HomeMy WebLinkAboutSWPP Notes & Details - C902 KinderCare CarmelMATERIAL HANDLING AND SPILL PREVENTION PLAN:
IN ORDER TO MINIMIZE THE RELEASE OF POTENTIAL POLLUTANTS DURING CONSTRUCTION, THE
CONTRACTOR SHALL IMPLEMENT THIS MATERIAL HANDLING AND SPILL PREVENTION PLAN. THE
CONTRACTOR SHALL REVIEW THIS PLAN WITH ALL SUBCONTRACTORS AND REQUIRE THAT THEY IMPLEMENT
THE PLAN AS WELL. IF A SPILL SHOULD OCCUR, PLEASE CONTACT THE APPROPRIATE AUTHORITIES BELOW:
EMERGENCY RESPONSE 911
HAMILTON COUNTY SHERIFF 317-773-1872
CARMEL FIRE DEPT.317-571-2660
CARMEL STORMWATER MGMT 317-571-2441
IDEM 317-233-7745
OWNER, EIG14T DEVELOPMENT 248-845-4674
1.CONSTRUCTION EQUIPMENT
A.FUELING, LUBRICATION, AND FLUIDS: ALL OPERATIONS INVOLVING THE ADDITION OF FLUIDS TO
EQUIPMENT SHOULD BE DONE IN ONE LOCATION, SO THAT SPILLS ARE LIMITED TO THAT SPECIFIC
LOCATION, WHICH WILL FACILITATE THAT CLEANUP OF SPILLS. IF OIL IS STORED ONSITE, IT MUST BE
KEPT IN THE DESIGNATED AREA. IF AN ONSITE FUELING TANK IS PLANNED TO BE ON SITE, IT SHALL
BE DOUBLE WALLED AND STORED IN THE DESIGNATED AREA. A SPILL KIT MUST BE AVAILABLE IN THE
DESIGNATED AREA. THIS LOCATION IS AN AREA THAT WILL ALLOW SPILLED FLUIDS TO MIGRATE
INTO SUBSURFACE SOILS. IN THE EVENT OF A SPILL, THE FLUID SHALL IMMEDIATELY BE CLEANED UP
BY REMOVING THE CONTAMINATED SOIL OR STONE WHICH SHALL BE DISPOSED OF IN AN
ACCEPTABLE MANNER. SPILLS ON HARD SURFACES SHALL BE SOAKED UP BY AN ACCEPTABLE
MATERIAL, SUCH AS OIL DRY, AND THE ABSORBENT MATERIAL DISPOSED OF IN A PROPER MANNER.
THE SPILL SHALL ALSO BE REPORTED IMMEDIATELY TO THE CONTRACTOR'S SUPERINTENDENT, AS
WELL AS CARMEL STORMWATER MANAGEMENT 317-571-2441
B.EQUIPMENT REPAIR, ESPECIALLY WHEN FLUIDS MUST BE REMOVED FROM THE EQUIPMENT OR THE
POSSIBILITY OF FLUID SPILLS IS HIGH, SHOULD ALWAYS BE DONE OFFSITE AT A FACILITY THAT IS
MORE SUITABLE THAN A CONSTRUCTION SITE TO HANDLE SPILLS. WHEN EQUIPMENT MUST BE
REPAIRED ONSITE, IT SHOULD BE MOVED TO THE MAINTENANCE AND FUELING AREA IF POSSIBLE.
OTHERWISE, SUITABLE ONSITE CONTAINERS SHOULD BE PLACED UNDER THE EQUIPMENT DURING
REPAIR TO CATCH ANY SPILLED FLUIDS AND THESE FLUIDS SHOULD BE DISPOSED OF IN A PROPER
MANNER. DUMPSTERS MUST BE COVERED WHEN NOT IN USE.
C.ALL REUSABLE FLUID CONTAINERS, SUCH AS GASOLINE CANS, SHALL BE INSPECTED FOR LEAKS EACH
TIME THEY ARE USED. IF LEAKS ARE FOUND, THE FLUID SHALL BE REMOVED FROM THE CONTAINER
IN A PROPER MANNER AND THE CONTAINER DISPOSED OF IN AN ACCEPTABLE MANNER. EMPTY
DISPOSABLES CONTAINERS, SUCH AS GREASE TUBES AND LUBRICATING OIL AND BRAKE FLUID
CONTAINERS, AND THEIR PACKAGING, SHALL BE DISPOSED OF IN A PROPER MANNER AND SHALL NOT
BE LEFT ON THE GROUND OR IN THE OPEN ON THE CONSTRUCTION SITE.
2.CONSTRUCTION MATERIAL AND THEIR PACKAGING
A.EROSION CONTROL MEASURES SHOWN ON THESE PLANS SHALL BE IMPLEMENTED PRIOR TO AND
DURING CONSTRUCTION IN THE PROPER SEQUENCING TO MINIMIZE SOIL EROSION. EROSION
CONTROLS SHALL BE INSPECTED AND MAINTAINED AS DESCRIBED ELSEWHERE IN THESE PLANS.
EXCESSIVE DUSTING OF SOIL ON THE SITE SHALL BE MINIMIZED BY REDUCING CONSTRUCTION
TRAFFIC ACROSS BARE SOIL DURING DRY AND/ OR WINDY WEATHER, AND BY APPLYING WATER OR
OTHER ACCEPTABLE DUST CONTROL MEASURES TO THE SOIL. UPON COMPLETION OF CONSTRUCTION
AND SUITABLE ESTABLISHMENT OF PERMANENT VEGETATION, TEMPORARY EROSION CONTROL
MEASURES SUCH AS SILT FENCE, CHECK DAMS, AND INLET PROTECTION DEVICES SHALL BE REMOVED
IN A MANNER TO MINIMIZE ADDITIONAL HAND DISTURBANCE. ANY AREAS DISTURBED BY THESE
OPERATIONS SHALL BE PROPERLY RE-VEGETATED.
B.LARGE WASTE MATERIALS CREATED BY CUTTING, SAWING, DRILLING, OR OTHER OPERATIONS SHALL
BE PROPERLY DISPOSED OF IN SUITABLE ONSITE WASTE CONTAINERS. THE SITE SHALL BE CHECKED
AT THE END OF THE DAY, AT A MINIMUM, AND ALL WASTE MATERIALS, INCLUDING THOSE BLOWN
ACROSS OR OFF THE SITE BY WIND, SHALL BE PICKED UP AND DISPOSED OF IN SUITABLE
CONTAINERS.WHERE POSSIBLE, OPERATIONS SUCH AS SAWING THAT CREATE SMALL PARTICLES
SHOULD BE PERFORMED IN ON SPOT IN AN AREA PROTECTED FROM WIND, AND WASTE PARTICLES
COLLECTED AND DISPOSED OF FREQUENTLY TO MINIMIZE WIND DISPERSAL. PACKAGING USED TO
TRANSPORT MATERIALS TO THE SITE FOR CONSTRUCTION OF THE FACILITY SHALL BE DISPOSED OF
PROPERLY, WHETHER THE MATERIAL IS TAKEN OUT OF ITS PACKAGE AND INCORPORATED INTO THE
PROJECT IMMEDIATELY OR STORED ONSITE FOR FUTURE USE. PACKAGED MATERIAL STORES ONSITE
SHALL BE INSPECTED REGULARLY AND ANY LOOSE PACKAGING SHALL BE REPAIRED OR DISPOSED OF
PROPERLY.
C.ALL DE-WATERING MUST HAVE PRIOR APPROVAL BY AVON S.W. MGMT. ALL DE-WATERING ACTIVITIES
SHALL BE DONE IN ACCORDANCE TO GOOD EROSION CONTROL PRACTICES. THERE PRACTICES
SHOULD BE INCLUDED THE USE OF DIRT BAGS SUCH AS DANDY DIRT BAGS. THE USE OF THESE TYPES
OF DE-WATERING DEVICES WILL REMOVE LARGE QUANTITIES OF SILT, SEDIMENT, AND DIRT AND
PREVENT THESE MATERIALS FROM ENTERING THE STORM SEWER SYSTEM.
D.IF LIME IS USED TO STABILIZE THE SOIL OF THE SITE, THEN ALL CONSTRUCTION EQUIPMENT USED
SHALL BE CLEANED OF ALL EXCESS MATERIAL WITH WATER IN THE CONSTRUCTION STAGING AREA
AS SHOWN WITHIN THESE PLANS.
E.NUTRIENTS AND FERTILIZERS SHALL ONLY BE USED TO ESTABLISH RAPID VEGETATION. WHEN THESE
PRODUCTS ARE UTILIZED, THE USER SHOULD PAY STRICT ATTENTION TO THE PRODUCTS
RECOMMENDED USAGE.
3.CONCRETE WASTE WATER
A.ALL CONCRETE WASTE WATER SHALL BE DISPOSED OF IN THE DESIGNATED AREA AS SHOWN ON
PLAN. THIS AREA IS EITHER A CONTAINER SPECIFICALLY DESIGNATED FOR CONSTRUCTION DEBRIS
AND CONCRETE WASTE, OR IT IS A 10 MIL THICK POLYETHYLENE LINED BERM. THIS AREA SHALL BE
INSPECTED ON A DAILY BASIS AT A MINIMUM, WHEN THIS AREA BECOMES 1 2 FULL, THE POLLUTANTS
SHALL BE EXCAVATED, PLACED IN AN ACCEPTABLE CONTAINER AND DISPOSED OF IN A PROPER
MANNER.
4. PAINT PRODUCTS
A. ALL EXCESS PAINT AND THEIR RELATED PRODUCTS SHALL BE DISPOSED OF IN THE MANNER BY WHICH
THE MANUFACTURER SUGGEST. UNDER NO CIRCUMSTANCES SHALL PAINT OR THEIR RELATED
PRODUCTS BE CLEANED OR DISPOSED OF IN SOIL, SANITARY SEWERS, STORM SEWERS OR DETENTION
BASINS. ANY VIOLATIONS OF THIS SHALL BE REPORTED TO THE JOB SUPERINTENDENT.
SWPPP INFORMATION
COPY OF
IDEM
NOTICE OF
SUFFICIENCY
COPY
OF
NOI
COPY
OF
DRAINAGE
APPROVAL
LETTER
COPY
OF
CONSTRUCTION
SITE
NOTICE AS
APPLICANABLE
COPY
OF
CONSTRUCTION
SITE
NOTICE AS
APPLICANABLE
DETAILED DESCRIPTION OF THE LOCATION OF
THE SWPPP DOCUMENTATION
(BINDER & SITE MAPS) ON THE SITE
MIN. 4'-0"MIN. 4'-0"MIN. 3'MIN. 3'NOTES:
1.THE SWPPP INFORMATION SIGN MUST BE LOCATED NEAR THE
CONSTRUCTION EXIT OF THE SITE. SUCH THAT IT IS ACCESSIBLE
AND VIEWABLE BY THE GENERAL PUBLIC, BIT NOT OBSTRUCTING
VIEWS AS TO CAUSE A SAFETY HAZARD.
2.ALL POSTED DOCUMENTS MUST BE MAINTAINED IN A CLEARLY
READABLE CONDITION AT ALL TIMES THROUGHOUT
CONSTRUCTION AND UNTIL THE NOTICE-OF-TERMINATION (NOT) IS
FILED FOR THE PERMIT.
3.CONTRACTOR SHALL POST OTHER STORM WATER AND/ OR
EROSION AND SEDIMENT CONTROL RELATED PERMITS ON THE
SIGN AS REQUIRED BY THE GOVERNING AGENCY.
4.SIGN SHALL BE LOCATED OUTSIDE OF PUBLIC RIGHT-OF-WAY AND
EASEMENTS UNLESS APPROVED BY THE GOVERNING AGENCY.
5.CONTRACTOR IS RESPONSIBLE FOR ENSURING STABILITY OF THE
SWPPP INFORMATION SIGN.
COPY
OF
CONSTRUCTION
SITE
NOTICE AS
APPLICANABLE
"SWPPP INFORMATION" MUST
BE DISPLAYED PROMINENTLY
ACROSS THE TOP OF THE SIGN,
AS SHOWN IN THE DETAIL
SIGN TO BE CONSTRUCTED OF A
RIGID MATERIAL, SUCH AS
PLYWOOD OR OUTDOOR SIGN
BOARD. SIGN MUST BE
CONSTRUCTED IN A MANNER TO
PROTECT DOCUMENTS FROM
DAMAGE DUE TO WEATHER
(WIND, SUN, MOISTURE, ETC.)
STRAW BALE ( IF APPROVED BY WPWD
INSPECTORS, ALTERNATIVE MATERIALS
OR PRODUCTS MAY BE USED TO PROVIDE
STRUCTURAL CONTAINMENT.)
ALTERNATIVE MATERIALS OR PRODUCTS
WILL REQUIRE DESIGN MODIFICATIONS.
POLYETHYLENE LINING ( 10 MIL);
THE LINING SHOULD EXTEND
OVER THE STRAW BALES
WOOD OR METAL STAKES TO
SECURE THE STRAW BALES (2 PER
STRAW BALE)
METAL PINS OR STAPLES TO
SECURE THE POLYETHYLENE
LINING TO THE STRAW BALES
STRAW BALE ( IF APPROVED BY WPWD
INSPECTORS, ALTERNATIVE MATERIALS
OR PRODUCTS MAY BE USED TO PROVIDE
STRUCTURAL CONTAINMENT.)
ALTERNATIVE MATERIALS OR PRODUCTS
WILL REQUIRE DESIGN MODIFICATIONS.
POLYETHYLENE LINING ( 10 MIL);
THE LINING SHOULD EXTEND
OVER THE STRAW BALES
WOOD OR METAL STAKES TO
SECURE THE STRAW BALES (2 PER
STRAW BALE)
METAL PINS OR STAPLES TO
SECURE THE POLYETHYLENE
LINING TO THE STRAW BALES
COMPACTED SOIL
MATERIAL
STRAW BALES ENTRENCHED
4" INTO THE SOIL
7'-0"
15'-0"
VARIES
MIN. 2'
MIN. 10'-0"
MIN. 21"
MIN. 5'MIN
.
1
'
MIN. 5'MAX. 24"MIN. 1.5'50'-0"
R25'24'25' @ 2% SLOPE 25' @ 1%
SLOPE
1 2 3 4 5 6
1 2 3 4 5 6
D
C
B
A 236 EAST MAIN STREETENGINEERING THAT WORKSENGINEERING WITH STYLEGAS CITY, IN 46933SCALE(36x24):
TEMPORARY INLET PROTECTION DETAIL OUTSIDE ROW
C902
1
N.T.S.
SWPP NOTES &
DETAILS
C902
SCALE(36x24):
SWPP INFORMATION SIGN DETAIL
C902
2
N.T.S.
SCALE(36x24):
EROSION CONTROL BLANKET INSTALLATION DETAIL
C902
5
N.T.S.
SCALE(36x24):
SILT FENCE INSTALLATION DETAIL
C902
6
N.T.S.
SCALE(36x24):
TEMPORARY CONCRETE WASH-OUT DETAIL
C902
7
N.T.S.
SCALE(36x24):
TEMPORARY CHECK DAM INSTALLATION DETAIL
C902
3
N.T.S.
SCALE(36x24):
TEMPORARY CONSTRUCTION ENTRANCE DETAIL
C902
4
N.T.S.