HomeMy WebLinkAboutChange_Order__1_-_Morphey_Construction_Crooked_Stick_Lane; ; ($70,786.60); 17-SW-09 - Crooked Stick Lane and The Proscenium, Additional Milling and Paving; CO #1; Engineering DocuSign Envelope ID:3F7134DD-64D7-4618-9E6C-F127E196348B City of Carmel Project Bundle : 1st St. NW (18-21 ) APPROVED 2nd St. SW ( 17-SW-09), Crooked Stick Lane ( 17-SW-09) Change Order #1 —Crooked Stick lane Additional paving Change Order#1 is for repaving from the southern construction limit to the intersection of Burning Tree Lane. Contract Price prior to this Change Order $ 770,800.00 Contract Price will! be increased/decreased by this Change Order $ 70,786.60 New Contract Price including this Change Order $ 841,586.60 Cumulative % Adjusted Contract Amount Change from Price Original Contract Original Contract $ 770,800.00 $ 770,800.00 N/A CO#1 —Additional asphalt milling and $70,786.60 $ 841,586,60 9.2% paving DocuSign Envelope ID:3F7134DD-64D7-4618-9E6C-F127E196348B CITY OF CARMEL TO: CONTRACT CHANGE ORDER NO.:1 DATE:5/13/2°21 PROJECT NAME:17-SW-09 CITY REQ. NO.:N/A CITY PO NO.:104491 CITY PO DATE: 12/4/2020 I. You are directed to make the following changes in this Contract: (Brief Description) SCHEDULED ADJUSTMENT ITEM AMOUNT (-0 OR(-) DAYS II. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: R.F.P.: W.D.C. No.: WA Other:See attached proposal The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $770,800 0 Contract Price will be increased/decreased by this Change Order $70,786,60 New Contract Price including this Change Order $841,586 60 Contract Time Prior to this Change Order N/A Days N/A Completion Date Net increased/decreased resulting from this Change Order° Days Current Contract Time including this Change Order N/A Days WA Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are The Above Changes Are Approved: Recommended Accepted: City of Carmel Morphey Construction jamAGS brattutri, ENGINEER CONTRACTOR talinard, Mayor 1 Civic Square 1499 N Sherman Drive ilvuvi,build Address Address MWAYrifflbrke,Member I on Ulm, 'LOVP'Wattbn, Member Carmel,IN 46033 Indianapolis,IN 46201 City/State/Zip City/State/Zip ere y Kashman, PE, City Engineer 7i7et By: , By: SteVen.p. Mitivurne. ATTEST: Jarr.•Huff Steven P. Milbourne Phone:317-571-2441 Phone: 317-i5b-9253 coAc 3-0 ‘SiieWONana, Clerk Date:5/13/2021 Date: 5/18/21 Date: 6/1°/2u21 000uoign Envelope ID:nFr1a400-64o7-4s1ousnc'F12rE1s6o4oB ImDI8NA DEPARTMENT OF zxnNSr0Krn?InN PAGE: l SCHEDULE OF PAY ITEMS REVISED: LETTING DATo: 3/3I/21 CONTRACT TD: PROJECT (S) : Crooked Stick Mill a Pane REvI CONTRACTOR: Mozphey Construction, Inc. +--__ ______ + (LTNO | ITEM | APPROX, | UNIT PRICE | BID AMOUNT | | NO | DESCRIPTION | QUANTITY >---------------- | --------------- | | | | AND UNITS | DOLLARS | CTS | DOLLARS |CTS | + ------ + | | | | / | | | | 37 |Mobilizatioo Add. eanim | 1.000 | 4, I81. 00 | 4, I6I. 00 | | |0/Milliog |CA | | | | | '______ --------- -------- ____-______+ | 38 |Iacb | 1.200 | 1, 608.00 | 1, 929. 60 | | | |7N | | | | | +__ + / | | | | | | | | 3919. 5 mm Surface | 400.000 | 100. 00 | 40, 000. 00 | | | |TN | | | | | + _ ____ _______ _ ____+ | | | | | | | | | 40|Milling 3" / 4, 800.000 | 4. 52 21, 696.80 | | | [8Y h | | | | ------------------- _-_ + | | | | | | | | � 41 |Add. MOT | 1.000 | 3, 0&0.08 | 3, 000. 00 | | | |LS | | | | | + _ + | | | | | � | | | | | ----------- + | ] � TOTAL | 70, 786. 60 | � | | | | | | ----------- --------------- + I . Milling limited to removal of all road materials, but sand blasting of curb not included if necessary. 2 . Call Steve Milbourue if there are any goeatiwoa - 317-716-6719.