HomeMy WebLinkAboutGN010.0 General NotesWaterman Kitchen Remodel Project
GN010.0 General Notes
· Structural – increase opening between Kitchen and Great Room. Remove
~50” of wall. Add 2-2x4’s at each end of expanded wall opening. Install new
2-2x8 support beams approximately 14’ in length. Structural Engineer
Report included.
· Mechanical – run new Wardflex 15A gas line (to match existing gas supply
lines in house) from gas supply manifold in basement to new stub-out and
shut-off valve to provide gas service to new gas range.
· Plumbing – water supply lines and drain of new island to use existing island
water supply lines and drain.
· Electrical – summary below
o Add two additional can lights (same model as existing) to existing 4
can light circuit
o Relocate existing pendant lights to new location above new island
o Relocate two existing 110v GFCI outlets on island
o Relocate existing 110v outlet (servicing the Great Room) from wall
being removed to section of wall remaining
o New combination microwave/wall oven to use existing 220v outlet
(no change)
o Relocate phone and cable TV jacks from wall being removed to
adjacent wall
o Delete 110v outlet on wall being removed.
o Relocate dedicated 110v/20A microwave electric outlet from wall
being removed to supply power to new gas range
11/10/20