HomeMy WebLinkAboutGN010.0#1
of
11
Date:
4.14.21
Sheet:
Revision:
www.caseindy.com
99 E. Carmel Drive, Suite 100
Carmel, Indiana 46032
317.846.2600 317.846.2601(f)
These drawings have been
prepared by Case Design &
Remodeling solely for its use and
should not be reproduced or relied
upon by any other parties.
Dimensions shown or scaled are
subject to change per actual job
condition and must be verified.
Materials are to be supplied as
specified as equal or standard
when not uniquely specified.
Installed materials may vary in
appearance from drawings.
Reference manufacturer's product
data for actual appearance and
specifications.
Woods Residence
Chip and Barb
12492 Brookshire Pkwy
Carmel, Indiana 46033
Approved By:
Date:
Dawn Ashburn
Lead Designer
dashburn@caseindy.com
G002
CONTRACT
Maggie Smith
Designer
msmith@caseindy.com
GENERAL / CONSTRUCTION NOTES
DDEEMMOOLLIITTIIOONN NNOOTTEESS PPLLUUMMBBIINNGG NNOOTTEESS
RELOCATE WATER LINES FOR NEW REFRIGERATOR LOCATION
RELOCATE WATER LINES FOR NEW SINK/FAUCET; INSTALL NEW APRON FRONT SINK
AND FAUCET WITH GARBAGE DISPOSAL
RELOCATE WATER LINES FOR NEW DISHWASHER LOCATION
ASSUMING NO MAJOR PLUMBING IN WALLS BEING REMOVED
EELLEECCTTRRIICC NNOOTTEESS
FURNISH AND INSTALL (10) NEW LED RECESSED CAN LIGHTS IN KITCHEN ON 3 WAY DIMMER SWITCHING
FURNISH AND INSTALL (4) NEW LED RECESSED CAN LIGHTS ON 1 NEW DIMMER SWITCH AT FRONT DOOR
INSTALL (3) NEW PENDANT LIGHTS ON 3WAY DIMMER SWITCHING; LIGHT BY H.O.
FURNISH AND INSTALL 2) NEW LED RECESSED CAN LIGHTS LEFT OF DINING AREA ON 1 NEW DIMMER SWITCH
INSTALL (1) NEW DINING LIGHT ON 1 NEW DIMMER SWITCH; LIGHT BY H.O.
FURNISH AND INSTALL (5) NEW GFCI OUTLETS IN BACKSPLASH AREA
FURNISH AND INSTALL (2) NEW OUTLETS AT EACH END OF ISLAND
FURNISH AND INSTALL (2) NEW WALL OUTLETS
FURNISH AND INSTALL NEW GARBAGE DISPOSAL SWITCH AT NEW SINK LOCATION
INSTALL (2) NEW WALL MOUNT LIGHTS OVER SINK WINDOW ON 1 NEW DIMMER SWITCH; LIGHT BY H.O.
FURNISH AND INSTALL LED TAPE LIGHT ON BACK OF (3) GLASS CABINET RAILS ON UTILITY CABINETS
FURNISH AND INSTALL LED TAPE LIGHT FOR UNDER CABINET LIGHTING ON 1 NEW DIMMER SWITCH
FURNISH AND INSTALL NEW OUTLET FOR NEW RANGE HOOD
RELOCATE POWER FOR NEW REFRIGERATOR
RELOCATE POWER FOR DOUBLE OVENS
RELOCATE POWER FOR NEW RANGE
RELOCATE POWER RELOCATE POWER FOR DISHWASHER
INSTALL NEW DEDICATED CIRCUIT FOR MICROWAVE DRAWER IN ISLAND
FLOORING TO REMAIN
REMOVE AND HAUL KITCHEN CABINETS, COUNTERTOPS, AND BACKSPLASH
REMOVE AND HAUL SINK/FAUCET AND DISHWASHER
REMOVE AND HAUL COOKTOP
REMOVE AND RELOCATE REFRIGERATOR FOR TEMPORARY USE
REMOVE AND SALVAGE DOUBLE OVENS FOR REINSTALLATION
REMOVE AND HAUL WINDOW AND TRIMS AT KITCHEN CABINETS; DEMO BACK BRICK ON EXTERIOR
REMOVE AND HAUL WINDOW AND TRIMS IN EXISTING DINING ROOM
DEMO WALL BETWEEN DINING AND FRONT LIVING ROOM
DEMO WALL BETWEEN DINING AND KITCHEN
REMOVE AND HAUL DINING LIGHT
REMOVE AND HAUL EXISTING KITCHEN CEILING LIGHT FIXTURES AND TABLE LIGHT
TERMINATE AND RELOCATE HVAC SUPPLIES IN DINING/FRONT LIVING ROOM WALL; TO TIE INTO OTHER EXISTING
SUPPLY
TERMINATE AND RELOCATE BASEBOARD REGISTERS ON EXISTING EXTERIOR DINING ROOM WALL AT WINDOWS; TO
BE RELOCATED
INSTALL NEW 3-PLY 10" HIGH STRUCTURAL BEAM WHERE DINING/FRONT LIVING ROOM WALL WAS REMOVED;
DRYWALL WRAP
FRAME IN AND INSULATE WHERE EXISTING DINING ROOM WINDOW IS TO BE SHORTENED; INSTALL EXTERIOR TRIM
TO MATCH OTHER EXISTING WINDOWS ON BACK SIDE OF HOUSE WITH CEDAR FRAME AND SIDING BELOW;
REMOVE BRICK FOR NEW WINDOW WHERE SMALLER KITCHEN WINDOW WAS REMOVED; FRAME FOR NEW ROUGH
OPENING OF 60.25X56.5"; INSTALL H.O. PROVIDED WINDOW MAINTAIN EXISTING LEFT SIDE OF WINDOW OPENING;
INSTALL H.O. PROVIDED WINDOW AND MATCH EXTERIOR TRIM TO OTHER WINDOWS ON BACK SIDE WITH CEDAR
FRAME
FIELD VERIFY FRAMING OF NEW POCKET DOOR TO FRONT HALLWAY FROM NEW DINING AREA; ASSUMING NO
PLUMBING/MAJOR HVAC IN WAY OF FRAMING FOR POCKET DOOR
FRAME NEW PARTIAL KNEE WALL FOR HIDDEN ISLAND SUPPORT
RELOCATE FLOOR REGISTER TO RIGHT OF REFRIGERATOR; VERIFY FINAL LOCATION/SIZE IN THE FIELD
INCREASE SIZE OF REGISTER IN DINING AREA TO ACCOMMODATE REMOVAL OF SUPPLY IN DINING WALL THAT IS
REMOVED
PATCH AND REPAIR DRYWALL WALLS AND CEILING FROM DEMOLITION AND REMOVAL OF WALLS, CEILING LIGHT
FIXTURES AND NEW WINDOW WORK
FURNISH AND INSTALL NEW CABINETRY PER PLANS AND CABINETRY HARDWARE; ACCESSORIES INCLUDED IN
CABINETS
VENT NEW EXHAUST HOOD TO EXTERIOR WITH EXTERIOR WALL DAMPER
VENT EXISTING WALL BASE VENTS THROUGH TOE KICK
FURNISH AND INSTALL NEW CAMBRIA COUNTERTOPS; INCLUDES 4CM ISLAND COUNTERTOP EDGE AND STANDARD
3CM FOR PERIMETER; INCLUDES BACKSPLASH AT RANGE
FURNISH AND INSTALL NEW 3X9 GLASS SUBWAY ON HORIZONTAL BRICK LAY
FOR BACKSPLASH; INCLUDES AROUND WINDOW TO CEILING; NO TRIM NEEDED
FURNISH AND INSTALL NEW 2PC CROWN TO MATCH EXISTING TO TIE INTO EXISTING AND FOR NEW CABINETRY
FURNISH AND INSTALL NEW BASE/SHOE TO MATCH THROUGHOUT NEW DINING/KITCHEN/LIVING ROOM SPACE
INSTALL NEW POCKET DOOR AND FRAMING WITH NEW JAMB/CASING TO MATCH EXISTING
PPRROOPPOOSSEEDD NNOOTTEESS
#2 4.22.21
#3 4.29.21
SSUUGGGGEESSTTEEDD PPAAIINNTT SSCCOOPPEE:: BBYY HH..OO..
PAINT WALLS IN NEW DINING AREA, NEW KITCHEN, AND FRONT LIVING ROOM
PAINT CEILINGS IN NEW DINING AREA, NEW KITCHEN, AND FRONT LIVING ROOM
PAINT 2PC CROWN MOLDING IN NEW DINING AREA, KITCHEN, AND FRONT LIVING ROOM
STAIN NEW 2PC MOLDING AT HOOD TO MATCH CABINETRY
PAINT BASE/SHOE THROUGHOUT NEW DINING AREA, NEW KITCHEN, AND FRONT LIVING ROOM
PAINT NEW 36" POCK DOOR BOTH SIDES AND NEW CASING/JAMB BOTH SIDES
PAINT INTERIOR CASING FOR 64X36 WINDOW; INCLUDE EXTERIOR 1X8 CASING AND APPROX 36" X 64" OF
SIDING TO FILL WHERE WINDOW WAS REDUCED
PAINT INTERIOR CASING FOR 58X54" WINDOW; INCLUDE EXTERIOR 1X8 CASING
06/03/21