HomeMy WebLinkAbout10.04.18 - Hotel Bid Package 1 Awards (ratification)Carmel Redevelopment Commission
Meeting Agenda Item
PRESENTER
Henry Mestetsky
ACTION REQUESTED
Approval
ITEM/SUBJECT
Ratification of Hotel Carmichael Bid Package 1 Awards
BUDGET APPROPRIATION
MEETING DATE
October 4, 2018
SUMMARY:
Bids for Bid Package 1 were opened at a public CRC meeting on September 26th . After review
by Shiel Sexton, the following prime contracts were awarded by City Center Boutique Hotel,
LLC:
Contract Contractor Amount
Building Concrete RL Turner Corporation $1,221,000
HollowCore Precast StresCore, Inc. $ 928,064
Structural Steel Indiana Steel Fabricating, Inc. $3,057,000
Sitework/Utilities Millennium Contractors, LLC $ 542,855
Total $5,748,919
These bids came in under Shiel Sexton’s estimate total of $6,455,000 by $706,081.
MOTION:
Ratify the awards of Bid Package 1 prime contracts, to the contractors noted above, for a total of
$5,748,919.