HomeMy WebLinkAboutCC-10-18-99-01 Hazel Dell PaymtResolution No. CC- 10-18 -99-0 1
A RESOLUTION OF THE COMMON COUNCIL OF THE CITY OF CARMEL,
INDIANA APPROVING PAYMENT OF CONSTRUCTION COSTS FOR HAZEL
DELL PARKWAY
WHEREAS, pursuant to Article III, Section 3.01 (b) of the Trust Indenture by and
among the City of Carmel Redevelopment Authority and Fifth Third Bank of Central
Indiana, dated as of August 1, 1997, approval by the Common Council is required prior to
payments from the Construction Fund therein described upon presentation of architect' s
or engineer' s certificates of work completed and materials furnished;
WHEREAS, American Consulting Engineers, Inc., has presented such certificates
regarding the Construction Project Invoices attached hereto as Exhibit A.
NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of
Carmel, Indiana, that the Construction Project Invoices attached hereto as Exhibit A are
hereby approved for payment from the Construction Fund described in the above-
referenced Trust Indenture.
nays.
day
nald E. Carter
Presented ~~e Mayor of the City of Carmel, Indiana the
,1999.
day of
Diana L. Cordray, IAMC, - r
rainard, Mayor
ATTEST:
Diana L. Cordray, IAMC~,Cl~~reasurer
EXHIBIT A
PAYMENT REQUISITION NO. 65
PAYEE
CHARACTER OF EXPENDITURE
Milestone Contractors
PO Box 66008
5950 S. Belmont Ave...
Indianapolis, IN 46266-6008
2. Sundown Gardens
13400 Old Meridian St.
Carmel, IN 46032
$29,976.57
$38,472.99
Construction cost in connection
with Hazel Dell Parkway.
Landscaping costs accrued in
association with Hazel Dell.
10/04/99
CONSTRUCTION PROIBCT INVOICE
Dar~.'
NamsofCompany:
Telephone No.;
Fctx No,:
Milestone Contractors LP
Milestone Contractors LP
P.O. B6x 66008
5950 S. Belmont Ave.
Indian.polls, IN 46266-6008
(31 '7). - 788-1040
(3 17)- 788-1098
Project Name: Hazel Dell Parkway
Invoicc No.: 035
Conmuction pay items as per PROGRESS ESTIMATE #035 as shown on rile attached invoice dated
10/1/99.
Submitted by American Consulting Engineers, Inc.
~roject Representative
Print Nmne
ProjectName: HAZ!~.I. DELL PARKWAY
Pro. i~ctNo.: 97-02
{nvoics No.: 035
Period: 9/1/99 Thru 9/30/99
ROAD ......................................................................
STRUCTURE NO. 1 (Blue Woo~ Creek Bride) .................................
STRUCTURE NO. ! (Cool Creek Bridge) ........................................
STRUCTURE NO. 3 (Mitchener Ditch) .........................................
29,976.57
0.00
0.00
0.00
BILLING THIS ESTIMATE
LESS RETAINAGE PROGRESS ESTIMATE
DUE THIS ESTIMATE
$ 29,976.57
0.00
$ 29,976.57
DATE: 10/01/99
CONTRACT: -97525
ESTIMATE: 035
PROJECT: ROAD
PERIOD: 9/01/99
PO
LETTING:
THRU 9/30/99
CITY OF CARMEL
PROGRESS ESTIMATE
CONTRACTOR
MILESTONE CONTRACTORS, L.P.
Page
DAN GRESKAMP
AMERICAN CONSULTING ENGINEERS, INC.
4165 MILLERSVILLE RD.
INDPLS., IN
ITEM ITEMS OF CONTRACT QUANTITY UNIT UNIT PRICE EXTENSION
0009 T.E.S.C., CURB INLET PROTECTION 9.0000 EACH 30.96000 278.64
0012 COMP. AGG. FOR BASE, O, SIZE NO. 53 2!.3500 TON I].01000 277.76
0013 COMP. AGG. ?OR SHLD., O, SIZE N0.53 106.5100 TON 16.99000 1,809.94
0023 BITUMINOUS MATERIAL FOR TACK COAT .6900 TON 142.05000 98.01
0034 GEOTEXTILES 16.2000 SYS 2.09000 33.86
0035 RIPRAP 19.5500 TON I9.87000 388.46
0037 MOBILIZATION AND DEMOB. FOR SEEDING 2.0000 EACH 541.88000 1,083.76
0038 MULCHED SEEDING, R 22,93].0000 SYS .36000 8,225.88
0039 SODDING 2,800.0000 SYS 2.43000 6,804.00
0041 RETAINING WALL, MODULAR BLOCK 5.6000 SFT 24.29000 !36.02
0044 PIPE, REINFORCED CONCRETE, 18 IN. -3.0000 LFT 22.60000 (67.80)
0060 PIPE END SECTION, 12 IN. 2.0000 EACH 167.26000 334.52
0088 ROAD CLOSURE SIGN ASSEMBLY 3.0000 EACH 928.95000 2,786.85
0090 BARRICADE, IIIB 1.0000 EACH 335.45000 335.45
0091 DETOUR ROUTE MARKER ASSEMBLY -2.0000 EACH 144.50000 (289.00]
0134 LINE, PAINT, SOLID, WHITE, 4 IN. 2,555.0000 LFT .~5000 127.75
0136 TRANSVERSE MARKINGS, THERMOPLASTIC, 164.0000 LFT 3.I~000 508.40
STOP LINE, 24 IN.
0138 TRANSVERSE MARKINGS, THERMOPLASTIC, 845.2000 LFT .83~00 7~i.52
CROSSWALK LINE, 6 IN.
0139 PAVEMENT MESSAGE MARKINGS, 27.0000 EACH 46.45000 !,254.15
THERMOPLASTIC, LANE INDICATION
ARROW
0140 PAVEMENT MESSAGE MARKINGS, 24.000-9 EACH 56.77000 1,362.48
THERMOPLASTIC, WORD (ONLY)
0282 THERMOPLASTIC, SOLID, WHITE, 4 IN. 4,129.~00 LFT .39000 1,610.31
DATE:
CONTRACT: -97525
ESTIMATE:
PROJECT: ROAD
PERIOD: 9/~1/99
PO NO.:
LETTING: 8/~6/97
THRU 9/3~/99
CITY OF CARMEL
PROGRESS ESTIMATE
CONTRACTOR
MILESTONE CONTRACTORS, L.P.
Page 2
DAN GRESKAMP
AMERICAN CONSULTING ENGINEERS, INC.
4165 MILLERSVILLE RD.
INDPLS., IN
ITEM ITEMS OF CONTRACT QUANTITY UNIT UNIT PRICE EXTENSION
0283 THERMOPLASTIC, BROKEN, WHITE, 4 IN. 639.oeoe LFT .39900 245.7~
~284 THERMOPLASTIC, SOLID, YELLOW, 4 IN. 3,553.~ LFT .39~ 1,385.67
~]03 LINE, THERMOPLKSTIC, YELLOW, i2 IN. i~8.~ LFT 1.65~ 178.20
~315 CONCRETE CURB, MODIFIED
29,976.57
DATE: I0/~I/99 CITY OF CARMEL
CONTRACT: '97525 PROGRESS ESTIMATE
ESTIMATE:
PROJECT: ROAD
PERIOD: 9/~1/99 THRU 9/30/99 CONTRACTOR
PO NO.: MILESTONE CONTRACTORS, L.P.
LETTING: 8/06/97
Page 3
DAN GRESKAMP
AMERICAN CONSULTING ENGINEERS, INC.
4165 MILLERSVILLE RD.
INDPLS., IN
ITEM ITEMS OF CONTRACT QUANTITY UNIT UNIT PRICE EXTENSION
LIQUIDATED DAMAGES OTHER DEDUCTIONS
PURSUANT TO '~ VISION ND PENALTIES OF IC 1971 5-i!-10 I HEREBY CERTIFY THAT THE FOREGOING ACCOUNT IS JUST AND CORRECT, T~{AT
T' A~ ~ T ~ ~ . , T~. A L ' JG ALL JUST CREDITS, AND T~AT NO PART OF T~E SAME ~AS BEEN PAID.
-
PER PLANS, SPECIFICATIONS, AND/OR SPECIAL PROVISIONS, THE FOLLOWING CONDITIONS APPLY ON THIS ESTIMATE. ERECTION OF BARRICADES
YES NO , ERECTION OF DETOUR SIGNS YES NO , CURING OF CONCRETE YES NO , MAINTENANCE OF TEMPORARY RUNAROUNDS YES NO ,
PREPARATION OF PAYROLLS YES NO , BASED ON FOREGOING CONDITIONS THIS ESTIMATE (SHOULD)(SHOULD NOT) BE DELAYED.
PROJECT ENGINEER"' ~
DATE
DISTRICT DATE
OPERATIONS SUPPORT DATE
A'MERICAN CONSULTING ENGINEERS, INC.
ARC H ITECTS ENGINEERS
4165 MILLERSVILLE ROAD INDIANAPOLIS, INDIANA 46205-2998
317.547.5580 FAX 317.543.0270
TELECOPIER COVER LETTER
Please deliver the followlAg pages immediately to:
Name:
Company:
From:
A.C.E. Project No.:
Dc~te:
Fax number called:
Total number of pages, including cover letter:
Telecopier operator for this transmission:
IF YOU DO NOT RECEIVE ALL OF THE PAGES, PLEASE CALL US BACK AS SOON AS POSSIBLE,
USING THE TELEPHONE NUMBER LISTED ABOVE.
kNL F-A/5
#
CONSTRUCTION PROJECT INVOICE
Dat~: 10/4/99
Name of Company:
Addrsss & Zip:
Sundown Gardens
Sundown Crardens, Inc.
13400 Old Merdian St.
Carmel,'IN 46032
ral~phon~ No.: (317) - 846-0620
Project Name: Hazel Dell Park'way 1 ,andsgaping
Invoice No.: 015
Construction pay items as per PROGRESS ESTIMATE #015 as shown on the attached invoice dated
10/4/99
SubmiRed by American Consulting Engineers, Inc.
Kesiden~ect~ tativ~
Prim Name
Project Name: HA73~.L Dg.l .l . PARKWAY LANDSCAPING
Project No.: 97-08
[nvo~ce No,: 015
Period: 9/1/99 Thru 9/30/99
LANDSCAPE .............................................................. $ 42,747.77
BILLING THIS ESTIMATE
LESS RETAINAGE PROGRESS ESTIMATE
DUE THIS ESTIMATE
$ 42,747.77
4-~74.78
$ 38,472.99
DATE: 1~/~4/99 CITY OF CARMEL
CONTRACT: -97526 PROGRESS ESTIMATE
ESTIMATE: ~15
PROJECT: LANDSCAPE
PERIOD: 9/~1/99 THRU 9/3~/99 CONTRACTOR
PO NO.: SUNDOWN GARDENS
LETTING: 12/17/97
Page
DAN GRESEAMP
AMERICAN CONSULTING ENGINEERS, INC.
4165 MILLERSVILLE RD.
INDPLS., IN
ITEM ITEMS OF CONTRACT QUANTITY UNIT UNIT PRICE EXTENSION
0~8 FRAXINUS PENNSYLVANICA 'URBANITE' 4.~ EACH 346.21~ 1,384.84
~11 ACER SACCHARUM 'GREEN MOUNTAIN' [~.~e~ EACH 374.51~ 3,745.1~
eel7 LIQUIDAMBAR STYRACIFLUA 1.eeee EACH 383.1eee~ 383.1e
ee23 AMELANCHIER X GRANDI. le.eeee EACH 3e6.59eee 3,e65.ge
'AUTUMN BRILLIANCE'
ee24 MALUS 'PRAIRIFIRE' ].eeee EACH 289.61eee 868.83
~e42 SUPPLEMENTAL WATERINGS 5ee,eee.eeee GAL .e666e ]],]ee.ee
DATE: i~/04/99 CITY OF CARMEL
CONTRACT: -97526 PROGRESS ESTIMATE
ESTIMATE: 015
PROJECT: LANDSCAPE
PERIOD: 91~1199 TERU 9/3e/99 CONTRACTOR
PO NO.: SUNDOWN GARDENS
LETTING: 12/17/97
Page 2
DAN GRESKAMP
AMERICAN CONSULTING ENGINEERS, INC.
4165 MILLERSVILLE RD.
INDPLS., IN
ITEM ITEMS OF CONTRACT QUANTITY UNIT UNIT PRICE EXTENSION
42,747.77
LIQUIDATED DAMAGES
OTHER DEDUCTIONS
PURSUANT TO THE PROVISION AND PENALTIES OF IC 1971 5-11-10 I HEREBY CERTIFY THAT THE ?OREGOING ACCOUNT IS JUST AND CORRECT, THAT
THE AMOUNT CLAIMED IS LEGALLY DUE, AFTER ALLOWING ALL JUST CREDITS, AND THAT NO PART OF THE SAME HAS BEEN PAID.
CONTRACTOR DATE
PER PLANS, SPECIFICATIONS, AND/OR SPECIAL PROVISIONS, THE FOLLOWING CONDITIONS APPLY ON THIS ESTIMATE. ERECTION OF BARRICADES
YES NO , ERECTION OF DETOUR SIGNS YES NO , CURING OF CONCRETE YES NO , MAINTENANCE OF TEMPORARY RUNAROUNDS YES NO ,
PREPARATION OF PAYROLLS YES NO , BASED ON FOREGOING CONDITIONS THIS ESTIMATE (SHOULD) ~HOULD NOT] BE DELAYED.
PROJECT ENGINEER
DATE
DISTRICT DATE
OPERATIONS SUPPORT DATE