HomeMy WebLinkAboutA011 Roof Stick Frame Detailrequired for cantilever.
BCI joist blocking
23/32" min. plywood/OSB
into each flange.
Nail with 8d nails
or rimboard closure.
®
F05
See Boise literature for
Nail Boise Rimboard
nail into each flange.
to BCI joist with 8d
Bo ise R
i
mboa
r
d
vertical load capacity.
®
F07
vertical load capacity.
See Boise literature forF07-A
of Boise joist & rimboard for
total vertical load capacity.
Sum vertical load capacities
F07-C
(stacked over wall below)
Load bearing wall above
See Boise literature for
vertical load capacity.
BCI Joist Blocking®
F06
above to bearing below.
Solid block all posts from
F08
required for cantilever.
BCI / AJS joist blocking
LVL Rim
8d nails @ 6" o.c.
®
Inverted hanger
F05-A
against top flange with 1/8"
Boise Rim Board
Web Stiffener for 14" & 16" joists.
5 - 3" (10d) nails
gap between bottom flange
1/8"
Stiffeners are required on both sides
- Hangers with side nailing.
- Any hanger with sides not
containing the top flange
with 3 - 3" (10d)
- Web stiffener nailed
of the joist.
11 7/8" joists, and
nails for 9 1/2" and
of the web when :
Point Load from above > 1500 lbs. (Factored)
Install web stiffeners tight
For Point Load from above:
F16-E
2x block
(stacked over wall below)
1/16"
Load bearing wall aboveF09
10-10d nails.
Nail with
Filler block.
Install tight to top flange.
mount hanger load exceeds 250 lbs.
Backer block required where top
Backer block (12" wide min.)
Nail with 10- 10d nails.
Install tight to top flange.
Joist hanger
F10
(see literature)
Filler Block
Contact Boise EWP Engineering for specific conditions.
Connection valid for all applications.
Nailing 12" OC
Web-Filler
Connection
Double BCI Joist®F58
VERIFYBEAMWILL BE
PROPERTYBRACEDTO AVOID
MOMENT ISSUES. PLEASE VERIFY
VERIFYBEAMWILL BE
PROPERTYBRACEDTO AVOID
MOMENT ISSUES. PLEASE VERIFY
BM-46BM-47Products
PlotID Net QtyProduct LengthPlies
BM-46 2 1-3/4" x 9-1/4" VERSA-LAM® 2.0 3100 SP 36' 0" 2
BM-47 2 1-3/4" x 9-1/4" VERSA-LAM® 2.0 3100 SP 28' 0" 2
By:
Date:
Scale:1/4"=1'
BC FRAMER
RIMBOARDIS NOT TO BE CUT. IF A PIECE OF
RIMBOARDENDS BETWEEN TWO JOISTS, BUTT
THE NEXT PIECE UP TO IT.
Boise I-Joist can be offset up to 3" to avoid vertical plumbing.
Joist
3" max
C L Joist
3" max
C L
OJ-AFASTENALL2-PLY LVL'S UP TO 11-7/8" WITH 2 ROWS OF 16DSINKER NAILS @12" OC STAGGERED
FASTEN ALL 2-PLYLVL'S 14"-18" 3 ROWS OF 16DSINKER NAILS @12" OC STAGGERED
FASTEN ALL 2-PLY LVL'S 20"-24" WITH 2 ROWS OF 16DSINKER NAILS @12" OC STAGGERED
FASTEN ALL 3-PLY LVL'S UP TO 11-7/8" WITH 2 ROWS OF 16DSINKER NAILS @12" OC STAGGERED, FROM BOTH SIDES
FASTEN ALL 3-PLYLVL'S 14"-18" 3 ROWS OF 16DSINKER NAILS @12" OC STAGGERED, FROM BOTH SIDES
FASTEN ALL 3-PLY LVL'S 20"-24" WITH 2 ROWS OF 16DSINKER NAILS @12" OC STAGGERED, FROM BOTH SIDES
FASTEN ALL 4-PLY LVL'S UP TO 18" WITH 2 ROWS OF 1/2" STAGGEREDTHROUGH BOLTS @12" OC STAGGERED
FASTEN ALL 4-PLYLVL'S 20"-24" WITH 3 ROWS OF 1/2" STAGGEREDTHROUGH BOLTS @12" OC STAGGERED
ALL 1/2" BOLTS , CAN BE REPLACEDWITH SDW22634 SCREWS
UNLESS OTHERWISE NOTEDON THE LAYOUT FOR ALL CONNECTION DETAILS
Revision Date:
Revision Date:ROOFCarter Lumber, Noblesville INSnellenbergerCarter NoblesvilleASSUMES RAFTERS WILL BE COLLAR TIEDANDRIDGE WILL NOT POST DOWN
FEATHEREDLINES INDICATE CEILING JOIST BEARING DIRECTION
DOUBLE ARROWS INDICATE CEILING JOIST DIRECTIONS
PINK DIAMONDINDICATE ROOF POST DOWNS
REDBOXES INDICATE RAFTER BEARING
NO OTHER ROOF WEIGHT MAY BEAR ON EWP PRODUCTS
GRAYAREAS INDICATE OVERFRAMING
07/21/20