Loading...
HomeMy WebLinkAboutCO_16_96th_&_Keystone_Parkway__16-ENG-05 DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE City of Carmel Project 16-ENG-05 96th Street and Keystone Parkway CHANGE ORDER # 16 The purpose of this change order is to address the additional costs to the contract due to Time and Materials work.This change order also addresses Increases/Decreases in existin,item quantities.See the attachments for more information. Contract Price prior to this Change Order 532,t98,690.81 Contract Price will be increased/decreased by this Change Order $36,089.75 New Contract Price including this Change Order $32,234,780.56 Amount Adjusted Contract Cumulative % Change Price from Original Contract Original Contract $28,793,000.00 $28,793,000.00 N/A CO 01 $25,843.67 $28,818,843.67 0.09% CO 02 $3,48130 $28,822,325.47 0.10% CO 03 $0.00 $28,822,325.47 0.10% CO 04 $46,996.32 $28,869,321.79 0.27% C005 ($172,023.87) $28,697,297.92 -0.33% CO 06 $68,110.98 $28,765,408.90 -0.10% CO 07 $164,830.51 $28,930,239.41 0.48% CO 08 $1,300,000.00 $30,230,239.41 4.99% CO 09 $235,881.10 $30,466,120.61 5.81% CO 10 $251,434.21 $30,717,554.72 6.68% CO 11 ($404,170.92) $30,313,383.80 5.28% CO 12 $232,862.12 $30,546,245.92 6.09% CO 13 $216,919.25 $30,763,165.17 6.84% C014 $1,213,176.86 $31,976,342.03 11.06% CO 15 $222,348.78 $32,198,690,81 11.83% CO 16 $36,089.75 $32,234,780.56 11.83% DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE CITY OF CARIvIEL TO: CONTRACT CHANGE ORDER NO.: 16 DATE: 10/14/2020 PROJECT NAME: 16-ENG-05 CITY REQ. NO.: CITY PO NO.: CITY PO DATE: I. You are directed to make the following changes in this Contract: The purpose of this change order is to address the additional costs to the contract due to Time and Materials work.This change order also addresses Increases/Decreases in existing item quantities.See the attachments for more information SCHEDULED ADJUSTMENT ITEM AMOUNT I+)OR(-)DAYS *See the attachment 11. The following referenced Documents further describe the changes outlined in Paragraph 1,and are to be considered a part of this Change Order: R.F.P.: W.Q.C.No.: Other: The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order S 32,198,690.81 Contract Price will be increased/decreased by this Change Order 5 36,089.75 New Contract Price including this Change Order $ 32,234,780.56 Contract Time Prior to this Change Order Days 9/3/2020 Completion Date Net increased/decreased resulting from this Change Ordei 0 Days Current Contract Time including this Change Ord 0 Days 9/3/2020 Completion Date This Change Order is for full and final settlement of all direct. indirect. impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are The Above Changes Are Approved: Recommended Accepted: �DocoSignetl by: American Structurepoint Inc. Rieth-Riley Construction Co,Inc jaw,t,s I'JV'aAlta l ENGINEER CONTRACTOR 9'�5 8 "�°;'� James �ralnard,Mayor 9025 River Road.Suite 200 Indianapolis.IN 46221 Address kin fly t,, id Address `Mt'y°A°nn Burke, Member L (Nil, tt0`i'°Wlit"son, Member Indianapolis,IN 46240 Indianapolis.IN 46221 City/State/Zip City/State/Zip I my shmnn, PE.City Engineer By: ATTEST: gY. ....a- ` p-DocuSignetl by Phone:(i7)401-0263 Phone:(317)518-2500 5ut, (Potf;, '- W 6SJ 9 /9 rvw... f Sue olfgang.Clerk Date: /4' 2d aZp Date: /0 41 204 Date: 12/3/2020 Version 2016-0X-31 AR.-6 DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE American Structure point, Inc, ;,jl• STRUCTUREPOINT p Change Order Details 96th Street and Keystone Parkway Description: 16-ENG-05 Construction of a roundabout interchange at the intersection of 96th Street and Keystone Parkway, including the reconstruction of Keystone Parkway from I-465 to 98th Street, and reconstruction of 96th Street from Haverstick Road to Enterprise Drive. The Project includes new construction of a twospan bridge over 96th Street. Change Order: 16 Date Created: 08/31/2020 Status: Pending Approval Date Approved; Type: Summary: Time and Materials Items/Quantity Changes • Change Order Description: ITEM 417: FORCE ACCOUNT WORK- Bridge Deck Sealing: With completion of the Keystone Bridge falling in the colder months in 2019, the recommended parameters for surface sealing of the concrete decks could not be met. In order to comfortably open the bridge to traffic, it was agreed upon to Lightly seal the concrete bridge decks with a non-epoxy sealer. This would provide some protection from salt prior to application of the epoxy penetrating sealer in the spring of 2020. ITEM 418: FORCE ACCOUNT WORK-Crane Move: Due to delay in the relocation of the IPL lines crossing Keystone Parkway, Rieth-Riley was forced to partially dismantle the crane in order to move it under the existing IPL lines between Pier 2 and Bent 1. Once the crane was moved under the lines, it then had to be re-assembled in order to drive the piling at Bent 1. ITEM 419: FORCE ACCOUNT WORK-GDO-8 vs Storm Pipe Conflict: The 18 IN storm pipe between STR 139 and STR 143 was designed in the same location as the median foundation for overhead sign structure GDO-8. This storm pipe was already installed when James H. Drew began excavation for the sign foundation. Gradex removed the 18 IN pipe, added a manhole structure (STR 139F) at the conflict point, and re-installed the 18 IN pipe in order to divert the pipe around the foundation. ITEM 420: FORCE ACCOUNT WORK- Moment Slab, Ramp SWR: Due to delay in the relocation of an existing IPL pole, Rieth-Riley was forced to • skip around this pole when constructing the concrete moment slab along the west side of Ramp SWR in 2019. This area was later filled with temporary HMA in order to safely allow a traffic switch to keep the project moving. During the 2020 construction season, Rieth-Riley removed the temporary HMA and constructed the concrete moment slab as planned. It was agreed that the Contractor would perform the work for the HMA removal and concrete moment slab construction utilizing Time and Materials. ITEM 421: FORCE ACCOUNT WORK- MSE Wall Cores: MSE walls constructed on the project were designed to have a subsurface drain just above the foundation for the walls. There was no provision for an outlet for these subsurface drains. MSE Wall panels were cored at various locations in order to provide an outlet for the subsurface drain pipe installed behind the MSE Wall panels. This added work was tracked as Time and Materials. Change Order Details: 96th Street and Keystone Page 1 of 9 10/14/2020 Parkway DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE ITEM 422: FORCE ACCOUNT WORK- Re-handle H-Piling: Rieth-Riley was forced to accept delivery of the steel H-piling to avoid further price increases from the supplier. Due to delays in the project, Rieth-Riley was not able to place this material at the Keystone Bridge.The H-piles were delivered and stored at the location of the former Chase Bank. As a result, Rieth-Riley incurred additional cost for handling the H-piling multiple times while moving it to the bridge construction location. ITEM 423: FORCE ACCOUNT WORK-Winter Concrete: Due to delays in construction of the project, Rieth-Riley performed various concrete construction operations during the cold weather months in both 2018/ 2019 and 2019/2020. The concrete supplier(IMI), added a surcharge per cubic yard for winter concrete. Rieth-Riley also had additional costs for rental of insulated blankets as well as additional labor required to cover/uncover concrete pours to prevent freezing. These additional costs were tracked as Time and Materials work. Item 424: FORCE ACCOUNT WORK- Pothole Patching: Rieth-Riley incurred additional costs to maintain the existing pavement on 96th Street prior to the eventual removal and replacement of the pavement as planned. It was agreed that Rieth-Riley would track the additional costs for patching 96th Street pavement as Time and Materials. ITEM 425: FORCE ACCOUNT WORK- Penske Chevrolet Approach, Grade Change: After Reith-Riley had set forms for the construction of the concrete approach at the entrance to Penske Chevrolet, it was determined that the low decks of the car hauler trailers would not clear utilizing the slopes as designed.The Contractor removed formwork, re-graded the subgrade for the approach, and re-set forms for the concrete approach at the newly agreed upon slopes. Additional costs for this re-work were tracked as Time and Materials required to perform the work. ITEM 426: FORCE ACCOUNT WORK- SE Keystone Storm Modifications (AT&T Conflict): There is an existing AT&T Duct bank that runs along the east side of Keystone Parkway. The proposed storm sewer was not designed around this utility as requested by the City of Carmel.Therefore, Gradex had to modify the designed storm structures and locations in order to avoid the duct bank. Item 427: FORCE ACCOUNT WORK- Haverstick Road, Water Line Lowering: While excavating for subgrade treatment at the south end of Haverstick Road, the 4in. fire line and water service line tying into the adjacent office building ended up being too shallow to obtain required coverage. Citizens Energy reviewed the situation and recommended that the lines be lowered to achieve required coverage. It was agreed that Gradex would perform the work on a Time and Materials basis. Item 428: FORCE ACCOUNT WORK- Rohrer Road and Grace Drive Crosswalk: The City of Carmel solicited Rieth-Riley Construction to construct a crosswalk at Rohrer Road and Grace Drive. Payment for that work was to be made under the 96th/Keystone contract. ITEM 429: FORCE ACCOUNT WORK - HMA Wedge and Removal: In order to safely open the road for winter, Rieth-Riley performed wedging throughout the project limits, providing safe transitions from the intermediate HMA layer to the moment slab or curb elevations. This also allowed for proper drainage. Additional costs associated with the HMA wedging (and removal) were tracked on a Time and Materials basis, ITEM 430: FORCE ACCOUNT WORK- Clearing Right of Way, Sarah Care Drive Approach: City of Carmel agreed to add a new drive approach from the south leg of Haverstick Road to the property behind the Sarah Care. This required additional clearing of right of way in order to make way for the new construction.Additional costs for this work were tracked on a Time and • Materials basis. Change Order Details: 96th Street and Keystone Page 2 of 9 10/14/2020 Parkway DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE ITEM 431: FORCE ACCOUNT WORK- Curb Ramp Replace, SE Leg of Gray Road RAB: Rieth-Riley was asked to replace a curb ramp and section of depressed sidewalk on the SE leg of the Gray Road RAB. The damage was apparently the result of utility work in the area. Since the Gray Road project is complete, this work is being paid on the 96th and Keystone project. ITEM 432: FORCE ACCOUNT WORK- South Haverstick HMA and Curb: Rieth-Riley was delayed in completing the HMA Paving and Concrete Curb and Gutter on the south leg of the 96th Street and Haverstick Road RAB. This delay was due to a 4 in. Fire Line and Water Service Line that needed to be lowered due to inadequate cover. The Citizens Energy Group water lines crossed Haverstick Road from west to east and fed the office building at the SE corner of the intersection. Lowering of the roadway on the south leg of the RAB (as planned) • resulted in the inadequate cover situation. Rieth-Riley was not able to complete the work on this south leg at the same time as the rest of the work in the intersection. Rieth-Riley claimed that bringing crews back in to complete this small amount of work would result in additional cost to the project due to inefficiencies. City of Carmel agreed to the Rieth- Riley request to track the remaining work via Time and Materials. Also included in this Change Order are quantity changes (overruns/ underruns) to various contract pay items as of 9/15/2020. Awarded Project Amount: $28,793,000.00 Authorized Project Amount: $32,198,690.80 Change Order Amount: $36,089.75 Revised Project Amount: $32,234,780.55 Increases/Decreases Line Number Item Unit Unit Price Current Change Revised Quantity Amount Quantity Amount Quantity Amount Section: 1 - 801-08400 0100 10 SET $6.600 8,975.00 $59,235.00 -7,940.00 -$52,404.00 1,035.00 $6,831.00 REGULATED ASBESTOS CONTAINING MATERIALS, REMOVE 0110 11 CYS $37,000 400.00 $14,800.00 -400.00 -$14,800.00 0.00 $0.00 REGULATED MATERIALS, DISPOSE,TYPE C 0120 12 CYS $25.000 400.00 $10,000.00 -400.00 -$10,000.00 0.00 $0.00 REGULATED MATERIALS, REMOVE,TYPE C 0130 13 CYS $45.000 400.00 $18,000.00 -400.00 -$18,000.00 0.00 $0,00 REGULATED MATERIALS,TRANSPORT,TYPE C 0140 14 EACH $4,400.000 2.00 $8,800.00 -1.00 -$4,400,00 1.00 $4,400.00 UNDERGROUND STORAGE TANK, REMOVE AND DISPOSE, 6,000-10,000 GALLONS CAPACITY 0250 25 TON $50.000 18.00 $900.00 -18.00 -$900.00 0.00 $0.00 TEMPORARY FILTER STONE Change Order Details: 96th Street and Keystone Page 3 of 9 10/14/2020 Parkway DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE Line Number Item Unit Unit Price Current Change Revised Quantity Amount Quantity Amount Quantity Amount 0270 27 SFT $7.600 1,586.00 $12,053.60 -1,586.00 -$12,053.60 0.00 $0.00 TEMPORARY SHEET PILING 0280 28 SYS $14.750 2,395.00 $35,326.25 298.62 $4,404.65 2,693.62 $39,730.90 SUBGRADE TREATMENT,TYPE II 0320 32 CYS $20.000 11,576.00 $231,520.00 -4,776.62 -$95,532.40 6,799.38 $135,987.60 B BORROW, UNDISTRIBUTED 0350 35 CYS $75.000 1,895.00 $142,125.00 -1,235.49 -$92,661.75 659.51 $49,463.25 STRUCTURE BACKFILL,TYPE 5 0370 37 TON $18.000 7,081.00 $127,458.00 -3,000.00 -$54,000.00 4,081.00 $73,458.00 COMPACTED AGGREGATE NO. 53 BASE 0400 40 TON $35.000 1,216.27 $42,569.45 382.49 $13,387.15 1,598.76 $55,956.60 COMPACTED AGGREGATE NO. 53 TEMPORARY FOR DRIVEWAYS 0420 42 LS $1,252.990 1.00 $1,252.99 -1.00 -$1,252.99 0.00 $0.00 PROFILOGRAPH, HMA 0430 43 TON $77.880 2,240.00 $174,451.20 1,297.19 $101,025.16 3,537.19 $275,476.36 HMA,4, 76, SURFACE,9.5 mm 0450 45 TON $50.630 15,267.00 $772,968,21 -900.00 -$45,567.00 14,367.00 $727,401.21 HMA, 4, 64, BASE,25.0 mrn 0460 46 TON $52.880 13,142.00 $694,948.96 423.38 $22,388.33 13,565.38 $717,337.29 HMA, 5, 76, INTERMEDIATE, OG 19.0 mm 0470 47 TON $52.460 17,900.00 $939,034.00 96.24 $5,048.75 17,996.24 $944,082.75 HMA,4,64, BASE, 19.0 mm 0670 67 LFT $66.000 390.00 $25,740.00 -140.00 -$9,240.00 250.00 $16,500.00 GUARDRAIL,TIMBER,TREATED 0680 68 EACH $2,236.000 4.00 $8,944.00 -3.00 -$6,708,00 1.00 $2,236.00 GUARDRAIL,TIMBER,TREATED,APPROACH 0740 74 LFT $16,000 425.00 $6,800.00 -425.00 -$6,800.00 0.00 $0.00 FENCE, CHAIN LINK, 48 IN. 0760 76 SYS $38.880 1,159.00 $45,061.92 1,398.08 $54,357.35 2,557.08 $99,419.27 SIDEWALK, CONCRETE 0780 78 SYS $151.720 1,733.00 $262,930.76 43.17 $6.549.75 1,776.17 $269,480.51 CURB RAMP, CONCRETE(ALL TYPES) 0820 82 LFT $18.210 1,300.00 $23,673.00 464.82 $8,464.37 1,764.82 $32.137.37 CURB,CONCRETE, MODIFIED 0850 85 LFT $139.090 89.00 $12,379.01 7.41 $1,030.66 96.41 $13,409.67 • CURB AND GUTTER,TURNOUT COMBINED 0860 86 LFT $50.530 165.00 $8,337.45 46.60 $2,354.70 211.60 $10,692,15 CURB AND GUTTER, COMBINED,TYPE II Change Order Details: 96th Street and Keystone Page 4 of 9 10/14/2020 Parkway DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE Line Number Rem Unit Unit Price Current Change Revised Quantity Amount Quantity Amount Quantity Amount 0870 87 LFT $25.210 1,587.00 $40,008.27 10.62 $267,73 1,597.62 $40,276.00 CURB AND GUTTER, ROLL CURB 0900 90 TON $109.260 710.00 $77,574.60 -300.00 -S32,778.00 410.00 $44,796.60 HMA FOR APPROACHES,TYPE B 0910 91 SYS $59.070 187.00 $11,046.09 41.63 $2,459.08 228.63 $13,505.17 PCCP FOR APPROACHES, 6 IN. 0920 92 SYS $69.070 1,730.00 $119,491.10 299.56 $20,690.61 2,029.56 $140,181.71 PCCP FOR APPROACHES, 9 IN. 0950 95 EACH $578.000 76.00 $43,928.00 -76.00 -$43,928.00 0.00 $0.00 MONUMENT, B 0960 96 EACH $506,000 3,00 $1,518.00 -3.00 -$1,518.00 0.00 $0.00 MONUMENT,C 0970 97 EACH $117.000 4.00 $468.00 -4.00 -$468.00 0.00 $0.00 MONUMENT,D 1120 112 MOS $2,314.810 34.00 $78,703.54 2.50 $5,787.03 36.50 $84,490.57 FIELD OFFICE,B 1270 127 LFT $64.860 6,597.00 $427,881.42 12.80 $830.21 6,609.80 $428,711.63 RAILING,CONCRETE FT, MODIFIED 1360 136 LFT $96.000 150.00 $14,400.00 -150.00 -$14,400.00 0.00 $0.00 TEMPORARY PIPE 1430 143 LFT $33.000 107.00 $3,531.00 1.00 $33.00 108.00 $3,564.00 PIPE,TYPE 1, CIRCULAR., 12 IN. 1530 153 LFT $82.000 691.00 $56,662.00 7.00 $574.00 698.00 $57,2.36.00 PIPE, SLOTTED DRAIN, 12 IN. 1560 156 TON $58.270 350.00 $20,394.50 -350.00 -$20,394.50 0.00 $0.00 HMA FOR STRUCTURE INSTALLATION,TYPE D 1660 166 SYS $1.000 9,046,00 $9.046.00 1,905.40 $1,905.40 10,951.40 $10,951.40 GEOTEXTILES FOR UNDERDRAIN 1690 169 EACH $2,500.000 15.00 $37,500.00 1.00 $2,500.00 16.00 $40,000.00 INLET,TYPE HA WITH SLOTTED DRAIN. 1840 184 EACH $1,700.000 29.00 $49,300.00 1.00 $1,700.00 30.00 $51,000.00 MANHOLE,C4 2010 201 i.,FT $35.040 6,083.00 $213,148.32 -360.00 -$12,614.40 5,723.00 $200,533.92 LEVELING PAD,CONCRETE 2090 209 EACH $222.000 14.00 $3,108.00 4.00 $888.00 18.00 $3,996.00 CONSTRUCTION SIGN,C 2100 210 EACH $444.000 10.00 $4,440.00 5.00 $2,220.00 15.00 $6,660.00 ROAD CLOSURE SIGN ASSEMBLY Change Order Details: 96th Street and Keystone Page 5 of 9 10/14/2020 Parkway DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE Line Number Item Unit Unit Price Current Change Revised Quantity Amount Quantity 4rnount Quantity Amount 2130 213 LET $0.700 152,416.00 $106,691.20 5,789.00 $4,052.30 158,205.00 $110,743.50 TEMPORARY PAVEMENT MARKING, REMOVABLE,4 IN. 2140 214 LFT $1.000 10,690.00 $10,690.00 235.00 $235.00 10,925.00 $10,925.00 TEMPORARY PAVEMENT MARKING, REMOVABLE, 5 IN. 2150 215 EACH $1.000 61.00 $61.00 15.00 $15.00 76.00 $76.00 TEMPORARY PAVEMENT MESSAGE MARKING. REMOVABLE, LANE INDICATION ARROW 2160 216 LFT $5.000 626.00 $3,130.00 75.00 $375.00 701.00 $3,505.00 TEMPORARY TRANSVERSE PAVEMENT MARKING, 24 IN. 2180 218 EACH $188.000 76.00 $14,288.00 8.00 $1,504.00 84.00 $15,792.00 CONSTRUCTION SIGN, A 2200 220 DAY $5.000 1,440.00 $7,200.00 109.00 $545.00 1,549.00 $7,745.00 FLASHING ARROW SIGN 2240 224 LFT $15.000 344.00 $5,160.00 120.00 $1,800.00 464.00 $6,960.00 BARRICADE, III-B 2260 226 EACH $5,000.000 6.00 $30,000.00 -2.00 -$10,000.00 4.00 $20,000.00 PORTABLE CHANGEABLE MESSAGE SIGN 2320 232 SET $14.000 2,532.00 $35,448.00 19.50 $273.00 2,551.50 $35,721.00 SIGN, PANEL,WITH LEGEND 2490 249 EACH $1,989.000 5.00 $9,945.00 3.00 $5,967.00 8.00 $15,912.00 OVERHEAD SIGN STRUCTURE,CABLE SPAN, REMOVE 2550 255 EACH $3,660.000 3.00 $10,980.00 1.00 $3,660.00 4.00 $14,640.00 TRAFFIC SIGNAL EQUIPMENT, REMOVE 2590 259 LFT $15.500 426.00 $6,603 00 12,40 $192.20 438.40 $6,795.20 CONDUIT, PVC, 4 IN. 2740 274 LFT $19.000 8,590.30 $163,215.70 745.67 $14,167.73 9,335.97 $177,383.43 CONDUIT, STEEL, GALVANIZED,2 IN. 2750 275 LFT $10.000 10,045.00 $100,450.00 1,771.70 $17,717.00 11,816.70 $118,167.00 WIRE, NO. 4 COPPER, IN PLASTIC DUCT, IN TRENCH,4 1/C 2760 276 EACH $3,441.000 1.00 $3,441,00 1.00 $3,441.00 2.00 56,882,00 CIRCUIT INSTALLATION, UNDERPASS, 6 LUMINAIRES 2770 277 EACH $3,931.000 4.00 $15,724.00 1.00 $3,931.00 5.00 $19,655.00 SERVICE POINT, I 2810 281 EACH $46.500 236.00 $10,974.00 1.00 $46.50 237.00 $11,020.50 MULTIPLE COMPRESSION FITTING, NON-WATERPROOFED 2890 289 LFT $1.250 2,796.00 $3,495.00 1,554.00 $1,942.50 4,350.00 $5,437.50 LINE,THERMOPLASTIC, BROKEN, WHITE, 5 IN. 2910 291 LET $2.000 1,638.00 $3,276.00 889.00 $1,778.00 2,527.00 $5.054.00 LINE.THERMOPLASTIC, SOLID, WHITE, 8 IN. Change Order Details: 96th Street and Keystone Page 6 of 9 10/14/2020 Parkway DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE Line Number Item Unit Unit Price Current Change Revised Quantity Amount Quantity Amount Quantity Amount 3010 301 LFT $12.000 73.00 $376.00 139.10 $1,669.20 21.2.10 $2,545.20 TRANSVERSE MARKING,THERMOPLASTIC,YIELD LINE, WHITE, 24 IN. 3050 305 LET $2.000 144.00 $288.00 64.00 $128.00 208.00 $416.00 LINE,THERMOPLASTIC, DOTTED, WHITE, 6 [N. 3080 308 LET $0.750 14,426.00 $10,819.50 4,057,32 $3,042.99 18,483.32 $13,862.49 LINE,THERMOPLASTIC,SOLID, YELLOW, 4 [N.. 3100 310 LFT $3.000 355.00 $1,065.00 128.00 $384.00 483.00 $1,449.00 TRANSVERSE MARKING,THERMOPLASTIC,CROSSHATCH LINE, YELLOW 12 IN. 3120 312 EACH $25.000 414.00 $10,350.00 -384.00 -$9,600.00 30.00 $750.00 SNOWPLOWABLE RAISED PAVEMENT MARKER 3160 316 TON $88.980 4,590.00 $408,418.20 -354.57 -$31,549.64 4,235,43 $376,868.56 HMA,4,76, SURFACE, 9.5 rum-SMA 3270 327 LFT $5.000 367.00 $1,835.00 48.00 $240.00 415.00 $2,075.00 TRANSVERSE MARKING, REMOVE 3540 110-07025 EACH $1,654.780 3.00 $4,964.34 1.00 $1,654.78 4.00 $6,619.12 MOBILIZATION AND DEMOBILIZATION 3660 805-78795 LFT $9.140 390.00 $3,564.60 347.12 $3,172.68 737.12 $6,737.28 SAW CUT FOR ROADWAY LOOP AND SEALANT 3670 805-78470 LFT $0.650 1,365.00 $387.25 815.20 $529.88 2,180.20 $1,417.13 SIGNAL CABLE,ROADWAY LOOP, COPPER 1CI14GA 3760 605-06125 LFT $24.840 3,376.00 $83,859.84 190.41 $4,729.78 3.566.41 $88,589.62 CURB,CONCRETE, MODIFIED 3780 502-08204 SYS $128.750 524.00 $67,465.00 -210.00 -$27,037.50 314.00 $40,427.50 PCCP, 12.5 IN 3910 805-04133 EACH $1,124.290 1.00 $1,124.29 1.00 $1,124.29 2 00 $2,248.58 SIGNAL POLE,PEDESTAL, 12FT 3940 805-11799 EACH $7,973.750 1.00 $7,973.75 1.00 $7,973.75 2 00 $15,947.50 RECTANGULAR RAPID FLASHING BEACON 4040 605-06255 SYS $256,020 45.00 $11,520.90 30.48 $7,803.49 15.48 519.32.1.39 CENTER CURB, D. CONCRETE (78 Items) Totals $6,047,241.21 -$275,646.78 $5,771,594.43 New Items Line Number Item Unit Pending Quantity Unit Price Dollar Amount Section; 1 -801-08400 4170 109-04299 DOL 7,179.38 $1.000 $7,179.38 FORCE ACCOUNT WORK Reason: Bridge Deck Sealing Change Order Details: 96th Street and Keystone Page 7 of 9 10/14/2020 Parkway DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE Line Number Item Unit Pending Quantity Unit Price Dollar Amount 4180 109-04299 DOL 3,929.42 $1.000 $3,929.42 FORCE ACCOUNT WORK Reason:Crane Move 4190 109-04299 DOL 3,600.75 51.000 $3,600.75 FORCE ACCOUNT WORK Reason: GDO-8 vs. Storm Pipe Conflict 4200 109-04299 DOL 19,100.28 51.000 $19,100.28 FORCE ACCOUNT WORK Reason: Moment Slab,Ramp SWR 4210 109-04299 DOL 2,622.98 $1.000 $2,622.98 FORCE ACCOUNT WORK Reason: MSE Wall Cores(Underdrain Outlets) 4220 109-04299 DOL 6,298.22 $1.000 $6,298.22 FORCE ACCOUNT WORK Reason: Re-handle H-Piling 4230 109-04299 DOL 52,462.30 $1.000 $52,462.30 FORCE ACCOUNT WORK Reason: Winter Concrete 4240 109-04299 DOL 2,281,12 $1.000 $2,281.12 FORCE ACCOUNT WORK Reason: Pothole Patching 4250 109-04299 DOL 3,778.15 $1.000 $3,778.15 FORCE ACCOUNT WORK Reason: Penske Chevrolet Approach, Grade Change 4260 109-04299 DOL 613.34 $1,000 $613.34 FORCE ACCOUNT WORK Reason: SE Keystone Storm Modifications (AT&T Conflict) 4270 109-04299 DOL 18,238.49 $1.000 $18,238.49 FORCE ACCOUNT WORK Reason: Haverstick Road,Water Line Lowering 4280 109-04299 DOL 77,080.32 $1.000 $77,080.32 FORCE ACCOUNT WORK Reason: Rohrer Road and Grace Drive Crosswalk 4290 109-04299 DOL 45,154,73 $1.000 $45,154.73 FORCE ACCOUNT WORK Reason: HMA Wedge and Removal 4300 109-04299 DOL 2,674.17 $1.000 $2,674.17 FORCE ACCOUNT WORK Reason: Clearing Right of Way,Sarah Care Drive Approach 4310 109-04299 DOL 5.496.58 $1.000 $5,498.58 FORCE ACCOUNT WORK Reason: Curb Ramp Replace, SE Leg Gray Road RAB 4320 109-04299 DOL 61.224.30 $1.000 $61,224.30 FORCE ACCOUNT WORK Reason: South Haverstick HMA and Curb (16Items) Total: +$311,736.53 Change Order Details: 96th Street and Keystone Page 8 of 9 10/14/2020 Parkway DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE Recommended for Processing: Timothy P.Conarroe,PE o-• ""'�""'�":}.,�n• 1 0'20-2O2 V o.4mxiioa a».a.m Resident Project Representative Date Contractor Date Owner Date Mange Order Details: 96th Street and keystone Paae 9 of 9 10/14/2020 ?arlc4A-ay