HomeMy WebLinkAboutD101.A FIRST FLOOR DEMOLITION PLAN -AREA A_DeC
eK
TYPICAL DEMO AT
12" = V-OF
I 2 2
1LI
GENERAL DEMOLITION NOTES
A. INVESTIGATE ALL EXISTING CONDITIONS (INCLUDING CONCEALED OR UNDOCUMENTED
CONDITIONS) PRIORTO DEMOLITION. NOTIFYTHE PROJECT TEAM OF ANY CONFLICTS
PRIOR TO PROCEEDING
B. ALL FURNITURE AND FURNISHINGS WILL BE REMOVED, RELOCATED ANDIOR STORED BY
OWNER UNLESS NOTED OTHERWISE.
C. ALL ITEMS BEING REMOVED SHALL REMAIN THE PROPERTY OF THE OWNER UNTIL
CONFIRMATION HAS BEEN MADE AS TO WHETHER THE OWNER WILL RETAIN SUCH
ITEMS. CONTRACTOR SHALL COORDINATE WITH OWNER REGARDING DELIVERY OF ALL
ITEMS BEING RETAINED; ALL ITEMS NOT BEING RETAINED BY THE OWNER OR
DESIGNATED ON THE DRAWINGS TO BE SALVAGED, RELOCATED OR REINSTALLED
REMOVE WALL CONSTRUCTION
SHALL BE COMPLETELY REMOVED FROM THE SITE.
FLUSH WITH EXISTING BULKHEAD
D. THE DEMOLITION CONTRACTOR SHALL PROVIDE AND INSTALL TEMPORARY DUST
PARTITIONS, CONSTRUCTION BARRIERS, TEMPORARY DOORS, WALK -OFF MATS AND
EQUIPMENT PROTECTION WHERE SHOWN ON THE DOCUMENTS OR IF NOT SHOWN, AS
REQUIRED BY THE WORK BEING PERFORMED. TEMPORARY DUST PARTITION SHALL BE
a�
COMPLETELY SEALED TO PREVENT CONSTRUCTION DUST FROM ENTERING OWNER'S
— CAREFULLY REMOVE WALL
ADJACENT SPACES. DUST PARTITION DOOR TO BE SELF CLOSING, POSITIVE LATCHING,
CONSTRUCTION FLUSH TO
AND PAD -LOCKABLE. SUCH PROTECTION SHALL BE MAINTAINED AND REPAIRED
EXISTING MULLION. REPAIR
PROMPTLY IF DAMAGED TO AVOID DUST INFILTRATION INTO ADJACENT AREAS.
MULLION AS REQUIRED
PROVIDE HEPA FILTER FILTRATION AND NEGATIVE AIR MACHINES WITH MONITORING
GAUGES. THE DEMOLITION CONTRACTOR SHALL ERECT TEMPORARY PARTITIONS AS
NEEDED BETWEEN THE CURRENT LOBBY AND THE NEW LOBBY FOR CONTINUOUS
— CAREFULLY REMOVE WALL
OPERATIONS OF LOBBY STAFF.
CONSTRUCTION FLUSH TO EXISTING
E. COVER ALL RETURN AIR GRILLES AND EXHAUST GRILLES IN CONSTRUCTION AREA WITH
METAL WINDOW SILLUDIGYP
MIN. MERV 13 FILTER MEDIA CHANGED REGULARLY.
IEEE 03DIA1 FOR
F. REFER TO MECHANICAL, ELECTRICAL, AND PLUMBING DOCUMENTS FOR RESPECTIVE
REPAIR
DEMOLITION INFORMATION.
G. FILL ALL FLOOR CONSTRUCTION WHERE PIPING, CONDUITS, AND OTHER
a
PENETRATIONS HAVE BEEN REMOVED.
H. DEMOLITION WORK SHALL BE PERFORMED DURING NORMAL WORKING HOURS UNLESS
NOISE WILL EXCEED OSHA THRESHOLDS. IF NOISE IS ANTICIPATED TO EXCEED OSHA
THRESHOLDS, CONTRACTOR SHALL COORDINATE WITH OWNER TO ADJUST WORT(
HOURS TO MORE APPROPRIATE TIMES. CONTRACTOR SHALL USE ALL METHODS TO
DECREASE NOISE IMPACT.
L DURING THE ENTIRE PERIOD OF DEMOLITION AND CONSTRUCTION, ALL EXISTING EXITS,
EXIT LIGHTING, FIRE PROTECTIVE DEVICES AND ALARMS FOR THE ENTIRE BUILDING
SHALL BE CONTINUOUSLY MAINTAINED. DAY-TQDAY FUNCTION OF THE REST OF THE
BUILDING SHALL BE FULLY MAINTAINED.
J. ASBESTOS CONTAINING MATERIAL IS NOT ANTICIPATED IN THE AREA OF DEMOLTION. IF
_L/WINDOW MULLION
ACWs
MMED AEESUSPECTED OR ENCOUNTED, CONTRACTOR SHALL NOTIFY THE ARCHITECT
K. REMOVE ALL WALL COVERING, OTHER WALL TREATMENT, AND ATTACHMENTS. PATCH,
SKIM COAT, AND PREPARE FOR FINAL FINISH ON WALLS NOT BEING COVERED BY NEW
CONSTRUCTION.
L. IF USING A DEMOLITION CHUTE, IT SHALL BE FULLY ENCLOSED.
M. CONTRACTOR TO REMOVE ALL PROJECTOR EQUIPMENT AND MOUNTINGS AND TURN
OVER TO OWNER.
KEYED DEMO PLAN NOTES (NOTED WITH O)
1 REMOVE WALL CONSTRUCTION IN ITS ENTIRETY. PRIOR TO
DEMOLITION, CAREFULLY INVESTIGATE CONCEALED CONDITIONS TO
VERIFY THERE IS NO ACTIVE INFRASTRUCTURE. WHERE WALL TO BE
DEMOLISHED STOPS SHORT OF CEILING, CAREFULLY REMOVE WALL
CONSTRUCTION TO MINIMIZE CEILING GRID REPAIR UNLESS NOTED
OTHERWISE
2 DEMO CASEWORK
3 ALLABANDONED OR UNECESSARV FIXTURES, OUTLETS OR
COVERPLATES TO BE REMOVED. MEP TRADES TO REMOVE/CAP ITEMS
AS REQUIRED SO THEY ARE FULLY CONCEALED BY NEW
CONSTRUCTIOWFINISHES. EXPOSED COVERPLATES OR CAPS ARE
NOT ACCEPTABLE UNLESS SPECIFICALLY APPROVED BY PROJECT
TEAM. THIS NOTE IS TYPICAL, THROUGHOUT ENTIRE FIRST FLOOR
4 REMOVE DOOR AND/OR GLAZING INCLUDING FRAME AND HARDWARE.
TURN HARDWARE OVER TO OWNER
5 REMOVE CEILING TILE, GRID AND SUSPENSION SYSTEM IN ITS
ENTIRETY. RE -SUPPORT REMAINING ADJACENT CEILING GRID AS
REQUIRED. COORDINATE WITH NEW CONSTRUCTION
6 REMOVE FLOORING. REMOVE ADHESIVE/GROUT
REMOVE EXISTING PLUMBING FIXTURE; PLUMBING TRADES TO
CAP/REMOVE PIPING AS REQUIRED
8 FOOD SERVICE CONTRACTOR TO REMOVE EQUIPMENT AND STORE
FOR OWNER TO RELOCATE.
Q 9 R
ONE ISTI WAL ONS UCTI AS UIR FOR W
O
U E
10 REMOVE EXISTING DOOR AND HARDWARE FROM STOREFRONT AS
SHOWN IN ELEVATIONS AND PREP FOR NEW OPENING. TURN DOOR
OVER TO OWNER WHEN COMPLETE
DOOR AND ALUMINUM FRAME - TURN HARDWARE OVER TO OWNER
12 EXISTING MEP ROOMS TO REMAIN
uL u•�� �•u I A-`V N 13 EXISTING WINDOWS, METAL SILL, KNEE WALL, BULKHEAD AND BLINDS
TO REMAIN. PROTECT AS REQUIRED
0014 EXISTING GYPSUM BOARD COLUMN SURROUND TO BE REMOVED AND
e5. :� - - - - - - - - - - - - - - - - - J - - - - e5 REINSTALLED AS PART OF NEW WORK. ADJACENT CONSTRUCTION
THAT IS BEING DEMOLISHED SHOULD BE CAREFULLY REMOVED TO
3�l EXTINMINIMGUISHER
CABINET
HOUSINGS
REMOVE AND THEY ETAINXIST FIRE
EXTINGUISHER XTING ISHER FOR
WHERE THEY EXIST. RETAIN
le4 8,� EXISTING FIRE EXTINGUISHERS FOR RE -USE
y 15 WHERE INDOW MULLION,
R WALLTO DETAIL
INTERSECTS EXTERIOR
WINDOW MULLION, REFER TO DETAIL CONSTRUCTION
I
16 REMOVE ACCORDION GRILLE, FRAME, AND HARDWARE IN ENTIRETY
iT REMOVE BULKHEAD IN ENTIRETY
18 DEMOLISH ALL CEILING TILES. EXISTING CEILING GRID TO BE
REPAIRED THEN RE -INSTALLED AS REQUIRED FOR NEW
CONSTRUCTION
19 DEMOLISH DAMAGED CEILING TILES ONLY, TH IS ROOM. EXISTING
CEILING GRID TO BE REPAIRED THEN RE -INSTALLED AS REQUIRED FOR
NEW CONSTRUCTION
20 REMOVE PORTION OF WALL TO DIMENSION INDICATED
' - - 04.2 21 REMOVE AND SALVAGE DIR17 WALL AND STORE FOR OW NER
22 REMOVEEXISTING STOREFRONT AND TURN OVERTOOWNERTO
-4 23 REMOVEANDSALVAGE FIRE EXTINGUISHER CABINET AND FIRE
�e4� RELOCATE
9 12'-6' I ------~ 6 6 - EXTINGUISHER IN ENTIRETY FOR REUSE IN NEW CONSTRUCTION ---- A ---- 23' S112----
r----———— ----=r _--=------------_r—_— --- ___ __ _
�e3T L I I as:asT - �rT'�T-�i4� - '4�� - - -
_. �� i2I y 3�C V/"111 A`- I /� i121 -
�- - -- --� ;2oI (1i J w�3�1� �' 1�F1 ��zfi�� 3'r1 B I I(sl (20,I 1201 I
I I
r� �° 1231�
�11
12.I?o,� I L. �LJ� •�I����� I _,I� I I (iz1 (1zI �1zI
le35� -
L 1-1 2�I --- - - jj --, j �y 7i r"k r',��
-'----
— - I - zo7 - 41201jl - - - - _ - - �321
II[, I r�l I I —���� 1 . ,
1 '741� II1� �e3�
2'I ^,I j II '2o II i •-I'�
�.3. I I
t141 ti'8� 1 2111
%
l - 22 I v f� I I IIIt� N I I
�s� C1o�> �s;� _� 1j I I I MI ,tiI �s �s ;201_
'`2j1 I I I I U 11 s�-n
_ 41
'-'1IIj�I
a3
-A 3 '�3
-
k�,_6
a .'. ,
_
tije2w
� eM eN e0 eP I eG I
iz;:a�l LJL II IIr-1 I s
�131 \? � I II
13
eG eH el eK eL
RELEASED FOR CONSTRUCTION
Subject to compliance with all regulations
of State and Local Codes
City of Calmed
��1Y�Jl
DATE: 09/24/19
NOTES:
A. REFER TO 3I3TSCALE SHEETS FOR PLAN KEYNOTES.
B. REFER TO SHEET D121 FOR CEILING DEMOLITION.
C. ALL DEMOLITION DIMENSIONS WE PROVIDED FOR
REFERENCE ONLY. CONTRACTOR SHALL FIELD VERIFY ALL
MEASUREMENTS.
D. SHADED AREA INDICATES AREA OF PREVIOUS AND
FUTURE WORK
N KEY PLAN
�12. = V-0= V-D'
GEICO
_N
O EeICAN
®■ STRUCTUREPOINT
7260 SM1adeland Slation I Indianapolis, Indiana M256
TEL 31].54].5560 1 fA%31].503.02]0
www.Snetumpnim.00m
GEICO CORPORATE
FIRST FLOOR
RENOVATION PHASE 3
101 W. 103RD ST.
INDIANAPOLIS, IN 46290
CERTIFIED BY
ISSUANCEINDEX
DATE:
05/37N9
PROJECT PHASE:
CONSTRUCTION DOCUMENTS
PHASE 3
REVISION SCHEDULE
NO. I DESCRIPTION I DATE
Project Number 2017.01381
FIRST FLOOR
DEMOLITION PLAN -
AREA A/D
D 1010A