HomeMy WebLinkAboutRieth-Riley/Eng/-170,725.77/CO #14/Spring Mill Road Reconstruction – Project #16-ENG-52 City of Carmel Projects 16-SW-07 & 16-ENG-52 Spring Mill Road Reconstruction CHANGE ORDER#14 Balancing Change Order—End Project Contract Price prior to this Change Order $9,104,835.24 Contract Price will berea..szy this Change Order (-$170,725.77) New Contract Price including this Change Order $8,934,109.47 Amount Adjusted Contract Cumulative%Change Price from Original Contract Original Contract $8,592,091.16 $8,592,091.16 N/A CO1 (-333.18) $8,591,757.98 -0.004% CO2 $36,031.35 $8,627,789.33 0.42% CO3 $123,808.23 $8,751,597.56 1.86% C04 $11,656.00 $8,763,253.66 1.99% C05 $4,140.25 $8,767,393.91 2.04% C06 $640,929,94 $9,408,323.85 9.50% CO7 $13,183.50 $9,421,507.35 9.65% CO8 $32,465.92 $9,453,973.27 10.03% C09 $91,297.27 $9,545,270.54 11.09% CON $7,996.08 $9,553,266.62 11.19% C011 $22,257.82 $9,575,524.44 11.45% C012 $16,160.21 $9,591,684.65 11.63% C013 (-$486,849.41) $9,104,835.24 5.97% C014 (-$170,725.77) $8,934,109.47 3.98% Page 1 of 2 z4fiL°1"`�0 CITY OF CARMEL t\ 1, DCl' TO: Lucas Clark CONTRACT CHANGE ORDER NO.: 14 Rieth-Riley Construction Co.,Inc. DATE: 7/19/19 P.O.Box 276 PROJECT NAME: Spring Mill Road Reconstruction / 1751 W.Minnesota Street Indianapolis. In 46221 Project#16-SW-07/Project#16-ENG-52 CITY REQ. NO.: CITY PO NO.: SW-100354/COIT- 34297 CITY PO DATE: SW-4/13/2017/COIT- 9/8/2016 I. You are directed to make the following changes in this Contract: *This Change Order will balance all items which over ran or under ran in quantity for Project #16-SW-07, set the Substantial Completion Date as 12/15/2017 and establish the Final Total Contract Amount of$8,934,109.47. NOTE: Final Contract Amounts: Project# 16-ENG-52 - PO#34297(COLT)=$8,169,713.53 Project#16-SW-07- PO#100354(SW)=$764,395.94 TOTAL CONTRACT=$8,934,109.47 NOTE: Substantial Completion Date: 12/15/2017 NOTE: Per the documents below this is a ZERO DOLLAR CHANGE ORDER II. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: * FINAL SMR 16 SW 07 Estimate 14 *Change Order 14 Report Springmill Road Reconstruction The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $ 9,104,835.24 Contract Price will be increased/Qeer-eased by this Change Order $ 170,725.77 New Contract Price including this Change Order $ 8,934,109.47 Contract Time Prior to this Change Order Days Completion Date Net increased/decreased resulting from this Change Order Day:, Current Contract Time including this Change Order Days Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. AR-1 Page 2 of 2 The Above Changes Are The Above Changes Are Ap roved: Recommended: Accepted: [� I United Consulting Rieth-Riley f V f (_5-PId ENGINEER CONTRACTOR Brai d, Ma r 1625 N. Post Road 1751 W. Minnesota Street Address Address Mary Burk Iember Indianapolis, IN 46219 Indianapolis, IN 46206 City/State/Zip City/State/Zip Lori t , Member By: By As efith Phone: av 7za sss2 Pho VIM Christine S. auley, Clerk- Treasurer Date: 7/22/2019 Date: l'3% I I a Jer y ashman, .E. ty Engineer —, / a / Date: "1 "( — / United Consulting, Inc. 'AUNlTED Consulting= Change Order Details Spring Mill Road Reconstruction 2 Description: Spring Mill Road Reconstruction from Millridge Drive to 106th Street City of Carmel Project No. 16-SW-07 First Group Engineering, Inc. Change Order: 2 Date Created: 06/10/2019 Status: Approved Date Approved: Type: Summary: Balancing Change Order - End Project Change Order Description: This Change Order is being created to balance final quantities for this project. Awarded Project Amount: $923,465.61 Authorized Project Amount: $935,121.71 Change Order Amount: -$170,725.77 Revised Project Amount: $764,395.94 Increases/Decreases Line Number Item Unit Unit Price Comma Gaye te,iad Q'—' yr Amami Quumatigr AMmot Quantity Amount Section: 1 -Default Section 146 146 CYS $33.740 10.00 $337.40 12.20 $411.63 22.20 $749.03 SEDIMENT, REMOVE Reason: Balancing Change Order 147 147 EACH $65.000 14.00 $910.00 -14.00 -$910.00 0.00 $0.00 TEMPORARY INLET PROTECTION Reason: Balancing Change Order 148 148 LFT $1.790 2,105.00 $3,767.95 -15.00 -$26.85 2,090.00 $3,741.10 TEMPORARY SILT FENCE Reason: Balancing Change Order 149 149 LBS $0.250 48.00 $12.00 -48.00 -$12.00 0.00 $0.00 TEMPORARY SEED MIXTURE Reason: Balancing Change Order 150 150 SYS $24.800 59.00 $1,463.20 59.20 $1,468.16 118.20 $2,931.36 SUBGRADE TREATMENT,TYPE II Reason: Balancing Change Order 151 151 SYS $1.830 1,597.00 $2,922.51 -1,597.00 -$2,922.51 0.00 $0.00 SUBGRADE TREATMENT,TYPE III Reason: Balancing Change Order Change Order Details: Spring Mill Road Page 1 of 5 08/14/2019 Reconstruction 2 I. Namior Item Unit Unit Price Current Mange Revised Quantity Aasereat Quantity Amount Quantity Amount 152 152 SYS $6.730 4,596.00 $30,931.08 1,183.00 $7,961.59 5,779.00 $38,892.67 SUBGRADE TREATMENT,TYPE IB Reason: Balancing Change Order 153 153 CYS $25.660 177.00 $4,541.82 19.00 $487.54 196.00 $5,029.36 STRUCTURE BACKFILL,TYPE 1 Reason: Balancing Change Order 155 155 CYS $73.450 36.00 $2,644.20 -9.00 -$661.05 27.00 $1,983.15 STRUCTURE BACKFILL,TYPE 5 Reason: Balancing Change Order 156 156 TON $32.870 295.00 $9,696.65 297.19 $9,768.64 592.19 $19,465.29 COMPACTED AGGREGATE NO. 53 BASE Reason: Balancing Change Order 157 157 TON $71.460 292.00 $20,866.32 27.98 $1,999.45 319.98 $22,865.77 HMA SURFACE,TYPE C Reason: Balancing Change Order 158 158 TON $56.710 487.00 $27,617.77 15.07 $854.62 502.07 $28,472.39 HMA INTERMEDIATE,TYPE C Reason: Balancing Change Order 158a 158a TON $54.130 641.00 $34,697.33 -116.30 -$6,295.32 524.70 $28,402.01 HMA INTERMEDIATE, OG,TYPE C Reason: Balancing Change Order 159 159 TON $51.900 1,207.00 $62,643.30 79.85 $4,144.22 1,286.85 $66,787.52 HMA BASE,TYPE C Reason: Balancing Change Order 160 160 TON $0.010 4.00 $0.04 -4.00 -$0.04 0.00 $0.00 ASPHALT FOR TACK COAT Reason: Balancing Change Order 161 161 TON $87.330 221.00 $19,299.93 41.99 $3,666.99 262.99 $22,966.92 HMA FOR SIDEWALKS Reason: Balancing Change Order 162 162 SYS $51.810 39.00 $2,020.59 71.60 $3,709.60 110.60 $5,730.19 SIDEWALK, CONCRETE, 4" Reason: Balancing Change Order 163 163 SYS $175.410 25.00 $4,385.25 5.90 $1,034.92 30.90 $5,420.17 CURB RAMP, CONCRETE Reason: Balancing Change Order 164 164 SYS $326.250 5.00 $1,631.25 -3.40 -$1,109.25 1.60 $522.00 DETECTABLE WARNING SURFACES Reason: Balancing Change Order 166 166 LFT $19.050 1,830.00 $34,861.50 -133.32 -$2,539.75 1,696.68 $32,321.75 CURB AND GUTTER, CONCRETE,TYPE II Reason: Balancing Change Order 168 168 LFT $48.660 262.00 $12,748.92 -34.50 -$1,678.77 227.50 $11,070.15 CONCRETE ROLL CURB &GUTTER Reason: Balancing Change Order Change Order Details: Spring Mill Road Page 2 of 5 08/14/2019 Reconstruction 2 Lase Nimier Item Unit Unit Pride Current Miaow Revised Quaatity Amount Quantity Aa.ant Quantity Amount 169 169 SYS $60.950 59.00 $3,596.05 59.20 $3,608.24 118.20 $7,204.29 PCCP FOR APPROACHES, 6 IN. Reason: Balancing Change Order 171 171 SYS $0.990 1,140.00 $1,128.60 -3.40 -$3.37 1,136.60 $1,125.23 GEOTEXTILES Reason: Balancing Change Order 172 172 TON $46.350 1,070.00 $49,594.50 16.24 $752.72 1,086.24 $50,347.22 RIPRAP, CLASS 1 Reason: Balancing Change Order 173 173 TON $23.160 260.00 $6,021.60 -241.44 -$5,591.75 18.56 $429.85 RIPRAP, REVETMENT Reason: Balancing Change Order 174 174 TON $95.960 4.00 $383.84 -4.00 -$383.84 0.00 $0.00 RIPRAE UNIFORM {HAND LAID} Reason: Balancing Change Order 175 175 EACH $50.000 2.00 $100.00 -2.00 -$100.00 0.00 $0.00 MOBILIZATION AND DEMOBILIZATION FOR SEEDING Reason: Balancing Change Order 176 176 SYS $1.170 1,375.00 $1,608.75 -627.00 -$733.59 748.00 $875.16 EROSION CONTROL BLANKET Reason: Balancing Change Order 177 177 M.G. $1.000 25.00 $25.00 -25.00 -$25.00 0.00 $0.00 WATER Reason: Balancing Change Order 178 178 CYS $45.640 1,169.00 $53,353.16 -1,169.00 -$53,353.16 0.00 $0.00 TOPSOIL Reason: Balancing Change Order 179 179 SYS $3.250 3,540.00 $11,505.00 -249.70 -$811.52 3,290.30 $10,693.48 SODDING, NURSERY Reason: Balancing Change Order 181 181 LFT $305.360 176.00 $53,743.36 -176.00 -$53,743.36 0.00 $0.00 24 IN. SDR 11 HDPE WATER MAIN Reason: Balancing Change Order 182 182 LFT $724.080 25.00 $18,102.00 -25.00 -$18,102.00 0.00 $0.00 20 IN. RESTRAINED JOINT DUCTILE IRON Reason: Balancing Change Order 183 183 EACH $17,268.550 2.00 $34,537.10 -2.00 -$34,537.10 0.00 $0.00 20" LINE STOP Reason: Balancing Change Order 184 184 EACH $6,202.220 2.00 $12,404.44 -2.00 -$12,404.44 0.00 $0.00 20 IN. CONNECTION Reason: Balancing Change Order 187 187 LFT $4.750 2,274.00 $10,801.50 -130.00 -$617.50 2,144.00 $10,184.00 PIPE,TYPE 4, CIRCULAR, 6 IN. Reason: Balancing Change Order Change Order Details: Spring Mill Road Page 3 of 5 08/14/2019 Reconstruction 2 Lime Number Item Unit Unit Price Cosiest Change Revised Quantity Aaoeat Quantity Aasoe t Quantity Amount 188 188 LFT $14.500 191.00 $2,769.50 -133.00 -$1,928.50 58.00 $841.00 PIPE, UNDERDRAIN, OUTLET 6 IN. Reason: Balancing Change Order 189 189 LFT $42.680 642.00 $27,400.56 -37.70 -$1,609.04 604.30 $25,791.52 PIPE,TYPE 2, CIRCULAR, 12 IN. Reason: Balancing Change Order 190 190 LFT $235.300 15.00 $3,529.50 -15.00 -$3,529.50 0.00 $0.00 PIPE,TYPE 2, CIRCULAR, 15 IN. Reason: Balancing Change Order 191 191 LFT $2.390 655.00 $1,565.45 -2.80 -$6.69 652.20 $1,558.76 VIDEO INSPECTION FOR PIPE Reason: Balancing Change Order 193 193 LFT $0.990 3,000.00 $2,970.00 -1,435.30 -$1,420.95 1,564.70 $1,549.05 VIDEO INSPECTION FOR UNDERDRAINS Reason: Balancing Change Order 194 194 CYS $50.000 94.00 $4,700.00 -26.70 -$1,335.00 67.30 $3,365.00 AGGREGATE FOR UNDERDRAINS Reason: Balancing Change Order 195 195 SYS $2.400 1,076.00 $2,582.40 -123.00 -$295.20 953.00 $2,287.20 GEOTEXTILES FOR UNDERDRAIN Reason: Balancing Change Order 197 197 EACH $866.870 6.00 $5,201.22 -2.00 -$1,733.74 4.00 $3,467.48 CASTING,ADJUST TO GRADE Reason: Balancing Change Order 205 205 EACH $244.000 17.00 $4,148.00 -6.00 -$1,464.00 11.00 $2,684.00 CONSTRUCTION SIGN,A Reason: Balancing Change Order 208 208 LET $14.000 81.00 $1,134.00 -81.00 -$1,134.00 0.00 $0.00 SIGN POST, SQUARE TYPE 1 REINFORCED ANCHOR BASE Reason: Balancing Change Order 209 209 EACH $20.000 8.00 $160.00 -8.00 -$160.00 0.00 $0.00 SIGN GROUND MOUNTED RESET Reason: Balancing Change Order 210 210 LFT $0.730 209.00 $152.57 140.00 $102.20 349.00 $254.77 LINE,THERMOPLASTIC, SOLID,WHITE, 4 IN. Reason: Balancing Change Order 211 211 LFT $0.730 2,073.00 $1,513.29 100.00 $73.00 2,173.00 $1,586.29 LINE,THERMOPLASTIC, SOLID,YELLOW, 4 IN. Reason: Balancing Change Order 212 212 LFT $5.650 15.00 $84.75 98.00 $553.70 113.00 $638.45 TRANSVERSE MARKING,THERMOPLASTIC, STOP LINE, WHITE, 24 IN. Reason: Balancing Change Order Change Order Details: Spring Mill Road Page 4 of 5 08/14/2019 Reconstruction 2 Use Number Item Unit Unit Price Current Change Revised Quantity Amount Quantity Amount Quantity Amount 213 213 LFT $1.400 103.00 $144.20 -103.00 $11-1.20 0.00 $0.00 TRANSVERSE MARKING,THERMOPLASTIC, CROSSWALK LINE, WHITE, 6 IN. Reason: Balancing Change Order (51Items) Totals $52,S5 .35 -$170,725.77 $422,233.58 Attachments Name 16-SW-07 Invoice_14.pdf SMR 16 SW 07 Estimate 14.pdf (2 Attachments) Change Order Details: Spring Mill Road Page 5 of 5 08/1 1/201 9 Reconstruction 2