HomeMy WebLinkAboutGSB change orders (approved 8-15-18)Company Product Project Dollar Amount Funding
GSB Architects Preparation of early bid packages for
foundation, steel, and superstructure
Hotel Carmichael 15,900.00$ 902 Fund
GSB Architects Exterior lighting design Hotel Carmichael 3,500.00$ 902 Fund
GSB Architects Acoustic and theater design sub-contract for
Feinstein Club
Hotel Carmichael
74,500.00$
902 Fund
GSB Architects Revisions to interior design of the hotel's public
spaces
Hotel Carmichael 32,176.00$ 902 Fund
GSB Architects Exterior envelope modifications Hotel Carmichael 18,056.00$ 902 Fund
GSB Architects Request for alternate bid for granite and
limestone on exterior base
Hotel Carmichael 14,944.00$ 902 Fund
Total 159,076.00$ 902 Fund
Carmel Redevelopment Commission
Approval of Change Orders
8/15/2018