:Seatwall add at 3rd avenue
Joe,
This breakdown is fine, I'm not questioning the cost I just wanted to have a little more backup for the change order.
Marc, please use the$1,228/LFT cost for your markup-there should be a total of 80 LFT onsite. Then send me a cover
sheet for change order processing.
Thanks,
David
David Machala
RPR,Construction Inspection
7260 Shadeland Station Indianapolis, IN 46256
T 317.547.5580 E dmachala@structurepoint.com
F 317.543.0270 W www.structurepoint.com
C 317.281.9563
From:Joe Davee<jodavee@smockfansler.com>
Sent:Thursday, November 29,2018 3:53 PM
To: Machala, Dave;Waltermann, Marc
Subject: RE: Seatwall add at 3rd avenue
Dave,
Below is the breakdown of the new seat wall cost,which is the number we need to hit regardless of whether it is a lump
sum change order,or a$1,228/LF unit price change order,or an added quantity of 105 IF on the base contract at
$935/LF. If you recall, we agreed the unit price cost of the new wall,with cladding on both sides,would end up
somewhere between the base bid, single sided,wall style and a rate at double the cost per LF. In this instance the
double sided cladding came at a 31%premium,which I do not feel is unreasonable.This also covers the added brick
ledges for all walls to compensate for the differential grade conditions of the adjacent walks.
Excavate, Place Concrete $36,440.00
Integral Color Brick Ledges $ 4,200.00
Precast Material $19,210.00
Precast Installation $38,390.00
Total $98,240.00
Please let me know if you need anything further.
Thanks,
i
Item #0198 Page 14/23
PT
WHITE POWER 3800 East White Avenue
Bo
P.O.Box 249
an U�IEA company
FORWARD Clinton,IN 47842
Tel(800)355 9401
Fax(785)832 2075
www.whiteconstruction.com
January 21, 2019
David Machala
American Structurepoint Inc.
Cell: (317)281-9563
Email: dmachala(structurepoint.com
Regarding: Electrical Work at Palladium
Project No. 16-ENG-108
Gentlemen:
We respectfully request a change order in the amount of$1,214.40 for additional electrical work
at the Palladium. Attached is back-up for your records.
Please feel free to contact me with any questions or concerns.
Marc Waltermann
White Construction, Inc.
Project Manager
Cell: 317-362-4217
marc.waltermannna.whiteconstruction.com
An Equal Opportunity Employer.
Page 15/23
INVOICE
INVOICE#: 910004292
INVOICE DATE: 08/28/18
CUSTOMER NUMBER: 009185
11 SERVICE ORDER: 10003702
='I' - - `PLF INSPP.'v; INN J`%AiIG`
CUSTOMER PO:
WHITE CONSTRUCTION INVOICE TOTAL: $ 1,104.00
ATTN: DUE DATE: 09/27/18
2647 WATERFRONT PKWY E DR
INDIANAPOLIS, IN 46214 TERMS: Due Upon
Receipt
For work performed at:
THE PALLADIUM
355 W CITY CTR DRIVE,
CARMEL, IN 46032
LABOR
DATE DESCRIPTION HOURS HOUR TYPE RATE EXTENDED
06/15/18 CHRISTOPHER K KEELY 12.00 REG 92.00 1,104.00
Labor Total: 1,104.00
COMMENTS
Met with general contractor to go over lighting feed issues.Went to OurMed Cohen picked up the underground tracer for
Monday morning.
Traced damaged underground lighting systems
Completed underground tracing. Met with the general contractor and relayed al of the information.
SUBTOTAL: 1,104.00
TAX: 0.00
INVOICE TOTAL: 1,104.00
REMIT TO: ERMCO INC P 0 BOX 1507 INDIANAPOLIS, IN 46206
317-780-2923
Item #0199 Page 16/23
Y WHITE POWER 3900 East White Box 249
p //��� P.O.Box Avenue
an 6�IEA company
FO/1 WA D Clinton,IN 47842
Tel(800)355 9401
Fax(765)832 2075
www.whaeconstrucaon.com
January 21, 2019
David Machala
America:Structurepoint Inc.
Cell: (317)281-9563
Email: dmachala@structurepoint.com
Regarding: Conduit Repair
Project No. 16-ENG-108
Gentlemen:
We respectfully request a change order in the amount of$2,227.50 to repair electrical conduits at
3rd Avenue and Center Green. Attached is back-up for your records.
Please feel free to contact me with any questions or concerns.
Marc Waltermann
White Construction, Inc.
Project Manager
Cell: 317-362-4217
marc.waltermann(awhiteconstruction.com
An Equal Opportunity Employer.
Page 1 /2 3
INVOICE
Lmirocesormeme
CONTRACTORS
Name City of Carmel Date: 10/30/2018
Address 3 Civic Square Invoice# 7720-18
Carmel, IN 46032 Project# CARM1806
ATTN: Todd Luckoski P.O.#
Item Description Unit Total
Repaired cut conduits and wire at 3rd Ave. and center Green area $2,025.00
As Agreed
Thank You
Balance Due TOTAL $2,025.00
Terms Net due upon receipt. 1 %%service charge added monthly.
REMIT TO:
Fredericks Inc.5448 W. State Road 132, P.O. Box 229, Pendleton, IN 46064
Phone: 765-778-7588 FAX: 765-778-7589
Item #0200 Page 18/23
il
WHITEUCTION White Construction, LLC.
CONSTR
3900 E. White Ave. P.O. Box 249
Clinton, IN 47842
Aiil 172019
David ialiala
A eri-an Struiture_ointLLn-
D_a_ha_a__ stru ture oint__o
Regarding: ndiana raffi Servi es S uantities
Pro a t: 1 -ENG-18
City Center Drive and 3rd Avenue SW RAB
r _ a hala:
We res e tfully re uest$831.42 for the additional S la or or for the se and loser of 3rd Ave
Atta hed is the la or rea out fro S for your re ords
Please feel free to Dnta t e ith any uestions or on ems
Res e tfully
Marc/W alter wu -vwv
ar Walter ann
White Constru tion n
Pro e_i anager
O 1800.355.9410
www.whiteconstruction.com
Page 19/23
Grove, Jennifer
From: Julie Sobczak <Julies@indianatrafficservices.com>
Sent: Friday, March 22, 2019 4:12 PM
To: Grove, Jennifer; Waltermann, Marc
Cc: Marlena@indianatrafficservices.com
Subject: RE: White Construction - 16-ENG-108 City Center and 3rd Avenue
Good Afternoon Marc, Jennifer,
I wanted to make sure that I got the information to you that we discussed yesterday with David
regarding the need for ITS to make a second trip to reclose the road. ITS agrees that the signs should
not be recharged to the city of Carmel, however we would like to be reimbursed for our labor cost to
repost the signs and barricades for the closure.
The total cost of the labor (1 Crew Leader and 3 Laborers) for 4 hours is $755.84. I am not asking for
recompense of any other costs associated with this. I hope that you find this acceptable.
Thank you,
Julie Sobczak
Controller
Indiana Traffic Services
PLEASE NOTE THAT OUR ADDRESS HAS CHANGED TO:
3865 N COMMERCIAL PARKWAY
GREENFIELD IN 46140
•
I fir
LET US KEEP YOU SAFE
(317) 891-8065 - Office
(317) 891-8248 - Fax
(317) 695-3959 - Cell
Item#0201 Page 20/23
V7
WHITE POWER 3900 East White Avenue
FORWARD Clinton,P.OBox 249
on,IN 47842
G1%IE
Tel(800)355 9401
Fax(765)832 2075
www.whiteconstruction.com
July 9,2019
David Machala
American Structurepoint Inc
Cell:(317)281-9563
Email:dmachala@structurepoint.com
Regarding: Palladium Troubleshooting/Repairs
Project No. 16-ENG-108
Gentlemen:
We respectfully request a change order in the amount of$4,131.90 to troubleshoot and repair at
Palladium as described in the attached document.
Please feel free to contact me with any questions or concerns.
Marc Waltermann
White Construlion EM LI
Pro all Eanager
Cell: 317-362-217
ar ' alter ann hite onstru tion o
An Equal Opportunity Employer.
Page 21/23
INVOICE
[71.015101,1Eite
CONTRACTOR S
Name White Constru tion Date: 7/9/2019
Address PO BoLi]2C9 nvoiCie❑ 8 -19
Clinton❑LiN 78 2 SOGC2019
ATTN: arE Walteri ann S3DH: 178-2019
Item Description Unit Total
❑rouLleshooting and re airs at Palladiu in Caruel❑ 03E177E13
As Agreed
han ou
Balance Due TOTAL $3,777.48
Terms:Net due upon receipt 1 Y%service charge added monthly.
REMIT TO:
Fredericks Inc. 5448 W. State Road 132, P.O. Box 229, Pendleton, IN 46064
Phone: 765-778-7588 FAX: 765-778-7589
SERVICE ORDER#: 178-2019
DATE: 05/10/19
EMPLOYEE: Brandon
gncesem me JOB NAME: Carmel Palladium
CONTACT: Marc walterman/Ed pennman.
CONTRACTORS WORK ADDRESS:
BILLING ADDRESS: P.O. Box 249, 3900 E.White Ave
PHONE#: 317-370-2091
PO Box 229-5448 W.SR 132 Pendleton,IN 46064 CELL PHONE#: 756-832-2075
Phone(765)778-7588 Fax(765)778-7589 EMAIL: marc.walterman@whiteconstruction.com
MATERIALS: DESCRIPTION OF WORK:
Date , Quantity Description Price Amount Receive a call from Ed Penmann from the carmel Palladium to
05/14/19 1 Kirby S110416801.003 $ 8.92 $ 8.92 investigate the ground/facad lights. We spent several hours
05/14/19 1 Kirby S1104168.01 $ 400.57 $ 400.57
05/14/19 _ 1 Chapman 1126121 $ 12.99 $ 12.99 Troubleshooting and repairing ground mounted facad lighting
05/22/19 Runyan $ - $ 220.42
$ - $
$ - $ -
•
$ - $ -
$ - $ -
$ - $ - LABOR:
$ - $ - Date Hours Employee Rate Amount
$ - $ - 05/16/19 5.00 HANL $ 60.00 $ 300.00
$ - $ - 05/10/19 5.00 HANR $ 60.00 $ 300.00
$ - $ - 05/13/19 8.50 HANL $ 60.00 $ 510.00
$ - $ - 05/13/19 8.50 HANR $ 60.00 $ 510.00
$ - $ - 05/14/19 7.00 HANL $ 60.00 $ 420.00
$ - $ - 05/14/19 7.00 HANR $ 60.00 $ 420.00
$ $ $ $ cv
Material Subtotal: $ 642.90 $ - $ - cra
Sales Tax @ 7%: $ 45.00 $ - n,
Material Total: $ 687.90 Labor Total: S 2,460.00 �
NJ
Mice Notes: SUMMARY: w
Material Total: $ 687.90
Labor Total: $ 2,460.00
Subtotal: 3,147.90
Mark-Up @ 20%: $ 629.58
Customer Signature: Date: PM Initial: BLF Complete Total: $ 3,777.48
Date: 07/03/19 Billing Amount: $ 3,777.48
Page 23/23
1
rraresrememg
CONTRACTORS
u ly 2 2019
City of Car el
Re: Palladium /Center Green power issue
Dear ❑arr i
❑ere is a rief eLdanation of the ele[3riCal ❑or❑that ❑e ❑erfor❑ed at he Center
Greenmuring our investigation of the o er issues at the Palladiu❑r e dis overed that the
Cb❑er a-odeib s are related to tL.o se❑arate CbnstruLtion ❑roleds❑
❑he first Co❑er issue -as the faLade lighting on the north side of the Palladiu he
LO❑er feed ❑as da❑aged during the round-a❑out Cro[eLt at 3ro Avenue and City Center Drive`.
❑o❑ever e Culled a ne❑ drLuit frol the last fiLture to the West and reLOnneLted it to a
❑ordng Lir ult._ he seLbnd ❑o❑er issue Las the ground-El ounted facade lights on the north
side of the ❑wilding❑❑his drLUit Las fed fro❑ the ❑anels in the tunnel ❑elo❑ the Center Green❑
During the Le slating rin❑Do[eCtLthe Conduit and ❑fires ❑ere da❑aged and un-noticed during
CbnstruLtionLilhe Cade Las Wiled out of the light fiL3ure ❑ase 2-3r ut still libnnel ied in the
large side Cb❑on the Center GreenLWe traLed the Conduit and Eire Dal I Ito this Co❑and
redared the da❑aged ❑ireLEverything is Lurrently funEtional at this ❑ointl 1 le tested voltage
and a erage and Canfir❑ed that the drLuits are not el I eeding their A❑❑aLity range❑
Best regardsb
Brandon ❑ila-un