Loading...
HomeMy WebLinkAboutCOVERPROJECT SCOPE OF WORK: THE EXISTING MAM ELECTRICAL SERVICE ENTRANCE SWITCHGEAR LINEUP IS A SINGLE CABINET THAT ACCEPTS, TRANSFERS, AND DISTRIBUTES THE TWO UTILITY FEEDS AND THE GENERATOR FEED. THIS EXISTING SWITCHGEAR WILL BE REPLACED WITH A NEW THREE SECTION SWITCHGEAR, ONE SECTION FOR EACH OF THE TWO UTILITY FEEDS AND THE GENERATOR. THE NEW SWITCHGEAR WILL BE INSTALLED IN SEPARATE ROOMS THAT HAVE BEEN PREVIOUSLY PREPARED FOR ADDITIONAL SPACE TO FACILITATE THE MSTALLATION. THE NEW SWITCHGEAR WILL BE INSTALLED IN PLACE AS COMPLETE AS POSSIBLE WHILE THE EXISTING REMAINS ONLINE AND THEN LOADS WILL BE CUTOVER TO THE NEW SWITCHGEAR. THIS WORK INCLUDES MSTALLATION OF TWO NEW i600A SWITCHGEAR LINEUPS, A 1600A GENERATOR SECTION, A NEW 1600A REMOTE MAIN, THREE 600A ATS UNITS, AND ONE 400A ATS. ADDITIONALLY, A PORTABLE GENERATOR AND LOAD BANK DOCKING STATION WILL BE INSTALLED AS A PART OF THIS PROJECT. CODE REVIEW NOTES: BUILDING AREA: FlRST FLOOR: 54779 SE; SECOND FLOOR: 43544 S.F. INTERIOR WORKING AREA (ON FlRST FLOOR): 4,000 SF. OCCUPANCY CLASSIFlCATION: BUSME55 GROUP B CONSTRUCTION TYPE II—B SEISMIC HAZARD EXPOSURE GROUP: GROUP I SEISMIC PERFORMANCE CATEGORY: CATEGORY B ALL WORK SHALL COMPLY WITH LOCALLY ADOPTED CODES AND AMENDMENTS: BUILDING CODE: 2014 INDIANA BUILDING CODE QBC 13) PWMBING CODE: 2012 INDIANA PWMBING COOE (iPC i6) ELECTRIC CODE 2009 INDIANA ELECTRIC CODE QEC 17) MECHANICAL CODE 2014 INDIANA MECHANICAL CODE (IMC 18) ENERGY CODE 2010 INDIANA ENERGY CONSERVATION CODE (IECC 19) FlRE CODE 2014 INDIANA FlRE CODE (IFC 22) ALL WALL PENETRATIONS SHALL BE PATCHE� TO EXISTING WALL CONDIPONS. FIRE WALLS SHALL BE RRE SEALED WITH AN APPROVED RRE SEALING METHOD. FOR THIS PROJECT THE FOLLOWING TERMS WILL HAVE THE �EFINITIONS LISTE�: REGULATIONS LAWS, ORDINANCES, STATUES, AND LAWFUL ORDERS ISSUED BY AUTHORITIES HAVE JURISOICTION, AND RULES, CONVENTIONS AND AGREEMENTS WITHIN THE CONSTRUCTION INDUSTRY THAT CONTROL PEftFORMANCE OF THE WOftK FURNISH: SUPPLY AND DELNER TO THE PROJECT SITE, READY FOR UNLOADING, UNPACKING, ASSEMBLY, INSTALLATION AND SIMILAR OPERATIONS INSTALL OPERATIONS AT THE PROJECT SITE INCWDWG UNLOADWG, TEMPORARILY STORING, UNPACKING, ASSEMBLING, ERECTING, PLACING, ANCHORING, APPLYING, WORKING TO OIMENSION, FlMSHING, CURING, PROTECTING, CLEANING AN� SIMILAR OPERATIONS. PROVIDE: FURNISH AND INSTALL, COMPLETE AND READY FOR INTENDED USE. PROJECT SITE: SPACE AVAILABLE FOR PERFORMWG CONSTRUCTION ACTIVITIES. AS RE�UIRED: AS RE�UIRED BY REGULATORY BODIES, BY REFERENCED STANDARDS, BY EXISTWG CON�ITIONS, BY GENERALLY ACCEPTED CONSTRUCTION PRACTICE Oft BY THE CONTRACT DOCUMENTS. IN THE EVENT OF AMBIGUITY OR CONFLICTS, THE MOST STRINGENT RE�UIREMENTS SHALL APPLY. RELEA5E0 FOR CONSTRIICTI�N Su6jec��o compliance with allregula�ions of S�a�e antl Local Codes City of Carmel r �un��\i l�rcval�/��. DATE: Qrj�08�20 2 � m G � V 701 Switchgear Replacement PERMIT SET: 4/16/20 � �\11 . � �_ CARM E L, I N D IANA �01 C TY CE� TER DR� CARME�9 N 460�2 .�� .nSdf1C? . ,�]nn�l$�k�''_, �C P� ��A 0 0 d.�'P/ 0 O J c :� �N�so flner�v CCn G> DESIGNERS/ENGMEERS�. dbb TechSite Your peer-eppravad misslortcn5cal faciliTy experts TechSite www.techsiteplan.com 8188 Business Way . Plain City, Ohio 43064 t 614.873J800. f 614.873J801 PHASE OF CONSTRUCTION: PHASE 1 — PRE—INSTALLATION (APPoL — MID—AUGUST) —INSTALL SWITCHGEAR A —INSTALL SWITCHGEAR B —INSTALL GENERATOR SWITCHGEAR —INSTALL PORTABLE GENERATOR DOCKING STATION, COMPLETE —INSTALL GENERATOR FEEDS TO SWITCHGEAR, COMPLETE —INSTALL SWITCHGEAR TIE FEEDS, COMPLETE —INSTALL NEW ATSs, COMPLETE —INSTALL ATS SOURCE FEEDS, COMPLETE —INSTALL ATS LOAD DISTRIBUTION PANELS, COMPLETE —INSTALL CONDUIT RUNS AS COMPLETE AS POSSIBLE FROM RESPECTIVE SWITCHGEAR —INSTALL NEW UNDERGROUND FEED FROM CARMEL i5T AVE TRANSFORMER TO NEW SWITCHGEAR—A AS COMPLETE AS POSSIBLE —INSTALL TEMPORARY GENERATOR AND CONNECT TO PORTABLE GENERATOR DOCKWG STATION PHASE 2— UTILITY CUTOVER (MID—AUGUST — END OF AUGUST) -0E—ENERGIZE EXISTING UTILJTY SOURCE A FEE� (SPRINGMILL) —COMPLETE UNDERGROUND UTILITY FEED TO SWITCHGEAR A —ENERGIZE AND COMPLETE START—UP OF NEW SWITCHGEAR —SET—UP SWITCHGEAR FOR OPERATION IN WRAPAROUND MODE THROUGH TIE PHASE 3 — LOAD CUTOVERS (SEPTEMBER) —CUTOVER LOADS ONE AT A TIME AFTER HOURS, 10PM-6AM (AS MANY AS POSSIBLE IN A SINGLE EVENING); RE—ENEftGIZE ON NEW SWITCHGEAR AFTER EACH EVENING CUTOVER —UPS—A —UPS—A BYPASS —CMLLER-1 —CMLLER-2 —CMLLER-3 —MCC—A —MCC—B —PHA —PHC —DP-1 —DP-2 —DP-3 —DP-4 —DP—S —LDP-1 —CMDP-3 —UPS—B —UPS—B BYPASS —REFEED MISCELLANEOUS MECHANICALS FOR DUAL BUS -0EMO UPS—D PHASE 4— GENERATOR CUTOVER (LATE SEPTEMBER — EARLY OCTOBER) —REMOVE TEMPORARY GENERATOR —COMPLETE GENERATOR FEEO TO NEW GENERATOR SWITCHGEAR PHASE 5— DEMO MAIN SWITCHGEAR AND MSTALL NEW SERVICE DISCONNECT (OCTOBER—NOVEMBER) —DE—ENERGIZE UTILITY SOURCE B FEED (CARMEL i5T AVE) AND TRANSFORMER —DEMO EXISTING MAM SWITCHGEAR -0EMO MAIN SWITCHGEAR PAD —POUR NEW MAIN SERVICE DISCONNECT PAD —INSTALL NEW MAW SERVICE DISCONNECT BREAKER —REUSE EXISTING UNDERGROUND FEEDS FROM CARMEL 1ST AVE UTILITY TRANSFORMER AND TERMINATE AT NEW SERVICE DISCONNECT SWITCH —COMPLETE FEEDER TO NEW SWITCHGEAR—B MAIN BREAKER —ENERGIZE NEW SWITCHGEAR IN FULL DUAL BUS CONFIGURATION. am �>>>� �Noo� � ww N O � � � 0 0 � �+ m a a a 0 0 0 0 0 � � � ¢ o o v� � � � � � a a > 3 3 3 3 6� U V U U � I Q m I tt � A` v Y E O W M � o a o � q ;, c � �'= ms � :/1"� a0� v i a � T^ s�-� y� > q L C � U d 'N �O V � �-�_ � E 3�g � M N N � ,� N � � Q p <n �* s m � = bb � � � � � V/ V 0 �� � �w �' �N Uo �� L ��a � QOM dE> o � ��N � w�� Eo i �O N a r�� _ ; � a � � TS JOB#: 3395 O r] � U � W �O � � � � ���z F" w U O�y � U -/� � 0