8847 Commerce Park Place Suite J Basement EstimateIndianapolis, IN 46268 August 11, 2020 Prepared For:Phone # 317-714-6536 Andy & Jamie Elkins 10515 Power Dr.www.cmhbuilders.com Carmel, IN 46033
_____________________________________________________
10/9/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=162942&it=False&pi=835661&print=true 2/6
Estimate
1000 Building Permits $626.00
Estimated permit cost. The final cost to be determined by municipalities.$626.00
1100 Framing $3,080.13
Framing labor and material.$3,080.13
Labor and material to complete framing in the basement.
--Includes all new walls and bulkheads.
--Includes all fasteners, tax, and delivery.
--Includes alteration to stairs needed for knee wall.
--Includes framing seating alcove per approved design.
1200 Rough In Plumbing $1,053.57
Sump pumps $1,053.57
Labor and material to install:
--New primary sump pump
--New water powered back up sump pump.
1300 HVAC Rough In $592.17
HVAC Labor and Material.$592.17
Labor and material to complete HVAC rough-in as follows:
--Includes 1 supplie and one return.
--Includes all final registers and grills.
1400 Electrical rough in $3,117.33
Electrical Rough-in $3,117.33
Labor and material to complete electrical rough-in.
--Estimating 10 can lights and sconce light junction
--Includes moving existing lights into storage and utility areas.
--Outlets and switches per code.
--Includes 1 USB/outlet in seating alcove.
--Includes 1 network cables, Replace 1 smoke detector.
--Additional charges may apply if existing smoke detector needs to be connected to whole home
smoke detection.
--Cable and network wiring to run into an unfinished area and to be connected by the service provider.
--Includes electrical sub-panel.
1450 Electrical Finish $1,210.36
(A) Electrical Finish $1,072.86
Labor and material to complete electrical finish as follows:
--Install all LED Can light trim kits.
10/9/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=162942&it=False&pi=835661&print=true 3/6
--Install all switches, outlets, and cover plates.
--All switches, outlets, and cover plates to match existing as close as possible.
--Add Additional $28.00 per dimmer switch.
Accent Lighting Budget $137.50
Light fixture budget
--Based on 1sconce light.
To be selected with CMH Builders designer during selections appointment.
1500 Insulation $883.83
Insulation labor and material.$883.83
Labor and material to install R-13 insulation in exterior walls.
--Based on sq. ft. of coverage
--Includes walls between finished and unfinished areas.
Optional ceiling insulation in new finished area only.
Labor and material to add R-13 insulation to the ceiling of the finished area only
Option #1 - Labor and material to install R-13 ceiling insulation in newly finished areas
only.
+$779.33
Client may decline this selection $0.00
1600 Drywall $3,418.75
Drywall $3,418.75
Labor and material to hang and finish drywall
--Includes smooth walls and textured ceilings.
--Ceiling texture to match the main level as close as possible, if present.
--Walls and ceilings inside utility and unfinished storage area to be free of drywall.
--Includes drywall, mud, corner bead, tape, tax, and delivery
--Includes repairs to existing drywall on stairs that are damaged during CMH Builders construction.
--An additional charge of $50.00 per hour per man plus material charge will apply for additional work
needed to repair existing drywall damage.
1700 Interior Trim $5,624.93
(A) Interior trim $1,362.41
Labor and material to complete interior trim as follows:
--Install 1 hollow core hinged doors,
--Install baseboards, casing, and door hardware.
--Doors to be 6 panel hollow core, baseboards will be 5 1/5 beaded style, casing will be 2 3/4" beaded
style
(C) Alcove trim $1,811.17
Labor and material to install shiplap in seating alcove.
--Based on 6" painted MDF boards spaced 1/4" apart to give a shiplap appearance.
10/9/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=162942&it=False&pi=835661&print=true 4/6
--Includes prep and paint.
--Does not include entry wall.
Decorative Columns $368.93
Labor and material to install flat stock trim on 2 existing drywall columns to create Shaker style
appearance per approved design.
--Includes prep and paint all column to match trim color.
Optional Skirt boards on stairs.
Labor and material to install skirt boards on stairs.
--Includes labor prep and paint.
Option - To be specified by client +$670.30
Client may decline this selection $0.00
Railing System with Metal Balusters $1,630.87
Labor and material to install up to 5 ln. ft. of stair railing to match existing as close as possible.
--Based on a stained wood handrail, 6" stained newel post, black metal balusters, stained wood knee
wall cap.
--Includes all prep and stain.
Stair Hand Rail $451.55
Labor and material to install Handrail on the stair wall.
--Based on CMH Builders custom wall mounted handrail.
--Includes new mounting hardware, prep, and stain.
--Stain color to be selected by the homeowner using CMH Builder's Designer.
1800 Painting $1,716.85
Complete painting package.$1,716.85
Labor and material to complete painting as follows:
--Sand and prime all new drywall.
--Textured ceiling to be painted with flat white primer.
--Custom color paint on finished walls.
--Based on 1 color 2 coats with Sherwin Williams Washable Flat paint.
--Walk-in closets to be painted to match walls.
--Standard depth closets to be painted flat white.
--Color to be selected by homeowners using CMH Builders designer.
--Additional charges will apply if a darker color is selected and requires more then 2 coats.
--Prep and paint all trim and doors.
--Based on Sherwin Williams Semi-Gloss White paint.
1900 Flooring $2,637.65
Carpet, Stairs Only $720.00
Labor and material to install carpet on stairs.
--Based on Level 2 carpet with 8 lb. pad.
--Includes tack strips, metal transition, tax, and delivery.
10/9/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=162942&it=False&pi=835661&print=true 5/6
LVT Flooring $1,917.65
Labor and material to install direct apply LVT flooring in all living areas.
--Based on Level 1 LVT flooring.
--Includes metal transition trim, adhesive, tax, and delivery.
--Multiple other options available at CMH Builders Showroom
--Includes needed floor repair around support post.
***Slab conditions to dictate the final cost of flooring labor. Certain slab conditions may increase the
cost of flooring labor (i.e. levelness, cracking, and control joints). CMH Builders flooring installer to
examine slab prior to installation to determine the final cost of flooring install.
4000 Cleaning $140.00
Cleaning $140.00
Labor to complete final construction cleaning.
--Based on wet mop hard surface flooring, vacuuming of carpet, wipe down all cabinets and
countertops.
6000 Discount ($500.00)
CMH Builders Promotion ($500.00)
Discount if the estimate is accepted and a November 2020 start date is selected.
--Discount is based on estimate total and is subject to change as estimate total changes.
Base Price $23,601.57
10/9/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=162942&it=False&pi=835661&print=true 6/6
****Additional Information****
1. All pricing is based on CMH Builders completing the entire scope of work using CMH Builders Supplier Materials. Unit
pricing may change if portions of the project removed from CMH Builders' scope.
2. CMH Builders offers a 2 year workmanship warranty on all basements, including a 1 time drywall touch up from settling
within the first year.
3. Due to potential changes of material costs from suppliers CMH Builders estimates are valid for 30 days.
4. All work completed by CMH Builders will be up to local building codes. This estimate does not include repairs or code
updates required by the municipal inspector in other areas of the home. Any upgrades required by the inspector, outside of
CMH Builders' scope of work, will require additional compensation.
5. Not all items displayed in CMH Builders proved design is included in the estimate above.
6. Estimate includes up to 2 visits at 2 hours each visit to make selections with CMH Builders Designer. Additional Charges
of $85.00 per hour will apply for any time spent past the amount listed.
Andy & Jamie Elkins, "Homeowner" has been presented with an estimate for basement finish and wishes to contract with
CMH Builders Inc. "Contractor" to complete a basement finish project at 10515 Power Dr.Carmel, IN 46033.
Homeowner agrees to estimate total with the understanding that final selections may increase or decrease the final project
cost. Homeowner to complete all project selections prior to signing Contract with Contractor to determine final pre-
construction cost. Contractor to present final contract documents to Homeowner within 5 Business Days of the successful
completion of all project selections.
The homeowner has been presented and agreed to the basement design completed by the Contractor. The basement design
is attached as Exhibit B to this Agreement.
Homeowner Agrees to pay an earnest money deposit of $1,000.00 when signing this agreement. Homeowner to selected
tentative start date with the understanding that the start date may change based on the date of the successful completion of
all project selections.
Signatures
Client: Andy & Jamie Elkins
Aug 11, 2020
Date
Builder: Brandon Kriese
Aug 11, 2020
Date