HomeMy WebLinkAbout19090147 Sewer Permit10701 N. College Avenue Suite A Indianapolis, Indiana 46280 phone 317-844-9200 fax 317-844-9203 www.tdco.eco
(Residential
SANITARY SEWER PERMIT
999913413
Permit Type
Final
Subdivision
Jacksons Grant
Project WO
2017-1315
Section Number
5
Project Name
Jacksons Grant Section 5
Lot Number
262
Project Developer
Jackson's Grant Real Estate Company
Address Number
522
Lift Station
02 Meridian Corridor Station
Address 2
Treatment Plant
MIX
Street
Dickson Lane
Parcel Acreage
EDU in Gallons
0.21
310
Local Sewer Charge - District Contribution
0.00
Plan Review and Inspection
0.00
Application Fee
150.00
EDU Fee
1908.00
Interceptor Fee
0.00
Other Fees
0.00
Fees Due
2068.00
Invoice Number
City
Zip Code
County
Builder
Phone Number
Owner
Phone Number
Occupant
Phone Number
Carmel
46032
Hamilton
Old Town Design Group
317-605-8796
PLEASE NOTE: Installation of building sewer shall be per the specifications of the TriCo Regional Sewer Utility (see
reverse) and any conditions noted below. All installations shall be inspected by TriCo personnel during "open trench"
phase and before backfilling with stone to twelve inches above the pipe. NO footing or foundation drains, or other
sources of ground or stormwater, shall be permitted to enter TriCo's sanitary sewer system. TriCo will assume no
liability for drains which are below the grade level of the nearest downstream manhole nor for laterals which are
extended beneath driveways or sidewalks. The permit holder (property owner, developer or builder) will be
responsible for damages to TriCo's sewer system. This includes damages to manholes, castings, manhole lids and
the like; caused by construction activity on the building site which is the subject of this permit.
Inspections by TriCo are MANDATORY and shall be arranged by contacting TriCo's office at 844-9200 24 hours in
advance. All new construction will be placed on billing two months after connection has been made or when water is
connected, whichever comes first.
The building has: Main ID: JG846JG847
Grease Trap Slab Foundation
Grease Interceptor Crawl Space Manhole IDs USMH JG-846 JG-847 DSMH
Grit Interceptor Basement YES Lid Elevation 856.78 857.31
Grinder Station First Floor Elevation
858.33 858.33
Water Service City of Carmel Basement Elevation 848.33 848.33
Calculation is based on both Manhole Lid Elevations and the elevation of the First Floor i 1.55 1.02 Ft.
Per Ordinance 9-13-99 and the elevations provided, the substructure shall be plumbed by: Ejector Pump Only
� �n TriCo currently requires that an I&I inspection is performed and a Certificate of Compliance is issued prior to occupancy /
'�q sale of a properrty. Please review attached 1/1 Permit.
/--d C) Manholes shall remain accessible at all times. Buried manholes will be corrected by the Developer/Owner.
The proper class of cleanout must be installed every 100 feet of lateral pipe measured from sewer main to structure.
The terms of the conditional permit, if any, are listed below.
Plans have been submitted.
All fees have been
No certificate of insurance
No additional permits required.
No manhole core permit required. I a TriCo
The facilitv is not classified as a FOG facility m r
By signing below, I attest thafl, am ,rlarwiththe-E
Builder / Owner Signature 4
Printed Name [/ VI / A I>
Approved By
(Notes)
and agree to accept responsibility for all work done under this pennit.
Phone Numbel(.S(Z-)(L- fl
09/19/2019
Permit is valid for ON YEAR from the date issued. Permit valid only with TriCo seal in red ink.