RELEASED FOR CONSTRUCTION
Subject to compliance with all regulations
of State and Local Codes
City of Camel
DATE: 08/23/19
ABBREVIATIONS
A
AIR
AAP
AREA ALARM PANEL
ADJ
ADJUSTABLE
AFF
ABOVE FINISHED FLOOR
ALT
ALTERNATE
AP
ACCESSPANEL
AV
ACID VENT
AW
ACID WASTE
BAS
BUILDING AUTOMATION SYSTEM
BHP
BRAKE HORSEPOWER
BOP
BOTTOM OF PIPE ELEVATION
BOT
BOTTOM
BTU
BRITISH THERMAL UNIT
BTUH
BRITISH THERMAL UNITS PER HOUR
CA
COMPRESSED AIR
CFM
CUBIC FEET PER MINUTE
CLG
CEILING
CO
CLEANOUT
CO2
CARBON DIOXIDE
CTR
CENTER
D
DRAIN LINE
DCW
DOMESTIC COLD WATER
DIET
DETAIL
DFU
DRAINAGE FIXTURE UNIT
DHR
DOMESTIC HOT WATER RETURN
DHW
DOMESTIC HOT WATER
DIA
DIAMETER
DIM
DIMENSION
DIN
DOWN
EA
EACH
EW
EYEWASH
EFF
EFFICIENCY
EJ
EXPANSION JOINT
ELEC
ELECTRICAL
ELEV
ELEVATION
EQUIP
EQUIPMENT
ET
EXPANSION TANK
ES
EMERGENCVSHOWER
EWC
ELECTRIC WATER COOLER
EWT
ENTERING WATER TEMPERATURE
EXT
EXTERIOR
FCO
FLOOR CLEANOUT
FD
FLOOR DRAIN
FLA
FULL LOAD AMPERES
FLR
FLOOR
FPM
FEET PER MINUTE
FT
FEET
FTHD
FEET HEAD
FTG
FOOTING
G
GAS
GA
GAUGE
GAL
GALLON
GPH
GALLONS PER HOUR
GPM
GALLONS PER MINUTE
HB
HOSE BIBB
HD
HUB DRAIN
HP
HORSEPOWER
HT
HEATTRACE
HTR
HEATER
GENERAL PLUMBING DEMOLITION NOTES
1. THE PLUMBING DEMOLITION DRAWINGS SHOW EXISTING
EQUIPMENT AND DEVICES WHICH ARE INTENDED TO BE
REMOVED. THESE DRAWINGS INDICATE THE REQUIRED
SCOPE OF WORKAND ARE NOT INTENDED TO REFER TO
EVERY PIECE OF EQUIPMENT OR PIPE THAT MUST BE
REMOVED IN ORDER TO COMPLETE THE WORK. IT SHALL BE
THE CONTRACTOR'S RESPONSIBILITY TO VISIT THE SITE
AND VERIFY THE CURRENT INSTALLATION BEFORE
SUBMITTING A BID FOR THE MECHANICAL WORK.
2. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO
VERIFY THE CONDITION OF ALL EXISTING EQUIPMENT.
EXACT SIZES OF EXISTING PIPING, ETC. BEFORE
DEMOLITION WORK IS BEGUN. REPORTANY
DISCREPANCIES BETWEEN PLANS AND ACTUAL FIELD
CONDITIONS TO ARCHITECT AND ENGINEER PRIOR TO THE
COMMENCEMENT OF DEMOLITION WORK.
3. WHERE DEMOLITION WORK WILL INTERRUPT PLUMBING
SERVICE TO AREAS OF THE FACILITY THAT ARE TO REMAIN
IN OPERATION, COORDINATE ANY INTERRUPTIONS WITH
THE OWNER AT LEAST TWO WEEKS PRIOR AND
ACCOMMODATE THE OWNER'S NEEDS ARE REQUIRED.
4. REMOVE THE INDICATED PLUMBING ITEMS AS SHOWN ON
PLANS. THIS INCLUDES ALL HANGERS, STRAPS, AND
RELATED MATERIAL.
5. THE PLUMBING CONTRACTOR SHALL BE RESPONSIBLE FOR
CUTTING AND PATCHING OF EXISTING CONSTRUCTION
UNLESS OTHERWISE NOTED ON PLANS. NO CUTTING OF
STRUCTURAL MEMBERS OR STRUCTURE WHICH WILL
DETERIORATE THE INTEGRITY AND STRENGTH OF THE
BUILDING WILL BE ALLOWED WITHOUT THE WRITTEN
APPROVAL FROM THE STRUCTURAL ENGINEER.
6. PATCH AND REPAIR OPENINGS THROUGH WALLS AND
FLOORS WHERE PIPES WERE REMOVED TO MATCH
EXISTING AND TO MAINTAIN FIRE RATINGS.
7. CONTRACTOR SHALL VERIFY CLEARANCE REQUIREMENTS
AND INDICATE ROUTING OF NEW PIPING BEFORE
FABRICATION BEGINS AS RISES AND DROPS MAY BE
NECESSARY DUE TO EXISTING FIELD CONDITIONS.
ABBREVIATIONS
PIPING ANNOTATION
VALVES
GENERAL SYMBOLS
ID
INSIDE DIAMETER
—DCW—
DOMESTIC COLD WATER
GASSHUTOFFVALVE
e
EQUIPMENTTAG
IE
INVERTELEVATION
IN
INCHES
IN WC
Me
INCHES WATER COLUMN
INDIRECTWASTE
—DHW—
DOMESTIC HOT WATER
—pd—
GATE VALVE
r' )
v
KEYNOTE
LA
LABORATORYAIR
LAV
LAVATORY
—DHR—
DOMESTIC HOT WATER RETURN
BALL VALVE
POINT OF NEW CONNECTION TO EXISTING
WHEN ON DEMO SHEET: END POINT OF DEMO
LV
LABORATORY VACUUM
LWT
MAP
LEAVING WATER TEMPERATURE
MASTER ALARM PANEL
DI
DEIONIZEDWATER
BUTTERFLVVALVE
$
ELEVATION SYMBOL
MB
MOP BASIN
w
MBH
ONE THOUSAND BTUH
MFR
MH
MANUFACTURER
MANHOLE
LA
LAB COMPRESSED AIR
I
BALANCING VALVE
I
DETAIL REFERENCE (TOP=DETAIL NUMBER,
BOTTOM=DRAWING NUMBER)
—X.
1010.
MEDICAL COMPRESSED AIR
---
CHECK VALVE
NIC
NPSH
NOT IN CONTRACT
NET POSITIVE SUCTION HEAD
NPT
NATIONAL PIPE THREAD
VAC—
LABVACUUM
PRESSURE REDUCING VALVE
REFER
PLAN CONTINUATION REFERENCE
NTS
OC
NOTTOSCALE
ON CENTER
OD
OUTSIDE DIAMETER
(BOTTOM=DRAWING NUMBER)
OFD
OVERFLOW DRAIN
—fdV—
MEDICAL VACUUM
SOLENOID VALVE
P
PUMP
SECTION DESIGNATION
PH
PHASE
PRV
PSF
PRESSURE REDUCING VALVE
POUNDS PER SQUARE FOOT
—SAN—
SANITARY WASTE LINE
��
PRESSURE RELIEF VALVE
(TOP=SECTION NUMBER,
BOTTOM=DRAWING NUMBER)
PSI
POUNDS PER SQUARE INCH
PSIG
RD
POUNDS PER SQUARE INCH GAUGE
ROOF DRAIN
—STRM—
STORM
THERMOSTATIC MIXING VALVE
FITTINGS
RPM
RV
REVOLUTIONS PER MINUTE
RELIEF VALVE
—OD—
OVERFLOW DRAIN LINE
�IVTI�
REDUCED PRESSURE
BACKFLOW PREVENTER
FLANGE
S
STORM
—IW—
INDIRECTWASTE
STRAINER
UNION
SAN
SCH
SANITARY
SCHEDULE
SD
SUBSOILDRAIN
SF
SQUAREFEET
—AW—
ACIDWASTE
PIPE FLEXIBLE CONNECTION
ANCHOR
SH
SHOWER
S/S
STAINLESS STEEL
STD
STANDARD
—V —
VENT LINE
GAS REGULATOR
PIPE GUIDE
STM
STORM
TO
TRENCH DRAIN
TDH
TOTAL DYNAMIC HEAD
—LV—
LAB VENT
THERMOMETER
PIPE SLEEVE
TEMP
TEMPERATURE
TMV
THERMOSTATIC MIXING VALVE
TP
TRAP PRIMER
—112—
HYDROGEN
y
J
ELBOW DOWN
TVP
TYPICAL
PRESSURE GAUGE
UR
V
URINAL
VENT
_02_
OXYGEN
ELBOW UP
VAC
VACUUM
FHB
WALL HYDRANTMOSE BIBB
VFD
VARIABLE FREQUENCY DRIVE
—N2—
NITROGEN
]
PIPE CAP
VTR
VENT THRU ROOF
FILTER
W
WASTENVATER
WAGD
WASTE ANESTHETIC GAS DISPOSAL
LNG—
NATURAL GAS
WC
WATER CLOSET
WATER METER
DRAINS
ANDCLEANOUTS
WCO
WH
WALL CLEANOUT
WALL HYDRANT
ZVB
ZONE VALVE BOX
�
FLOOR SINK
VACUUM BREAKER
PIPING OR EQUIPMENT
TO BE DEMOLISHED
On)
FLOOR DRAIN
ORD
ROOF DRAIN
GENERAL NOTES:
1. THE CONTRACTORS WORK SHALL CONFORM TO THE
OWNERS POLICIES ON CONSTRUCTION PROCEDURES.
OC
PIPE TRAP
2. COORDINATE WITH THE OWNE R FOR ANY EQUIP MENT
'
CLEANOUT
REMOVED THAT NEEDS TO BE RETURNED TO THE OW NE R.
3. COORDINATE WITH OWNER FOR ANY TEMPORARY SYSTEM
FLOOR CLEANOUT
SHUTDOWNS NECESSARY TO COMPLETE THE WORK.
FCO
4. RE -INSULATE AND PATCH PIPING RISERS AS REQUIRED.
5. COORDINATE WITH OWNER FOR ANY FLOOR CORING
WORK THAT IS REQUIRED.
SP-NGA
spin a strength • yoga
VIRTUAL
GIVLIC\71
SOLUTIONS
33 E. OGDEN AVE. SUITE 304
LA GRANGE IL, 60525
312.583.7023
W W W.VESCHICAGO.COM
#AA26003751
�0
N
M
M>
W
C)
U
L
W
C
r
�
U
C
�
_
Q
U
Cf)
r
E
r
LO
�
M
�
U
r
i 4PP G15TEq`?:o
PE11SO0637
w
'? STATE OF :',R
VES project number: 190301
sheet title:
PLUMBING SYMBOLS
AND ABBREVIATIONS
sheet number:
P001
02018 Virtual Energy Solutions, Inc.