HomeMy WebLinkAboutMagner Estimate10/22/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=167028&it=False&pi=864776&print=true 1/6
_____________________________________________________
8847 Commerce Park Place Suite J Basement EstimateIndianapolis, IN 46268 August 31, 2020 Prepared For:Phone # 317-714-6536 Jordan Magner 2977 Da Vinci Drwww.cmhbuilders.com Carmel, IN 46074
_____________________________________________________
10/22/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=167028&it=False&pi=864776&print=true 2/6
Estimate
1000 Building Permits $626.00
Estimated permit cost. The final cost to be determined by municipalities.$626.00
1050 Demolition $384.00
Demolition $384.00
Labor to remove and haul away as follows:
--Removing 1 existing wall.
--Includes disposal fees.
1100 Framing $4,153.44
Framing labor and material.$4,153.44
Labor and material to complete framing in the basement.
--Includes all new walls and bulkheads.
--Includes all fasteners, tax, and delivery.
1300 HVAC Rough In $1,101.39
HVAC Labor and Material.$1,101.39
Labor and material to complete HVAC rough-in as follows:
--Includes 1 supplies and one return.
--Includes moving 1 existing supply.
--Includes moving HVAC in theater room.
--Includes all final registers and grills.
--Includes bathroom exhaust fan/light combo.
1400 Electrical rough in $3,849.50
Electrical Rough-in $3,849.50
Labor and material to complete electrical rough-in.
--Estimating 20 can lights.
--Includes moving existing lights into storage and utility areas.
--Outlets and switches per code.
--Includes 1 network cables, 1 smoke detector.
--Cable and network wiring to run into an unfinished area and to be connected by the service provider.
--Includes electrical sub-panel.
1450 Electrical Finish $1,608.33
(A) Electrical Finish $1,608.33
Labor and material to complete electrical finish as follows:
--Install all LED Can light trim kits.
--Install all switches, outlets, and cover plates.
10/22/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=167028&it=False&pi=864776&print=true 3/6
--All switches, outlets, and cover plates to match existing as close as possible.
--Add Additional $28.00 per dimmer switch.
1500 Insulation $1,166.20
Insulation labor and material.$1,166.20
Labor and material to install R-13 insulation in exterior walls.
--Based on sq. ft. of coverage
--Includes walls between finished and unfinished areas.
Optional ceiling insulation in new finished area only.
Labor and material to add R-13 insulation to the ceiling of the finished area only
Option #1 - Labor and material to install R-13 ceiling insulation in newly finished areas
only.
+$1,123.82
Client may decline this selection $0.00
1600 Drywall $6,064.48
Drywall $6,064.48
Labor and material to hang and finish drywall
--Includes smooth walls and textured ceilings.
--Ceiling texture to match the main level as close as possible, if present.
--Walls and ceilings inside utility and unfinished storage area to be free of drywall.
--Includes drywall, mud, corner bead, tape, tax, and delivery
--Includes repairs to existing drywall on stairs that are damaged during CMH Builders construction.
--An additional charge of $50.00 per hour per man plus material charge will apply for additional work
needed to repair existing drywall damage.
1700 Interior Trim $1,487.05
(A) Interior trim $1,487.05
Labor and material to complete interior trim as follows:
--Install 1 hollow core hinged doors,
--Install baseboards, casing, and door hardware.
--All doors, trim, and hardware to match existing close as possible.
(C) Optional Shiplap, painted
Labor and material to install shiplap on the bar wall.
--Based on 6" painted MDF boards spaced 1/4" apart to give a shiplap appearance.
--Includes prep and paint.
Option #1 - Select this option to add to estimate.+$1,473.23
Client may decline this selection $0.00
1800 Painting $3,419.19
Complete painting package.$3,419.19
Labor and material to complete painting as follows:
10/22/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=167028&it=False&pi=864776&print=true 4/6
--Sand and prime all new drywall.
--Textured ceiling to be painted with flat white primer.
--Custom color paint on finished walls.
--Based on 1 color 2 coats with Sherwin Williams Washable Flat paint.
--Walk-in closets to be painted to match walls.
--Standard depth closets to be painted flat white.
--Color to be selected by homeowners using CMH Builders designer.
--Additional charges will apply if a darker color is selected and requires more then 2 coats.
--Prep and paint all trim and doors.
--Based on Sherwin Williams Semi-Gloss White paint.
1900 Flooring $3,403.40
Carpet flooring $3,403.40
Labor and material to install carpet per approved design.
--Based on Level 2 carpet.
--Includes new 8 lb. pad.
--Includes tack strips, metal transition, tax, and delivery.
2100 Cabinets
(A) Optional Dry Bar
Labor and material to install dry bar cabinets.
--Based on Shaker white cabinets.
--Includes soft close dovetail drawers, soft close doors, plywood box construction.
--Includes Level 1 hardware
--Includes 2 custom stained floating shelves.
Option #2 - Select this option to add to estimate.+$3,118.70
Client may decline this selection $0.00
2200 Countertops
Optional Wet Bar Countertop, Granite
Labor and material to install countertop on the wet bar.
--Based on 11 sq. ft. of level A granite countertop.
--Includes CMH Builders standard stainless steel undermount bar sink.
--Final cost is subject to change based on selection and size.
Option #1 - Select this option to add to estimate.+$857.57
Client may decline this selection $0.00
4000 Cleaning $140.00
Cleaning $140.00
Labor to complete final construction cleaning.
--Based on wet mop hard surface flooring, vacuuming of carpet, wipe down all cabinets and
countertops.
10/22/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=167028&it=False&pi=864776&print=true 5/6
Base Price $27,402.98
10/22/2020 Main Basement Estimate
https://coconstruct.com/app/shared/Proposal.aspx?propid=167028&it=False&pi=864776&print=true 6/6
****Additional Information****
1. All pricing is based on CMH Builders completing the entire scope of work using CMH Builders Supplier Materials. Unit
pricing may change if portions of the project removed from CMH Builders' scope.
2. CMH Builders offers a 2 year workmanship warranty on all basements, including a 1 time drywall touch up from settling
within the first year.
3. Due to potential changes of material costs from suppliers CMH Builders estimates are valid for 30 days.
4. All work completed by CMH Builders will be up to local building codes. This estimate does not include repairs or code
updates required by the municipal inspector in other areas of the home. Any upgrades required by the inspector, outside of
CMH Builders' scope of work, will require additional compensation.
5. Not all items displayed in CMH Builders proved design is included in the estimate above.
6. Estimate includes up to 2 visits at 2 hours each visit to make selections with CMH Builders Designer. Additional Charges
of $85.00 per hour will apply for any time spent past the amount listed.
Jordan Magner, "Homeowner" has been presented with an estimate for basement finish and wishes to contract with CMH
Builders Inc. "Contractor" to complete a basement finish project at 2977 Da Vinci DrCarmel, IN 46074.
Homeowner agrees to estimate total with the understanding that final selections may increase or decrease the final project
cost. Homeowner to complete all project selections prior to signing Contract with Contractor to determine final pre-
construction cost. Contractor to present final contract documents to Homeowner within 5 Business Days of the successful
completion of all project selections.
The homeowner has been presented and agreed to the basement design completed by the Contractor. The basement design
is attached as Exhibit B to this Agreement.
Homeowner Agrees to pay an earnest money deposit of $1,000.00 when signing this agreement. Homeowner to selected
tentative start date with the understanding that the start date may change based on the date of the successful completion of
all project selections.
Signatures
Client: Jordan Magner
Sep 7, 2020
Date
Builder: Louis Catellier
Aug 31, 2020
Date