HomeMy WebLinkAboutBowen_Change_Order_2_-_Utilities (2) DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE
ti1,5 Jones & HenryFluid thinking®
1980 East 116th Street,Suite 260,Carmel,IN 46032
ENGINEERS, LTD. Phone:317.818.1805 JHEng.com
November 4, 2020
John Duffy, Director of Utilities
City of Carmel Utilities
30 West Main St.
Carmel, IN 46032
Subject: Contract 100—Change Order 2
City of Carmel, IN
WWTP Secondary Expansion Project
J&H Project Number:451.7504.001
Dear Mr. Duffy,
Enclosed is a copy of Change Order 2 for the Contract 100 WWTP Secondary Expansion Project. It increases
Bowen Engineering Cooperation's contract price for Contract 100 by$111,530. A summary of the additional
work performed is provided on the fourth page of this packet.
The change order has been prepared under my direction. I have reviewed its contents and recommend that it be
approved. Please do not hesitate to contact me with any questions or comments.
Sincerely,
JONES& HENRY ENGINEERS, LTD.
P-14454--1.414A"--
Philip Teague, P.E.
Project Manager
Cannel,IN I Cincinnati,OH I Fort Wayne,IN I Kalamazoo,MI I Toledo,OH
DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE
I r el Utilities Cr)
CHANGE ORDER
Change Order No. 2
Date: 10/20/202
Contract Date: April 2020
Name of Project: Secondary Expansion •
• e
•
Owner: City of Carmel
Contractor: Bowen Engineering Corporation
The following changes are hereby made to the Agreement:
Description of Change in Work: See Attached Description of Changes
Justification:
Original Contract Price: $9,884,000.00
Previous Changes to Contract Price: $173,360.00
Current Contract Price adjusted by previous
Change Order(s): $10,057,360.00
The Contract Price due to this Change
Order will be increased by: $111,530.00
The new Contract Price including this
Change Order will be: $10,168,890.00
Change to Contract Time:
The Contract Time will be adjusted by 0 calendar days.
The date for completion of all work will be by substantial completion.
(Date)
Requested by: City of Carmel 10/20/20
(Owner) (Date)
Recommended by: -�� /'�'-�u;r _ l( /��t �� v
(Consulting E gineer) /(Date)
Accepted by: Bowen Engineering Corporation
(Contractor)
Mark Cvetkovich, PM 10-27-20
(Name and Title) (Date)
Secondary Expansion A-25 CITY OF CARMEL
Change Order Form
DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE
n urine/ Utilities
Approved By
Owner:
City of Carmel, Indiana
Board of Public Works
DoeoSIgned by:
By:( s%"" 6rai"ri
James Brainerd Member
c—DoeuSIpned by:
By:�hail atAJA. tit,
Mary Ann BuBlgird Member
DocuSIQned by:
By: Levi riRthoyyaaln.
Lo ' WaisonBoard Member
Date:12/2/2020
One Copy—Owner
One Copy—Contractor
One Copy—Engineer
Secondary Expansion A-25 CITY OF CARMEL
Change Order Form
DocuSign Envelope ID:A7F9746E-7D86-4267-AAA4-0745A105ADCE
10/16/2020
Secondary Expansion Change order
2
PCO Description Cost
13 Added conduits- not approved $0.00
14 Increase RAS Pumps to 20hp to match existing $12,810.00
15 Modulating card added to feed Gates for Final 6&7 $2,130.00
16 Airline Relocation at Mixed Liquor Channel $16,420.00
17 Elect Duct Bank interference at Mixed Liquor Charm( $0.00
18 Mixed Liquor 36" Force Main Conflict $9,560.00
20 UG Pipe fitting credit 2-45's vs 1-90 -$3,210.00
21 Aeration effluent trough repair $9,260.00
22 6"Water relocation at aeration tank 6 $3,940.00
23 Aeration tank 10 influent gate replacement $14,400.00
24 To be paid by City outside of Contract $0.00
26 Final 6 influent pipe reroute $7,360.00
27 Final 6 effluent pipe reroute $36,640.00
28 Water line relocation at final effluent line $2,220.00
Total $111,530.00
DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE
ACKNOWLEDGEMENT
STATE OF INDIANA )
SS:
COUNTY OF 1
Before me, a Notary Public in and for said County and State,personally appeared James
Brainard, Mary Ann Burke. and Lori Watson, by me known to be the Members of the City of Carmel
Board of Public Works and Safety, and Sue Wolfe.ang, Clerk of the City of Carmel, who acknowledged
the execution of the foregoing "Agreement" on behalf of the City of Carmel, Indiana.
Witness my hand and Notarial Seal this .q day of ACC nexx 2020.
Jennifer I Stites Sjj1)
Notary Public Seal State of Indiana Lp iA�A
H2milton County f�l
Commission Number NP0723135 NO k�RY P LI
My Commission Expires 10/22/2027
qf .5firtcs
My Commission Expires: Printed Name
\V .,)a ' My County of Residence: Mai I I lU p
Date: 17),4 IMO
DocuSign Envelope ID:A7F9746E-7DB6-4267-AAA4-0745A105ADCE
Approved and Adopted this end day of December , 20 20
CITY OF CARMEL, INDIANA
By and through its Board of Public Works and Safety
BY:
DocuSIuned by:
,hai+it,S &rai►ti,ar),
`.S7iykFax eaeea+ . ... ...---
James 3rainard,Presiding Officer
Date: 12/3/2020
DocuSIpned by:
LAunt QtAJA, bold,
Mary Ann Burke, Member
Date: 12/3/2020
EDocuSIgned by:
tVi (Ja.hetA,
Lori S.Watson Member
1Date:
ATTEST:
�--DocuSigned by:
SW, OJOV-yul
—GGSHO`J1JI KR144L S...
Sue Wolfgang, Clerk
Date:12/3/2020