HomeMy WebLinkAboutC1.2 Pre Construction SWPPPBELLEVUECARMEL, INC1.2
REVISIONS
PRE-CONSTRUCTION STORMWATER
POLLUTION PREVENTION AND
DEMOLITION PLANPRE-CONSTRUCTION STORMWATER POLLUTIONPREVENTION AND DEMOLITION PLAN
INDIANAPOLIS - TERRE HAUTE
MUNCIE - LAFAYETTE - NEW ALBANY
www.hwcengineering.com
0'
(IN FEET)
GRAPHIC SCALE
20' 40' 60'
Call 811 or 800-382-5544 Before you Dig!
BENCHMARK INFORMATION:
THIS SHEET TO BE USED FOR
EROSION CONTROL ONLY.
PERSON ONSITE RESPONSIBLE FOR EROSION CONTROL:
NOTE:
SEE SHEET C8.0 FOR A LIST IN SEQUENCE
OF CONSTRUCTION ACTIVITIES.
DEMOLITION GENERAL NOTES:
CARMEL GENERAL NOTES:
INDEX OF SWPPP ELEMENTS
DEMOLITION KEYNOTES: #
STORMWATER POLLUTION
PREVENTION NOTES:
LEGEND:
EXISTING REMOVENOTE:
CONTRACTOR SHALL PROTECT THE EXISTING CITY DUAL DUCT
BANK IN THE RIGHT-OF-WAY. IN THE EVENT OF CONFLICT WITH
THE PROPOSED IMPROVEMENTS, RELOCATION OF THE DUAL DUCT
BANK AND ALL ASSOCIATED/APPURTENANT/ANCILLARY ITEMS
SHALL BE THE SOLE RESPONSIBILITY OF THE DEVELOPER SUBJECT
TO REVIEW AND APPROVAL OF THE CITY.
NOTE:
ALL EXISTING PERIMETER ROAD DRAINAGE STRUCTURES AND
BRIDGES ACROSS THE FRONTAGE OF THIS DEVELOPMENT ARE
INDICATED ON THE PLANS. PROVISIONS HAVE BEEN MADE TO
IMPROVE OR REPLACE ANY DRAINAGE STRUCTURES AND
BRIDGES AS NECESSARY OR AS REQUESTED BY THE CITY TO
ACCOMMODATE THE PAVEMENT WIDENING, AUXILIARY LANES,
MULTI-USE PATH, AND ANY OTHER REQUIRED IMPROVEMENTS TO
THE PROPERTY OR THE ROADWAY. THE COST TO IMPROVE OR
REPLACE ANY DRAINAGE STRUCTURES AND BRIDGES WILL BE
BORNE BY THE DEVELOPER.
LEGEND
*
01/27/21