HomeMy WebLinkAboutKindsfather Scope9/21/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=153297&it=False&pi=828467&print=true 1/7
_____________________________________________________
8847 Commerce Park Place Suite J Basement Estimate
Indianapolis, IN 46268 July 15, 2020
Prepared For:
Phone # 317-714-6536 Brian Kindsfather
6534 Iroquois Ln
www.cmhbuilders.com Carmel, IN 46033
_____________________________________________________
9/21/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=153297&it=False&pi=828467&print=true 2/7
Estimate
1000 Building Permits $626.00
Estimated permit cost. The final cost to be determined by municipalities.$626.00
1050 Demolition $480.00
Demolition $480.00
Labor to remove and haul away as follows:
--Includes removing walls.
--Includes removing carpet.
--Includes removing 1 door.
--Includes disposal fees.
1100 Framing $2,937.31
Framing labor and material.$2,937.31
Labor and material to complete framing in the basement.
--Includes all new walls and bulkheads.
--Includes framing for media area niche.
--Includes framing where existing plumbing will be moved.
--Includes all fasteners, tax, and delivery.
1200 Rough In Plumbing $1,395.31
(A) Plumbing rough in.$1,395.31
Labor and material to rough in plumbing as follows:
--All water lines and drains wet bar
--Includes ice maker line
--Additional charges may apply if the existing under slab plumbing needs to be removed, replaced, or
repaired.
1250 Finish Plumbing $935.56
(A) Plumbing finish $634.35
Labor and material to finish plumbing for bathroom.
--Includes all drains, sink strainer and supply lines.
-Includes labor to install wet bar faucet
--See Budget items below for faucet.
Bathroom fixtures $301.21
Bathroom fixture budget.
--Includes wet bar faucet.
1400 Electrical rough in $3,610.70
9/21/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=153297&it=False&pi=828467&print=true 3/7
Electrical Rough-in $3,610.70
Labor and material to complete electrical rough-in.
--Estimating 5 new can lights, 2 pendant lights,
--18 existing cans to remain in place
--Includes 1 outlet on both sides on media area bar.
--Outlets and switches per code.
--Include 1 smoke detector.
--Includes electrical sub-panel.
1450 Electrical Finish $1,922.61
(A) Electrical Finish $1,635.11
Labor and material to complete electrical finish as follows:
--Install all LED Can light trim kits.
--Install all switches, outlets, and cover plates.
--All switches, outlets, and cover plates to match existing as close as possible.
--Add Additional $28.00 per dimmer switch.
Accent Lighting Budget $287.50
Light fixture budget
--Based on 2 Pendant lights.
To be selected with CMH Builders designer during selections appointment.
1500 Insulation $344.50
Insulation labor and material.$344.50
Labor and material to install R-13 insulation in exterior walls.
--Based on sq. ft. of coverage
--Includes walls between finished and unfinished areas.
1600 Drywall $3,882.76
Drywall $3,882.76
Labor and material to hang and finish drywall
--Includes smooth walls and textured ceilings.
--Ceiling texture to match the main level as close as possible, if present.
--Walls and ceilings inside utility and unfinished storage area to be free of drywall.
--Includes drywall, mud, corner bead, tape, tax, and delivery
--Includes repairs to existing drywall on stairs that are damaged during CMH Builders construction.
--An additional charge of $50.00 per hour per man plus material charge will apply for additional work
needed to repair existing drywall damage.
-- Includes drywall for niche
1700 Interior Trim $13,581.67
(A) Interior trim $2,293.44
9/21/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=153297&it=False&pi=828467&print=true 4/7
Labor and material to complete interior trim as follows:
--Install 1 hollow core hinged doors, 1 hollow core bi-pass door.
--Install baseboards, casing, and door hardware.
--All doors, trim, and hardware to match existing close as possible.
(C) Shiplap, painted Fireplace wall $881.87
Labor and material to install shiplap on the seating bar wall.
--Based on 6" painted MDF boards spaced 1/4" apart to give a shiplap appearance.
--Includes prep and paint.
--Does not include interior walls.
(C) Shiplap, painted seating bar $881.87
Labor and material to install shiplap on the seating bar wall.
--Based on 6" painted MDF boards spaced 1/4" apart to give a shiplap appearance.
--Includes prep and paint.
--Based on 3 walls of seating bar.
--Does not include interior walls.
Barn Door $897.74
Labor and material to install barn doors
--Includes K-style barn door
--Includes hardware
--Ledger board to be painted to match walls
--Includes credit for hollow core hinged door.
Bookcase door to Storage $2,100.00
Labor and material to install bookcase door to storage room per approved design.
--Based on painted custom-built bookcase with plywood box construction and adjustable shelves.
Bookcase door to Unfinished Utility Area $2,100.00
Labor and material to install bookcase door to unfinished utility room per approved design.
--Based on painted custom-built bookcase with plywood box construction and adjustable shelves.
Crown Molding $545.74
Labor and material to install crown molding in media area.
--Includes labor and material to prep and paint crown molding.
Live edge industrial shelves.$1,668.67
Labor and material to install 2 sets of industrial live edge shelving per approved design.
--Based on 1/2" black iron support brackets and 3 stained live edge shelves per set.
--Stain color to be selected by homeowner using CMH Builders Designer.
Media Area Platform $797.31
Labor and material to install platform in media area per approved design.
--Includes wood construction with 1 step.
9/21/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=153297&it=False&pi=828467&print=true 5/7
--To be cover with carpet.
Railing System with Metal Balusters $1,415.03
Labor and material to install up to 5 ln. ft. of stair railing to match existing as close as possible.
--Based on a stained wood handrail, black metal balusters, stained wood knee wall cap.
--Includes all prep and stain.
--If column is not needed newel post will be used.
--Based on running from wall to column at bottom of stairs.
1800 Painting $4,925.59
Labor and material to prep and paint $4,925.59
Labor and material to complete the custom color paint on finished walls.
--Based on 1 color 2 coats with Sherwin Williams Washable Flat paint.
--Walk-in closets to be painted to match walls.
--Standard depth closets to be painted flat white.
--Includes sanding and priming
--Includes painting all ceilings based on Sherwin Williams flat white.
--Includes painting all trim and doors based based on Sherwin Williams semi gloss white paint.
--Color to be selected by homeowners using CMH Builders designer.
--Additional charges will apply if a darker color is selected and requires more then 2 coats.
1900 Flooring $5,653.78
Carpet flooring $1,633.63
Labor and material to install carpet per approved design.
--Based on Level 2 carpet.
--Includes new 8 lb. pad.
--Includes tack strips, metal transition, tax, and delivery.
LVT Flooring $4,020.15
Labor and material to install direct apply LVT flooring in all areas excluding media, bathroom, and
unfinished areas.
--Based on Level 2 LVT flooring.
--Includes metal transition trim, adhesive, tax, and delivery.
--Multiple other options available at CMH Builders Showroom
***Slab conditions to dictate the final cost of flooring labor. Certain slab conditions may increase the
cost of flooring labor (i.e. levelness, cracking, and control joints). CMH Builders flooring installer to
examine slab prior to installation to determine the final cost of flooring install.
2000 Ceramic/Porcelain Tile $2,129.36
Wet Bar Backsplash Labor $1,536.00
Labor to install tile on wet bar backsplash
--Labor cost is based on 3" x 6" Subway tiles installed in a brick pattern
9/21/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=153297&it=False&pi=828467&print=true 6/7
Wet Bar backsplash material $593.36
Backsplash tile budget
--Based on 3" x 6" white glazed subway tile.
--Includes thin-set, grout, metal trim. tax, and delivery.
--Final cost may change if tile pattern, level, and/or square footage changes
2100 Cabinets $4,186.00
(A) Wet Bar $4,186.00
Labor and material to install wet bar cabinets.
--Based on Shaker platinum cabinets.
--Includes soft close dovetail drawers, soft close doors, plywood box construction.
--Includes Level 1 hardware
2200 Countertops $11,157.72
Custom bar top with Chicago rail $7,800.00
Labor and material to install custom bar top per approved design.
--Based on custom-built knotty alder bar top.
--Includes labor and material to stain
--Includes Chicago rail.
Wet Bar Countertop, Granite $3,357.72
Labor and material to install countertop on the wet bar.
--Based on 40 sq. ft. of level A granite countertop.
--Includes CMH Builders standard stainless steel undermount bar sink.
--Final cost is subject to change based on selection and size.
4000 Cleaning $140.00
Cleaning $140.00
Labor to complete final construction cleaning.
--Based on wet mop hard surface flooring, vacuuming of carpet, wipe down all cabinets and
countertops.
6000 Discount ($1,000.00)
CMH Builders Promotion ($1,000.00)
Discount if the estimate is accepted and a October start date is selected by 6/30/20.
--Discount is based on estimate total and is subject to change as estimate total changes.
Base Price $56,908.87
9/21/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=153297&it=False&pi=828467&print=true 7/7
****Additional Information****
1. All pricing is based on CMH Builders completing the entire scope of work using CMH Builders Supplier Materials. Unit
pricing may change if portions of the project removed from CMH Builders' scope.
2. CMH Builders offers a 2 year workmanship warranty on all basements, including a 1 time drywall touch up from settling
within the first year.
3. Due to potential changes of material costs from suppliers CMH Builders estimates are valid for 30 days.
4. All work completed by CMH Builders will be up to local building codes. This estimate does not include repairs or code
updates required by the municipal inspector in other areas of the home. Any upgrades required by the inspector, outside of
CMH Builders' scope of work, will require additional compensation.
5. Not all items displayed in CMH Builders proved design is included in the estimate above.
6. Estimate includes up to 2 visits at 2 hours each visit to make selections with CMH Builders Designer. Additional Charges
of $85.00 per hour will apply for any time spent past the amount listed.
Brian Kindsfather, "Homeowner" has been presented with an estimate for basement finish and wishes to contract with CMH
Builders Inc. "Contractor" to complete a basement finish project at 6534 Iroquois LnCarmel, IN 46033.
Homeowner agrees to estimate total with the understanding that final selections may increase or decrease the final project
cost. Homeowner to complete all project selections prior to signing Contract with Contractor to determine final pre-
construction cost. Contractor to present final contract documents to Homeowner within 5 Business Days of the successful
completion of all project selections.
The homeowner has been presented and agreed to the basement design completed by the Contractor. The basement design
is attached as Exhibit B to this Agreement.
Homeowner Agrees to pay an earnest money deposit of $1,000.00 when signing this agreement. Homeowner to selected
tentative start date with the understanding that the start date may change based on the date of the successful completion of
all project selections.
Signatures
Client: Brian Kindsfather
Jul 15, 2020
Date
Builder: Louis Catellier
Jul 15, 2020
Date