HomeMy WebLinkAboutTroy Estates - Public ROW & EC Cost Estimate - 10.21.2020Lennar Homes of Indiana, Inc. Project: Troy Estates HWC Project No. 2019-305-S Date: 10/21/2020 ITEM NAME:UNIT QUANTITY UNIT COST AMOUNT POST-CONSTRUCTION BMP DIVERSION MANHOLE EA 1 5,275.00$ 5,275.00$ WATER QUALITY STRUCTURE BMP-1 EA 1 18,400.00$ 18,400.00$ WATER QUALITY STRUCTURE BMP-2 EA 1 65,557.00$ 65,557.00$ 89,232.00$ This Engineer's Estimate is an opinion of probable construction cost made on the basis of Engineer's experience and represent Engineer's judgement as a qualified professional generally familiar with the industry. However, since Engineer has no control over the cost of materials, equipement, labor or market conditions, Engineer cannot guarantee that actual construction cost will not vary from this Engineer's Estimate. Kristopher K. Eichhorn, PE PS 10/21/2020 HWC Engineering PERFORMANCE BOND - ENGINEERS ESTIMATE POST-CONSTRUCTION BMP MEASURES TOTAL: Lennar Homes of Indiana, Inc. Project: Troy Estates HWC Project No. 2019-305-S Date: 10/21/2020 EROSION CONTROL ITEM NAME:UNIT QUANTITY UNIT COST AMOUNT Perimeter Silt Fence LFT 4,270 1.00 $4,270.00 Rear Yard Silt Fence LFT 4,350 1.00 $4,350.00 Front Yard Silt Fence LFT 5,430 1.00 $5,430.00 Paved Area Inlet Protection (Flexstorm)EA 25 150.00 $3,750.00 Yard Area Inlet Protection EA 21 65.00 $1,365.00 Permanent Seed with Blanket (S150)SYS 6,727 1.17 $7,870.59 Permanent Seed with Mulch SYS 44,279 0.45 $19,925.55 Temporary Seed with Mulch (Pads)AC 9 1200.00 $11,280.00 Construction Entry LS 1 8195.00 $8,195.00 Concrete Washout LS 1 588.00 $588.00 Staging Area LS 1 3105.00 $3,105.00 $70,129.14 This Engineer's Estimate is an opinion of probable construction cost made on the basis of Engineer's experience and represent Engineer's judgement as a qualified professional generally familiar with the industry. However, since Engineer has no control over the cost of materials, equipement, labor or market conditions, Engineer cannot guarantee that actual construction cost will not vary from this Engineer's Estimate. Kristopher K. Eichhorn, PE PS 10/21/2020 HWC Engineering PERFORMANCE BOND - ENGINEERS ESTIMATE EROSION CONTROL: TOTAL Lennar Homes of Indiana, Inc. Project: Troy Estates HWC Project No. 2019-305-S Date: 10/21/2020 ITEM NAME:UNIT QUANTITY UNIT COST AMOUNT 141st STREET COLLECTOR STREET IMPROVEMENTS REQUIRED 1.5" MILL FOR OVERLAY SY 0.00 5.00$ -$ 1.5" HMA SURFACE TON 160.00 91.85$ 14,696.00$ 2.5" HMA INERMEDIATE TON 260.00 79.70$ 20,722.00$ 3.5" HMA BASE TON 340.00 71.00$ 24,140.00$ 2.5" HMA INTERMEDIATE TON 265 75.80$ 20,087.00$ 3" HMA BASE TON 325 71.80$ 23,335.00$ 2' STONE SHOULDER LS 1 13,248.00$ 13,248.00$ PAVEMENT STRIPING LS 1 7,500.00$ 7,500.00$ 123,728.00$ ASPHALT PATH IMPROVEMENTS REQUIRED 1.5" HMA SURFACE TON 100 92.02$ 9,202.00$ 2.5" HMA INTERMEDIATE TON 160 80.55$ 12,888.00$ 6" - #53 COMP. AGG.TON 380 25.80$ 9,804.00$ 31,894.00$ 155,622.00$ This Engineer's Estimate is an opinion of probable construction cost made on the basis of Engineer's experience and represent Engineer's judgement as a qualified professional generally familiar with the industry. However, since Engineer has no control over the cost of materials, equipement, labor or market conditions, Engineer cannot guarantee that actual construction cost will not vary from this Engineer's Estimate. Kristopher K. Eichhorn, PE PS 10/21/2020 ROW IMPROVEMENTS REQUIRED TOTAL: PERFORMANCE BOND - ENGINEERS ESTIMATE 141st STREET COLLECTOR STREET IMPROVEMENTS REQUIRED SUBTOTAL: ASPHALT PATH IMPROVEMENTS REQUIRED SUBTOTAL: