HomeMy WebLinkAboutM2-2OF DIFFUSER
FLEXIBLE DUCT UPSTREAM
MAXIMUM OF 5' OF
PATTERN CONTROLLER
VOLUME
NOT TAPED
VALVE
CEILING
FLOW
RIGID DUCT
DAMPER
AIR
TO BE BANDED
CONNECTIONS
FLEX. DUCT
FLEXIBLE DUCT
SQUARE THROAT WITH TURNING VANES
RETURN AIR TRANSITION
SUPPLY AIR RADIUS ELL
CENTERLINE RADIUS OF RECTANGULAR DUCT MUST MATCH
SMALLER DIMENSION OF DUCT. USE TO TRANSITION RTU
SUPPLY DROP TO MAIN TRUNK.
WRAP FIBERGLASS INSULATION WITH FACTORY
APPLIED FOIL VAPOR BARRIER WITH A
PERMEANCE OF 0.02 OR LESS. MINIMUM
INSTALLED R VALUE = 6. INSULATION MUST BE
INSTALLED DRY.
CUT INSULATION TO PROPER
LENGTH TO AVOID
DISFIGURING OF INSULATION
RIGID DUCT
ALL DUCT OVER 24" WIDE
TO BE SECURELY
INSULATED WITH WELDED
STICK PINS
STAPLE 2" FLANGE WITH
TAPE OVER JOINT WITH
STAPLE TO PROVIDE
VAPOR TIGHT SEAL. ALL
SEAMS TO BE SEALED
WITH HARDCAST.
SEQUENCE OF OPERATION
UNITS 1,2, OCCUPIED MODE UNIT TO CYCLE ON & OFF TO PROVIDE HEAT & COOL AS NEEDED. OUTDOOR
AIR MODULATING DAMPER TO BRING IN THE MINIMUM AMOUNT OF OUTSIDE
AIR INTO THE SPACE ACCORDING TO OUTSIDE AIR VENTILATION REQUIREMENTS ON SHEET M2-2.
UNOCCUPIED MODE, OUTSIDE AIR DAMPERS TO CLOSE &
HEAT & COOL TO CYCLE ON & OFF AS CALLED FOR BY THE THERMOSTAT.
1
THERMOSTAT
HONEYWELL VISION PRO TOUCH SCREEN PRESTIGE #THX 9421
DUAL FUEL THERMOSTATS ON UNITS #4 & #5.
(1) YL7220A7503 Jade Economizer Kits
Each kit includes the following.
(1) W7220A1000 Jade Economizer
(1) C7250A1000 Outside Temperature Sensor
(1) C7250A1000 Return Air Temperature Sensor
Honeywell MS7505A2030 damper actuator main outside air intake damper. to be interlocked
to open whenever any one of the 2, units operate in the occupied mode.
1, MD 12" X 16" with LOW VOLTAGE ACUATOR
2, MD 10" X 8" with LOW VOLTAGE ACUATOR
SIDEWALL LOUVER
GREENHECK ESD-603
EXTERIOR COLOR TO BE SLCTD.
12" X 16"
S6
32"X32" T&B AIG-H DISCHARGE
GRILLES.
INTAKE LOUVER RUSKIN
#ELF820DD 12"X16"
W/ BACKDRAFT GASKETED DAMPER
R4
20" X 8" SUPPLY AIR GRILLE MOUNTED ON
SIDE OF DUCT W/ VOLUME CONTROL
6" X 12" SUPPLY AIR GRILLE MOUNTED ON
SIDE OF DUCT W/ VOLUME CONTROL
TITUS S300FL
TITUS LINEAR BAR DIFFUSER
FL-15 1, SLOT 1.5" WIDE 4' LONG
MOUNTED TO CEILING
NECK SIZES RETURN AIR GRILLES
A 18 X 16
B 20 X 10
C 20 X 12
D 18 X 14
E 14 X 20
F 6 X 6
G 10 X 10
H 8 X 8
I 8 X 6
J 16 X 12
K 20 X 20
L 14 X 20
M 28 X 28
600
42" X 42"
700 - 800
200
100 - 175
1200 - 1350
1000
TITUS 50F
250 - 350
400 - 450
18"X48" DOUBLE DEFLECTION DUCT
MOUNTED. TIN COLORED TITUS 300 W/
VOLUME CONTROL.
S7
SHOEMAKER ADJUSTABLE #
945 12" X 6"
S5
GRILLES & DIFFUSERS
SUPPLY GRILLE
TITUS 12" X 12" OMNI WHITE
SUPPLY GRILLE
TITUS 12" X 12" OMNI WHITE
SUPPLY GRILLE
TITUS 24" X 24" OMNI WHITE
S2
S3
S1
S11
SUPPLY GRILLE
TITUS 16" X 4" 300FS
SYMBOL DESIGNATION MODEL NECK SIZE MAX AIRFLOW
RETURN GRILLE
TITUS 50F EGGCRATE 12" X 12"
240 CFM
R1
R2
RETURN GRILLE
TITUS 50F 24" X 48"
RETURN GRILLE
TITUS 50F EGGCRATE 24" X 24"
R3
S4
S8
S9
S10
TITUS LINEAR BAR DIFFUSER
FL-20 1, SLOT 2" WIDE 2' LONG
MOUNTED TO CEILING OR WALL
INTERGRAL PATTERN CONTROLLER
S12
SHOEMAKER ADJUSTABLE #
945 16 X 6
S13
INTERGRAL PATTERN CONTROLLER
MODEL
MANUFACTURER
AREA SERVED
SEER
VOLTAGE / PHASE /
FREQUENCY
HEATING CAPACITY
(BTU) INPUT
MAX. FUSE SIZE BY(EC)
AIRFLOW (CFM)
MCA
EQUIPMENT NOTES
CONTROLED BY
OCC SENSORS
H VAC EQUIPMENT
ID #
80 cfm @ .2 SP
EXHAUST FAN EF
120/1/60
BROAN
ARW80L
RESTROOMS
LENNOX
1ST FLOOR
UNIT #1
BASEMENT
LENNOX
UNIT #2
2 UNITS TWINNED
TOGETHER
4000 CFM
2000 EACH
180 K BTU
90 EACH
COOLING CAPACITY
(BTU)
96 K BTU
48 K EACH
120 V / 60 / 1
208 V / 60 / 3
ALTERNATE M2. DEHUMIDIFICATION & HUMIDIFICATION, PROVIDE SEPERATE
ALTERNATE PRICE FROM THE REPLACING HVAC EQUIPMENT ALTERNATE.
* *
EL16XP1-060-230 Heat Pump 5.0 ton
C35-60D-2F-1 Coil/5 Ton/Cased
EL296UH135XV60D Furnace-Gas/135Btuh/5Ton
94M43 1 EDA-060D Dehumidification System Field Installed
98M62 1 EDA Insulation & Piping Kit Field Installed
Y2788 1 Healthy Climate® Power Humidifier HCWP3-18 Field Installed
12J20 1 Thermal Expansion Valve 3.5 - 5 Tons Field Installed
* * UNIT #1
*
* *
ELS090S4D-230-3-E
(2)CX35-48C-F, COILS
(2) ML193UH090P48C
1) THESE DRAWINGS INDICATE REQUIRED SIZES AND POINTS OF TERMINATION FOR PIPING,
DUCTWORK, CONDUIT, ETC. THE EQUIPMENT SHOWN ILLUSTRATES
SUGGESTED ROUTING, BUT NECESSARY OFFSETS AND FITTINGS MAY NOT
BE SHOWN. CONTRACTOR SHALL INSTALL HIS WORK IN A MANNER THAT WILL
CONFIRM WITH THE STRUCTURE UNLESS DOING SO VIOLATES GOVERNING
CODES. ALL DIMENSIONS SHOWN ON THESE PLANS ARE IN FEET AND/ OR INCHES
UNLESS OTHERWISE NOTED.
2) CONTRACTOR SHALL BE GUIDED BY THE ARCHITECT'S REFLECTED CEILING PLAN
FOR EXACT LOCATION OF DIFFUSERS, REGISTERS AND GRILLES UNLESS OTHERWISE NOTED.
3) DUCTS PENETRATING FLOOR SLABS AND/OR WALLS SHALL BE SEALED AS
REQUIRED BY CODE. DUCTS PENETRATING FIRE RATED WALLS AND/OR FLOORS
SHALL HAVE OPENING AROUND DUCT SEALED WITH A MATERIAL HAVING THE SAME FIRE
RATING AS THE WALL OR FLOOR. PROVIDE FIRE DAMPERS AT ALL DUCT PENETRATIONS
THROUGH FIRE RATED WALLS OR FLOORS.
4) ALL TRENCHES WITHIN THE CONFINES OF THE BUILDING SHALL BE KEPT AWAY
FROM FOOTINGS A DISTANCE OF ONE FOOT HORIZONTAL FOR EACH FOOT OF
DEPTH BELOW THE NEAREST FOOTING, OR TRENCH SHALL BE FILLED WITH CONCRETE
TO AN ELEVATION SUCH AS TO ESTABLISH THE REQUIRED ONE-FOR-ONE RATIO OR PROXIMITY.
5) DIFFUSERS, GRILLES AND REGISTERS LOCATED IN GYP. BOARD CEILINGS SHALL
HAVE PLASTER FRAMES.
6) EXPOSED DUCTWORK SHALL BE ROUND SPIRAL PIPE UNLESS OTHERWISE
NOTED.
7) MECHANICAL CONTRACTOR SHALL PREFORM TEST READINGS ON ALL NEW FANS
AND UNITS, AND ADJUST SPEED TO DELIVER SPECIFIED QUANTITY OF AIR. A TEST
AND BALANCEING REPORT LOG SHALL BE MADE SHOWING ALL AIR SUPPLY QUANTITIES,
FAN AND UNIT TESTING READINGS, ETC., AND SHALL BE SUBMITTED TO THE ENGINEER
BEFORE FINAL INSPECTION OF THE PROJECT. ALL EQUIPMENT SHALL BE ADJUSTED TO
OPERATE AS INTENDED BY THE SPECIFICATIONS. ALL THERMOSTATS AND CONTROL
DEVICES SHALL BE ADJUSTED TO OPERATE AS INTENDED. ADJUST BURNERS, FANS, ETC.,
FOR PROPER AND EFFICIENT OPERATIONS. ADJUST ALL SUPPY OULETS TO SUPPLY THE
AMOUNT OF AIR SHOWN ON DRAWINGS. CALIBRATE, SET AND ADJUST ALL AUTOMATIC
TEMPERATURE CONTROLS. CHECK PROPER SEQUENCING OF ALL INTERLOCK SYSTEMS.
8) LIGHT FIXTURE LOCATIONS TAKE PRECEDENCE OVER DIFFUSER AND GRILLE
LOCATIONS. LOCATE DIFFUSERS AND GRILLES TO ACCOMMODATE LIGHTING
LAYOUTS.
9) MECHANICAL CONTRACTOR SHALL PROVIDE AND INSTALL ALL CONTROL
VOLTAGE COMPONENTS & WIRING INCLUDING NECESSARY CONDUIT BETWEEN DEVICES.
MECHANICAL CONTRACTOR IS RESPONSIBLE FOR SUBCONTRACTING ANY OF THIS WORK
TO A QUALIFIED ELECTRICAL CONTRACTOR LICENSED FOR WORK IN THE JURISDICTION OF
THIS PROJECT. ELECTRICAL SUBCONTRACTOR MUST BE APPOVED BY THE G.C. ALL CHANGE
ORDERS SUBMITTED BY THE ELECTRICAL SUBCONTRACTOR SHALL BE ABSORBED BY MECHANICAL
CONTRACTOR. DESIGNATED PROJECT ELECTRICAL CONTRACTOR SHALL PROVIDE POWER TO
DEVICE OR DEVICE CONTROLLER PER PLANS.
10) ALL TAKEOFFS FROM BRANCH DUCTS TO INDIVIDUAL DIFFUSERS, GRILLES, AND
REGISTERS SHALL HAVE A SPIN-ON TYPE DUCT CONNECTOR WITH BALANCING
DAMPER AND LOCKING QUADRANT.
11) SEALANTS USED ON DUCT SYSTEMS SHALL HAVE A FLAME SPREAD RATING OF
NOT MORE THAN 25 AND A SMOKE DEVELOPMENT CLASSIFICATION OF NOT MORE THAN 50
OR AS PER LATEST BUILDING CODE RUQUIREMENTS. ALL SEAMS, JOINTS, CORNERS, ETC. ARE
TO BE SEALED TO MAKE DUCT COMPLETELY AIR TIGHT.
12) DUCT INSULATION: PROVIDE 1 1/2 LB/CU. FT. DENSITY WRAP INSULATION WITH
VAPOR RETARDING JACKET WITH FSK FINISH. COVER ALL SUPPLY AIR DUCTS, SILENCERS,
TERMINALS, OUTSIDE AIR INTAKES, EXHAUST AIR DUCTS WITH 1-1/2" THICK INSULATION R-6
MINIMUM. ALL JOINTS SHALL BE TIGHTLY BUTTED.
TAPE ALL JOINTS AND COVER ALL PIN PENETRATIONS WITH 4" RFFRK TAPE TO PROVIDE A
COMPLETE VAPOR BARRIER ENVELOPE.
A) EXTERNALLY INSULATE ALL SUPPLY AND RETURN METAL DUCTS WITH ABOVE
WRAP EXCEPT VERTICAL DROPS FROM ROOFTOP UNITS. DROPS FROM ROOFTOP UNITS
SHALL BE INTERNALLY INSULATED WITH 1" DUCT LINER. DUCT LINER SHALL MEET
ASTM C 1071, TYPE 1, FLEXIBLE, ASTM G21 AND G22, NFPA 90A AND 90B, FHC 25/50
AND LIMITED COMBUSTIBILITY. INSTALL ACCORDING TO SMACNA AND NAIMA FIBROUS
GLASS DUCT LINER APPLICATION STANDARDS.
13) FLEXIBLE DUCT: HART & COOLEY MODEL F216, METALIZED VAPOR BARRIER, R-6 INSULATION,
UL-181 RATED AND INSTALLED BY ASTM C-518 STANDARDS. FLAME SPREAD LESS THAN 25, SMOKE
DEVELOPED LESS THAN 50. DUCT SHALL BE INSTALLED LEVEL WITH MINIMAL BENDS AND
SUPPORTED AS REQUIRED PER DETAIL.
14) ALL MECHANICAL EQUIPMENT MOUNTED ON THE ROOF SHALL BE PLACED AT
LEAST 10'-0" AWAY FROM ANY EDGE OR CHANGE IN ROOF ELEVATION.
15) ALL DISCONNECTS FOR MECHANICAL EQUIPMENT SHALL BE PROVIDED BY THE
ELECTRICAL CONTRACTOR.
16) ALL STARTERS AND DISCONNECTS FOR MECHANICAL EQUIPMENT SHALL BE
INSTALLED BY THE ELECTRICAL CONTRACTOR.
H V A C PLAN NOTES
17) ELECTRICAL CONTRACTOR RESPONSIBLE FOR INSTALLING & CONNECTING THE
FIRE ALARM SYSTEM ALL DUCT DETECTORS. SEE ELECTRICAL PLANS FOR LOCATIONS.
49 CFM
150 CFM
UNI AREA SERVED
OUTSIDE AIR VENTILATION REQUIREMENT TABLE
VENTILATION
REQUIRED
VENTILATION
OUTSIDE AIR
UNIT
VENTILATION
OA DELIVERED
TO ROOMS
EXHAUST
AIR
HUMIDITY
CONTROL
UNIT 1 BANK / OFFICE SPACES
RESTROOMS 2 X 75CFM
1954 SF /5 PPL. 1000PSF X 5 CFM PP + .06 CFM PSF
52 CFM
BANK / OFFICE SPACES 2100 SF /5 PPL. 1000PSF X 5 CFM PP + .06 CFM PSF
UNIT 2
MOTORIZED DAMPERS
MD1 10 X 8
LOW VOLTAGE CONNECTION
118 CFM
167 CFM
126 CFM
178 CFM 75 CFM
MD2 14 X 10
tel: 765.649.8477
www.krMarchitecture.com
ANDERSON
INDIANAPOLIS
DETROIT
DRAWN BY
krM JOB NO.
DRAWING NO.
REVISIONS
DRAWING NAME
M2-2
MECHANICAL
DETAILS &
SCHEDULES
KRM
20128
02/12/2021
BID SET
4775 E 126th St Carmel IN 46033
STATE BANK
20128 - CARMEL BRANCH
BID SET
02/12/2021
8-7-19
SCALE: 1" = 1'-0"
3
AIR CLEANER
05/07/21