CARMEL PLAN COMMISSION
DEPARTMENT REPORT
SEPTEMBER 17, 2019
2. Docket No. 19060018 DP: Carmel Hotel and Office.
The applicant seeks site plan approval for two building pads and associated parking on 2.96 acres. The site is
located at 12166 N. Meridian Street. The site is zoned MC/Meridian Corridor. Filed by Brad Schrage of
American Structurepoint on behalf of Michael Garvey of Diversified Land Acquisitions, LLC.
Project Overview:
The Petitioner proposes a development plan for two new buildings to be constructed on the vacant ADT site located north
of the Ritz Charles. The Meridian Medical Plaza office buildings are located immediately north of this site, to the west is
the Spring Lake Estates neighborhood zoned S-2, and to the east across Meridian Street is the Wagner Reese office
building, also zoned MC. Please view the Petitioner’s informational packet for more detail.
Unified Development Ordinance (UDO) Standards this project MEETS:
MC/Meridian Corridor:
• Permitted Uses: Hotel (upper floors only*) and general
office
• Minimum Front Yard setback from US 31 for buildings
and parking – 50’ required, 69.4’ proposed
• Minimum Side Yard (north) – 15’ for principal building
required, 61’ proposed
• Minimum Rear Yard (west) – 0’ for all buildings and
surface parking if cooperative agreement is in place,
about 120’ proposed for building, 6’ for parking
• Maximum Lot Coverage – 80% allowed, about 67%
proposed
• Minimum Building height –3 stories required, 3 story
office building and 5 story hotel proposed
• Maximum building height – 8 stories
allowed
• Number of Parking spaces – 133 spaces
plus shared parking with Ritz Charles site
proposed
o Hotel requires 1 space per room
and 1 per employee per largest
shift – at least 127 required
o Office requires 1 space per 350
sq. ft. – 137 required
Article 5:
• Trash enclosures proposed on the site
plan, will be architecturally compatible
with principal buildings when submitted
for ADLS approval
UDO Standards NOT MET, therefore adjustments or variance requests are needed:
• Minimum Side Yard (north) – 20’ for surface parking required, 5’ proposed in one area, 30’ proposed in another
• At least 2 primary buildings required for wide lot width covering at least 75% of the lot’s width; 1 hotel and 1
office building proposed at about 45% lot width coverage
• *Docket No. 18050007 UV: UDO Section 2.39 Hotel Use on upper floors only allowed, hotel use proposed on
ground floor. Approved by BZA on June 25, 2018 4-0 with a Condition that the site plan was not finalized and
including attached residential dwelling units are a possibility. (Background info – the residential component was
desired when there was a parking garage proposed as part of the project. Surface parking is now proposed
instead of the parking garage.)
Meridian Corridor (MC) District analysis:
The purpose of the Meridian Corridor (MC) district is to further develop and build out the US 31 Corridor. Quality
development of mixed use sites is encouraged. The goal is to transition the corridor to a more pedestrian friendly area,
with public transit options and mixed use development opportunities that can share parking and provide day and evening
activities and vitality. The MC is not intended to be in conflict with suburban residential areas. However, it can be
adjacent to these areas, with proper transitions. Appropriate transitional elements are considered the tapering of building
heights, staggered building facades, and the use of landscaping buffers.
5
Site Plan, Parking and Engineering:
The Petitioner is seeking approval for an overall development plan for two new buildings – a hotel and an office building.
The buildings will be oriented west/east, fronting onto Meridian Street. A five story hotel with 127 rooms and a three
story office building with 48,000 sq. ft. of floor area are proposed. The development plan will provide pads for these two
buildings, along with associated stormwater management, utility infrastructure, parking, sidewalks, and access drives. The
Petitioner has secured an access agreement with the Ritz Charles to enter the site from Illinois Street to the west. They
also propose two street cuts onto the frontage road along Meridian Street (east of the buildings).
The MC district requires 1 space per unit plus one space per employee on the largest shift for hotels. Office uses require
one space per 350 sq. ft. This means that 137 parking spaces are needed for the office building and at least 127 spaces are
needed for the hotel. The number of employees has not been provided yet. Petitioner, please tell us the number of
employees for the hotel on their largest shift. The MC does allow for off-site parking to count towards the total number
of spaces for a site. A shared parking agreement has been reached with the Ritz Charles. The office and hotel uses
proposed for this site have compatible off hour parking needs. Therefore, the 133 proposed parking spaces, along with the
shared parking agreement of the Ritz, Staff believes this parking arrangement will work. If necessary, an additional
agreement could be sought from the office buildings to the north.
Two dry detention ponds are proposed along the east side of the buildings. Both the Carmel Engineering Dept. and
Crossroad Engineers are currently reviewing the plans and working with the Petitioner on compliance.
Active Transportation:
A new sidewalk will be installed along the frontage road. Additional sidewalks will be installed providing access from the
frontage road to and around each of the buildings. A connection will also be added across the Ritz Charles site to provide
protected pedestrian access to Illinois Street. Lastly, a pedestrian connection is proposed in the middle of the parking to
the west of the buildings.
Bicycle parking will be provided adjacent to the each of the front doors of the respective buildings. The hotel would
require 4 short term spaces and 9 long term spaces. The office building would require 5 short term spaces. Long term
parking spaces are encouraged for office buildings, but are not required. We will find out more about long term bicycle
parking when the Petitioner submits ADLS approvals for each of these buildings at a later date.
Landscaping:
The Urban Forester has reviewed the landscaping plan and made comments for the Petitioner to update their plans.
Multiple landscape islands are proposed throughout the parking areas to help delineate drive aisles. A long landscape
border is proposed on the west property line, which will help to meet buffer requirements and preserve existing trees in
that grassy area.
DOCS Remaining Comments/Concerns:
The Department is still working through review comments with the Petitioner.
Recommendation:
The Dept. of Community Services recommends the Plan Commission sends this item to the Commercial Committee
meeting on Tuesday, October 1, 2019, for further review and discussion.