Client: Larry Wesner
Property: 800 E 104th St
Indianapolis, IN 46280
Operator: RJRMICHA
Estimator: Rick Michaelis Jr. Business: (317) 601-0902
Company: Michaelis Corporation
Business: 2601 East 56th Street
Indianapolis, IN 46220
Type of Estimate: Vehicle Damaged Property
Date Entered: 7/15/2019 Date Assigned:
Price List: ININ8X_JUL19
Labor Efficiency: Restoration/Service/Remodel
Estimate: 19-2003RR
10/15/19
William Hohlt
2
MICHAELIS CORPORATION
CONSTRUCT. RENOVATE. RESTORE.
2601 East 56th Street
Indianapolis IN 46220
(317) 251-1935 P
(317) 251-2599 F
1-844-FIX-INDY
19-2003RR 9/13/2019 Page: 2
19-2003RR
19-2003RR
DESCRIPTION QTY RESET REMOVE REPLACE TAX O&P TOTAL
Taxes, insurance, permits & fees (Bid 1.00 EA AS INCURRED
Item)
Dumpster load - Approx. 40 yards, 7-8 1.00 EA 700.00 0.00 0.00 140.00 840.00
tons of debris
Job-site cargo/storage container - 20' 2.00 MO 0.00 87.83 0.00 35.14 210.80
long - per month
***To be set at end of driveway so homeowner can access contents.
Job-site cargo container - pick up/del. 2.00 EA 0.00 99.40 13.92 42.54 255.26
(each way) 16'-40'
Content Manipulation charge - per hour 12.00 HR By Customer
***Labor to pack out garage and garage attic into and out of an onsite pod.
Header - double 2" x 10" 20.00 LF 0.00 7.15 5.01 29.60 177.61
***Below line items are to create temporary interior garage beam to remove and replace TMP wall and damaged load bearing wall.
Temporary shoring post - Screw jack 6.00 DA 0.00 30.98 0.00 37.18 223.06
(per day)
Carpenter - General Framer - per hour 16.00 HR 0.00 54.51 0.00 174.44 1,046.60
Total: 19-2003RR 18.93 458.90 2,753.33
Main Level
Main Level
DESCRIPTION QTY RESET REMOVE REPLACE TAX O&P TOTAL
Header - double 2" x 10" 12.00 LF 0.00 7.15 3.01 17.76 106.57
***Garage door header is split.
2" x 4" x 20' #2 & better Fir / Larch 3.00 EA 0.00 10.58 2.22 6.78 40.74
(material only)
2" x 2" x 8' #2 & better Fir / Larch 14.00 EA 0.00 2.16 2.12 6.46 38.82
(material only)
2" x 4" x 104 5/8" pre-cut stud (for 9' 26.00 EA 0.00 4.30 7.83 23.92 143.55
wall, mat only)
Sheathing - OSB - 1/2" 255.44 SF 0.00 1.08 6.62 56.50 339.00
Labor to frame 2" x 4" load bearing 331.77 SF 0.00 1.12 0.46 74.42 446.46
wall - 16" oc
***Load bearing
General Demolition - per hour 16.00 HR 37.80 0.00 0.00 120.96 725.76
Total: Main Level 22.26 306.80 1,840.90
10/15/19
William Hohlt
3
MICHAELIS CORPORATION
CONSTRUCT. RENOVATE. RESTORE.
2601 East 56th Street
Indianapolis IN 46220
(317) 251-1935 P
(317) 251-2599 F
1-844-FIX-INDY
19-2003RR 9/13/2019 Page: 3
Garage2' 6"16' 2" 16' 6" 1' 2"9' 2' 7"
2' 11"
2' 8"
3'19' 6"20' 2"2' 6"
11' 1"
11' 5"Garage Height: 8'
540.00 SF Walls
817.88 SF Walls & Ceiling
30.88 SY Flooring
67.50 LF Ceil. Perimeter
277.88 SF Ceiling
277.88 SF Floor
67.50 LF Floor Perimeter
DESCRIPTION QTY RESET REMOVE REPLACE TAX O&P TOTAL
1/2" drywall - hung, taped, floated, 569.94 SF 0.00 1.99 17.55 230.36 1,382.09
ready for paint
Seal/prime then paint the surface area 569.94 SF 0.00 0.82 6.38 94.76 568.49
(2 coats)
Paint the surface area - one coat 281.16 SF 0.00 0.56 2.17 31.94 191.56
Water softener - Detach & reset 1.00 EA By Customer
Detach & Reset Fluorescent light 2.00 EA By Customer
fixture
Remove & Replace Casing - 3 1/4" 29.00 LF 0.39 2.19 2.92 15.54 93.28
Overhead door & hardware - 9' x 7' 1.00 EA 0.00 686.53 35.98 144.50 867.01
(Install) Overhead (garage) door opener 1.00 EA 0.00 129.25 0.00 25.86 155.11
***Homeowner will purchase opener.
Paint overhead door - 2 coats (per side) 1.00 EA 0.00 101.77 2.50 20.86 125.13
Electrician - per hour 4.00 HR 0.00 88.02 0.00 70.42 422.50
110 volt copper wiring run, box and 2.00 EA 0.00 58.84 1.54 23.84 143.06
outlet
***Add two additional outlets.
Remove & Replace 110 volt copper 2.00 EA 4.05 72.53 3.39 31.32 187.87
wiring run, box and double outlet
***Change two existing outlets to double outlets.
Paint casing - two coats 29.00 LF 0.00 1.23 0.22 7.18 43.07
Remove Pegboard 30.00 SF 0.23 0.00 0.00 1.38 8.28
(Install) Pegboard 30.00 SF 0.00 1.21 0.00 7.26 43.56
Vinyl window, horizontal sliding, 12- 1.00 EA By Customer
23 sf
Add on for grid (double or triple glazed 13.00 SF By Customer
windows)
Add on for obscure glass 13.00 SF By Customer
Remove & Replace Ceiling hook 8.00 EA By Customer
10/15/19
William Hohlt
4
MICHAELIS CORPORATION
CONSTRUCT. RENOVATE. RESTORE.
2601 East 56th Street
Indianapolis IN 46220
(317) 251-1935 P
(317) 251-2599 F
1-844-FIX-INDY
19-2003RR 9/13/2019 Page: 4
CONTINUED - Garage
DESCRIPTION QTY REMOVE REPLACE TOTALTAX O&P RESET
Totals: Garage 72.65 705.22 4,231.01
Total: Main Level 94.91 1,012.02 6,071.91
Exterior
DESCRIPTION QTY RESET REMOVE REPLACE TAX O&P TOTAL
Storm door assembly 1.00 EA 0.00 219.78 10.64 46.08 276.50
(Material Only) Limestone veneer 353.49 SF 0.00 23.13 176.43 1,670.52 10,023.17
***Mason has found existing stone is no longer available and would cost $17,000 to manufacture. He thinks 2" cut limestone, after painted,
will blend well. He has been quoted at $6,000 for material only, that will still need a small bevel cut. Will meet with homeowner to make
sure the stone is agreeable and follow up with full labor + Material pricing.
Masonry (Labor) 1.00 EA OPEN ITEM
***Labor cost can not e determined as labor hours are not defined. Mason will need to grind each stone on the top and bottom edge to
create the bevel.
Paint brick 353.49 SF 0.00 0.73 6.93 53.00 317.98
Light bulb - Halogen spot/flood 2.00 EA By Customer
(PAR30) - mat. only
Motion sensor for exterior light fixture 2.00 EA By Customer
Exterior light fixture 2.00 EA By Customer
Fascia - metal - 4" 15.00 LF 0.00 3.26 1.17 10.02 60.09
Gutter / downspout - aluminum - 6" 16.00 LF By Customer
Totals: Exterior 195.17 1,779.62 10,677.74
Siding
DESCRIPTION QTY RESET REMOVE REPLACE TAX O&P TOTAL
Soffit & fascia - metal - 2' overhang 25.00 LF 0.00 11.76 10.05 60.82 364.87
Attic vent - gable end - vinyl 1.00 EA 0.00 106.21 5.14 22.26 133.61
Remove & Replace Vinyl J trim 8.00 LF 0.79 2.44 0.30 5.22 31.36
Siding - vinyl 8.00 SF 0.00 3.00 0.76 4.96 29.72
Vinyl outside corner post 4.00 LF 0.00 4.19 0.54 3.46 20.76
Totals: Siding 16.79 96.72 580.32
10/15/19
William Hohlt
5
MICHAELIS CORPORATION
CONSTRUCT. RENOVATE. RESTORE.
2601 East 56th Street
Indianapolis IN 46220
(317) 251-1935 P
(317) 251-2599 F
1-844-FIX-INDY
19-2003RR 9/13/2019 Page: 5
Labor Minimums Applied
DESCRIPTION QTY RESET REMOVE REPLACE TAX O&P TOTAL
Door labor minimum 1.00 EA 0.00 73.40 0.00 14.68 88.08
Totals: Labor Minimums Applied 0.00 14.68 88.08
Line Item Totals: 19-2003RR 325.80 3,361.94 20,171.38
Grand Total Areas:
540.00 SF Walls 277.88 SF Ceiling SF Walls and Ceiling817.88
277.88 SF Floor 30.88 SY Flooring 67.50 LF Floor Perimeter
0.00 SF Long Wall 0.00 SF Short Wall 67.50 LF Ceil. Perimeter
277.88 Floor Area 300.82 Total Area 540.00 Interior Wall Area
631.50 Exterior Wall Area 70.17 Exterior Perimeter of
Walls
0.00 Surface Area 0.00 Number of Squares 0.00 Total Perimeter Length
0.00 Total Ridge Length 0.00 Total Hip Length
10/15/19
William Hohlt
6
MICHAELIS CORPORATION
CONSTRUCT. RENOVATE. RESTORE.
2601 East 56th Street
Indianapolis IN 46220
(317) 251-1935 P
(317) 251-2599 F
1-844-FIX-INDY
19-2003RR 9/13/2019 Page: 6
Summary
Line Item Total 16,483.64
Material Sales Tax 311.88
Storage Tax 13.92
Subtotal 16,809.44
Overhead 1,680.97
Profit 1,680.97
Replacement Cost Value $20,171.38
Net Claim $20,171.38
Rick Michaelis Jr.
10/15/19
William Hohlt