HomeMy WebLinkAboutS410 - FLOOR FRAMING DETAILSSEE ARCH.
FINISH FLOORCONT. 2x6 RIBBON BOARD
CONT. 2x WOOD SILL
PLATE (MATCH STUD
SIZE), FASTEN PER
SHEARWALL SCHEDULE
GYPCRETE, SEE ARCH.
3/4" FLOOR SHEATHING, REFER TO
DIAPHRAGM SCHEDULE FOR
NAILING PATTERN
PRE-FABRICATED WOOD FLOOR
TRUSS, SEE PLAN
CEILING, SEE ARCH.
2x WOOD STUD WALL
BEARING WALL, SEE
SCHEDULE
DOUBLE 2x TOP PLATE (SIZE
TO MATCH STUD WALL)
FASTEN TRUSS TO TOP PLATE
WITH (3) -16d NAILS (TYP., UNO)
GYPSUM SHEATHING, SEE ARCH.
FACE BRICK, SEE ARCH.
2x WOOD STUD WALL BEARING
WALL, SEE SCHEDULE
EXTERIOR WALL
SHEATHING, REFER TO
SHEAR WALL PLANS AND
SCHEDULE
SEE ARCH.
FINISH FLOOR
GYPCRETE, SEE ARCH.
3/4" FLOOR SHEATHING, REFER
TO DIAPHRAGM SCHEDULE
FOR NAILING PATTERN
PRE-FABRICATED WOOD FLOOR
TRUSS, SEE PLAN
CEILING, SEE ARCH.
2x WOOD STUD WALL
BEARING WALL, SEE
SCHEDULE
DOUBLE 2x TOP PLATE (SIZE TO
MATCH STUD WALL)
LADDER TRUSS
GYPSUM SHEATHING, SEE ARCH.FACE BRICK, SEE ARCH.
2x WOOD STUD WALL BEARING
WALL, SEE SCHEDULE
EXTERIOR WALL SHEATHING,
REFER TO SHEAR WALL PLAN
AND SCHEDULE
CONT. 2x WOOD SILL
PLATE (MATCH STUD SIZE),
FASTEN PER SHEARWALL
SCHEDULE
2x4 WOOD BRACE AT 4'-0"
O.C. MAX SPACING
(FASTEN EACH SIDE WITH
(4) -10d NAILS
2x6 BLOCKING AT EACH
WOOD BRACE (FASTEN
SHEATHING TO BLOCKING
WITH (4) -10d NAILS)
CONT. 2x4 FOR CEILING
ATTACHMENT
CONT. 2x WOOD SILL PLATE
(MATCH STUD SIZE), FASTEN PER
SHEARWALL SCHEDULE GYPCRETE, SEE ARCH.
3/4" FLOOR SHEATHING, REFER
TO DIAPHRAGM SCHEDULE FOR
NAILING PATTERN
PRE-FABRICATED WOOD FLOOR
TRUSS, SEE PLAN
CEILING, SEE ARCH.
2x WOOD STUD WALL BEARING
WALL, SEE SCHEDULE
DOUBLE 2x TOP PLATE (SIZE TO
MATCH STUD WALL)
FASTEN TRUSS TO TOP PLATE
WITH (3) 16d NAILS (TYP., UNO)
GYPSUM SHEATHING, SEE ARCH.
OSB SHEARWALL SHEATHING (AS
REQUIRED AT SHEAR WALLS), SEE
SHEARWALL PLAN AND SCHEDULE
FOR LOCATIONS AND NAILING
WOOD SHEAR BLOCKING BETWEEN
EVERY OTHER TRUSS (AS REQUIRED
AT SHEAR WALLS), SEE SHEARWALL
SCHEDULE FOR ADDITIONAL
INFORMATION
CONTINUE FLOOR SHEATHING
THROUGH WALL CAVITY
DRAFTSTOPPING, SEE ARCH.
SEE ARCH.
FINISH FLOOR
DOUBLE 2x TOP PLATE (MATCH
STUD SIZE)
STAIRWELL SIDEUNIT SIDE
CONT. 2x WOOD SILL PLATE
(MATCH STUD SIZE), FASTEN PER
SHEARWALL SCHEDULEGYPCRETE, SEE ARCH.
3/4" FLOOR SHEATHING, REFER
TO DIAPHRAGM SCHEDULE FOR
NAILING PATTERN
PRE-FABRICATED WOOD FLOOR
TRUSS, SEE PLAN
2x WOOD STUD WALL BEARING
WALL, SEE SCHEDULE
HANG TRUSS FROM LVL WITH
SIMPSON DHUTF SERIES
FIREWALL HANGER (INSTALL
OVER GYP. AND OSB LAYERS)
GYPSUM SHEATHING, SEE ARCH.
STAIR FRAMING
LEDGERS/STRINGERS TO BE
ATTACHED DIRECTLY TO STUDS
WITH SCREWS RATED FOR
APPLICATION OVER (2) LAYERS
OF DRYWALL
CEILING, SEE ARCH.
STAIR LANDING FRAMING BY
OTHERS SEE ARCH.
FINISH FLOOR
*OSB SHEAR WALL SHEATHING
NOT PRESENT AT SIM.
OSB SHEARWALL SHEATHING (AS
REQUIRED AT SHEAR WALLS), SEE
SHEARWALL PLAN AND SCHEDULE FOR
LOCATIONS AND NAILING
SEE 5/S400 AND 6/S400 FOR
ALTERNATE DETAIL
ELEVATOR SIDE CORRIDOR SIDE
GYPCRETE, SEE ARCH.
3/4" FLOOR SHEATHING, REFER TO
DIAPHRAGM SCHEDULE FOR NAILING
PATTERN
PRE-FABRICATED WOOD FLOOR TRUSS,
SEE PLAN
ELEVATOR SHAFT WALL, SEE ARCH.
SEE S500 FOR TYP. MASONRY DETAILS
SIMPSON HU416 FACE MOUNT
MASONRY HANGER. ENSURE ALL TITEN
2 ANCHORS ARE ATTACHED TO GROUT
FILLED MASONRY. PROVIDE HUC416
HANGERS AT WALL CORNERS
BOND BEAM, SEE S500
SEE ARCH.
FINISH FLOOR
SEE ARCH.
TRUSS BEARING(GROUT SOLID)BOND BEAM-9" B.F.F.
T.O. FRAMING
GYPCRETE, SEE ARCH.
3/4" FLOOR SHEATHING, REFER
TO DIAPHRAGM SCHEDULE
FOR NAILING PATTERN
PRE-FABRICATED WOOD
FLOOR TRUSS, SEE PLAN
CEILING, SEE ARCH.
GYPSUM SHEATHING, SEE ARCH.
EXTERIOR FINISH, SEE ARCH.
2x WOOD STUD WALL BEARING
WALL, SEE SCHEDULE
2" LIGHTWEIGHT CONCRETE
TOPPING WITH WATERPROOFING
ADDITIVE (XYPEX OR EQUAL) OVER
WATERPROOF MEMBRANE
P.T. BALCONY FRAMING, SEE
PLAN. ATTACH TO LEDGER
WITH SIMPSON LU28-SS
HANGER
P.T. 2x12 LEDGER AROUND
PERIMETER OF BALCONY, ATTCH TO
LVL WITH (2) 3/4" DIA. BOX BOLTS AT
16" O.C.
STEEL BEAM, SEE PLAN
AND SCHEDULE
P.T. 3/4" PLYWOOD SHEATHING
FLASHING TO PREVENT WATER
INFILTRATION, SEE ARCH. FOR
DETAILS
RIPPED 2x SLEEPERS AT 12" O.C.,
SLOPE TOP EDGE 1/8" PER FOOT AND
ALIGN PERPENDICULAR TO EXT.
EDGES SEE PLAN
FINISH FLOOR
3"4"CEILING, SEE ARCH.
EXTERIOR FINISH, SEE ARCH.
2x WOOD STUD WALL BEARING
WALL, SEE SCHEDULE
EXTERIOR WALL SHEATHING, REFER
TO SHEAR WALL PLAN AND SCHEDULE
CONT. 2x WOOD SILL PLATE (MATCH
STUD SIZE), FASTEN PER SHEARWALL
SCHEDULE
P.T. BALCONY FRAMING, SEE
PLAN. ATTACH TO LEDGER WITH
SIMPSON LU28-SS HANGER
P.T. 2x12 LEDGER AROUND
PERIMETER OF BALCONY, ATTCH TO
LVL WITH (2) 3/4" DIA. A193 GR. 8
STAINLESS STEEL BOLTS AT 16" O.C.
LVL BEAM, SEE PLAN AND SCHEDULE
LIGHTWEIGHT CONCRETE TOPPING
WITH WATERPROOFING ADDITIVE
(XYPEX OR EQUAL) OVER
WATERPROOF MEMBRANE. SLOPE
1/4"/12" TOWARDS EXTERIOR
P.T. 3/4" PLYWOOD SHEATHING
FLASHING TO PREVENT WATER
INFILTRATION, SEE ARCH. FOR
DETAILS
-9" B.F.F.
T.O. FRAMING
RIPPED 2x SLEEPERS AT 12" O.C.,
SLOPE TOP EDGE 1/8" PER FOOT
AND ALIGN PERPENDICULAR TO
EXT. EDGES
SEE PLAN
FINISH FLOOR
EXTERIOR FINISH, SEE
ARCH
WALL SHEATHING, REFER TO
SHEAR WALL PLANS AND
SCHEDULE
SHEAR WALL HOLDOWN, SEE
SCHEDULE
SHEAR WALL END POST, SEE
SCHEDULE
INTERRUPT SILL PLATE FOR
HOLDOWN ANCHORAGE
SIMPSON ATS-SBC5H
ANCHORAGE SYSTEM
WELDED TO STEEL BEAM
3/16
STEEL BEAM, SEE PLAN AND
SCHEDULE
L5x5x5/16 SUPPORT ANGLE
(COORDINATE ELEV. WITH ARCH.)
3/16 2@12
-9" B.F.F.
T.O. FRAMING
CEILING, SEE ARCH.
EXTERIOR FINISH, SEE
ARCH.
2x WOOD STUD WALL
BEARING WALL (BEYOND),
SEE SCHEDULE
2" LIGHTWEIGHT CONCRETE TOPPING
WITH WATERPROOFING ADDITIVE
(XYPEX OR EQUAL) OVER WATERPROOF
MEMBRANE
P.T. BALCONY FRAMING, SEE PLAN.
ATTACH TO LEDGER WITH SIMPSON
SUL210 (OR SUR210) HANGER
WOOD HEADER, SEE
PLAN AND SCHEDULE
P.T. 3/4" PLYWOOD SHEATHING
FLASHING TO PREVENT
WATER INFILTRATION,
SEE ARCH. FOR DETAILS
1/8"
12"
BALCONY RAILING BY OTHERS,
SEE ARCH.
EXTERIOR WALL WITH THIN BRICK
BEYOND, SEE ARCH.
P.T. 2x SUB FASCIA BOARD
RIPPED 2x SLEEPERS AT 12" O.C., SLOPE
TOP EDGE 1/8" PER FOOT AND ALIGN
PERPENDICULAR TO EXT. EDGES
P.T. (2) 2x12 BACKING FOR
LEDGER ATTACHMENT,
BEAR BACKING ON HEADER
BRICK LINTEL, SEE S210
NOTE: AT FOURTH FLOOR BALCONIES, EXTEND HEADER
AND BRICK LINTEL TO ENDS OF WALL AND BOLT LINTEL TO
HEADER WITH 5/8" DIA. A193 GR. 8 S.S. BOLTS AT 8" O.C.
STEEL BEAM, SEE PLAN
AND SCHEDULE
SIMPSON ATS-SBC5H
WELDED TO TOP FLANGE
OF STEEL BEAM
SHEAR WALL HOLDOWN,
SEE SCHEDULE
SHEAR WALL END POSTS,
SEE SCHEDULE
INTERRUPT SHEATHING
FOR ATS ANCHORAGE
3/16
WALL SHEATHING, REFER
TO SHEAR WALL PLANS
AND SCHEDULE
PRE-ENGINEERED WOOD
FLOOR TRUSS
STEEL BEAM, SEE
PLAN AND SCHEDULE
SEE ARCH.
FINISH FLOOR
CONT. 2x WOOD SILL
PLATE (MATCH STUD
SIZE), FASTEN PER
SHEARWALL SCHEDULE
FACE BRICK, SEE ARCH.
2x WOOD STUD WALL
BEARING WALL, SEE
SCHEDULE
EXTERIOR WALL
SHEATHING, REFER TO
SHEAR WALL PLANS AND
SCHEDULE
2x4 FOR DRYWALL
ATTACHMENT
PRIMARY GARAGE
LINTEL, SEE S210 FOR
SIZE. PROVIDE 3/8" THICK
STIFFENERS AT 16" O.C.
FOR ALL PRIMARY
GARAGE LINTELS
SECONDARY STEEL
LINTEL, SEE S210 FOR
SIZE. BOLT TO LOW
BEAM WITH 3/4" DIA. A193
GR. 8 STAINLESS STEEL
BOLTS STAGGERED AT
16" O.C.WOOD BEAM, SEE
PLAN AND SCHEDULE
3/16 3@12
3/16 3@12
3" MIN.PRE-ENGINEERED WOOD
FLOOR TRUSS
CONT. 2x WOOD SILL
PLATE (MATCH STUD
SIZE), FASTEN PER
SHEARWALL SCHEDULE
FACE BRICK, SEE ARCH.
2x WOOD STUD WALL
BEARING WALL, SEE
SCHEDULE
EXTERIOR WALL
SHEATHING, REFER TO
SHEAR WALL PLANS AND
SCHEDULE
2x4 FOR DRYWALL
ATTACHMENT
STEEL LINTEL, SEE S210
FOR SIZE. BOLT TO
HEADER WITH 3/4" DIA.
A193 GR. 8 STAINLESS
STEEL BOLTS
STAGGERED AT 5" O.C.
WOOD BEAM, SEE
PLAN AND SCHEDULE
SEE ARCH.
FINISH FLOOR
WOOD STUD INFILL AS
REQUIRED
3" MIN.WOOD STUD WALL, SEE SCHEDULE
OSB SHEAR WALL SHEATHING
DOUBLE 2x10 NAILER
PRE-ENGINEERED
WOOD FLOOR TRUSS
STEEL BEAM, SEE
PLAN AND SCHEDULE
SEE S200 FOR SILL
PLATE ANCHORAGE
INEGSS
LOINA E NPROF REEN o.
GRE S
DRETEI
STATE OF
NA ADNII
11100391 NNAMFFOHHPESOJ
SHEET NUMBER:
PROJECT NUMBER: DRAWN BY:PROJECT TITLE:This is an original design, created by KJG Architecture,
Inc. The concepts, ideas, plans and details are the sole
property of KJG Architecture, Inc. None of the
aforementioned shall be used by or disclosed to any
person, firm or organization for any purpose without the
prior written permission of KJG Architecture, Inc.
NO. DESCRIPTION:DATE
ISSUED:
DRAWING TITLE:
PROFESSIONAL SEAL:
PROJECT DATE:
DISCLAIMER:
KJG ENGINEERING
527 Sagamore Pkwy W., Suite 101
West Lafayette, Indiana 47906
Ph: 765.497.4598 Fx: 765.497.4599
www.kjgengineering.com
08/16/2021MÉLANGE FLATSBUILDING 12VETERANS WAY & MONON GREEN BOULEVARDCARMEL, INDIANA 4603208/16/2021
S410
FLOOR FRAMING
DETAILS
E2020.174 KBM
1" = 1'-0"S410
1 TRUSS BEARING DETAIL
1" = 1'-0" S410
2 TRUSS BEARING DETAIL
1" = 1'-0" S410
3 TRUSS BEARING DETAIL
1" = 1'-0"S410
4 TRUSS ATTACHMENT AT RATED STAIR
1" = 1'-0"S410
5 TRUSS ATTACHMENT AT ELEVATOR SHAFT
1" = 1'-0" S410
6 BALCONY FRAMING DETAIL
1" = 1'-0"S410
8 BALCONY FRAMING DETAIL
1" = 1'-0"S410
12 HOLDOWN AT STEEL BEAM
1" = 1'-0" S410
7 BALCONY FRAMING DETAIL
1" = 1'-0" S410
11 HOLDOWN AT STEEL BEAM
1" = 1'-0"S410
9 STEEL LINTEL AT GARAGE BEAM
1" = 1'-0" S410
10 STEEL LINTEL AT GARAGE BEAM
1" = 1'-0" S410
13 PARTITION WALL SUPPORT DETAIL
1 CONSTRUCTION SET 08/16/21
2 ADDENDUM 1 11/01/21
01/31/22