HomeMy WebLinkAboutEP105 - ROOF POWER PLANRTU-1
CU-3-206CU-3-306
CU-3-406
CU-2-208CU-2-308
CU-2-408
CU-2-210CU-2-310
CU-2-410
CU-1-212
CU-1-312
CU-1-412
CU-1-409
CU-1-209CU-1-309
CU-1-307CU-1-207
CU-1-407
CU-1-205
CU-1-305 CU-1-405
CU-2-203
CU-2-303 CU-2-403
CU-1-402
CU-1-202
CU-1-302
CU-2-204
CU-2-304 CU-2-404
CU-DS-2
CU-DS-1
HP-CC-2
CU-DS-1
51
51
51
51
15
15
15
16
16
16
16
17,19,21
20,22
24,26
27,29
EF-2
1HA2- 18
1HA1- 51
1HA2- 16
A. SEE SHEET E-000 FOR SYMBOLS AND ABBREVIATIONS.
B. SEE SHEET E-501 FOR MECHANICAL EQUIPMENT POWER SCHEDULE.
C. SEE SHEETS E-502 THROUGH E-503 FOR PANEL SCHEDULES.
D. SEE SHEETS E-601, E-602 AND E-603 FOR ELECTRICAL DETAILS.
E. WIRING SYSTEM SHALL BE CONDUIT AND CONDUCTOR UNLESS NOTED
OTHERWISE. USE SOLID CONDUCTOR FOR SIZE #10 AWG AND SMALLER. USE
STRANDED CONDUCTOR FOR LARGER SIZES.
F. ALL COVER PLATES FOR ELECTRICAL DEVICES SHALL BE OF A COLOR TO
MATCH THE AREA COLOR SCHEME AS DIRECTED BY THE INTERIOR DESIGNER.
G. ALL WORK SHALL COMPLY WITH ALL NATIONAL, STATE AND LOCAL CODES
AND ORDINANCES PERTAINING TO THE WORK IN THIS PROJECT.
H. EXPOSED CONDUIT SHALL BE RUN PARALLEL TO AND AT RIGHT ANGLES TO
BUILDING LINES.
I. REFER TO ARCHITECTURAL DRAWINGS FOR DESIGNATION AND LISTING OF
FIRE RATED ASSEMBLIES. COORDINATE ALL DESIGN EFFORTS WITH FIRE
RESISTANCE OF MATERIALS AND CONSTRUCTION.
J. ALL EXTERIOR EQUIPMENT AND DEVICES SHALL BE WEATHER PROOF AND
RAIN TIGHT.
K. ELECTRICAL CONTRACTOR SHALL FURNISH AND INSTALL ALL INTERCONNECT
WIRING FOR MECHANICAL AND PLUMBING EQUIPMENT FURNISHED BY
OTHERS.
GENERAL SHEET NOTES
18166
Project:
Developer:
Sheet Number:
Engineer:
By:
Sheet Title:
CDG Number:
Last Revision Date:
Set Issue Date
Drawn By Checked By
Sheet Issue DateWINDSOR BUILDINGCarmel, IN 46032CONSTRUCTION
DOCUMENTS800 West Monon Green Blvd.EP105
ROOF POWER PLAN
08/31/202108/31/2021
KREG SMEAD BARRY SIMPSON
1/8" = 1'-0"
ROOF POWER PLAN1016'8'4'
N