HomeMy WebLinkAboutCC-08-07-00-01 Hazel Dell PaymtResolution No. CC-08-07-00-01
A RESOLUTION OF THE COMMON COUNCIL OF THE CITY OF CARMEL,
INDIANA APPROV1NG PAYMENT OF CONSTRUCTION COSTS FOR HAZEL
DELL BOND PROJECT
WHEREAS, pursuant to Article Ilk Section 3.01 (b) of the Trust Indenture by and
among the City of Carmel Redevelopment Authority and Fifth Third Bank of Central
Indiana, dated as of August 1, 1997, approval by the Common Council is required prior
to payments from the Construction Fund therein described upon presentation of
architect's or engineer' s certificates of work completed and materials furnished;
WHEREAS, American Consulting Engineers, Inc., has presented such certificates
regarding the Construction Project Invoices attached hereto as Exhibit A.
NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of
Carreel, Indiana, that the Construction Project Invoices attached hereto as Exhibit A are
hereby approved for payment from the Construction Fund described in the above-
referenced Trust Indenture.
PASSED by the Common Council of the City of Carmel, lndiana this //7'l, day
of_C-,Y/~dz~r _,2000, byavoteof [~ ayesand_ ~ nays.
afCarme~,( ';/r~e''r''f~,2000.
Approved by me, Mayor of the City 1
Brainard, Mayor
ATTEST:
Diana L~ Cordray, iAMC, Cl~e-Treasurer
CITY OF CARMEL REDEVELOPMENT AUTHORITY
CONSTRUCTION FUND PAYMENT REQUISITION
TO:
Fifth Third Bank of Central Indiana, as Trustee
251 North Illinois Street
Suite 1000
Indianapolis, Indiana 46204
Attn: Corporate Trust Department
Date: August 1, 2000
Trust Indenture between City of Carmel Redevelopment Authority and Fifth
Third Bank of Central Indiana, as Trustee, dated as of August 1, 1997 (the
"Trust Indenture")
AFFIDAVIT
STATE OF INDIANA )
)
COUNTY OF HAMILTON )
SS:
The undersigned, having been duly sworn upon her oath, certifies that:
She has been designated by the Carreel Redevelopment Authority as an individual
authorized to execute and present affidavits on the Authority's behalf relating to
payments from the Construction Fund for items that are not subject to certification by
the architect or engineer, in accordance with Article IV, Section 3,01 (b) of said Trust
Indenture.
The amounts set forth in Exhibit A hereto are requested to be paid to the respective
Payees identified therein for the services or assets described, from the Construction
Account of the Construction Fund created by Section 3.01 of the Trust Indenture.
Copies of the statements of the respective Payees or other supporting
documentation are also attached hereto.
The obligations set forth in Exhibit A have been properly incurred, are proper
charges against the Construction Account, and have not been the basis of any
previous withdrawals from the Construction Account.
CITY OF CARMEL REDEVELOPMENT
AUTHORITY
City Engineer, City of Carmel, Indiana
STATE OF INDIANA
COUNTY OF HAMILTON
)
)
)
SS:
Before me, the undersigned, a Notary Public in and for said County and State, personally
appeared~Kate Weese , City Engineer for the City of Carmel, Indiana, who having
been duly sworn upon her oath acknowledged the execution of the foregoing Affidavit for and on
behalf of said Authority.
Witness my hand and Notarial Seal this~f_~ day of August, 2000
My Commission Expires:
residing in
Indiana
, Notary Public
County,
EXHIBIT A
PAYMENT REQUISITION NO. 117
PAYEE
AMOUNT
DUE
CHARACTER OF EXPENDITURE
Trotter Construction, Inc.
5851 E. 34th Street
Indianapolis, IN 46218
$143,566.71
Construction costs in connection
with Pennsylvania St.
08/01/00
CONSTRUCTION PROJECTINVOICE
COMPANY NAME: Trotter Construction, Inc.
AND ADDRESS 5851 E 34th Street
indianapolis, IN 46218
TELEPHONE NO.: (317) 543-0053
FAX NO.:
PROJECT NAME:
PROJECT NO.:
INVOICE NO.:
(317) 543-3115
Pennsylvania Street Improvements
97-04
Og
DATE: July 28, 2000
Construction pay items as per Progress Pay Estimate No. 09 as shown on the
attached invoice for work completed between the dates of July 7, 2000 and July 26,
2000.
TOTAL PAY THIS ESTIMATE:
MINUS 10% RETAINAGE:
TOTAL NOW DUE:
(-)
$159,518.57
$15,951.86
$143,566.71
Submitted by CrossRoad Engineers, PC
Project Representative - printed name
Date
CITY OF CARMEL
PENNSYLVANIA STREET IMPROVEMENT PROJECT
PROJECT #97-04
PROGRESS PAY ESTIMATE NO. 09
For work done during the period of: 07-07-00 through
t Ltem
5
6
7
9
Descnptlen
CLEARING RIGHT OF WAY
CONCRETE CURS. REMOVE
CATCH BASIN, REMOVE
SURFACE MILLING BITUMINOUS
PIPE, REMOVE
EXCAVATTON, COMMON
BORROW
EXCAVATION. COMMON FOR DITCH GRADIN
TEMP EROSION & SEDIMENT CONTROL, PE~
10 TEMP EROSION & SEDIMENT CONTROL, CU
11 TEMP EROSION & SEDIMENT CONTROL, DR
12 TEMP EROSION & SEDIMENT CONTROL~ CU
13 B BORROW FOR STRUCTURE BACKFILL
14 COMPACTED AGG. FOR SHOULDER, O, SIZE
15 COMPACTED AGGREGATE FOR APPR O. St.
16 COMPACTED AGGREGATE FOR DRIVES, O, ,c
17 HMA BASE, 250 mm MAINELINE D
18 HMA BASE, 250 mm MAINELINE C
19 HMA BASE, 25.0 mm MAINELiNE
20 HMA ~NT~RMEDIATE, 19 0 mm MAINEL~NE
21 HMA SURFACE, 9.5 mm MV, MAINELiNE
22 BiTLJMINOUS MATERIAL FOR TACT COAT
23 CURB RAMP, CONCRETE
24 SIDEWALK, CONCRETE
25 SIDEWALK, BITUMINOUS
26 CURB, CONCRETE
27 CURB AND GU"q'ER, COMBINED
28 CENTER CURB, CONCRETE, MODIFIED
29 BiTUMiNOUS MIXTURE FOR APPROACHES, L
30 GEOTEXTILES
I 31 RIPRAP, REVETMENT 18 IN.
32 MOBIL3ZAT~ON & DEMOBILIZATION FOR SEEI
33 MULCHED SEEDING, R
i34 SODDING
35 TREES, REPLANT
' 36 SANITARY SEWER SERVICE ADJUSTMENT
37 PIPE. RCP, 12 TN
40 PIPE. RCP, 21
41 PIPE. RCP, 24
42 PIPE, RCP, 27 IN
43 PIPE, RCP. 30 IN
44 PIPE, RCP, 33 IN.
45 PIPE, RCP, 42 ~N
46 PIPE, RCP, 54 IN.
47 PIPE, GROUP K, 6 IN
48 PIPE END SECTION, METAL, 12 IN,
Quantitythis Totak Quantity UnLt
Estimate to Date Price
070 LS $68,79659
65.00 LFT 2282 50 LFT $255
3.00 7,00 EA $60.00
! SY $665
84.00 LF 622.00 LF $11.60
1762.67 CY 5378 71 CY $880
3193.03 CY 12243.03 CY $1318
LS -100 LS $16.126.96
LF 5860 00 LF $170
EA I 00 EA $66.00
EA EA $6600
EA 1300 EA $37.83
306.51 CY 701961 CY $1475
TN TN $20.53
TN TN $23 47
TN TN $32.31
TN TN $2643
TN TN $31 52
TN TN $26,43
TN TN $2913
TN TN $32,72
SY SY $014
SY SY $31.46
SY SY $2422
TN TN $37.99
LF LF $10,68
LF LF $992
SY SY $73.76
TN TN $7445
SY SY $396
TN TN $2167
EA EA $660.00
SY SY $044
SY SY $2.59
EA 12.00 EA $15000
LF 75 00 LF $3991
481.00 LF 2224.50 LF $24 43
LF 35900 LF $25 64
LF 155 00 LF $2811
LF 55900 LF $3804
LF 1239 50 LF $45,08
LF 933.50 LF $5314
LF 67700 LF $54.02
LF 1114 00 LF $61.11
LF 28 00 LF $96.36
LF 34.50 LF $9886
2185.00 LF 267600 LF $328
EA EA $154.86
07-26-00
Total Pay Total Pay
this Estimate to Date
$165.75 $5.76938
$180,00 $420.00
$974.40 $7,215.20
$15,158.96 $46.25691
$42,084.14 $161,36314
$16,126.96
$9,96200
$6600
$49179
$4,521.02 $10353925
I of 4
$1,800.00
$3,03316
$11,750.83 $54,344.54
$9,30476
$4,357 05
$21,264 36
$55,87666
$49,60619
$36,57154
$68,07654
$2,69808
$3,410.67
$'7,166.80 $8,77728
CITY OFCARMEL
PENNSYLVANIA STREETIMPROVEMENTPROJECT
PROJECTOr97-04
PROGRESS PAY
For work done during the period of:
49 P~PE END SECTION, METAL, 21 IN
50 PIPE END SECTION, METAL, 33 IN
51 PIPE END SECTION, METAL, 53 IN
52 PIPE, PVC, 6 IN, SCHEDULE 40
53 PfPE END SECTION REINSTALL
54 AGGREGATE FOR UNDERDRAINS, 8
55 GEOTEXTiLES FOR UNDERDRAIN
56 ! RING AND COVER, 4
57 INLET. E7
58 PIPE, PLUG EXISTING
59 P~PE HOLE iN EXISTING STRUCTURE, PLUG 1.00
80 CASTING, ADJUST TO GRAOE 2.00
61 ~NLET, H5
62 MANHOLE, K5
63 SANITARY MANHOLE, C4
64 MANHOLE, L4
65 MANHOLE, L15
66 MANHOLE, J15
67 , iNLET 815 4.00
68 LNLET C15 3.00
69 MANHOLE, J4
70 CONSTRUCTION DRUM, LEAVE IN PLACE
71 BARRICADE, IlIA
72 ROAD CLOSURE SIGN ASSEMBLY
73 DETOUR CLOSURE SIGN ASSEMBLY
74 CONSTRUCTION SIGN, A
75 SIGN, SHEET, ENCAPSULATED LENS WITH L
,_76 SIGN POST, A
77 LINE, THERMOPLASTIC, BROKEN WHITE, 4"
78 LINE, THERMOPL~,.STIC, SOLID WHITE, 4"
79 TRANSVERSE MARKINGS, THERMO CROSS%
~_ 80 LINE, THERMOPLASTIC, BROKEN YELLOW, 4
81 LINE, THERMOPLASTtC, SOLID YELLOW, 4"
82 TRANSVERSE MARKINGS, THERMQ. STOP
83 PVMT MESSAGE MRKNGS, THERMO, LANE
84 PVMT MESSAGE MRKNGS, THERMO,, WORE
85 SNOWPLOWABLE RAISED PAVEMENT MARK
86 LINE, THERMOPLASTtC. DOTFED, WHITE, 4",
87 RELD OFFICE, 550 SQFT, 1.00
88 MAINTAINING TRAFFIC 0.05
89 CONSTRUCTION ENGINEERING 0.05
90 MOBILIZATION & DEMOBILIZATION
91 MATERIAL TESTING 0.10
92 TRAFFIC SIGNAL, 12" RYG
93 TRAFFIC SIGNAL, 12' RY GA
94 TRAFFIC SIGNAL, 12" RYG, YA, GA
95 PEDESTRIAN SIGNAL, INTERNATIONAL, 12"
96 PEDESTRIAN PUSHBUTTON & SIGN
97 HANDHOLE
98 CONDUIT, 2"
99 TRAFFIC SIGNAL POLE, 40' SiC. ARM, 15'
100 TRAFRC SIGNAL POLE, 45' SIG. ARM, 15' VIO
642.00
713,28
74.08
ESTIMATE NO. 09
07-07-00 through
EA EA $236 42
EA EA $37847
EA EA $1,74402
LF 642 00 LF $10.40
EA EA $75.61
CY 751 26 CY $2310
SY 253.57 SY $110
EA EA $33500
EA 100 EA $793.88
EA EA $72.25
EA 2.00 EA $145.52
EA ,2.00 EA $235.00
EA 100 EA $1,422.72
EA 100 EA $2,973.40
EA EA $1,986 52
EA 3.00 EA $5,264.01
EA EA $5,285 80
EA 2400 EA $2,655.73
EA 27 00 EA $%47788
EA 15.00 EA $1,477.88
EA 2.00 EA $1,372.03
EA EA $6575
EA EA $212.10
EA EA $47723
EA EA $37.12
EA 1400 EA $132,56
SFT SFT $2485
LF LF $862
LF LF $0.26
LF LF $0.26
LF LF $141
LF LF $0 27
LF LF $0 25
LF LF $2.85
EA EA $6062
EA EA $87.57
EA EA $28 72
LF LF $0.62
MOS 7 75 MOS $41000
LS 070 LS $30,795.00
LS 070 LS $108,125.00
LS 0.50 L~ $85,65000
LS 0.30 LS $27,27000
EA EA $444 70
EA EA $452.84
EA EA $708 12
EA EA $459.35
EA EA $16602
EA EA $85800
LF LF $16.82
EA EA $5,884,82
EA EA $6,88621
07-26-00
$6,6?6.80 $6,676.$0
$16,476.77 $17,354 11
$81.49 $278.93
$79388
$145.52 $291.04
$470.00 $470.00
$1,422.72
$2,973.40
2of4
$15,792,03 '
$63,737.52
$5,911.52 $39,902.76
$4,433.64 $22.168.20
$2,744.06
$1.85584
$410,00 $3,17750
$1,539.75 $21,556.50
$5,406.25 $75,687.50
$42,82500
$2,727.00 $8,181.00
CITY OF CARMEL
PENNSYLVANIA STREET IMPROVEMENT PROJECT
PROJECT
PROGRESS PAY
For work done during the period of:
101 TRAFFIC SIGNAL POLE, 75' SIG. ARM, 25' VID
102 TRF SIG, POLE FOUNDATION (NCLUDING RE
103 POWER CABLE. 2C/BGA
104 POWER CABLE, 3C/14GA
105 POWER CABLE, 5C/14GA
106 POWER CABLE, 7C/14GA
107 POWER CABLE, 11CI14GA
108 VIDEO CAMERACABLE, CX
109 8PHASECONTROLLERW/PCABINET&FOU
110 VIDEO DETECTION SYSTEM, COMPLETE
111 ELECTRIC SERVICE
112 REMOVAL OF TRAFFIC SIGNAL EQUIPMENT
113 PIPE CATCH BAS~N, 12"(UNDISTRIBUTED)
114 PIPE, PVC, SCHEDULE 40, 8" (UNDISTRIBUTE
115 INLET, C5
116 ManRole, C-4, Drop
117 ResetExistingCMPforDe(taDra~nage
118 Pipe, Type 2, Circular, 18 IN
119 18 IN Metal End Section
120 Additional Sanitary Improvements
121 Reconstruct Structure 87A 1.00
122 Reconstructt Structure to Grade 1.78
123 Cost of Structurel'~,87B, not installed 1.00
124 Delta Light Relocation
125 EncaseConduitatStructure#124 1.00
126 Pedistal Foundation, A
127 Pedistal and Base, 10 ft.
128 HMA BASE, 250 mm MAINLINE, C
129 HMA BASE, 25 0 mm MAINLINE 1006,16
130 HMA INTERMEDI~,TE, 19.0 mm MAINLINE
131 HMA SURFACE, 95 mm MV, MAINLINE
132 BITUMINOUS MATERIAL FOR TACK COAT
133 SIDEWALK, BITUMINOUS
134 INLETS. RELOCATE 1.00
135 TRAFFIC SIGNAL POLE, 50' gig ARM, 25' VID
136 TRAFFIC SIGNAL POLE, 45' SIG ARM, 25' VID
137 TRAFFIC SIGNAL POLE, 40' SIG ARM, 25' VID
138 TRAFFIC SIGNAL POLE, 40' SIG ARM, 20'
139 TRAFFIC SIGNAL POLE, 35' SIG ARM, 25' VID
140 TRAFFIC SIGNAL POLE, 30' SIG ARM, 25'
141 SIGNAL SUPPORT FOUNDATION, 3 FT. X 12 F
ESTIMATE NO. 09
07-07-00 through
EA EA $13,073.25
CY CY $407.36
LF LF $2.66
LF LF $1 92
LF LF $2,97
LF LF $2.94
LF LF $332
LF LF $296
EA EA $13,676,65
EA EA $33,259 20
EA EA $53125
LS LS $2,181.94
EA EA $425.00
LF LF $11.55
EA EA $1,550 00
EA 1 00 EA $3,946.00
EA EA $400.00
LF LF $19.00
EA EA $23642
LS 0.44 LS $52,000,00
LS 1 00 LS $350 00
LF 1.78 LF $525.00
LS 100 LS $1,130,80
LS LS $3,894 00
LS 100 LS $450.00
EA EA $592.66
EA EA $61768
TN TN $3340
TN 100616 TN $28.31
TN TN $31.27
TN TN $35.51
SY SY $0.15
TN TN $4017
LS 1.00 LS $1,88824
EA EA $14,07618
EA EA $7,383.09
EA EA $7,205.85
EA EA $7,20586
EA EA $6.653.69
EA EA $6,62949
EA EA $1,908.51
07-26-00
$3,94600
$22,880,00
$350.00 $35000
$934,50 $934.50
$1,130.80 $1,13080
$450.00 $45000
$28,484.39 $28,484.39
$1,886.24 $1,58824
3of4
CITY OF CARMEL
PENNSYLVANIA STREET IMPROVEMENT PROJECT
PROJECT #97-04
PROGRESS PAY ESTIMATE NO. 09
For work done during the period of: 07-07-00 through
07-26-00
4of4
$159,518.5'7 $1,106,341.76
CITY OF CARMEL
PENNSYLVANIA STREET IMPROVEMENT PROJECT
PROJECT ~97-04
PROGRESS PAY ESTIMATE NO. 09
For work done during the period of: 07-07-00 through
TOTALS AND PAY ESTIMATE CALCULATIONS
TOTAL PAY THIS ESTIMATE
TOTAL PAY TO DATE
DEDUCT 10% RETAINAGE
DEDUCT PREVIOUS NET PAY ESTIMATES
NET PAY ESTIMATE NO. 09
CrossRoad Engineers, PC
Inspecting Firm
CoRtractor
07-26-00
$159,518.57
$1,106,341.76
$110,634.18
$852,140.88
S143,566.71
I of 1