FIRE PROTECTION SPECIFICATIONS
1. GENERAL PROVISIONS
A THE PROVISIONS OF THE INSTRUCTIONS TO BIDDERS, GENERAL CONDITIONS,
SUPPLEMENTARY CONDITIONS, ALTERNATES, ADDENDA'S', AND DIVISION 1 ARE A PART OF
THIS SPECIFICATION. CONTRACTORS AND SUBCONTRACTORS SHALL EXAMINE SAME AS
WELL AS OTHER DIVISIONS OF THE SPECIFICATIONS WHICH AFFECT WORK UNDER THIS
DIVISION.
B. THIS CONTRACTOR SHALL PROVIDE ALL LABOR, EQUIPMENT, SUPPLIES, SERVICES, AND
SHALL PERFORM ALL WORK COMPLETE AND IN STRICT ACCORDANCE WITH THIS
SPECIFICATION AND APPLICABLE DRAWINGS.
C. THIS CONTRACTOR IS INSTRUCTED TO READ CAREFULLY THE SPECIFICATIONS FOR ALL
PARTS OF THE WORK, WHICH INCLUDE THE ARCHITECTURAL, ELECTRICAL, MECHANICAL,
PLUMBING, FIRE PROTECTION, CIVIL STRUCTURAL AND ALL OTHER DRAWINGS AS WELL AS
THE SPECIFICATIONS FOR ALL THE DIVISIONS THAT ARE PART OF THE CONTRACT
DOCUMENTS.
D. ALL ITEMS OF LABOR, MATERIAL AND EQUIPMENT NOT SPECIFICALLY MENTIONED HEREIN
OR SHOWN ON PLANS, BUT INCIDENTAL TO, OR REQUIRED FOR THE COMPLETE
INSTALLATION AND PROPER OPERATION OF THE WORK, SHALL BE FURNISHED AS IF
CALLED FOR IN DETAIL BY THE SPECIFICATIONS OR DRAWINGS.
E. AS USED IN THIS SPECIFICATION, "PROVIDE" MEANS "FURNISH AND INSTALL". "FURNISH"
MEANS TO PURCHASE AND DELIVER TO THE PROJECT SITE COMPLETE WITH EVERY
NECESSARY APPURTENANCE AND SUPPORT; AND INSTALL" MEANS i0 UNLOAD AT THE
DELNERY POINT AT THE SITE AND PERFORM EVERY OPERATION NECESSARY FOR PROPER
INSTALLATION PER CODES AND MANUFACTURERS REQUIREMENTS, TO ESTABLISH SECURE
MOUNTING AND CORRECT OPERATION AT THE PROPER LOCATION IN THE PROJECT.
2. PERMITS, CODES, INSPECTIONS, AND TESTS
A. THE ARE PROTECTION CONTRACTOR SHALL SECURE AND PAY FOR ALL PERMITS AND
INSPECTIONS REQUIRED FOR THE PROSECUTION OF FIRE PROTECTION WORK. ALL
PERMITS AND CERTIFICATES OF INSPECTION AND APPROVAL SIGNED BY THE CONTROLLING
BUILDING DEPARTMENT SHALL BECOME PROPERTY OF THE OWNER.
B. THE ARE PROTECTION SYSTEM SHALL BE INSTALLED PER THE REQUIREMENTS OF NFPA
13 AND THE LOCAL AUTHORITIES HAVING JURISDICTION.
C. DRAWINGS INDICATE THE MINIMUM DESIGN REQUIREMENTS. NATIONAL, STATE, AND LOCAL
CODES SHALL BE FOLLOWED. COMPLY WITH THE LATEST EDITIONS OF THE LOCAL
GOVERNING PLUMBING CODE, LOCAL GOVERNING MECHANICAL CODE, AND NFPA
STANDARDS. THE CONTRACTOR SHALL INCLUDE THE COST OF SATISFYING SUCH CODES
AND STANDARDS IN HIS BID. FOLLOWING COMPLETION OF THE ARE PROTECTION WORK,
FURNISH TO THE OWNER, IN DUPLICATE, CERTIFICATES OF INSPECTION AND APPROVAL BY
REGULATORY AGENCIES HAVING JURISDICTION.
(1) DEMONSTRATE TO THE OWNER'S SATISFACTION THE PROPER OPERATION OF EACH OF
THE SYSTEMS COMPRISING THIS CONTRACT BEFORE FINAL PAYMENT.
(2)IMMEDIATELY CORRECT ANY WORK FOUND AT VARIANCE WITH THESE SPECIFICATIONS,
THE NATIONAL, STATE, AND LOCAL CODES, AND REQUIREMENTS OF GOVERNING
REGULATORY AGENCIES.
3. VISIT TO THE STTE
A THE CONTRACTOR SHALL VISIT THE SITE OF THE WORK AND BECOME FAMILIAR WITH ALL
CONDITIONS AFFECTING THE WORK. THE SUBMISSION OF A PROPOSAL SHALL
PRESUPPOSE KNOWLEDGE OF ALL SUCH CONDITIONS AND NO ADDITIONAL COMPENSATION
SHALL BE ALLOWED WHERE EXTRA LABOR OR MATERIALS ARE REQUIRED BECAUSE OF
IGNORANCE OF THESE CONDITIONS.
4. PROTECTION
A THE FIRE PROTECTION CONTRACTOR SHALL PROVIDE ALL NECESSARY PROTECTION FROM
DIRT AND WATER DURING CONSTRUCTION NECESSITATED BY FIRE PROTECTION WORK.
PROTECTION METHODS ARE SUBJECT TO APPROVAL BY THE ARCHITECT.
5. EQUIPMENT AND MATERIALS
A ALL EQUIPMENT AND MATERIALS SHALL BE NEW AND SHALL CONFORM TO
UNDERWRITERS' LABORATORIES STANDARDS, WHERE APPLICABLE. WHERE SPECIFICATIONS
DESCRIBE, OR PLAIDS SHOW, MATERIALS OR EQUIPMENT OF HIGHER QUALITY THAN
REQUIRED BY CODE AND LOCAL RULING, THE DRAWINGS AND SPECIFICATIONS SHALL
GOVERN THE QUALITY OF THE MATERIAL OR EQUIPMENT.
B. THE CONTRACTOR SHALL SUBMIT PROOF, IF REQUESTED BY THE OWNER THAT THE
MATERIALS, APPLIANCES, EQUIPMENT OR DEVICES FURNISHED AND INSTALLED UNDER
THIS CONTRACT, MEET THE REQUIREMENTS OF THE UNDERWRITERS' LABORATORIES, INC.,
AS REGARDS ARE AND CASUALTY HAZARDS. THE LABEL OF OR USING BY THE
UNDERWRITERS' LABORATORIES, INC. WILL BE ACCEPTED AS CONFORMING WITH THIS
REQUIREMENT. IN UEU OF THE LABEL OR UETNG, THE CONTRACTOR MAY SUBMIT
INDEPENDENT PROOF SATISFACTORY TO THE ARCHITECT THAT THE MATERIALS,
APPLIANCES OR DEVICES CONFORM TO THE PUBLISHED STANDARDS, INCLUDING METHODS
OF TEST OF THE UNDERWRITERS' LABORATORIES, INC. UNDERWRITERS' LABORATORIES,
INC. AND ITS PUBLICATIONS WILL BE REFERRED TO HEREINAFTER BY THE ABBREVIATION
UL, WITH OR WITHOUT ADDITIONAL IDENTIFYING SYMBOLS.
6. GUARANTEE
A. THE FIRE PROTECTION CONTRACTOR SHALL GUARANTEE FOR A PERIOD OF ONE YEAR
El
7. CUTTING, PATCHING, FIRESTOPPING AND PAINTING
A THIS CONTRACTOR SHALL BE RESPONSIBLE FOR CUTTING ALL HOLES REQUIRED FOR
INSTALLATION OF FIRE PROTECTION WORK. HOLES SHALL BE CUT IN A NEAT MANNER
B. UNLESS NOTED OTHERWISE, ALL HOLES OR DAMAGE CAUSED BY THE REMOVAL OF
EXISTING WORK OR THE INSTALLATION OF NEW WORK SHALL BE PROPERLY PATCHED BY
C. FIRESTOP SYSTEM (REQUIRED FlRESTOPPING MATERIALS) SHALL BE DETERMINED BY THE
WALL OR FLOOR/CEILING ASSEMBLY AND PENETRATION TYPE AND SHALL BE UL USTED
AND TESTED IN ACCORDANCE WITH ASIM E814. ARE RATING OF THE FIRESTOP SYSTEM
SHALL BE EQUIVALENT TO THE ASSEMBLY WHICH IS PENETRATED.
D. ACCEPTABLE FIRE BARRIER PRODUCTS: HILT] "FS-ONE", NELSON 'RAMESEAU OR
APPROVED EQUAL AS MANUFACTURED BY 3M.
B. CLEANING AND PAINTING
A CLEAN NEW PIPING AFTER WORK IS COMPLETE TO REMOVE PIPE DOPE, LOOSE MILL
SCALE AND OTHER EXTRANEOUS MATERIALS.
B. TOUCH UP AND REPAIR ANY DAMAGED FACTORY FINISHES ON EQUIPMENT AND MATERIALS
FURNISHED. OTHER PAINTING WILL BE DONE UNDER THE PAINTING DIVISION OF THE
SPECIFICATIONS.
10. COORDINATION AND CONDUCT OF WORK
A ARE PROTECTION DRAWINGS ARE DIAGRAMMATIC, INDICATING GENERAL ARRANGEMENT,
APPROXIMATE SIZES, GENERA LOCATIONS OF EQUIPMENT, SPRINKLER HEADS, AND
PIPING. VERIFY DIMENSIONS IN FIELD; ADJUST TO MANUFACTURER'S SHOP DRAWINGS.
DO NOT SCALE DRAWINGS.
B. ALL REQUESTS FOR INFORMATION SUPPLEMENTAL TO THE CONSTRUCTION DOCUMENTS
SHALL BE SUBMITTED IN WRRING TO THE ARCHITECT FOR DISTRIBUTION TO THE
APPROPRIATE PARTY(S).
C. DRAWINGS AND SPECIFICATIONS ARE TO BE CONSIDERED AS SUPPLEMENTING EACH
OTHER. WORK SPECIFIED BUT NOT SHOWN, OR SHOWN BUT NOT SPECIFIED, SHALL BE
PERFORMED OR FURNISHED AS THOUGH MENTIONED IN BOTH SPECIFICATIONS AND
DRAWINGS.
D. ARCHITECTURAL AND STRUCTURAL DRAWINGS SUPERSEDE FIRE PROTECTION DRAWINGS.
DETERMINE THAT WORK OF THIS DIVISION CAN BE ACCOMMODATED WITHIN SPACES
PROVIDED. NOTIFY ARCHITECT OF ANY INTERFERENCES BEFORE STARTING INSTALLATION.
E. DETERMINE SIZES, LOCATIONS FOR CHASES AND OPENINGS NECESSARY FOR INSTALLATION
OF PLUMBING AND FIRE PROTECTION WORK. COOPERATE WITH OTHER TRADES IN
SETTING SLEEVES, INSERTS AND HANGERS.
F. COORDINATE THIS WORK WITH ALL TRADES. ARRANGE OPERATIONS SO AS NOT TO
DELAY INSTALLATION OF COMPLETION OF ANY PARTS OF INTERRELATED WORK SO THAT
CONSTRUCTION MAY PROCEED ON SCHEDULE.
G. COOPERATE WITH ALL TRADES IN PREPARING INTERFERENCE DRAWINGS FOR AREAS
WHERE THERE IS POSSIBLE CONFUCT BETWEEN TRADES. EXACT LOCATION OF PIPES,
AND EQUIPMENT SHALL BE BASED ON FIELD MEASUREMENTS WITH FINAL ARRANGEMENT
DETERMINED BY INTRA-TRADE AGREEMENTS SUBJECT TO ARCHITECTS APPROVAL.
H. ARCHITECT RESERVES THE RIGHT TO MAKE REASONABLE CHANGES IN INDICATED
LOCATIONS WITHOUT EXTRA COST TO THE OWNER.
I. ALL WORK SHALL BE INSTALLED IN A NEAT AND WORKMANLIKE MANNER BY FIRST -CUSS
MECHANICS. THE CONTRACTOR SHALL PROVIDE ADEQUATE AND COMPETENT SUPERVISION
OF THE JOB AS REQUIRED.
L PIPING AND EQUIPMENT SHALL BE ARRANGED SUBSTANTIALLY AS INDICATED. ANY
CHANGE RESULTING IN A SAVINGS IN LABOR OR MATERIAL SHALL BE MADE ONLY IN
ACCORDANCE WITH A CONTRACT CHANGE ORDER. DEVIATIONS SHALL BE MADE ONLY
WHERE NECESSARY TO AVOID INTERFERENCES AND ONLY AFTER DRAWINGS SHOWING THE
PROPOSED DEVIATIONS HAVE BEEN SUBMITTED TO AND APPROVED BY THE ARCHITECT.
K. COORDINATE ALL SHUTDOWNS OF FIRE PROTECTION SYSTEM IN ADVANCE WITH THE
OWNER.
11. SUBMITTALS
A PROVIDE A MINIMUM OF SIX (6) SUBMITTAL DRAWINGS FOR EQUIPMENT, SPRINKLER
B. WHERE ONLY ONE MAKE OF EQUIPMENT IS NAMED, IT SHALL BE PROVIDED AS
SPECIFIED.
C. VERBAL REQUESTS OF APPROVALS FOR ANY SUBSTITUTION WILL NOT BE BINDING ON
D. THIS CONTRACTOR ASSUMES ALL RESPONSIBIUTY FOR ALL COSTS FOR REDESIGN
CHANGES NECESSARY BY ALL TRADES TO ACCOMMODATE THE USE OF EQUIPMENT NOT
SPECIFIED ON PROJECT DOCUMENTS.
E. BIDS SHALL BE BASED UPON THE SPECIFIED PRODUCTS OR LISTED ALTERNATIVES.
E SHOULD THE CONTRACTOR PROPOSE TO FURNISH MATERLALS, EQUIPMENT, AND DEVICES,
OTHER THAN THOSE SPECIFIED AND USTED, THE CONTRACTOR SHALL SUBMIT A WRITTEN
REQUEST FOR SUBSTITUTIONS, TO THE ENGINEER, AT LEAST FOURTEEN (14) CALENDAR
DAYS PRIOR TO BID OPENING. THE REQUEST SHALL BE AN ALTERNATE TO THE ORIGINAL
BID AND SHALL INCLUDE AND BE ACCOMPANIED WITH COMPLETE SPECIFICATIONS CUT
SHEET SUBMITTAL AS OUTLINED IN SECTION 11A OF THIS SPECIFICATION SECTION,
COMPLETE WITH DESCRIPTIVE (MANUFACTURER, BRAND NAME, CATALOG NUMBER, ETC.)
AND TECHNICAL DATA FOR ALL ITEMS. INDICATE ANY ADDITIONS OR DEDUCTIONS TO THE
CONTRACT PRICE WITH THE SUBSTITUTION SUBMITTAL AND ON THE BID FORM.
G. ACCEPTANCE OR REJECTION OF THE PROPOSED SUBSTITUTIONS SHALL BE SUBJECT TO
APPROVAL OF THE ARCHITECT AND ENGINEER. IF REQUESTED, THE CONTRACTOR SHALL
SUBMIT INSPECTION SAMPLES OF BOTH THE SPECIFIED AND THE PROPOSED SUBSTITUTE
ITEMS.
H. IF ANY SUBSITNTIONS ARE APPROVED, AN ADDENDUM USTING THE APPROVED ITEM(S)
WILL BE ISSUED TO ALL BIDDING CONTRACTORS PRIOR TO THE BID DATE.
I. IN ALL CASES WHERE SUBSTITUTIONS ARE PERMITTED, THE CONTRACTOR SHALL BEAR
ANY EXTRA COST OF EVALUATING THE EQUAUTY OF THE MATERIAL AND EQUIPMENT TO
BE INSTALLED.
J. WHERE ONLY ONE MAKE IS NAMED IN THE SPECIFICATIONS OR ON THE DRAWINGS, IT
SHALL BE PROVIDED.
K. VERBAL REQUESTS OR APPROVALS SHALL NOT BE BINDING ON THE ENGINEER OR
OWNER.
12. EQUIPMENT AND PIPING IDENTIFICATION
A. LABEL ALL PIPING SYSTEMS WITH PIPE MARKERS INSTALLED ADJACENT TO VALVES,
WHERE PIPES PASS THROUGH WALLS OR FLOORS, NEAR ALL BRANCHES AND CHANGES
OF DIRECTION, AT 20 FEET INTERVALS ON STRAIGHT RUNS OF PIPE, AND AT ACCESS
DOOR LOCATIONS. ALL PIPE MARKERS SHALL CONFORM TO ANSI A13.1 'SCHEME FOR
THE IDENTIFICATION OF PIPING SYSTEMS.
B. THE CONTRACTOR SHALL FURNISH AND INSTALL A SYSTEM OF NAMEPLATES DESIGNED TO
IDENTIFY EACH PIECE OF EQUIPMENT.
(1) NAMEPLATE LETTER AND NUMBERS SHALL MATCH EQUIPMENT DESIGNATION AS
INDICATED ON THE DRAWINGS.
(2) NAMEPLATES SHALL BE LAMINATED PHENOLIC WITH BLACK SURFACE AND WHITE
CORE. USE 1/16" THICK MATERIAL FOR PLATES UP TO 2" BY 4". FOR LARGER SIZES
USE 1/8" THICK. LETTERS AND NUMBERS SHALL BE A MINIMUM OF 1/2" HIGH.
(1) FASTEN NAMEPLATES TO ALL EQUIPMENT BY THE USE OF STAINLESS STEEL SHEET
METAL SCREWS.
13. AS -BUILT DRAWINGS
A. AS WORK PROGRESSES, RECORD ON A SET OF "AS -BUILT` PRINTS ANY DEVIATIONS
FROM DESIGN DRAWINGS. DELIVER TO THE OWNER BEFORE SUBMITTING REQUEST FOR
FINAL PAYMENT. THE "AS -BUILT" PRINTS SHALL BE AN ACCURATE DEPICTION OF THE
PROJECT AS COMPLETED.
14. OPERATING AND MAINTENANCE MANUALS
A PROVIDE TO OWNER, AT PROJECT TURNOVER, THREE (3) HARDBOUND COPIES OF
OPERATING AND MAINTENANCE MANUALS FOR ALL EQUIPMENT AND SYSTEMS INSTALLED.
MANUALS SHALL INCLUDE ALL RELEVANT INFORMATION NEEDED FOR DAY-TO-DAY
OPERATION AND MANAGEMENT OF EACH SYSTEM, AS WELL AS EQUIPMENT MAINTENANCE
INFORMATION REQUIRED TO SUPPORT THE MAINTENANCE PROGRAM.
11. SUBMITTALS
A. PROVIDE
B. WHERE ONLY ONE MAKE OF EQUIPMENT IS NAMED, IT SHALL BE PROVIDED AS
SPECIFIED.
C. VERBAL REQUESTS OF APPROVALS FOR ANY SUBSTITUTION WILL NOT BE BINDING ON
D. THIS CONTRACTOR ASSUMES ALL RESPONSIBILITY FOR ALL COSTS FOR REDESIGN
CHANGES NECESSARY BY ALL TRADES TO ACCOMMODATE THE USE OF EQUIPMENT NOT
SPECIFIED ON PROJECT DOCUMENTS.
E. BIDS SHALL BE BASED UPON THE SPECIFIED PRODUCTS OR USTED ALTERNATIVES.
F. SHOULD THE CONTRACTOR PROPOSE TO FURNISH MATERIALS, EQUIPMENT, AND DEVICES,
OTHER THAN THOSE SPECIFIED AND LISTED, THE CONTRACTOR SHALL SUBMIT A WRITTEN
REQUEST FOR SUBSTITUTIONS, TO THE ENGINEER, AT LEAST FOURTEEN (14) CALENDAR
DAYS PRIOR TO BID OPENING. THE REQUEST SHALL BE AN ALTERNATE TO THE ORIGINAL
BID AND SHALL INCLUDE AND BE ACCOMPANIED WITH COMPLETE SPECIFICATIONS CUT
SHEET SUBMITTAL AS OUTLINED IN SECTION 11.A OF THIS SPECIFICATION SECTION,
COMPLETE WITH DESCRIPTIVE (MANUFACTURER, BRAND NAME, CATALOG NUMBER, ETC.)
AND TECHNICAL DATA FOR ALL ITEMS. INDICATE ANY ADDITIONS OR DEDUCTIONS TO THE
CONTRACT PRICE WITH THE SUBSTITUTION SUBMITTAL AND ON THE BID FORM.
G. ACCEPTANCE OR REJECTION OF THE PROPOSED SUBSTITUTIONS SHALL BE SUBJECT TO
APPROVAL OF THE ARCHITECT AND ENGINEER. IF REQUESTED, THE CONTRACTOR SHALL
SUBMIT INSPECTION SAMPLES OF BOTH THE SPECIFIED AND THE PROPOSED SUBSTITUTE
ITEMS.
H. IF ANY SUBSTITUTIONS ARE APPROVED, AN ADDENDUM UETNG THE APPROVED ITEMS)
WILL BE ISSUED TO ALL BIDDING CONTRACTORS PRIOR TO THE BID DATE.
I. IN ALL CASES WHERE SUBSTITUTIONS ARE PERMITTED, THE CONTRACTOR SHALL BEAR
ANY EXTRA COST OF EVALUATING THE EQUALITY OF THE MATERIAL AND EQUIPMENT TO
BE INSTALLED.
J. WHERE ONLY ONE MAKE IS NAMED IN THE SPECIFICATIONS OR ON THE DRAWINGS, IT
SHALL BE PROVIDED.
K. VERBAL REQUESTS OR APPROVALS SHALL NOT BE BINDING ON THE ENGINEER OR
OWNER.
12.EQUIPMENT AND PIPING IDENTIFICATION
A LABEL ALL PIPING SYSTEMS WITH PIPE MARKERS INSTALLED ADJACENT TO VALVES,
WHERE PIPES PASS THROUGH WALLS OR FLOORS, NEAR ALL BRANCHES AND CHANGES
OF DIRECTION, AT 20 FEET INTERVALS ON STRAIGHT RUNS OF PIPE, AND AT ACCESS
DOOR LOCATIONS. ALL PIPE MARKERS SHALL CONFORM TO ANSI A13.1 'SCHEME FOR
THE IDENTIFICATION OF PIPING SYSTEMS".
B. THE CONTRACTOR SHALL FURNISH AND INSTALL A SYSTEM OF NAMEPLATES DESIGNED TO
IDENTIFY EACH PIECE OF EQUIPMENT.
(1) NAMEPLATE LETTER AND NUMBERS SHALL MATCH EQUIPMENT DESIGNATION AS
INDICATED ON THE DRAWINGS.
(2) NAMEPLATES SHALL BE LAMINATED PHENOLIC WITH BLACK SURFACE AND WHITE
CORE. USE 1/16" THICK MATERIAL FOR PLATES UP TO 2" BY 4". FOR LARGER SIZES
USE 1/8" THICK. LETTERS AND NUMBERS SHALL BE A MINIMUM OF 1/2" HIGH.
(1) FASTEN NAMEPLATES TO ALL EQUIPMENT BY THE USE OF STAINLESS STEEL SHEET
METAL SCREWS.
13. AS -BUILT DRAWINGS
A. AS WORK PROGRESSES, RECORD ON A SET OF "AS -BUILT" PRINTS ANY DEVIATIONS
FROM DESIGN DRAWINGS. DELIVER TO THE OWNER BEFORE SUBMITTING REQUEST FOR
FINAL PAYMENT. THE "AS -BUILT" PRINTS SHALL BE AN ACCURATE DEPICTION OF THE
PROJECT AS COMPLETED.
14. OPERATING AND MAINTENANCE MANUALS
A. PROVIDE TO OWNER, AT PROJECT TURNOVER, THREE (3) HARDBOUND COPIES OF
OPERATING AND MAINTENANCE MANUALS FOR All EQUIPMENT AND SYSTEMS INSTALLED.
MANUALS SHALL INCLUDE ALL RELEVANT INFORMATION NEEDED FOR DAY-TO-DAY
OPERATION AND MANAGEMENT OF EACH SYSTEM, AS WELL AS EQUIPMENT MAINTENANCE
INFORMATION REQUIRED TO SUPPORT THE MAINTENANCE PROGRAM.
15. OPERATING INSTRUCTIONS
A. PROVIDE TO OWNER AFFER ALL EQUIPMENT IS IN OPERATION AND AT AN AGREEABLE
TIME, INSTRUCTIONS FOR THE PURPOSE OF TRAINING OWNER'S PERSONNEL IN ALL
PHASES OF OPERATION AND MAINTENANCE OF EQUIPMENT AND SYSTEMS. SCHEDULE
TRAINING WITH OWNER, PROVIDE AT LEST SEVEN DAYS PRIOR NOTICE. PROVIDE THIS
TRAINING TO ALL PERSONNEL AND ON ALL SHIFTS.
16. ARE PROTECTION
A. GENERAL
(1) FURNISH ALL LABOR, CONSTRUCTION EQUIPMENT AND MATERIALS NECESSARY FOR
THE COMPLETE INSTALLATION OF THE ARE PROTECTION SYSTEM AS INDICATED. ALL
WORK SHALL BE IN STRICT COMPLIANCE WITH ALL GOVERNING STATE AND LOCAL CODE
REQUIREMENTS, IN FULL CONFORMITY WITH THE BEST CURRENT TRADE PRACTICES AND
SUBJECT TO APPROVAL OF THE ARCHITECT OR HIS REPRESENTATIVE.
(2) ALL WORK DETAILS NOT COVERED IN THESE SPECIFICATIONS SHALL BE GOVERNED
BY THE REQUIREMENTS OF THE LATEST EDITION OF NFPA-13.
(3) SUPPORT ALL SPRINKLER PIPING PER NFPA 13 REQUIREMENTS.
(4) PIPE BENDING IS NOT ACCEPTABLE.
(5) ALL FIRE PROTECTION PIPING SYSTEMS MUST BE COMPLETELY DRAINABLE.
B. DESIGN AND INSTALLATION REQUIREMENTS
(1) PREPARE SHOP DRAWINGS AND HYDRAULIC CALCULATIONS IN ACCORDANCE WITH
NFPA REQUIREMENTS. SUBMIT DRAWINGS TO LOCAL GOVERNMENT AGENCIES AND
OWNER'S INSURANCE UNDERWRITER FOR APPROVAL AFER THE ABOVE AND PRIOR TO
CONSTRUCTION, SUBMIT THE DOCUMENTS TO THE ARCHITECT AND ENGINEER FOR
REVIEW.
(1)1) THE CONTRACTOR SHALL ESTABUSH ACTUAL AVAILABILITY OF THE WATER FROM
HISTORICAL DATA OR BY PERFORMING A FLOW TEST.
(1)2) VERIFY HAZARD OCCUPANCY CLASSIFICATION REQUIREMENT WITH THE OWNER.
(2) CONTRACTOR SHALL BE LICENSED BY ALL STATE AND LOCAL AUTHORITIES.
(3) INSTALL U.L OR F.M. APPROVED SPRINKLERS AS REQUIRED FOR COVERAGE. ALL
SPRINKLERS SHALL BE NEW AND CENTERED IN CEILING TILE WHERE POSSIBLE.
(4) PROVIDE SPRINKLER HEADS TO MATCH EXISTING HEADS INSTALLED IN ADJACENT
AREAS. TYPE AND MANUFACTURER SHALL BE APPROVED BY THE OWNER.
(1) COORDINATE SHUTDOWN OF THE EXISTING SPRINKLER SYSTEM WITH THE OWNER.
(2) ARE PROTECTION PIPING SHALL BE TESTED WITH WATER AT A PRESSURE OF 200
PSI FOR 2 HOURS.
C. FIRE PROTECTION EQUIPMENT AND MATERIALS
(1) PIPE AND FITTINGS
a. FIRE PROTECTION PIPING, SHALL BE WELDED OR SEAMLESS BLACK STEEL AS
SCHEDULED IN NFPA, WITH THREADED JOINTS.
b. FITTINGS SHALL BE MALLEABLE IRON, THREADED TYPE, AS SCHEDULED IN NFPA.
(1) SPRINKLER HEADS
a. SPRINKLER HEADS SHALL BE UL USTED AND FM APPROVED, MEETING NFPA
REQUIREMENTS.
Is. TEMPERATURE RATING OF HEADS SHALL BE 165 DEGREES FAHRENHEIT.
c. ACCEPTABLE MANUFACTURERS: VIKING, CENTRAL, STAR, RELIABLE.
d. ESCUTCHEON OR COVER PLATE FINISH/COLOR SHALL MATCH ADJACENT SURFACE
OR BUILDING STANDARD.
e. ALL SPRINKLER HEAD LOCATIONS SHALL BE CENTERED IN COUNG TILES OR
OTHERWISE COORDINATED WITH ARCHITECTURAL DESIGN ELEMENTS. REFER TO
ARCHITECTURAL REFLECTED CEILING PLAN.
• Integrated
Engineering
Consultantsjnc.
9700 ROCKSIDE RD. SUITE #290
CLEVELAND, OH 44125
(P): 216.901.6711
(F): 216.901.6712
wwwJeoinc.cc
PE11800575
•'.
<•, STATE OF
FIRE PROTECTION NOTES
1. DRAWINGS ARE DIAGRAMMATIC: DETERMINE LOCATIONS OF SYSTEMS AND COMPONENTS IN
FIELD.
2. PITCH PRESSURE PIPING IN DIRECTION OF FLOW.
3. PRODUCT INSTALLATION SHALL ADHERE TO MANUFACTURERS' RECOMMENDATIONS.
4. NEITHER ACCURACY NOR COMPLETION OF UTILITY LOCATIONS SHOWN ON DRAWINGS IS
GUARANTEED. DETERMINE EXACT LOCATIONS OF EXISTING UTILITIES IN FIELD, WHETHER
OR NOT SHOWN ON DRAWINGS. EXERCISE CAUTION AND IDENTIFY LOCATIONS OF
UNMARKED UTILITY UNES AS NECESSARY TO PERFORM WORK OF THIS SECTION.
5. ALL WORK SHALL BE IN ACCORDANCE WITH ALL APPLICABLE CODES AND DRAWINGS.
6. IT SHALL BE THE RESPONSIBILITY OF THIS CONTRACTOR TO COORDINATE HIS WORK WITH
THAT OF ALL OTHERS TRADES AND GENERAL ARCHITECTURE.
7. ANY INTERFERENCE SHALL BE BROUGHT TO THE ATTENTION OF THE CONSTRUCTION
MANAGER AND THE OWNER'S REPRESENTATIVE, AND SHALL BE RESOLVED PRIOR TO THE
INSTALLATION OF THE WORK INVOLVED.
B. VERIFY EXACT SIZES, LOCATIONS, INVERTS AND ELEVATIONS PRIOR TO FABRICATING AND
INSTALLING ANY PIPING.
9. ALL PIPING PENETRATING CEILINGS AND WALLS SHALL BE INSTALLED WITH CHROME
(STAINLESS WHERE NOTED) PLATED ESCUTCHEONS AT THE PENETRATION. PIPING
PENETRATING RATED PARTITIONS SHALL BE PROTECTED AS BY LOCAL CODE AUTHORITY.
10. ALL SLEEVES THROUGH CONCRETE FLOORS AND ALL CORE DRIVING OF CONCRETE
FLOORS AND WALLS SHALL BE BY THIS CONTRACTOR.
11. RUN PIPING CONCEALED, UNLESS SPECIFIED OTHERWISE, AND CLEAR OF CEILING
INSERTS.
14. PROVIDE CLAMPS, OFFSETS, EXPANSION JOINTS, ANCHORS AND GUIDES AS NECESSARY
TO PREVENT STRESS ON PIPING.
15. SPRINKLER CONTRACTOR SHALL HYDRAULICALLY CALCULATE NEW SYSTEM REQUIREMENTS
BASED ON THE OCCUPANCY CLASSIFICATIONS AS INDICATED IN THE SPECIFICATIONS.
16. SPRINKLER CONTRACTOR SHALL OBTAIN A COPY OF THE BUILDING SYSTEM ROW TEST.
THESE FINDINGS SHALL BE USED FOR THE HYDRAULIC SPRINKLER SYSTEM
CALCULATIONS.
17. SPRINKLER CONTRACTOR SHALL SCHEDULE WALK THRU WITH FIRE PREVENTION
INSPECTOR FOR FINAL ACCEPTANCE AS REQUIRED.
18. SPRINKLER CONTRACTOR IS TO VERIFY SPRINKLER DISTRIBUTION SYSTEM & LAYOUT
COMPUES WITH NFPA 13 REQUIREMENTS.
19. FIRE PROTECTION PLANS AS SHOWN ARE FOR CONDITIONAL PLAN APPROVAL ONLY, FIRE
PROTECTION CONTRACTOR IS TO OBTAIN CURRENT HYDRANT TEST DATA AND PROVIDE
HYDRAULIC CALCULATIONS FOR SYSTEM PIPE SIZING IN ACCORDANCE WITH NFPA 13.
CONTRACTOR IS TO SUBMIT SHOP DRAWINGS INDICATING HYDRAULIC CALCULATIONS,
PIPING LAYOUT & SIZING. SHOP DRAWINGS AND CALCULATIONS ARE TO BE SIGNED &
SEALED BY A CERTIFIED FIRE PROTECTION SYSTEM DESIGNER. ALL WORK IS TO BE
DONE IN ACCORDANCE WITH ALL STATE, LOCAL, GOVERNING AND APPUCABLE CODES.
20. REPAIR ALL DAMAGED FIREPROOFING ON EXISTING STRUCTURE AFTER ALL FIRE
PROTECTION WORK IS COMPLETED.
21. STATE CERTIFIED FIRE PROTECTION SYSTEM DESIGNER SHALL SUBMIT FINAL PLANS FOR
PERMITTING AND CONSTRUCTION.
22. SPRINKLER CONTRACTOR SHALL VERIFY SPRINKLER HEAD COUNT PER FLOOR. A
PROFESSIONAL ENGINEER COMPETENT IN AUTOMATIC FIRE SPRINKLER DESIGN SHALL BE
REQUIRED FOR RENOVATIONS EXCEEDING 225 SPRINKLER HEADS (LIGHT HAZARD).
REMOVE EXISTING SPRINKLER HEAD AND
INSTALL NEW 1" OFFSEr
SPRINKLER MAIN
� NEW SPRINKLER HEAD WITH CEILING PLATE
\ MATCH EXISTING HEAD TYPE.
NEW SUSPENDED CEILING.
NEW CONCEALED PENDANT SPRINKLER DETAIL
SCALEAONE
THREADED ROD
CUT TO LENGTH
CLEVIS TYPE
PIPE HANGER
0\ CARRIER PIPE
\\ STEEL CAMP
O
ELASTOMERIC PAD
CLEVIS TYPE PIPE SUPPORT FOR
UNINSULATED PIPING DETAIL
H
E
L
L Y E R
LEWIS=
ARCHITECTURE
INTERIOR DESIGN
Project:
10 Liberty
Mutual.
INSURANCE
450 East 96th St
3rd Floor
Indianapolis IN 46240
Project No: 047.56
Drawn by: jM
Checked by: HjHH
Approved by: Hj H H
Client Approval: Date:
Issue For Bid: 11 /02/18
Issue For Permit: 11 /05/ 1 8
No. Date Revision
Scale:
Drawing:
Fire Protection
Schedules,
Legends and
Notes
No. FP-0n03
DATE: 10/23/19