HomeMy WebLinkAboutRitcher 005 Elec 3 Line Diagram(E)
LOADS
N
G
SUPPLY SIDE CONNECTION
PER NEC 230.46, NEC 230.79(D),
NEC 705.12(A)
N
L2
L1
(E)200A / 2P
L2
L1
(E)200A MAIN SERVICE PANEL
(E)200A / 2P MAIN BREAKER
15
(E) GROUNDING
ELECTRODE(S)
INTERCONNECTION NOTES
1. SUPPLY SIDE INTERCONNECTION ACCORDING TO [NEC705.12(A)].
2. SUPPLY SIDE PV DISCONNECT SHALL BE LISTED AS SUITABLE FOR USE AS
SERVICE EQUIPMENT [NEC 690.13(C)]
3. SUPPLY SIDE PV DISCONNECT IS GROUNDED AND BONDED AS A SERVICE WITH A
SEPARATE SUPPLY SIDE BONDING JUMPER SIZED PER [NEC 250.102(C)(1)] TO
CONNECT TO THE EXISTING RESIDENCE GROUNDING ELECTRODE SYSTEM BY A
NEW GROUNDING ELECTRODE CONDUCTOR SIZED PER [NEC 250.66]. THE EXISTING
GROUNDING ELECTRODE SYSTEM TO COMPLY WITH [NEC 250 III]. [NEC 690.47].
DISCONNECT NOTES
1. DISCONNECTING SWITCHES SHALL BE WIRED SUCH THAT WHEN THE SWITCH IS
OPENED THE CONDUCTORS REMAINING LIVE ARE CONNECTED TO THE
TERMINALS MARKED “LINE SIDE” (TYPICALLY THE UPPER TERMINALS)
2. AC DISCONNECT MUST BE ACCESSIBLE TO QUALIFIED UTILITY PERSONNEL, BE
LOCKABLE, AND BE A VISIBLE-BREAK SWITCH
N
EGC
80A
FUSES
CLASS R
PV AC DISCONNECT
FUSED, 100kAIC - R
LOCKABLE, VISIBLE OPEN
SERVICE RATED
100A, 240V, 2-POLE
16
GEC
(N) 6 AWG COPPER, SOLID (GEC)
TO BE IRREVERSIBLY SPLICED
TO (E) GEC TO COMPLY WITH
NEC 250.64(D)(1)
120/240 VAC
60HZ
1 PHASE
TO UTILITY
GRID
(E)
L1
N
L2
N
G
L2
L1
(N)20A/2P
2 1
L1
L2
G
(1) CIRCUIT
OF 13 MODULES
2 1
L1
L2
G
(1) CIRCUIT
OF 12 MODULES
(N)20A/2P
L2
L1
L2
L1
(N)20A/2P
2 1
L1
L2
G
(1) CIRCUIT
OF 12 MODULES
L1
L2
G
L1
L2
G
L1
L2
G
G
L2
L1
(N)20A/2P
2 1
L1
L2
G
(1) CIRCUIT
OF 12 MODULESL1
L2
G
3
G
G
G
G
G
JUNCTION BOX
JUNCTION BOX
JUNCTION BOX
JUNCTION BOX
+ -+ -++--++--
+ -+ -++--++--
+ -+ -++--++--
+ -+ -++--++--
(49) JinKO Solar Eagle JKM375M-6RL3-B
UL 1703 COMPLIANT
(49) Enphase Energy IQ7PLUS-72-2-US MICRO
INVERTERS
UL 1741 COMPLIANT
12 MODULES MAX FOR ALL SUB-BRANCH
CIRCUIT(S) TO COMPLY WITH VRISE CALCSEnphase IQ Combiner 3
X-IQ-AM1-240-3
(SOLAR LOADS ONLY)
JUNCTION BOX
(OPTIONAL IF UF-B
CABLE USED FOR
ENTIRE HOMERUN)
DATE
DRAWING BY
PROJECT NUMBER
SHEET NAME
PAGE NUMBER REVISION
CONFIDENTIAL - THE INFORMATION
HEREIN CONTAINED SHALL NOT BE
USED FOR THE BENEFIT OF
ANYONE EXCEPT
BLUERAVENSOLAR NOR SHALL IT
BE DISCLOSED IN WHOLE OR IN
PART TO OTHERS OUTSIDE
RECIPIENTS ORGANIZATION,
EXCEPT IN CONNEC TION WITH THE
SALE AND USE OF THE RESPECTIVE
EQUIPMENT, WITHOUT THE
WRITTEN PERMISSION OF
BLUERAVENSOLAR LLC.
ENPHASE ENERGY
362648
June 4, 2021SITE INFORMATION:Sara Elizabeth Richter13956 Four Seasons WayCarmel, Indiana 46074DC SYSTEM SIZE: 18.375 kW DCCONTRACTOR:
BRS FIELD OPS
385.498.6700
PV INSTALLATION
PROFESSIONAL
Scott Gurney
# PV-011719-015866
NABCEP
CERTIFIED
PV5
ELEC. 3 LINE DIAG.
0
1403 N RESEARCH WAY, BUILDING J
OREM, UT 84097
800-377-4480
WWW.BLUERAVENSOLAR.COM
49 INVERTERS x 290.4 W AC = 14.23 kW AC
PANEL WATTAGE = 375 W DC
Utility Company: Duke Energy IN Permit Issuer: City of Carmel
07/27/21