Loading...
HomeMy WebLinkAboutNeterer Estimate8/4/2021 Main Basement Estimate https://coconstruct.com/app/shared/Proposal.aspx?propid=258787&it=False&pi=1040977&print=true 1/8 _____________________________________________________ 8847 Commerce Park Place Suite J                                                                        Basement Estimate Indianapolis, IN  46268                                                                                               May 31, 2021                                                                                                                                          Prepared For: Phone # 317-714-6536                                                                                               Mark & Patty Neterer                                                                                                                                         14480 Quail Pointe Drive www.cmhbuilders.com                                                                                               Carmel, IN 46032 _____________________________________________________ 08/09/21 8/4/2021 Main Basement Estimate https://coconstruct.com/app/shared/Proposal.aspx?propid=258787&it=False&pi=1040977&print=true 2/8 Estimate 1000 Building Permits $626.00 Estimated permit cost. $626.00 1100 Framing $6,623.00 Framing labor and material. $6,623.00 Labor and material to complete framing in the basement. --Includes all new walls and bulkheads. --Includes all fasteners, tax, and delivery. --Includes enlarging existing fitness room doorway 1200 Rough In Plumbing $3,940.94 (A) Plumbing rough in. $3,940.94 Labor and material to rough in plumbing for wet bar and bathroom as follows: --All water lines and drains for toilet, vanity and wet bar. --Ejector pump with alert system. --Includes rough-in for surface mounted ejector pump in wet bar. --Additional charges may apply if the existing under slab plumbing needs to be removed, replaced, or repaired. Option for backup sump pumps. Option for backup sump pumps. Option #1 - Select this option for: Water-powered backup sump pumps. +$707.20 Option #2 - Select this option for: Battery powered backup sump pump +$929.58 Option #3 - Select this option for: New primary sump pump with water-powered backup +$1,115.20 Option #4 - Select this option for: New Primary sump pump with battery-powered backup sump pump. +$1,337.58 Client may decline this selection $0.00 1250 Finish Plumbing $1,457.74 (A) Plumbing finish $710.93 Labor and material to finish plumbing for bathroom and wet bar as follows: --Includes all drains, sink strainer and supply lines. --Includes labor to install vanity faucet, toilet, hand towel holder, toilet paper holder, 1/4" frameless mirror, wet bar faucet. --See Budget items below for toilet, faucets, bathroom accessories. 08/09/21 8/4/2021 Main Basement Estimate https://coconstruct.com/app/shared/Proposal.aspx?propid=258787&it=False&pi=1040977&print=true 3/8 --Includes surface mounted ejector pump. --Surface mounted ejector pump to be mounted in wet bar sink base cabinet. (B) Plumbing finish toilets $153.80 Toilet budgets. --Mansfield standard height elongated toilet is included in the estimated total Option #1 - Select this option to: Upgrade to a Mansfield comfort height round toilet. +$43.75 Option #2 - Select this option to: --Upgrade to a Mansfield comfort height elongated toilet. +$56.25 Option #3 - Select this option to remain with the Mansfield standard height elongated toilet as quoted. $0.00 Bathroom fixtures $593.01 Bathroom fixture budget. --Includes vanity faucet, towel ring, toilet paper holder, 1/4" polished edge mirror, wet bar faucet. 1300 HVAC Rough In $794.48 HVAC Labor and Material. $794.48 Labor and material to complete HVAC rough-in as follows: --Includes extending one supply and installing one return. --Includes all final registers and grills. --Includes bathroom exhaust fan/light combo. 1400 Electrical rough in $4,930.62 Electrical Rough-in $4,930.62 Labor and material to complete electrical rough-in. --Estimating 16 can lights, 2 pendant junctions, closet light under stairs and vanity light junction. --Includes moving existing lights into storage and utility areas. --Outlets and switches per code. --Includes 2 TV outlets and one microwave circuit --Includes 1 CO/smoke detector. --Includes electrical sub-panel. --Add an Additional $50.00 per network cable if needed. --Cable and network wiring to run into an unfinished area and to be connected by the service provider. 1450 Electrical Finish $1,819.13 (A) Electrical Finish $1,243.26 Labor and material to complete electrical finish as follows: --Install all LED Can light trim kits. --Install all switches, outlets, and cover plates. 08/09/21 8/4/2021 Main Basement Estimate https://coconstruct.com/app/shared/Proposal.aspx?propid=258787&it=False&pi=1040977&print=true 4/8 --All switches, outlets, and cover plates to match existing as close as possible. --Add Additional $28.00 per dimmer switch. Accent Lighting Budget $450.00 Light fixture budget --Based on 1 vanity light and 2 pendant lights. --Selected with CMH Builders designer during selections appointment. AV Chase. $125.87 Labor and material to install AV chase in media area. --Based on 2 " PVC Chase installed behind TV and terminate below TV. 1500 Insulation $2,205.31 (A) Wall Insulation labor and material. $1,194.43 Labor and material to install R-13 insulation in exterior walls. --Based on sq. ft. of coverage --Includes walls between finished and unfinished areas. Ceiling insulation in new finished area only. $1,010.88 Labor and material to add R-13 insulation to the ceiling of the finished area only 1600 Drywall $5,312.19 Drywall $5,312.19 Labor and material to hang and finish drywall --Includes smooth walls and smooth ceilings. --Walls and ceilings inside utility and unfinished storage area to be free of drywall. --Includes drywall, mud, corner bead, tape, tax, and delivery --Includes repairs to existing drywall on stairs that are damaged during CMH Builders construction. --An additional charge of $50.00 per hour per man plus material charge will apply for additional work needed to repair existing drywall damage. --NOTE: Additional charges may apply if existing drywall needs repairs and/or replaced. 1700 Interior Trim $7,014.54 (A) Interior trim $3,792.54 Labor and material to complete interior trim as follows: --Install 3 hollow core hinged doors and 1 15 lite French Door. --Install baseboards, casing, and door hardware. --All doors, trim, and hardware to match existing as close as possible. Shiplap, Stained $2,358.00 Labor and material to install shiplap on the television media wall. 08/09/21 8/4/2021 Main Basement Estimate https://coconstruct.com/app/shared/Proposal.aspx?propid=258787&it=False&pi=1040977&print=true 5/8 --Based on pre-stained 6" shiplap siding. Workout Mirror $864.00 Labor and Material to install 2 workout mirrors. --Based on 3' x 6' mirror. 1800 Painting $4,215.36 Complete painting package. $4,215.36 Labor and material to complete the painting as follows: --Sand and prime all new drywall. --Textured ceiling to be painted with flat white primer. --Custom color paint on finished walls. --Paint color selected by Homeowners using CMH Builders designer. --Paint color to be ___ --Based on 1 color 2 coats with Sherwin Williams Washable Flat paint. --Walk-in closets to be painted to match walls. --Standard depth closets to be painted flat white. --Additional charges will apply if a darker color is selected and requires more than 2 coats. --Prep and paint all trim and doors. --Includes painting existing door on stair landing. --Based on Sherwin Williams Semi-Gloss White paint. --NOTE: Includes painting walls, ceiling and trim in finished workout room 1900 Flooring $6,180.00 Carpet, Stairs Only $720.00 Labor and material to install carpet on stairs. --Carpet to be _____ --Based on Level 2 carpet with 8 lb. pad. --Includes tack strips, metal transition, tax, and delivery. LVP Flooring $5,460.00 Labor and material to install floating LVP flooring in workout room, game area, wet bar, media area & bath per approved design. --Based on Level 2 floating LVP flooring. --Flooring to be _____ --Includes tax and delivery. --Multiple other options available at CMH Builders Showroom ***Slab conditions to dictate the final cost of flooring labor. Certain slab conditions may increase the cost of flooring labor (i.e. levelness, cracking, and control joints). CMH Builders flooring installer to examine slab prior to installation to determine the final cost of flooring install. 2000 Ceramic/Porcelain Tile $4,076.80 Media Wall Tile $1,488.00 08/09/21 8/4/2021 Main Basement Estimate https://coconstruct.com/app/shared/Proposal.aspx?propid=258787&it=False&pi=1040977&print=true 6/8 Labor and material to install wet bar backsplash. --Based on 2" x 8" brickwork tile installed in a brick pattern. --Includes thin-set, grout, grout caulk, metal trim. tax, and delivery. --Grout color selected by Homeowners using CMH Builders designer. --Grout color to be ___ --Final cost may change if tile pattern, level, and/or square footage changes Wet Bar Backsplash $2,588.80 Labor and material to install wet bar backsplash. --Based on 2" x 8" brickwork tile installed in a brick pattern. --Includes thin-set, grout, grout caulk, metal trim. tax, and delivery. --Grout color selected by Homeowners using CMH Builders designer. --Grout color to be ___ --Final cost may change if tile pattern, level, and/or square footage changes 2100 Cabinets $7,953.60 (A) Wet Bar $7,437.00 Labor and material to install wet bar cabinets. --Based on Shaker white cabinets. --Includes soft close dovetail drawers, soft close doors, plywood box construction. --Includes Level 1 hardware --Includes 4 custom stained floating shelves w/ industrial piping. (B) Vanity Cabinet $516.60 Labor and material to install the vanity cabinet. --Based on 30" white Shaker cabinet --Includes Onyx Granite Gloss countertop with integrated sink. --Countertop to be in color ____ 2200 Countertops $4,920.82 Wet Bar Countertop, Granite $4,920.82 Labor and material to install countertop on the wet bar. --Based on # sq. ft. of level A granite countertop. --Countertop to be _____ --Includes CMH Builders standard stainless steel undermount bar sink. --Final cost is subject to change based on selection and size. 4000 Cleaning $210.00 Cleaning $210.00 Labor to complete final construction cleaning. --Based on wet mop hard surface flooring, vacuuming of carpet, wipe down all cabinets and countertops. 08/09/21 8/4/2021 Main Basement Estimate https://coconstruct.com/app/shared/Proposal.aspx?propid=258787&it=False&pi=1040977&print=true 7/8 6000 Discount ($1,000.00) CMH Builders Promotion ($1,000.00) Discount if the estimate is accepted and deposit paid by close of business on May 28, 2021. --Discount is based on estimate total and is subject to change as estimate total changes. Base Price $61,280.53 08/09/21 8/4/2021 Main Basement Estimate https://coconstruct.com/app/shared/Proposal.aspx?propid=258787&it=False&pi=1040977&print=true 8/8                                                                                                ****Additional Information**** 1. All pricing is based on CMH Builders completing the entire scope of work using CMH Builders Supplier Materials.  Unit pricing may change if portions of the project removed from CMH Builders' scope. 2. CMH Builders offers a 2 year workmanship warranty on all basements, including a 1 time drywall touch up from settling within the first year. 3. Due to potential changes of material costs from suppliers CMH Builders estimates are valid for 30 days. 4. All work completed by CMH Builders will be up to local building codes.  This estimate does not include repairs or code updates required by the municipal inspector in other areas of the home. Any upgrades required by the inspector, outside of CMH Builders' scope of work, will require additional compensation. 5.  Not all items displayed in CMH Builders proved design is included in the estimate above. 6. Estimate includes up to 2 visits at 2 hours each visit to make selections with CMH Builders Designer.  Additional Charges of $85.00 per hour will apply for any time spent past the amount listed.  Mark & Patty Neterer,  "Homeowner"  has been presented with an estimate for basement finish and wishes to contract with CMH Builders Inc. "Contractor" to complete a basement finish project at 14480 Quail Pointe DriveCarmel, IN 46032.  Homeowner agrees to estimate total with the understanding that final selections may increase or decrease the final project cost.   Homeowner to complete all project selections prior to signing Contract with Contractor to determine final pre- construction cost. Contractor to present final contract documents to Homeowner within 5 Business Days of the successful completion of all project selections. The homeowner has been presented and agreed to the basement design completed by the Contractor. The basement design is attached as Exhibit B to this Agreement. Homeowner Agrees to pay an earnest money deposit of $1,000.00 (nonrefundable deposit) when signing this agreement. Homeowner to selected a tentative start date with the understanding that the start date may change based on the date of the successful completion of all project selections. Signatures Client: Mark & Patty Neterer May 31, 2021 Date Builder: Todd Lipking May 31, 2021 Date 08/09/21