1. GENERAL PROVISIONS
A THE PROVISIONS OF THE INSTRUCTIONS TO BIDDERS, GENERAL CONDITIONS, SUPPLEMENTARY
CONDITIONS, ALTERNATES, ADDENDA'S', AND DIVISION 1 ARE A PART OF THIS SPECIFICATION.
CONTRACTORS AND SUBCONTRACTORS SHALL EXAMINE SAME AS WELL AS OTHER DIVISIONS
OF THE SPECIFICATIONS WHICH AFFECT WORK UNDER THIS DIVISION.
B. THIS CONTRACTOR SHALL PROVIDE ALL LABOR, EQUIPMENT, SUPPLIES, SERVICES, AND SHALL
PERFORM ALL WORK COMPLETE AND IN STRICT ACCORDANCE WITH THIS SPECIFICATION AND
APPUCABLE DRAWINGS. ANY DEVIATIONS SHALL BE CLEARLY DEFINED AND ITEMIZED IN
ACCORDANCE WITH SECTION 10.F OF THIS SPECIFICATION.
C. THIS CONTRACTOR IS INSTRUCTED TO READ CAREFULLY THE SPECIFICATIONS FOR ALL PARTS
OF THE WORK, WHICH INCLUDE THE ARCHITECTURAL, ELECTRICAL MECHANICAL, PLUMBING,
FIRE PROTECTION, CAL, STRUCTURAL AND ALL OTHER DRAWINGS AS WELL AS THE
SPECIFICATIONS FOR ALL THE DIVISIONS THAT ARE PART OF THE CONTRACT DOCUMENTS.
D. ALL ITEMS OF LABOR, MATERIAL AND EQUIPMENT NOT SPECIFICALLY MENTIONED HEREIN OR
SHOWN ON PLANS, BUT INCIDENTAL TO, OR REQUIRED FOR THE COMPLETE INSTALLATION AND
PROPER OPERATION OF THE WORK, SHALL BE FURNISHED AS IF CALLED FOR IN DETAIL BY
THE SPECIFICATIONS OR DRAWINGS.
E. AS USED IN THIS SPECIFICATION, "PROVIDE" MEANS *FURNISH AND INSTALL°. "FURNISH"
MEANS i0 PURCHASE AND DELIVER TO THE PROJECT SITE COMPLETE WITH EVERY
NECESSARY APPURTENANCE AND SUPPORT; AND "INSTALL" MEANS i0 UNLOAD AT THE
DELIVERY POINT AT THE SITE AND PERFORM EVERY OPERATION NECESSARY FOR PROPER
INSTALLATION PER CODES AND MANUFACTURERS REQUIREMENTS, TO ESTABUSH SECURE
MOUNTING AND CORRECT OPERATION AT THE PROPER LOCATION IN THE PROJECT.
2. PERMITS, CODES, INSPECTIONS, AND TESTS
A. THE PLUMBING CONTRACTOR SHALL SECURE AND PAY FOR ALL PERMITS AND INSPECTIONS
REQUIRED FOR THE PROSECUTION OF PLUMBING WORK. ALL PERMITS AND CERTIFICATES OF
INSPECTION AND APPROVAL SIGNED BY THE CONTROLLING BUILDING DEPARTMENT SHALL
BECOME PROPERTY OF THE OWNER.
B. DRAWINGS INDICATE THE MINIMUM DESIGN REQUIREMENTS. NATIONAL STATE, AND LOCAL
CODES SHALL BE FOLLOWED. COMPLY WITH THE LATEST EDITIONS OF THE LOCAL GOVERNING
PLUMBING CODE, LOCAL GOVERNING MECHANICAL CODE, AND NFPA STANDARDS. THE
CONTRACTOR SHALL INCLUDE THE COST OF SATISFYING SUCH CODES AND STANDARDS IN HIS
BIDSOLLOWING COMPLETION OF THE PLUMBING WORK, FURNISH TO THE OWNER, IN
DUPLICATE, CERTIFICATES OF INSPECTION AND APPROVAL BY REGULATORY AGENCIES HAVING
JURISDICTION.
(1)DEMONSTRATE TO THE OWNER'S SATISFACTION THE PROPER OPERATION OF EACH OF THE
SYSTEMS COMPRISING THIS CONTRACT BEFORE FINAL PAYMENT.
(2)IMMEDIATELY CORRECT ANY WORK FOUND AT VARIANCE WITH THESE SPECIFICATIONS, THE
NATIONAL, STATE, AND LOCAL CODES, AND REQUIREMENTS OF GOVERNING REGULATORY
AGENCIES.
(3) TEST PIPING FOR LEAKS; REPAIR LEAKS IN COPPER TUBING BY SWEATING OUT JOINTS,
THOROUGHLY CLEANING BOTH TUBE AND FITTING, AND RE -SOLDERING OR RE -BRAZING;
CORRECT LEAKS IN SCREWED JOINTS BY REPLACING THREAD OR FRYING OR BOTH.
a. DOMESTIC WATER SHALL BE TESTED WITH WATER AT A PRESSURE OF 125 PSI FOR 6
HOURS.
b. NATURAL GAS SHALL BE TESTED WITH COMPRESSED AR AT A PRESSURE OF 1-1/2
TIMES THE PROPOSED MAXIMUM WORKING PRESSURE (BUT NOT LESS THAN 3 PSI)
FOR 24 HOURS. TESTING PROCEDURE SHALL CONFORM TO NFPA 54 "NATIONAL
FUEL GAS CODE" AND ICC FUEL GAS CODE REQUIREMENTS.
c. SANITARY DRAIN AND VENT AND STORM PIPING SHALL BE TESTED WITH WATER PER
GOVERNING PLUMBING CODE AND THE LOCAL AUTHORITY.
3. VISIT TO THE SIZE
A THE CONTRACTOR SHALL VISIT THE SITE OF THE WORK AND BECOME FAMILIAR WITH ALL
CONDITIONS AFFECTING THE WORK. THE SUBMISSION OF A PROPOSAL SHALL PRESUPPOSE
KNOWLEDGE OF ALL SUCH CONDITIONS AND NO ADDITIONAL COMPENSATION SHALL BE
ALLOWED WHERE EXTRA LABOR OR MATERIALS ARE REQUIRED BECAUSE OF IGNORANCE OF
THESE CONDITIONS.
4. PROTECTION
A. THE PLUMBING CONTRACTOR SHALL PROVIDE ALL NECESSARY PROTECTION FROM DIRT AND
WATER DURING CONSTRUCTION NECESSITATED BY PLUMBING WORK. PROTECTION METHODS
ARE SUBJECT TO APPROVAL BY THE ARCHITECT.
5. EQUIPMENT AND MATERIALS
A ALL EQUIPMENT AND MATERIALS SHALL BE NEW AND SHALL CONFORM TO UNDERWRITERS'
LABORATORIES STANDARDS, WHERE APPLICABLE WHERE SPECIFICATIONS DESCRIBE, OR
PLANS SHOW, MATERIALS OR EQUIPMENT OF HIGHER QUALITY THAN REQUIRED BY CODE AND
LOCAL RULING, THE DRAWINGS AND SPECIFICATIONS SHALL GOVERN THE QUALITY OF THE
MATERIAL OR EQUIPMENT.
B. THE CONTRACTOR SHALL SUBMIT PROOF, IF REQUESTED BY THE OWNER THAT THE MATERIALS,
APPLIANCES, EQUIPMENT OR DEVICES FURNISHED AND INSTALLED UNDER THIS CONTRACT,
MEET THE REQUIREMENTS OF THE UNDERWRITERS' LABORATORIES, INC., AS REGARDS FIRE
AND CASUALTY HAZARDS. THE LABEL OF OR LISTING BY THE UNDERWRITERS' LABORATORIES,
INC. WILL BE ACCEPTED AS CONFORMING WITH THIS REQUIREMENT. IN UEU OF THE LABEL
OR USTING, THE CONTRACTOR MAY SUBMIT INDEPENDENT PROOF SATISFACTORY TO THE
ARCHITECT THAT THE MATERIALS, APPLIANCES OR DEVICES CONFORM TO THE PUBLISHED
STANDARDS, INCLUDING METHODS OF TEST OF THE UNDERWRITERS' LABORATORIES, INC.
UNDERWRITERS' LABORATORIES, INC. AND ITS PUBLICATIONS WILL BE REFERRED TO
HEREINAFTER BY THE ABBREVIATION UL, WITH OR WITHOUT ADDITIONAL IDENTIFYING SYMBOLS.
6. GUARANTEE
A THE PLUMBING CONTRACTOR SHALL GUARANTEE FOR A PERIOD OF ONE YEAR THAT ALL WORK
AND EQUIPMENT WILL REMAIN FREE FROM ALL DEFECTS IN WORKMANSHIP AND MATERIALS,
AND THAT IT WILL COMPLY WITH ALL THE SPECIFIC REQUIREMENTS OF THE SPECIFICATIONS
AND OTHER CONTRACT DOCUMENTS GOVERNING THE WORK.
B. ALL WORK FOUND BY THE ENGINEER TO BE DEFECTIVE WILL BE REPLACED WITH NEW WORK
MEETING ALL THE REQUIREMENTS OF THE CONTRACT. THE PLUMBING CONTRACTOR WILL
BUR ALL COSTS OF SUPPLYING SUCH NEW WORK, AND INSTALLING AND FINISHING SAME,
AND WILL ASSUME ALL COSTS FOR REPLACING OTHER WORK DAMAGED BY THE REMOVAL AND
REPLACEMENT OF ANY OF THE WORK. THE PLUMBING CONTRACTOR WILL BEAR ALL COSTS
FOR FREIGHT, DRAYAGE AND DEMURRAGE, AND ALL LABOR IN CONNECTION THEREWITH.
7. CUTTING, PATCHING, FIRESTOPPING AND PAINTING
A THIS CONTRACTOR SHALL BE RESPONSIBLE FOR CUTTING ALL HOLES REQUIRED FOR
INSTALLATION OF PLUMBING WORK. HOLES SHALL BE CUT IN A NUT MANNER SATISFACTORY
TO THE ARCHITECT.
B. CONTRACTOR SHALL EMPLOY AN BUILDING OWNER APPROVED ROOFING CONTRACTOR FOR ALL
ROOF PENETRATIONS. ROOF SHALL BE REPAIRED SO AS NOT TO VOID ROOF WARRANTY.
C. UNLESS NOTED OTHERWISE, ALL HOLES OR DAMAGE CAUSED BY THE REMOVAL OF EXISTING
WORK OR THE INSTALLATION OF NEW WORK SHALL BE PROPERLY PATCHED BY THIS
CONTRACTOR. HOLES SHALL BE NEATLY PATCHED AND PAINTED WITH SUITABLE MATERIAL TO
MATCH EXISTING SURFACES. HOLES THROUGH FLOORS OR ARE WALLS SHALL BE SEALED
WITH THE APPROPRIATE INTUMESCENT CAULK, PUTTY, STRIP OR SHEET TYPE FIRE BARRIER
PRODUCT.
D. FlRESTOP SYSTEM (REQUIRED FIRESTOPPING MATERIALS) SHALL BE DETERMINED BY THE WALL
OR FLOOR/CEILING ASSEMBLY AND PENETRATION TYPE AND SHALL BE UL LISTED AND TESTED
IN ACCORDANCE WITH ASTM E814. FIRE RATING OF THE FlRESTOP SYSTEM SHALL BE
EQUIVALENT TO THE ASSEMBLY WHICH IS PENETRATED.
E. ACCEPTABLE FIRE BARRIER PRODUCTS: HILT] 'FS-ONE", NELSON 'FLAMESEAL" OR APPROVED
EQUAL AS MANUFACTURED BY 3M.
8. EXCAVATING, TRENCHING, AND BACKFILUNG:
A FURNISH MATERIALS, TOOLS, LABOR AND SUPERVISION NECESSARY TO PROVIDE ALL
EXCAVATING, TRENCHING AND BACKFlWNG REQUIRED FOR THE PROPER INSTALLATION OF
EQUIPMENT AND PIPING.
B. EXACT ROUTING OF TRENCHING SHALL BE DETERMINED BY THE CONTRACTOR AND APPROVED,
IN ADVANCE, BY THE OWNER.
C. ALL WORK SHALL COMPLY WITH THE REQUIREMENTS OF THE GOVERNING AUTHORITIES.
D. WHERE TRENCHES ARE EXCAVATED SUCH THAT THE BOTTOM OF THE TRENCH FORMS THE
BED FOR THE PIPE, SOLID AND CONTINUOUS LOAD -BEARING SUPPORT SHALL BE PROVIDED
BETWEEN JOINTS. BELL HOLES, HUB HOLES AND COUPLED HOLES SHALL BE PROVIDED AT
POINTS WHERE THE PIPE IS JOINED. SUCH PIPE SHALL NOT BE SUPPORTED ON BLOCKS TO
GRADE.
9. CLEANING AND PAINTING
A CLEAN NEW PIPING AFTER WORK IS COMPLETE TO REMOVE PIPE DOPE, LOOSE MILL SCALE
AND OTHER EXTRANEOUS MATERIALS.
B. TOUCH UP AND REPAIR ANY DAMAGED FACTORY FINISHES ON EQUIPMENT AND MATERIALS
FURNISHED. OTHER PAINTING WILL BE DONE UNDER THE PAINTING DIVISION OF THE
SPECIFICATIONS.
10. COORDINATION AND CONDUCT OF WORK
A PLUMBING CONTRACTOR SHALL COORDINATE ALL NEW (GAS, DOMESTIC WATER, SANITARY)
UTILITY CONNECTIONS AND METERING REQUIREMENTS WITH LOCAL UTILITY COMPANY.
B. PLUMBING DRAWINGS ARE DIAGRAMMATIC, INDICATING GENERAL ARRANGEMENT, APPROXIMATE
SIZES, GENERAL LOCATIONS OF EQUIPMENT, AND PIPING. VERIFY DIMENSIONS IN FIELD;
ADJUST TO MANUFACTURER'S SHOP DRAWINGS. DO NOT SCALE DRAWINGS.
C. ALL REQUESTS FOR INFORMATION SUPPLEMENTAL TO THE CONSTRUCTION DOCUMENTS SHALL
BE SUBMITTED IN WRITING TO THE ARCHITECT FOR DISTRIBUTION TO THE APPROPRIATE
PARIY(S).
D. DRAWINGS AND SPECIFICATIONS ARE TO BE CONSIDERED AS SUPPLEMENTING EACH OTHER.
WORK SPECIFIED BUT NOT SHOWN, OR SHOWN BUT NOT SPECIFIED, SHALL BE PERFORMED
OR FURNISHED AS THOUGH MENTIONED IN BOTH SPECIFICATIONS AND DRAWINGS.
E. ARCHITECTURAL AND STRUCTURAL DRAWINGS SUPERSEDE PLUMBING DRAWINGS. DETERMINE
THAT WORK OF THIS DIVISION CAN BE ACCOMMODATED WITHIN SPACES PROVIDED. NOTIFY
ARCHITECT OF ANY INTERFERENCES BEFORE STARTING INSTALLATION.
F. DETERMINE SIZES, LOCATIONS FOR CHASES AND OPENINGS NECESSARY FOR INSTALLATION OF
PLUMBING WORK. COOPERATE WITH OTHER TRADES IN SETTING SLEEVES, INSERTS AND
HANGERS.
G. COORDINATE THIS WORK WITH ALL TRADES. ARRANGE OPERATIONS SO AS NOT TO DELAY
INSTALLATION OR COMPLETION OF ANY PARTS OF INTERRELATED WORK SO THAT
CONSTRUCTION MAY PROCEED ON SCHEDULE.
H. COOPERATE WITH ALL TRADES IN PREPARING INTERFERENCE DRAWINGS FOR AREAS WHERE
THERE IS POSSIBLE CONVICT BETWEEN TRADES. EXACT LOCATION OF PIPES, AND
EQUIPMENT SHALL BE BASED ON FIELD MEASUREMENTS WITH FINAL ARRANGEMENT
DETERMINED BY INTRA-TRADE AGREEMENTS SUBJECT TO ARCHITECT'S APPROVAL.
I. ARCHITECT RESERVES THE RIGHT TO MAKE REASONABLE CHANGES IN INDICATED LOCATIONS
WITHOUT EXTRA COST TO THE OWNER.
J. ALL WORK SHALL BE INSTALLED IN A NEAT AND WORKMANLIKE MANNER BY FIRST CLASS
MECHANICS. THE CONTRACTOR SHALL PROVIDE ADEQUATE AND COMPETENT SUPERVISION OF
THE JOB AS REQUIRED.
K. PIPING AND EQUIPMENT SHALL BE ARRANGED SUBSTANTIALLY AS INDICATED, ANY CHANGE
RESULTING IN A SAVINGS IN LABOR OR MATERIAL SHALL BE MADE ONLY IN ACCORDANCE
WITH A CONTRACT CHANGE ORDER. DEVIATIONS SHALL BE MADE ONLY WHERE NECESSARY
TO AVOID INTERFERENCES AND ONLY AFTER DRAWINGS SHOWING THE PROPOSED DEVIATIONS
HAVE BEEN SUBMITTED TO AND APPROVED BY THE ARCHITECT.
L COORDINATE ALL SHUTDOWNS Of THE PLUMBING SYSTEM IN ADVANCE WITH THE OWNER.
11. SUBMITTALS
A. PROVIDE A MINIMUM OF SIX (6) SUBMITTAL DRAWINGS FOR PLUMBING FIXTURES, EQUIPMENT,
RELEASED FOR CONSTRUCTION R SPECIFIED COMPONENTS FOR APPROVAL BY THE ARCHITECT AND ENGINEER.
NE MAKE OF EQUIPMENT IS NAMED, IT SHALL BE PROVIDED AS SPECIFIED.
SUsect to compliance with all regulations
of State and Local Codes STS OF APPROVALS FOR ANY SUBSTITUTION WILL NOT BE BINDING ON THE
OWNER.
City of Carmel
�G
DATE: 10/23/19
D. THIS CONTRACTOR ASSUMES ALL RESPONSIBILITY FOR All COSTS FOR REDESIGN CHANGES
NECESSARY BY ALL TRADES TO ACCOMMODATE THE USE OF EQUIPMENT NOT SPECIFIED ON
PROJECT DOCUMENTS.
E. BIDS SHALL BE BASED UPON THE SPECIFIED PRODUCTS OR LISTED ALTERNATIVES. DRAWINGS
AND SPECIFICATIONS ARE BASED ON THE PRODUCTS SPECIFIED BY TYPE, MODEL, AND SIZE
AND THUS ESTABLISH MINIMUM QUALITIES, WHICH SUBSTITUTES MUST MEET TO QUALIFY FOR
REVIEW.
F. SHOULD THE CONTRACTOR PROPOSE TO FURNISH MATERIALS, EQUIPMENT, AND DEVICES,
OTHER THAN THOSE SPECIFIED AND USTED, THE CONTRACTOR SHALL SUBMIT A WRITTEN
REQUEST FOR SUBSTITUTIONS, TO THE ENGINEER, AT LEAST FOURTEEN (14) CALENDAR DAYS
PRIOR TO BID OPENING. THE REQUEST SHALL BE AN ALTERNATE TO THE ORIGINAL BID AND
SHALL INCLUDE AND BE ACCOMPANIED WITH COMPLETE SPECIFICATIONS CUT SHEET SUBMITTAL
AS OUTLINED IN SECTION 11.A OF THIS SPECIFICATION SECTION, COMPLETE WITH DESCRIPTVE
(MANUFACTURER, BRAND NAME, CATALOG NUMBER, ETC.) AND TECHNICAL DATA FOR ALL
ITEMS. INDICATE ANY ADDITIONS OR DEDUCTIONS TO THE CONTRACT PRICE WITH THE
SUBSTITUTION SUBMITTAL AND ON THE BID FORM. FAILURE TO PERFORM THESE ACTIONS
EQUATES TO ACKNOWLEDGEMENT THAT THE PROJECT HAS BEEN BID WITH STRICT
ACCORDANCE TO THIS SPECIFICATION AND APPLICABLE DRAWINGS.
G. ACCEPTANCE OR REJECTION OF THE PROPOSED SUBSTITUTIONS SHALL BE SUBJECT TO
APPROVAL OF THE ARCHITECT AND ENGINEER. IF REQUESTED, THE CONTRACTOR SHALL
SUBMIT INSPECTION SAMPLES OF BOTH THE SPECIFIED AND THE PROPOSED SUBSTITUTE
ITEMS.
H. IF ANY SUBSTITUTIONS ARE APPROVED, AN ADDENDUM USTING THE APPROVED ITEMS) WILL
BE ISSUED TO ALL BIDDING CONTRACTORS PRIOR TO THE BID DATE.
I. IN ALL CASES WHERE SUBSTITUTIONS ARE PERMITTED, THE CONTRACTOR SHALL BEAR ANY
EXTRA COST OF EVALUATING THE EQUALITY OF THE MATERIAL AND EQUIPMENT TO BE
INSTALLED.
J. WHERE ONLY ONE MAKE IS NAMED IN THE SPECIFICATIONS OR ON THE DRAWINGS, IT SHALL
BE PROVIDED.
K. VERBAL REQUESTS OR APPROVALS SHALL NOT BE BINDING ON THE ENGINEER OR OWNER.
12. EQUIPMENT AND PIPING IDENTIFICATION
A. LABEL ALL PIPING SYSTEMS WITH PIPE MARKERS INSTALLED ADJACENT TO VALVES, WHERE
PIPES PASS THROUGH WALLS OR FLOORS, NEAR ALL BRANCHES AND CHANGES OF
DIRECTION, AT 20 FEET INTERVALS ON STRAIGHT RUNS OF PIPE, AND AT ACCESS DOOR
LOCATIONS. ALL PIPE MARKERS SHALL CONFORM TO ANSI A13.1 'SCHEME FOR THE
IDENTIFICATION OF PIPING SYSTEMS%
B. THE CONTRACTOR SHALL FURNISH AND INSTALL A SYSTEM OF NAMEPLATES DESIGNED TO
IDENTIFY EACH PIECE OF EQUIPMENT.
(1) NAMEPLATE LETTER AND NUMBERS SHALL MATCH EQUIPMENT DESIGNATION AS INDICATED
ON THE DRAWINGS.
(2) NAMEPLATES SHALL BE LAMINATED PHENOLIC WITH BLACK SURFACE AND WHITE CORE.
USE 1/16' THICK MATERIAL FOR PLATES UP TO 2' BY 41. FOR LARGER SIZES USE
1/8" THICK. LETTERS AND NUMBERS SHALL BE A MINIMUM OF 1/2" HIGH.
(3) FASTEN NAMEPLATES TO ALL EQUIPMENT BY THE USE OF STAINLESS STEEL SHEET METAL
SCREWS.
13. AS -BUILT DRAWINGS
A. AS WORK PROGRESSES, RECORD ON A SET OF 'AS -BUILT" PRINTS ANY DEVIATIONS FROM
DESIGN DRAWINGS. DELIVER TO THE OWNER BEFORE SUBMITTING REQUEST FOR FINAL
PAYMENT. THE "AS -BUILT" PRINTS SHALL BE AN ACCURATE DEPICTION OF THE PROJECT AS
COMPLETED.
14. OPERATING AND MAINTENANCE MANUALS
A. PROVIDE TO OWNER, AT PROJECT TURNOVER, THREE (3) HARDBOUND COPIES OF OPERATING
AND MAINTENANCE MANUALS FOR ALL EQUIPMENT AND SYSTEMS INSTALLED. MANUALS SHALL
INCLUDE ALL RELEVANT INFORMATION NEEDED FOR DAY-TO-DAY OPERATION AND
MANAGEMENT OF EACH SYSTEM, AS WELL AS EQUIPMENT MAINTENANCE INFORMATION
REQUIRED TO SUPPORT THE MAINTENANCE PROGRAM.
15. OPERATING INSTRUCTIONS
A. PROVIDE TO OWNER AFTER ALL EQUIPMENT IS IN OPERATION AND AT AN AGREEABLE TIME,
INSTRUCTIONS FOR THE PURPOSE OF TRAINING OWNER'S PERSONNEL IN ALL PHASES OF OPERATION
AND MAINTENANCE OF EQUIPMENT AND SYSTEMS. SCHEDULE TRAINING WITH OWNER, PROVIDE AT
LEAST SEVEN DAYS PRIOR NOTICE. PROVIDE THIS TRAINING TO ALL PERSONNEL AND ON ALL
SHIFTS.
16. INSULATION
A. PROVIDE ALL INSULATION MATERIALS (INSULATION, JACKETS, FITTING COVERS, ADHESIVES, CEMENTS,
MASTICS, SEVERS AND FINISHES) WITH A FLAME -SPREAD INDEX OF 25 OR LESS AND SMOKE
DEVELOPED INDEX OF 50 OR LESS, AS TESTED UNDER PROCEDURE ASTM E-84 (NFPA 255).
B. ALL INSULATION SHALL BE INSTALLED OVER CLEAN, DRY SURFACES. INSULATION MUST BE DRY AND
IN GOOD CONDITION. NET OR DAMAGED INSULATION IS NOT ACCEPTABLE. NO INSULATION SHALL
BE APPLIED PRIOR TO PRESSURE TEST COMPLETION OF THE RESPECTIVE PIPING SYSTEM.
CALL INSULATION SHALL BE CONTINUOUS (INCLUDING VAPOR BARRIER) THROUGH WALL AND CEILING
OPENINGS, SLEEVES, AND PIPE HANGER LOCATIONS.
D.ALL INSULATION PRODUCTS SHALL BE APPLIED IN ACCORDANCE WITH MANUFACTURER'S WRITTEN
RECOMMENDATIONS. THE WORKMANSHIP SHALL BE FIRST CLASS AND ALL JOINTS SHALL BE MADE
TIGHT.
E INSULATE VALVE BONNETS AND UNIONS ON DOMESTIC WATER PIPING WITH INSULATION MATCHING
PIPE INSULATION.
F. INSULATE DOMESTIC COLD WATER PIPING AND FITTINGS WITH OWENS-CORNING ONE-PIECE
FIBERGLASS PIPE INSULATION WITH ALL SERVICE JACKET, 1/2" THICKNESS FOR PIPING LESS THAN
OR EQUAL TO 1.T, 1' THICKNESS FOR PIPES LARGER THAN 1.5". INSULATE DOMESTIC HOT WATER
PIPING AND FITTINGS WITH THE SAME INSULATION, 1" THICKNESS FOR PIPING LESS THAN OR EQUAL
TO 1.5, 2' THICKNESS FOR PIPING LARGER THAN 1.5.
G.INSULATE HORIZONTAL STORM PIPING AND ROOF DRAIN SUMPS WITH OWENS-CORNING ONE PIECE
FIBERGLASS PIPE INSULATION WITH ALL SERVICE JACKET, 1/2" THICKNESS.
H.INSULATE ELECTRIC WATER COOLER TRAP AND WASTE PIPING WITHIN CABINET WITH 1/2' THICK
ARMALEX AP PIPING INSULATION.
I. REPAIR EXISTING INSULATION WHERE REMOVED FOR NEW CONNECTION. INSULATION SHALL BE THE
SAME AS SPECIFIED FOR NEW SERVICE.
K.ALL INSULATION USED AS PLENUM WRAP COVERING FOR COMBUSTIBLE MATERIALS IN A PLENUM
SPACE SHALL BE 3M PLENUM PROTECTION SYSTEM (PP-100-P), ONE LAYER OF 3M FIRE BARRIER
DUCT WRAP &A, IN ACCORDANCE WITH UL910 & UL1887.
17. MATERIALS
A. PIPE AND FITTINGS
(1) DOMESTIC WATER SHALL BE TYPE "L" COPPER.
(2) SANITARY DRAIN AND VENT PIPING LOCATED IN RETURN AIR PLENUM SHALL BE SERVICE WEIGHT
NO HUB CAST IRON PIPE. ALL CAST IRON PIPE AND FITTINGS SHALL COMPLY WITH ASTM A 888
(OR A 74) AND BE MARKED WITH THE COLLECTIVE TRADEMARK OF THE CAST IRON SOIL PIPE
INSTITUTE (CISPI) AND BE USED BY THE NSF INTERNATIONAL
(3) FITTINGS FOR COPPER PIPE SHALL BE WROUGHT COPPER SOLDER JOINT TYPE. ONLY LEAD
FREE SOLDER IS ACCEPTABLE.
(4) FITTINGS FOR BLACK STEEL PIPE 2" AND SMALLER SHALL BE 150 PSIG SWP MALLEABLE IRON
SCREWED FITTINGS. FOR 2-1/2' AND LARGER, FITTINGS SHALL BE FACTORY FORMED WELDING
FITTINGS.
(5) FITTINGS FOR SANITARY DRAIN AND VENT PIPING LOCATED IN RETURN AIR PLENUM SHALL BE
SERVICE WEIGHT NO HUB CAST IRON PIPE WITH STAINLESS STEEL MECHANICAL JOINT
COUPLINGS. COUPUNGS SHALL COMPLY WITH 'CISPI 310. THE ELASTOMERIC SEALING SLEEVE
SHALL CONFORM TO 7STM C 56C AND SHALL BE PROVIDED WITH A CENTER STOP.
MECHANICAL JOINT COUPUNGS SHALL BE INSTALLED IN ACCORDANCE WITH THE
MANUFACTURER'S INSTALLATION INSTRUCTIONS.
B. DOMESTIC WATER VALVES
(1)DOMESTIC WATER SHUT-OFF VALVES SHALL BE BRONZE BODY, TWO PIECE, FULL PORT, LEVER
HANDLE BALL VALVES WITH TEFLON SEATS, CHROME PLATED BRASS BALL, BRASS STEM AND
SOLDER ENDS. 600 PSI WOG. ACCEPTABLE MANUFACTURERS: MILWAUKEE, HAMMOND, APOLLO
(2) HORIZONTAL CHECK VALVES SHALL BE BRONZE BODY, SWING TYPE DESIGN, BRONZE DISC,
STAINLESS STEEL LEVER WITH SOLDER ENDS. 200 PSI WOG. ACCEPTABLE MANUFACTURERS:
MILWAUKEE, HAMMOND. APOLLO
(3) MANUAL BALANCING VALVES SHALL BE BRONZE BODY, COMBINATION VENTURI AND HALL VALVE
WITH TWO PRESSURE/TEMPERATURE TEST PORTS, MEMORY STOP, INLET UNION CONNECTION
AND THREADED ENDS, 400 PSI AT 2507. ACCEPTABLE MANUFACTURERS: FLOW DESIGN INC.
"FLOWSET".
18. PIPING INSTALLATION
A. PROVIDE MACHINE CUT STEEL PIPE SLEEVE 1" URGER THAN OUTSIDE DIAMETER OF PIPE. WHERE
FLOORS ARE CORE DRILLED, STEEL SLEEVES ARE NOT REQUIRED. SEAL OPENINGS TO MAINTAIN THE
INTEGRITY OF THE FIRE RATING.
B. PROVIDE ALL INSERTS, FASTENERS AND SUPPORTS TO PROPERLY SUPPORT AND RETAIN PIPING; TO
CONTROL EXPANSION, CONTRACTION, ANCHORAGE, DRAINAGE, AND PREVENT SWAY AND VIBRATION.
PIPING SHALL BE $O SUPPORTED AS NOT TO PLACE A STRAIN ON VALVES, FIXTURES OR
EQUIPMENT.
C. THE DRAWINGS INDICATE THE GENERAL LOCATION AND ARRANGEMENT OF THE PIPING SYSTEMS. SO
FAR AS PRACTICAL INSTALL PIPING AS INDICATED MAKING CONNECTIONS TO ALL EQUIPMENT AND
FIXTURES. INSTALL PIPING AS DIRECT AS POSSIBLE AVOIDING UNNECESSARY OFFSETS. HOWEVER, IF
OFFSETS ARE REQUIRED IN ORDER TO OBTAIN MAXIMUM HEADROOM OR TO AVOID CONDUCT WITH
OTHER WORK, THEY SHALL BE MADE AS REQUIRED OR AS REQUESTED BY THE ARCHITECT WITHOUT
ADDITIONAL COST TO THE OWNER. THE ARCHITECT RESERVES THE RIGHT TO MAKE MINOR CHANGES
IN THE LOCATION OF PIPING AND EQUIPMENT DURING THE ROUGHING -IN, WITHOUT ADDITIONAL COST
TO THE OWNER. ALL CHANGES PROPOSED BY OTHERS SHALL BE APPROVED BY THE ARCHITECT.
D.INSTALL PIPING FREE OF SAGS OR BENDS
E. ALL PIPING SYSTEMS MUST BE INSTALLED $O THEY CAN BE COMPLETELY DRAINED. PROVIDE TEE
FITTING, BALL VALVE WITH HOSE THREAD FITTING AND CAP AT ALL LOW POINTS, TRAPPED SECTIONS,
BASES OF RISERS, AND ON EQUIPMENT SIDE OF SHUT OFF VALVES TO PERMIT DRAINING. PROVIDE
BALL VALVES AT ALL HIGH POINTS TO ALLOW VENTING. ALL DRAIN VALVES AND VENTS SHALL BE
ACCESSIBLE
F. TERMINATE PLUMBING VENT PIPES AT LEAST 12 INCHES ABOVE ROOF.
G.BUILDING DRAINS SHALL BE PACHED A MINIMUM SLOPE OF 1/4 INCH PER FOOT FOR PIPES UP TO
2-1/2 INCH AND 1/8 INCH PER FOOT FOR PIPES GREATER THAN 2-1/2 INCHES.
H. PROVIDE WATER HAMMER ARRESTERS WHERE QUICK -CLOSING VALVES ARE UTILIZED, AND
INSTALL IN ACCORDANCE WITH THE MANUFACTURER'S SPECIFICATIONS.
J. PROVIDE CHECK VALVES WHERE BACKFLOW PROTECTION IS REQUIRED, AND INSTALL IN ACCORDANCE
WITH THE MANUFACTURER'S SPECIFICATIONS. PROVIDE AT FIXTURES SUCH AS BUT NOT LIMITED TO;
DISHWASHERS, COFFEE MAKERS, ICE MACHINES, BEVERAGE DISPENSERS, REFRIGERATORS. PROVIDE
WATTS OD7 OR EQUIVALENT.
K. PROVIDE DIELECTRIC UNIONS AT COUPLING OF DISSIMILAR METALS
19. DISINFECTION
A. CHLORINATE ALL DOMESTIC WATER SYSTEMS AS FOLLOWS. FIRST FLUSH SYSTEM WITH CLEAN
POTABLE WATER UNTIL DIRT WATER DOES NOT APPEAR AT OUTLETS. THEN FILL WITH A
WATER/CHLORINE SOLUTION (50PPM CHLORINE) AND ALLOW TO STAND FOR 24 HOURS. FOLLOWING
STANDING TIME, FLUSH THE SYSTEM WITH CLEAN POTABLE WATER UNTIL CHLORINE IS PURGED FROM
THE SYSTEM. REPEAT CHLORINATION, IF NECESSARY, UNTIL NO BACTERIOLOGICAL CONTAMINATION IS
PRESENT IN THE SYSTEM. PROCEDURE SHALL CONFORM TO ANNA C651 AND BE ACCEPTED BY THE
LOCAL HEALTH DEPARTMENT.
20. PLUMBING FIXTURES AND EQUIPMENT
A GENERAL
(1) PROVIDE FIXTURES OF TYPE, STYLE AND MATERIAL AS SCHEDULED ON THE DRAWINGS. INCLUDE
ALL TRIM, CARRIERS, SEATS, ETC. AS INDICATED OR RECOMMENDED BY MANUFACTURER AS
REQUIRED FOR A COMPLETE INSTALLATION.
(2) PROVIDE VACUUM BREAKERS AS PART OF THE FIXTURE OR EQUIPMENT TRIM WHEREVER THERE
IS A POSSIBILITY OF BACK SIPHONING.
(3) PROVIDE DOUBLE CHECK VALVES FOR PLUMBING FIXTURE OR SPECIAL EQUIPMENT WHERE
BACKFLOW PROTECTION IS REQUIRED, AND INSTALL IN ACCORDANCE WITH THE MANUFACTURER'S
SPECIFICATIONS, USE WATTS SERIES 7 BRONZE DUAL CHECK VALVE.
(4) PROVIDE FIXTURES CONSTRUCTED OF VITREOUS CHINA WITH ALL VISIBLE SURFACES GLAZED.
FURNISH ENAMELED CAST IRON FIXTURES CONSTRUCTED WITH NON -STAINING, ACID RESISTANT,
PORCELAIN ENAMELED COAT THOROUGHLY FUSED ON THE SURFACES. FURNISH STAINLESS STEEL
SINKS WITH SATIN FINISH, UNLESS NOTED OTHERWISE.
(5) PROVIDE ALL STOPS, SUPPLIES, TRAPS AND ESCUTCHEONS NECESSARY FOR A COMPLETE
INSTALLATION. ALL COMPONENTS SHALL BE CHROME PLATED BRASS.
(6) STOPS SHALL BE STRAIGHT OR ANGLE TYPE AS REQUIRED BY THE INSTALLATION, WITH LOOSE
KEY, META_ STEM AND WASHER CUP WITH SET SCREW WASHER RETAINER.
(7) SUPPLIES SHALL BE FLEXIBLE CHROME PLATED COPPER.
(8) TRAPS SHALL BE 17 GAUGE CHROME PLATED BRASS WITH CLEAN -OUT PLUG. FURNISH WITH
SLIP NUTS, WALL BEND AND ESCUTCHEON.
(9) PROVIDE CARRIERS AND SUPPORTS AS REQUIRED FOR PROPER FIXTURE INSTALLATION. TYPE
SHALL PERMIT FIELD ADJUSTMENT TO AT VARIATIONS IN CONSTRUCTION. UNLESS NOTED
OTHERWISE, SUPPORT ALL WALL MOUNTED PLUMBING FIXTURES ON CONCEALED CHAR CARRIERS
WITH FOOT SUPPORT.
(10)PROODE FAUCET AERATORS AND OUTLETS OF TYPES APPROVED BY THE LOCAL HEALTH
DEPARTMENT AND LOCAL PLUMBING CODE, REFER TO IPC TABLE 604.4.
(11)INSULATE ALL EXPOSED WATER SUPPUES AND TRAPS WHERE FIXTURES ARE INDICATED TO
COMPLY WITH THE REQUIREMENTS OF THE AMERICANS WITH DISABILITIES ACT. INSULATION KITS
SHALL BE 3/16" THICK MOLDED CLOSED CELL VINYL CONSTRUCTION WITH PVC SATIN WHITE
COVER.
PLUMBING
ABBREVIATIONS
AFF
ABOVE FINISHED FLOOR
OR
GRADE
AP
ACCESS PANEL
GOD
GRADE CLEANOUT
AV
ACID VENT
ID
INSIDE DIAMETER
AW
ACID WASTE
INN
INVERT
AC
AIR CHAMBER
MC
MECHANICAL CONTRACTOR
ARCH
ARCHITECT
MAR
MANUFACTURER
B.T.
BATH TUB
N.C.
NORMALLY CLOSED
BPW
BED PAN WASHER
N.O.
NORMALLY OPEN
BLDG
BUILDING
NIC
NOT IN CONTRACT
C.A.P.
COLLEGE OF AMERICAN PATHOLOGIST
NTS
NOT TO SCALE
Cl
CAST IRON
OD
OUTSIDE DIAMETER
CLG.
CEIUNG
PC
PLUMBING CONTRACTOR
CLDI
CEMENT LINED DUCTILE IRON
TYP
TYPICAL
CP
CHROME PLATED
VB
VACUUM BREAKER
CONT
CONTINUATION
SH
SHOWER
CS
CUP SINK
SK
SINK
DIA
DIAMETER
SS
SOIL STACK
DOV
DRAIN OFF VALVE
SPEC
SPECIFICATION
DWG
DRAWING
S.S.
STAINLESS STEEL
EA
EACH
VS
VENT STACK
EC
ELECTRICAL CONTRACTOR
VIR
VENT THRU ROOF
EL
ELEVATION
VOID
VITRIFIED CLAY PIPE
EEW
EMERGENCY EYE WASH
WS
WASTE STACK
ESH
EMERGENCY SHOWER
W & T
WASTE & TRAP
EX, EXIST
EXISTING
W & V
WASTE & VENT
EJ
EXPANSION JOINT
WC
WATER CLOSET
FUR
FLOOR
XCW
EXISTING DOMESTIC COLD WATER
FT
FOOT
XHW
EXISTING DOMESTIC HOT WATER
GALV
GALVANIZED
XHWR
EXISTING DOMESTIC HOT WATER RETURN
GC
GENERAL CONTRACTOR
PLUMBING
LEGEND
CAP OR END OF PIPE
G'1
CV
CHECK VALVE
RICO
CLEANOUr
Cw
COLD WATER
It
GTE
CONNECT TO EXISTING
J
ELBOW DOWN OR DROP
O
ELBOW UP OR RISE
EXISTING PIPING
1.1
FIXTURE IDENTIFICATION
-------OFCO
FLOOR CLEANOUT
Hw
HOT WATER
HVAR
HOT WATER RETURN
_SA N
SANITARY PIPING ABOVE FLOOR
- -SAN- -
SANITARY PIPING BELOW FLOOR
8
TEE LOOKING DOWN
0
TEE LOOKING UP
--AI,
UNION
---- V ----
VENT ABOVE GROUND
---- V ----
VENT BURIED
___41 WCO
WALL CLEANOUT
DG
ISOLATION / SHUT-OFF VALVE
----fZ4-
GOV DOUBLE CHECK VALVE
1/2" HW SUPPLY_
TANKLESS POINT -OF -USE
WATER HEATER, 5�1 ONLY
3/4" CONDENS
LINE FROM ICE
MACHINE
1 1/2" AIR
JR. SMITH FIGURE NO. 3822
2" HUB DRAIN W/ J.R. SMITH
WATER SAVER TRAP PRIMER
#2698, S_1 ONLY.
PLUMBING NOTES
1. GENERAL NOTES, SYMBOLS UST AND DETAILS ARE APPLICABLE TO All DRAWINGS MARKED P.
2. DRAWINGS ARE DIAGRAMMATIC: DETERMINE LOCATIONS OF SYSTEMS AND COMPONENTS IN FIELD.
3. PBCH PRESSURE PIPING IN DIRECTION OF FLOW.
4. DIMENSIONS SHOWN ON PLAN ARE HORIZONTAL DIMENSIONS SHOWN IN ELEVATION ARE VERTICAL EXCEPT THAT, IN WAY
OF STRUCTURAL DIMENSIONS ARE MEASURED PERPENDICULAR TO FLANGE.
5. NEITHER ACCURACY NOR COMPLETION OF UTILITY LOCATIONS SHOWN ON DRAWINGS IS GUARANTEED. DETERMINE EXACT
LOCATIONS OF EXISTING UTILITIES IN FIELD, WHETHER OR NOT SHOWN ON DRAWINGS. EXERCISE CAUTION, AND IDENTIFY
LOCATIONS OF UNMARKED UTILITY LINES AS NECESSARY TO PERFORM WORK OF THIS SECTION.
6. ALL PLUMBING WORK SHALL BE IN ACCORDANCE WITH LOCAL AND STATE PLUMBING CODES AND DRAWINGS.
7. IT SHALL BE THE RESPONSIBUTY OF THIS CONTRACTOR TO COORDINATE HIS WORK WITH THAT OF ALL OTHER TRADES,
INCLUDING (BUT NOT UNITED TO), ELECTRICAL WAG, PROCESS PIPING, SPRINKLER, STRUCTURAL AND GENERAL
ARCHITECTURE.
8. ANY INTERFERENCE SHALL BE BROUGHT TO THE ATTENTION OF THE CONSTRUCTION MANAGER AND THE OWNER'S
REPRESENTATIVE, AND SHALL BE RESOLVED PRIOR TO THE INSTALLATION OF THE WORK INVOLVED.
9. NO WORK SHALL BE INSTALLED IN VIOLATION OF ANY GOVERNING CODES. ANY WORK SHOWN ON THE DRAWINGS WHICH
IS IN VIOLATION OF SUCH CODES SHALL BE BROUGHT TO THE ATTENTION OF THE CONSTRUCTION MANAGER AND THE
OWNER'S REPRESENTATIVE AND SHALL BE RESOLVED PRIOR TO THE INSTALLATION OF THE WORK INVOLVED.
10. ALL PIPING PENETRATING CEILINGS AND WALLS SHALL BE INSTALLED WITH CHROME (STAINLESS WHERE NOTED) PLATED
ESCUTCHEONS AT THE PENETRATION. ALL PIPING PENETRATING EXTERIOR WALLS AND ROOFS SHALL BE FLASHED IN AN
APPROVED MANNER AND SHALL BE SEALED WEATHERTIGHT. PIPING PENETRATING RATED PARTITIONS SHALL BE PROTECTED
AS REQUIRED BY LOCAL CODE AUTHORITY.
11. MANUFACTURERS' MODEL NUMBERS ARE SPECIFIED SOLELY TO ESTABLISH STANDARDS OF QUALITY FOR PERFORMANCE
AND MATERIALS.
12. PRODUCT INSTALLATION SHALL ADHERE TO MANUFACTURERS' RECOMMENDATIONS.
13. PROVIDE ACCESS PANELS FOR EQUIPMENT THAT REQUIRES PERIODIC SERVICE.
14. ALL PIPING ABOVE GRADE SHALL BE PROPERLY SUPPORTED BY THE BUILDING STRUCTURE AND SHALL NOT REST ON
CEIUNG TILES OR CEIUNG STRUCTURE.
15. ALL PLUMBING EQUIPMENT, PIPING, INSULATION, ETC., INSTALLED IN WAG PLENUM SPACES SHALL MEET CODE
REQUIREMENTS FOR SMOKE AND COMBUSTIBILITY.
16.
17. ALL SLEEVES THROUGH CONCRETE FLOORS AND ALL CORE DRIVING OF CONCRETE FLOORS AND WALLS SHALL BE BY
THIS CONTRACTOR.
18. SCHEDULE WORK OF THIS SECTION TO AVOID INTERFERING WITH EXISTING STRUCTURE.
19. RUN PIPING CONCEALED, UNLESS SPECIFIED OTHERWISE, AND CLEAR OF CEIUNG INSERTS.
20. PROVIDE CLAMPS, OFFSETS, EXPANSION JOINTS, ANCHORS AND GUIDES AS NECESSARY TO PREVENT STRESS ON PIPING.
21. PROVIDE VENTS AT HIGH POINTS IN PIPING SYSTEMS AND DRAIN VALVES AT LOW POINTS.
22. VERIFY EXACT SIZES, LOCATIONS, INVERTS AND ELEVATIONS PRIOR TO RUNNING ANY PIPING. REFER TO ARCHITECTURAL
DRAWINGS FOR EXACT LOCATIONS OF ALL FIXTURES AND EQUIPMENT.
23. PIPE SUPPORTS FOR PLUMBING SERVICE IN BUILDING SHAFTS ARE BY THIS CONTRACTOR. CAREFULLY COORDINATE WITH
MISC. IRON CONTRACTOR PLACEMENT OF STEEL GRATE SUPPORT BEAMS. SHAFT PIPE SUPPORT SHALL BEAR FROM WALL
AND FROM FLOOR SUPPORT BEAMS.
24. CONTRACTOR SHALL FIELD VERIFY CONNECTION TO EXISTING SANITARY.
PLUMBING DEMOLITION NOTES
1. THESE DRAWINGS ARE DIAGRAMMATIC ONLY AND ARE TO BE USED AS A GUIDELINE ONLY FOR THE SCOPE OF DEMOLITION
WORK. THE PLUMBING CONTRACTOR SHALL VISIT THE PROJECT SITE DURING THE BID PHASE TO VERIFY THE EXACT
CONDITIONS AND SCOPE OF WORK REQUIRED FOR A COMPLETE AND INCLUSIVE DEMOLITION PACKAGE. IT IS THE INTENT
TO RE -USE EXISTING SYSTEMS AS NOTED WHERE PRACTICAL.
2. THE PLUMBING CONTRACTOR SHALL BE HELD TO HAVE EXAMINED THE PREMISES AND SITE $O AS TO COMPARE THEM
WITH THE CONTRACT DOCUMENTS AND TO HAVE SATISFIED HIMSELF AS TO THE CONDITIONS OF THE PREMISES, THE SITE,
ANY OBSTRUCTIONS, THE ACTUAL FLOOR PLANS AND CONDITIONS, ACCESS PANELS. AND ALL OTHER EXISTING CONDITIONS.
THE PLUMBING CONTRACTOR SHALL VERIFY ALL DIMENSIONS IN THE FIELD, SHALL CHECK LOCATION OF AND CONNECTION
TO EXISTING FACILITIES, AND SHALL ASSUME ALL RESPONSIBIUTY FOR SAME.
3. ANY EXISTING EQUIPMENT, PIPING DEVICES BEING DISTURBED BY THE WORK SHALL BE REWORKED BY THIS CONTRACTOR
AS REQUIRED TO RETURN TO ITS FORMER EXISTING OPERATING CONDITION.
4. THE PLUMBING CONTRACTOR SHALL COORDINATE WITH THE OWNER/BUILDING MANAGEMENT ALL INTERRUPTION OF SERVICES
WITHIN THE AREA OF WORK AND BUILDING.
5. ALL EXISTING FIXTURES, DEVICES, EQUIPMENT, ETC. NOT INDICATED ON THE PLANS DRAWINGS SHALL BE CONSIDERED TO
BE EXISTING TO REMAIN, UNLESS SPECIFICALLY NOTED OTHERWISE.
6. FOR ALL RENOVATION/REMOLDING WORK, INCLUDING ALL AREAS OF NO OR MINIMAL WORK, EXISTING PLUMBING SERVICES
SHALL BE MAINTAINED TO FIXTURES, DEVICES, EQUIPMENT, OTHER PIPING, ETC. THAT ARE REQUIRED TO BE MAINTAINED.
THE PLUMBING CONTRACTOR SHALL BE RESPONSIBLE TO MAINTAIN THESE SERVICES, FIXTURES, DEVICES, EQUIPMENT,
OTHER PIPING THAT ARE EXISTING TO REMAIN, WHETHER OR NOT INDICATED ON THE PLANS.
7. DISCONNECT AND REMOVE ALL EXISTING FIXTURES, DEVICES, EQUIPMENT, PIPING, ETC. LOCATED WITHIN THE AREA OF
WORK INDICATED AS "TO BE REMOVED". CUT AND CAP ALL UNDER FLOOR AND UNDERGROUND PIPING PER LOCAL CODE
REQUIREMENTS.
8. ALL FIXTURES, DEVICES, EQUIPMENT, PIPING, ETC. SHALL BE REMOVED COMPLETE, BACK TO SOURCE, SUCH AS SHUT OFF
VALVES AND/OR METERING.
9. MAINTAIN ALL SERVICES IN ALL AREAS OF WORK AND SURROUNDING AREAS NOT IN DEMOLITION.
10. THE PLUMBING CONTRACTOR SHALL COORDINATE WITH THE ARCHITECTURAL, MECHANICAL WAG, AND ELECTRICAL
DEMOLITION DRAWINGS FOR ALL EQUIPMENT BEING DEMOLISHED, AND SHALL DISCONNECT AND REMOVE COMPLETE THE
PLUMBING SERVICES TO ALL FIXTURES, DEVICES AND EQUIPMENT.
11. FIXTURES, DEVICES, AND EQUIPMENT INDICATED AS "XW. (EXISTING TO BE RELOCATED), SHALL BE STORED FOR RE -USE
AS INDICATED BY "XIS", (NEW LOCATION OF EXISTING DEVICE), ON NEW PLAN DRAWINGS. FIXTURES, DEVICES, AND
EQUIPMENT SHALL BE CLEANED AND IN COMPLETE OPERATIONAL CONDITION UPON COMPLETION OF RE -INSTALLATION.
12. ALL CUTTING AND PATCHING OF WALLS, CEILINGS, OR FLOORS THAT ARE DISTURBED BY DEMOLITION SHALL BE RETURNED
TO THEIR ORIGINAL CONDITION. REFER TO THE ARCHITECTURAL DOCUMENTS FOR EXACT SPECIFICATION REQUIREMENTS.
PATCH FLOOR TO ORIGINAL CONSTRUCTION SPECIFICATIONS AND U.L. ARE RATING USTINGS FOR ALL FLOOR MOUNTED
FIXTURES, DEVICES, AND EQUIPMENT WHICH HAVE BEEN REMOVED.
13. ALL EQUIPMENT AND/OR DEVICES THAT ARE REMOVED AND NOT RE -USED SHALL BE TURNED OVER TO OWNER/BUILDING
MANAGEMENT OR DISPOSED OF PER THEIR DIRECTION.
14. ALL MATERIAL TO BE DISPOSED SHALL BE DONE UNDER STRICT ACCORDANCE WITH ALL FEDERAL, STATE, AND LOCAL
CODE REQUIREMENTS.
PLUMBING FIXTURE SCHEDULE
S-1
COUNTERTOP SINK: ELKAY SINGLE BOWL SINK LRADQ2219. 18 GAUGE TYPE 302 STAINLESS
STEEL, SELF RIMMING, THREE FAUCET HOLES, FULLY UNDERCOATED WITH LK35 STAINLESS
STEEL STRAINER AND 1-1/2" TAILPIECE, 1-1/2" CHROME PLATED CAST BRASS P-TRAP.
FAUCET: SYMMONS SYMMETRICS S-23-3, POLISHED CHROME. SINGLE LEVER HANDLE,
PULLOUT SPRAY HEAD.
S-2
COUNTERTOP SINK: ELKAY ASAEA SINGLE BOWL SINK LLVR1916. 18 GAUGE TYPE 304
STAINLESS STEEL, SELF RIMMING, THREE FAUCET HOLES, FULLY UNDERCOATED WITH LK35
STAINLESS STEEL STRAINER AND 1-1/2" TAILPIECE, 1-1/2' CHROME PLATED CAST BRASS
P-TRAP. FAUCET: CHICAGO FAUCET 895-E35ABCP, POLISHED CHROME. LEVER HANDLES,
WITH 0.5 GPM AERATOR E2605-&KCP.
IH-1
TANKLESS POINT -OF -USE WATER HEATER. TEAM MODEL SP3277, WALL MOUNTED, 277
VOLT/1 PHASE, 3.0 KW; TO HEAT 0.5 GPM AT A TEMPERATURE RISE OF 41 DEGREES F.
PLUMBING FIXTURE CONNECTION SCHEDULE
FIXTURE
SANITARY
VENT
COLD WATER
HOT WATER
1 REMARKS
SINK
1 2'
1 1-1/2"
1 1/2'
1 1/2"
n
SINK I I I
1/2" GIN SUPPLY
1
I
�1 1/2" WASTE
I
I
I
n FINISH FLOOR
I l
> a ' ._ . 4 11 a a <
II I
I�WASTE AND VENT PIPING
ILA IN WALL. SEE STACK
DIAGRAM FOR SIZES
SINK - UNDER COUNTER DETAIL
SCALE NONE
GENERAL PLUMBING NOTES
1. ALL "BUILDING STANDARDS" AND/OR "BUILDING SPECIFICATIONS" SHALL BE CONSIDERED AN INTEGRAL PART OF THESE
DOCUMENTS AND THE CONTRACTOR SHALL BE RESPONSIBLE TO OBTAIN A COPY OF THESE DOCUMENTS AND COMPLY
WITH ALL REQUIREMENTS, STANDARDS, AND SPECIFICATIONS CONTAINED WITHIN.
2. THESE DRAWINGS ARE GENERALLY DIAGRAMMATIC AND ARE INTENDED TO CONVEY THE SCOPE OF WORK AND INDICATE
GENERAL ARRANGEMENT OF PIPING, FIXTURES, EQUIPMENT DEVICES, ETC. THE LOCATIONS OF ALL ITEMS SHOWN ON
THESE DRAWINGS OR CALLED FOR IN THE SPECIFICATIONS THAT ARE NOT DEFINITELY FIXED BY DIMENSIONS ARE
APPROXIMATE. THE EXACT LOCATIONS NECESSARY TO SECURE THE BEST CONDITIONS AND RESULTS MUST BE
DETERMINED AT THE PROJECT. ALL LOCATIONS OF WORK EXPOSED TO NEW ARE SUBJECT TO APPROVAL OF THE
ARCHITECT PRIOR TO ROUGH -INS.
3. ANY DISCREPANCIES BETWEEN DRAWINGS AND SPECIFICATIONS SHALL BE PROMPTLY BROUGHT TO THE ATTENTION OF THE
ENGINEER FOR CLARIFICATION DURING THE BIDDING PERIOD. NO ALLOWANCE SHALL SUBSEQUENTLY BE MADE TO THE
CONTRACTOR BY REASON OF HIS FAILURE TO HAVE BROUGHT SAID DISCREPANCIES TO THE ATTENTION OF THE
ARCHITECT/ENGINEER DURING THE BIDDING PERIOD OR OF ANY ERROR ON THE CONTRACTOR'S PART.
4. ALL EQUIPMENT SHALL BE INSTALLED IN A NEAT, PROFESSIONAL AND WORKMANLIKE MANNER, RECTIUNEAR TO FINISHES
AND BUILDING STRUCTURE.
5. REFER TO ARCHITECTURAL ELEVATIONS TO DERIVE EXACT LOCATIONS OF ALL RELATED EQUIPMENT, DEVICES, ETC.
6. THE PLUMBING CONTRACTOR SHALL VERIFY EXISTING CONDITIONS TO INSURE THAT ALL NEW WORK WILL FIT INTO THE
EXISTING STRUCTURE AND CONDITIONS IN THE MANNER INTENDED AND AS SHOWN ON THE DRAWINGS. THE CONTRACTOR
SHALL NOTIFY THE ARCHITECT/OWNERS REPRESENTATIVE PRIOR TO ANY ROUGH -INS, FABRICATIONS, OR PERFORMING ANY
WORK IN THE AREA INVOLVING DIFFERENCES. NOTIFICATION SHALL BE IN THE FORM OF A RFl, INCLUDING A DRAWING OR
SKETCH INDICATING FIELD MEASUREMENTS AND NOTES RELATED TO THE AREA
7. ALL PIPING RUNNING THROUGH BUILDING EXPANSION JOINTS SHALL BE EQUIPPED WITH APPROPRIATE EXPANSION FITTINGS.
8. ALL COMPONENTS SHOWN ON THE STACK AND OR RISER DIAGRAMS, BUT NOT ON THE PLAN OR VICE VERSA, SHALL BE
INCLUDED AS IF SHOWN ON BOTH
9. THE PLUMBING CONTRACTOR SHALL REFER TO THE PLUMBING SPECIFICATIONS FOR ACCEPTABLE PIPING TYPES/LOCATIONS.
10. IT IS NOT INTENDED THAT THE PLANS INDICATE ALL OBSTRUCTIONS, NECESSARY BENDS, AND OFFSETS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO INSTALL HIS WORK TO CONFORM TO CODE REQUIREMENTS, THE STRUCTURE,
MAINTAIN HEADROOM AND KEEP OPENINGS AND PASSAGEWAYS CLEAR. REFER TO THE ARCHITECTURAL DRAWINGS FOR ALL
DIMENSIONS AS REQUIRED.
11. IT IS NOT INTENDED THAT THE PLANS INDICATE ALL PIPING ROUTES, OFFSETS, TRANSITIONS, ETC. CONTRACTOR SHALL BE
RESPONSIBLE FOR DETERMINING ACTUAL PIPE ROUTING, QUANTITY AND OFFSETS AND TRANSITIONS WITHIN ACCESSIBLE
LOCATIONS.
12. SUPPORT ALL EQUIPMENT, AND PIPING FROM BUILDING STRUCTURE TO PROVIDE A VIBRATION FREE INSTALLATION. NOTIFY
ARCHITECT AND STRUCTURAL ENGINEER OF ALL WEIGHTS AND METHODS OF SUPPORT PRIOR TO ANY ROUGH -INS OR
INSTALLATIONS.
13. ALL MATERIALS AND EQUIPMENT SHALL BE NEW, UNLESS NOTED OTHERWISE.
14. FIELD VERIFY THE EXACT LOCATION OF ANY PLUMBING EQUIPMENT THAT REQUIRES ELECTRICAL CONNECTIONS WITH
RESPECTIVE CONTRACTORS.
15. REPAIR FIREPROOFING AFTER INSTALLATION OF HANGERS AND SUPPORTS TO ORIGINAL CONDITIONS.
16. MAINTAIN CODE AND MANUFACTURER'S RECOMMENDED SERVICE CLEARANCES FOR EQUIPMENT.
17. ALL MATERIALS IN CEILING SPACE SHALL BE PLENUM RATED PER CODE.
18. DIMENSIONS SHOWN ON PUN ARE HORIZONTAL. DIMENSIONS SHOWN IN ELEVATION ARE VERTICAL EXCEPT THAT, IN WAY
OF STRUCTURAL DIMENSIONS ARE MEASURED PERPENDICULAR TO FLANGE.
19. NEITHER ACCURACY NOR COMPLETION OF UTILITY LOCATIONS SHOWN ON DRAWINGS IS GUARANTEED. DETERMINE EXACT
LOCATIONS OF EXISTING UTILITIES IN FIELD, WHETHER OR NOT SHOWN ON DRAWINGS. EXERCISE CAUTION AND IDENTIFY
LOCATIONS OF UNMARKED UTILITY UNES AS NECESSARY TO PERFORM WORK OF THIS SECTION.
20. ALL WORK SHALL BE IN ACCORDANCE WITH ALL APPLICABLE CODES.
21. ANY INTERFERENCE SHALL BE BROUGHT TO THE ATTENTION OF THE CONSTRUCTION MANGER, AND SHALL BE RESOLVED
PRIOR TO THE INSTALLATION OF THE WORK INVOLVED.
22. ALL PIPING PENETRATING CEILINGS AND WALLS SHALL BE INSTALLED WITH CHROME (STAINLESS WHERE NOTED) PLATED
ESCUTCHEONS AT THE PENETRATION. ALL PIPING PENETRATING EXTERIOR WALLS AND ROOFS SHALL BE FLASHED IN AN
APPROVED MANNER AND SHALL BE SEALED WEATHERTIGHT. PIPING PENETRATING RATED PARTITIONS SHALL BE PROTECTED
AS REQUIRED BY LOCAL CODE AUTHORITY.
23. MANUFACTURERS' MODEL NUMBERS ARE SPECIFIED SOLELY TO ESTABLISH STANDARDS OF QUALITY FOR PERFORMANCE
AND MATERIALS.
24. PRODUCT INSTALLATION SHALL ADHERE TO MANUFACTURERS' RECOMMENDATIONS.
25. TOPS OF ALL FLOOR DRAINS SHALL BE SET FLUSH WITH FINISHED FLOOR.
26. ALL PIPING ABOVE CEIUNGS SHALL BE PROPERLY SUPPORTED BY THE BUILDING STRUCTURE AND SHALL NOT REST ON
CEUNGS TILES OR CEILING STRUCTURE.
27. CONTRACTOR SHALL COORDINATE ELECTRICAL CHARACTERISTICS AND REQUIREMENTS OF ALL PLUMBING EQUIPMENT WITH
THE ELECTRICAL DRAWINGS, AND SHALL FURNISH EQUIPMENT WIRED FOR THE VOLTAGES 1 PHASE SHOWN HEREIN.
28. ALL PLUMBING EQUIPMENT, PIPING INSULATION, ETC., INSTALLED IN HVAC PLENUM SPACES SHALL MEET CODE
REQUIREMENTS FOR SMOKE AND COMBUSTBIITY.
29. PROVIDE SHUTOFF VALVES ON ALL BRANCH PIPING AND ON ALL SUPPLIES TO INDIVIDUAL FIXTURES AND EQUIPMENT.
PROVIDE BALL VALVES ON ALL WATER MAIN BRANCHES IN CORRIDORS AND WHERE INDICATED ON DRAWINGS. ALL VALVES
SHALL BE ACCESSIBLE, PROVIDE VALVES AT RACK FOR RO/DI ONLY. VALVES FOR RO/DI BRANCH PIPING SHALL BE
LOCATED NOT MORE THAN 6 PIPE DIAMETERS FROM MAN TO CENTERUNE OF VALVE.
30. ALL SLEEVES THROUGH CONCRETE FLOORS AND ALL CORE DRILLING OF CONCRETE FLOORS AND WALLS SHALL BE BY
THIS CONTRACTOR.
31. CONCRETE PADS AND PLATFORMS FOR WORK OF THIS SECTION WILL BE PROVIDED BY GENERAL CONTRACTOR. PROVIDE
INFORMATION AND HARDWARE AS NECESSARY TO GENERAL CONTRACTOR TO COORDINATE WORK.
32. SCHEDULE WORK OF THIS SECTION TO AVOID INTERFERING WITH FIRE -PROOFING WORK.
33. COORDINATE ROOF PENETRATIONS WITH WORK OF ALL JOB TRADES AND WITH FLASHING REQUIREMENTS.
34. PLUMBING CONTRACTOR SHALL FIELD VERIFY SANITARY INVERTS PRIOR TO FABRICATION OR INSTALLATION OF PLUMBING.
CONTACT ENGINEER IMMEDIATELY IF THERE IS A DISCREPANCY.
35. RUN PIPING CONCEALED, UNLESS SPECIFIED OTHERWISE, AND CLEAR OF CEILING INSERTS.
36. STRUCTURAL WELDING SHALL BE 1/4 INCH FILLET UNLESS REQUIRED OTHERWISE.
37. PROVIDE CLAMPS, OFFSETS, EXPANSION JOINTS, ANCHORS AND GUIDES AS NECESSARY TO PREVENT STRESS ON PIPING.
38. PROVIDE BALANCING VALVES AT SYSTEM LOOP RETURNS AND AT RETURN RISERS, PROVIDE SHUT-OFF VALVES AT SYSTEM
LOOP SUPPUES AND SUPPLY RISERS.
39. PROVIDE VENTS AT HIGH POINTS IN PIPING SYSTEMS AND DRAIN VALVES AT LOW POINTS.
40. PITCH PRESSURE PIPING IN DIRECTION OF FLOW.
41. VERIFY EXACT SIZES, LOCATIONS, INVERTS AND ELEVATIONS PRIOR TO RUNNING ANY PIPING. REFER TO ARCHITECTURAL
DRAWINGS FOR EXACT LOCATIONS OF ALL FIXTURES AND EQUIPMENT. REFER TO KITCHEN LAYOUT DRAWING FOR EXACT
LOCATION AND ROUGH -IN REQUIREMENTS OF ALL KITCHEN FIXTURES AND EQUIPMENT.
42. PIPE SUPPORTS FOR PLUMBING & FIRE SERVICE IN BUILDING SHAFTS ARE BY THIS CONTRACTOR. CAREFULLY COORDINATE
WITH MISC. IRON CONTRACTOR PLACEMENT OF STEEL GRATE SUPPORT BEAMS. SHAFT SUPPORT SHALL BEAR FROM WALL
AND FROM FLOOR SUPPORT BEAMS.
43. GENERAL FLOOR CONTROL VALVES OF PIPED SERVICES SHALL BE IN THE PIPE SHAFTS UNLESS OTHERWISE INDICATED.
44. ALL WASTE PIPING FROM LAB SINKS & HOODS SHALL BE VALVED IN BASE CABINET OF HOOD. NO CONNECTION TO LAB
WASTE OR LAB VENT PIPING SYSTEM SHALL BE MADE.
45. ALL HORIZONTAL RAIN WATER PIPING IN EXTERIOR STAIRWELLS TO BE HEAT TRACED AND INSULATED AS SPECIFIED.
46. WATER HEATERS SHALL BE INSTALLED WITH DRAIN PANS UNDER HEATERS. ROUTE PAN DRAINS TO NEAREST FLOOR DRAIN
OR SAFE DRAIN.
47. PIPING SHALL NOT RUN OVER ELECTRICAL PANELS AND SHALL BE COORDINATED WITH WORK OF OTHER TRADES.
DEMOLITION ANNOTATION LEGEND
"X"
DENOTES EXISTING FIXTURE/EQUIPMENT/PIPING TO BE REMOVED IN ITS ENTIRETY INCLUDING
BRANCH DOMESTIC WATER, SANITARY AND VENT PIPING BACK TO SOURCE OR NEXT ACTIVE
DEVICE OR PIPING BEING MAINTAINED.
"XR"
DENOTES EXISTING FIXTURE/EQUIPMENT/PIPING TO BE RELOCATED IN ITS ENTIRETY.
RELOCATION TO NEW LOCATION ('XN") IS INDICATED ON NEW WORK* DRAWINGS.
"XN"
DENOTES NEW LOCATION OF EXISTING RELOCATED ("XR") FIXTURE/EQUIPMENT/PIPING.
REWORK OR PROVIDE NEW DOMESTIC WATER, SANITARY, VENT PIPING, ETC. TO NEW LOCATION
AS REQUIRED/INDICATED.
"XM"
DENOTES EXISTING FIXTURE/EQUIPMENT/PIPING TO BE MALNTANED.
/
//
/
//
/
4/
� `11 ' / 011
I
I � /
I /
I /
<Z.
"� w� //
Y
ti
� 1/
�I
/ I
I
I
CO TP� 'TAN\ I z" '�'
t
SANITARY STACK DIAGRAM
SCALE: NONE
I/N
• Integrated
/'� Engineering
ConsW tants, Inc.
9700 ROCKSIDE RD. SUITE #290
CLEVELAND, OH 44125
(P): 216.901.6711
(F): 216.901.6712
www.ieoin0.00
PE11800575
0'
q STATE OF
HELLYER
LEWISC
ARCHITECTURE
INTERIOR DESIGN
Project:
10
Liberty
Mutual.
INSURANCE
450 East 96th St
3rd Floor
Indianapolis IN 46240
Project No: 047.S6
Drawn by:
jM
Checked by:
HjHH
Approved by:
HjHH
Client Approval:
oa.r
Issue For Bid:
11 /02/I8
Issue For Permit: 11 /OS / 1 8
No.
Date
Revision
Scale:
Drawing:
Plumbing
Schedules,
Legends and
Notes
No. P-0.03