General
Construction operations shall be carried out in such a manner and sequence that erosion and water pollution will be
minimized and held within acceptable limits. The completed project shall present a workmanlike appearance and
conform to the line, grade and cross section of the project plans. All trees, stumps, brush and similar materials are to be
removed from the site or disposed of in such a way as to have the least detrimental effect on the environment.
Vegetative Establishment
Vegetation will be established on all disturbed areas. Disturbed areas are to be seeded as soon as possible and as
described in the construction sequence on this Sheet.
Maintenance
All seeded lawns shall be maintained for 60 days following final inspection by landscape architect after written request from the contractor.
Maintenance to include watering, weeding, cultivating, mulching, mowing and all other necessary operations required for proper establishment
of lawns.
Seeding
Topsoil shall be de-compacted to a depth of 6 inches and prepared in order to ensure a sufficient planting medium. Select a seed mixture based
on the specifications for permanent seed. Apply 9 pounds of 12-0-12 fertilizer per 1000 sq. ft. in lawn filter strip area ONLY. Do not apply
fertilizer in areas to receive Native Seed. Seed shall be applied with mechanical spreader or seed drill at rates specified per acre. Apply seed 1/2
one direction and 1/2 perpendicular to the first. Lightly rake and roll with 200 lb. roller. Apply hydromulch, straw mulch or erosion control
blanket as specified on plans.
Mulch
Unless otherwise specified, erosion control blanket shall be installed as specified on the plans.
Wood Fiber Hydromulcher: If approved by City Engineer, wood fiber hydromulch may be applied. Apply wood fiber at at rate of 1 ton/acre.
Apply with a hydromulcher with tacking agent used according to manufacturer's recommendations.
Maintenance
All seeded lawns shall be maintained for 60 days following final inspection by landscape architect after written request from the contractor.
Maintenance to include watering, weeding, cultivating, mulching, mowing and all other necessary operations required for proper establishment
of lawns.
Ô
Ô
SEED MIXTURES RATE PER ACRE PURE LIVE SEED OPTIMUM SOIL PH
1. PERENNIAL RYEGRASS
- WHITE CLOVER
70 LBS.
2 LBS.5.6 TO 7.0
2. PERENNIAL RYEGRASS
- TALL FESCUE
70 LBS.
50 LBS.5.6 TO 7.0
3. TALL FESCUE
- WHITE CLOVER
70 LBS.
2 LBS.5.5 TO 7.5
OPEN LOW-MAINTENANCE AREAS (REMAINING IDLE MORE THAN SIX MONTHS)