HomeMy WebLinkAbout05 Envelope ComcheckCOMcheck Software Version 4.1.5.1
Envelope Compliance Certificate
Project Title:
90.1 (2007) Standard
Project Type:New Construction
Vertical Glazing / Wall Area:13%
Location:Carmel, Indiana
Climate Zone:5a
Construction Site:
BENNETT PKWY & MICHIGAN RD
CARMEL, IN 46077
Owner/Agent:
JOE FARR
JDF DEVELOPMENT, LLC
IN
317.569.0908
JFARR@JDFDEVELOPMENT.COM
Designer/Contractor:
Shawn Curran
Curran Architecture
5719 LAWTON LOOP E. DR.
# 212
INDIANAPOLIS, IN 46216
(317)288-0681
Project Information
Energy Code:
THE AVENUE AT BENNETT FARM
Building Area Floor Area
1-Retail : Nonresidential 10969
Envelope Assemblies
Assembly Cavity
R-Value
Cont.
R-Value
Proposed
U-Factor
Budget U-
Factor(a)
Gross Area
or
Perimeter
Exterior Wall 1: Steel-Framed, 16" o.c., [Bldg. Use 1 - Retail]4644 19.0 7.5 0.060 0.064
STOREFRONT: Metal Frame Curtain Wall/Storefront, Perf. Specs.:
Product ID NA, SHGC 0.45, PF 0.30, [Bldg. Use 1 - Retail] (b)
908 ------0.300 0.450
ENTRANCE DOORS: Glass (> 50% glazing):Metal Frame, Entrance
Door, Perf. Specs.: Product ID NA, SHGC 0.45, [Bldg. Use 1 -
Retail] (b)
147 ------0.300 0.800
Exterior Wall 2: Steel-Framed, 16" o.c., [Bldg. Use 1 - Retail]1491 19.0 7.5 0.060 0.064
STOREFRONT: Metal Frame Curtain Wall/Storefront, Perf. Specs.:
Product ID NA, SHGC 0.45, PF 0.30, [Bldg. Use 1 - Retail] (b)
181 ------0.300 0.450
DRIVE-THRU WINDOW: Metal Frame, Perf. Type: Energy code
default, Single Pane, Clear , SHGC 0.82, [Bldg. Use 1 - Retail]
17 ------1.250 0.550
ENTRANCE DOORS: Glass (> 50% glazing):Metal Frame, Entrance
Door, Perf. Specs.: Product ID NA, SHGC 0.45, [Bldg. Use 1 -
Retail] (b)
21 ------0.300 0.800
Exterior Wall 3: Steel-Framed, 16" o.c., [Bldg. Use 1 - Retail]3622 19.0 7.5 0.060 0.064
EXIT DOORS: Insulated Metal, Swinging, [Bldg. Use 1 - Retail]126 ------0.300 0.700
Exterior Wall 5: Steel-Framed, 16" o.c., [Bldg. Use 1 - Retail]1491 19.0 7.5 0.060 0.064
STOREFRONT: Metal Frame Curtain Wall/Storefront, Perf. Specs.:
Product ID NA, SHGC 0.45, [Bldg. Use 1 - Retail] (b)
181 ------0.300 0.450
ENTRANCE DOORS: Insulated Metal, Swinging, [Bldg. Use 1 - Retail]21 ------0.400 0.700
Floor 1: Slab-On-Grade:Unheated, Horizontal with vertical 4 ft., [Bldg.
Use 1 - Retail] (c)
504 ---10.0 0.640 0.640
Roof 1: Insulation Entirely Above Deck, [Bldg. Use 1 - Retail]10969 ---20.0 0.048 0.048
Project Title:
Data filename:
THE AVENUE AT BENNETT FARM
\\cai-dc\projects\200275 JDF Development Michigan Road III\DOCS\COMCHECK ENVELOPE.cck
02/25/21Report date:
91 ofPage
(a)Budget U-factors are used for software baseline calculations ONLY, and are not code requirements.
(b)Fenestration product performance must be certified in accordance with NFRC and requires supporting documentation.
(c)Slab-On-Grade proposed and budget U-factors shown in table are F-factors.
Envelope Compliance Statement
Compliance Statement: The proposed envelope design represented in this document is consistent with the building plans,
specifications, and other calculations submitted with this permit application. The proposed envelope systems have been
designed to meet the 90.1 (2007) Standard requirements in COMcheck Version 4.1.5.1 and to comply with any applicable
mandatory requirements listed in the Inspection Checklist.
Shawn Curran
Name - Title Signature Date
Envelope PASSES: Design 5% better than code
Project Title:
Data filename:
THE AVENUE AT BENNETT FARM
\\cai-dc\projects\200275 JDF Development Michigan Road III\DOCS\COMCHECK ENVELOPE.cck
02/25/21Report date:
92 ofPage
Inspection Checklist
Requirements: 100.0% were addressed directly in the COMcheck software
COMcheck Software Version 4.1.5.1
Text in the "Comments/Assumptions" column is provided by the user in the COMcheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception
is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Energy Code: 90.1 (2007) Standard
Section
#
& Req.ID
Plan Review Complies?Comments/Assumptions
4.2.2
[PR1]1
Plans and/or specifications provide all
information with which compliance
can be determined for the building
envelope and document where
exceptions to the standard are
claimed.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
THE AVENUE AT BENNETT FARM
\\cai-dc\projects\200275 JDF Development Michigan Road III\DOCS\COMCHECK ENVELOPE.cck
02/25/21Report date:
93 ofPage
Section
#
& Req.ID
Footing / Foundation
Inspection
Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
5.5.3.3
[FO1]1
Below-grade wall insulation R-
value.
R-_____R-_____Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
5.5.3.5
[FO3]1
Slab edge insulation R-value.R-_____
Unheated
Heated
R-_____
Unheated
Heated
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
5.8.1.2
[FO4]1
Slab edge insulation installed per
manufacturer’s instructions.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.5.3.5
[FO5]1
Slab edge insulation
depth/length.
_____ ft _____ ft Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
5.8.1.7.3
[FO7]1
Insulation in contact with the
ground has <=0.3% water
absorption rate per ASTM C272.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
THE AVENUE AT BENNETT FARM
\\cai-dc\projects\200275 JDF Development Michigan Road III\DOCS\COMCHECK ENVELOPE.cck
02/25/21Report date:
94 ofPage
Section
#
& Req.ID
Framing / Rough-In Inspection Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
5.4.3.2
[FR1]3
Factory-built fenestration and
doors are labeled as meeting air
leakage requirements.
Fenestration____
_ cfm/ft2
Doors_____
cfm/ft2
Fenestration____
_ cfm/ft2
Doors_____
cfm/ft2
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.4.3.4
[FR4]3
Vestibules are installed where
building entrances separate
conditioned space from the
exterior, and meet exterior
envelope requirements. Doors
have self-closing devices, and are
>=7 ft apart.
Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement
does not apply.
Location on plans/spec:
Shell Building
5.5.4.3a
[FR8]1
Vertical fenestration U-Factor.U-_____U-_____Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
5.5.4.3b
[FR9]1
Skylight fenestration U-Factor.U-_____U-_____Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
5.5.4.4.1
[FR10]1
Vertical fenestration SHGC value.SHGC:_____SHGC:_____Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
5.5.4.4.2
[FR11]1
Skylight SHGC value.SHGC:_____SHGC:_____Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
5.8.2.1,
5.8.2.4
[FR12]2
Fenestration products rated in
accordance with NFRC.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.8.2.2
[FR13]1
Fenestration products are
certified as to performance labels
or certificates provided.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.8.2.3,
5.5.3.6
[FR14]2
U-factor of opaque doors
associated with the building
thermal envelope meets
requirements.
U-_____
Swinging
Nonswinging
U-_____
Swinging
Nonswinging
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
THE AVENUE AT BENNETT FARM
\\cai-dc\projects\200275 JDF Development Michigan Road III\DOCS\COMCHECK ENVELOPE.cck
02/25/21Report date:
95 ofPage
Section
#
& Req.ID
Insulation Inspection Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
5.4.3.1
[IN1]1
All sources of air leakage in the
building thermal envelope are
sealed, caulked, gasketed,
weather stripped or wrapped with
moisture vapor-permeable
wrapping material to minimize air
leakage.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.5.3.1
[IN2]1
Roof R-value. For some ceiling
systems, verification may need to
occur during Framing Inspection.
R-_____
Above deck
Metal
Attic
R-_____
Above deck
Metal
Attic
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
5.8.1.2,
5.8.1.3
[IN3]1
Roof insulation installed per
manufacturer’s instructions.
Blown or poured loose-fill
insulation is installed only where
the ceiling slope is <= 3:12.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.5.3.1.1
[IN5]3
High-albedo roofs meet solar
reflectance of 0.70 and thermal
emittance of 0.75 or SRI of 82.
SR:_____
SRI:_____
SR:_____
SRI:_____
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.5.3.2
[IN6]1
Above-grade wall insulation R-
value.
R-_____
Mass
Metal
Steel
Wood
R-_____
Mass
Metal
Steel
Wood
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
5.8.1.2
[IN7]1
Above-grade wall insulation
installed per manufacturer’s
instructions.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.5.3.4
[IN8]1
Floor insulation R-value.R-_____
Mass
Steel
Wood
R-_____
Mass
Steel
Wood
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
5.8.1.1
[IN10]2
Building envelope insulation is
labeled with R-value or insulation
certificate providing R-value and
other relevant data.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.8.1.4
[IN11]2
Eaves are baffled to deflect air to
above the insulation.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.8.1.5
[IN12]2
Insulation is installed in
substantial contact with the
inside surface separating
conditioned space from
unconditional space.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.8.1.6
[IN13]2
Recessed equipment installed in
building envelope assemblies
does not compress the adjacent
insulation.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
THE AVENUE AT BENNETT FARM
\\cai-dc\projects\200275 JDF Development Michigan Road III\DOCS\COMCHECK ENVELOPE.cck
02/25/21Report date:
96 ofPage
Section
#
& Req.ID
Insulation Inspection Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
5.8.1.7
[IN14]2
Exterior insulation is protected
from damage with a protective
material. Verification for exposed
foundation insulation may need
to occur during Foundation
Inspection.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.8.1.7.1
[IN15]2
Attics and mechanical rooms
have insulation protected where
adjacent to attic or equipment
access.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.8.1.7.2
[IN16]2
Foundation vents do not interfere
with insulation.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
5.8.1.8
[IN17]3
Insulation intended to meet the
roof insulation requirements
cannot be installed on top of a
suspended ceiling. Mark this
requirement compliant if
insulation is installed accordingly.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
THE AVENUE AT BENNETT FARM
\\cai-dc\projects\200275 JDF Development Michigan Road III\DOCS\COMCHECK ENVELOPE.cck
02/25/21Report date:
97 ofPage
Section
#
& Req.ID
Final Inspection Complies?Comments/Assumptions
5.4.3.3
[FI1]1
Weatherseals installed on all loading
dock cargo doors in Climate Zones 4-
8.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
THE AVENUE AT BENNETT FARM
\\cai-dc\projects\200275 JDF Development Michigan Road III\DOCS\COMCHECK ENVELOPE.cck
02/25/21Report date:
98 ofPage
Project Title:
Data filename:
THE AVENUE AT BENNETT FARM
\\cai-dc\projects\200275 JDF Development Michigan Road III\DOCS\COMCHECK ENVELOPE.cck
02/25/21Report date:
99 ofPage