HomeMy WebLinkAbout06010035-Sewer
CLAY To.WNSHIP REGlo.NAL WASTE DISTRICT
SANITARY SEWER PERMIT
[x] Conditional Permit [] Final Permit
INDIVIDUAL Lo.TS/EXISTING BUILDINGS
Project Title:
Primary
Village of WestClay block F - Khara Spa'
Location:
Owner/Builder:
Dr Dion Chavis
Lot#
Street address: 12730 Meeting House Road
City: ,Carmel
Zip: 46032
County: Hamilton
- =---,-,.,.~
~ -~ ~ ~- -- ---",-,,"-~
Interceptor Charges Paid: 270.10
PRI:5 5.00 EQUF,eI':4950.00. Application fee: 300.00
. ~ t.1UlfX"<:P ff O((J '75
PLEASE No.TE: Installation of buil ing sewer shall be per the specifications l:Jf the Clay Township
Regional Waste District (see reverse) and any conditions noted below. All installations shall be inspected by District
personnel during "open trench" phase and before backfilling with sand or stone to six inches above the pipe. NO.
footing or foundation drains, or other sources of ground or stormwater, shall be permitled to enter the District's
sanitary sewer system. The District will assume no liabilitv for drains which are below the luade level of the
nearest downstream manhole nor for laterals which are extended beneath drivewavs or sidewalks. The
permit holder (property owner, developer or builder) will be responsible for damages to the District's sewer system.
This includes damages to manholes, castings, manhole lids and the like; caused by construction activity on the
building site which is the subject of this permit. .
Inspections by the District are MANDATo.RY and shall be arranged by contacting the District's office at 844-9200
24 hours in advance. All new construction will be placed on billing six months after connection has been made or
when water is connected, whichever comes first.
X ~\JML.The District reserves the right to inspect all sump pump connections to ensure no illegal
. . connections have been made.
X W l'lU have received a copy of o.rdinance No. 9-13-99 and agree.to follow all District standards. Building
has a [ ] crawl space [x ] slab or [ ] basement that [ ]will be finished with grinder pump installed to \
comply with elevation requirements [ ]rough-in plumbing with Qrinder pump installed during construc!ion,
[ ] rough-in plumbing only and Qrinder pump will not be installed during construction, [ ] no plumbing in
the basement. (Please check appropriate box.)
)WMleonditional Permit Terms: 'Line must be constructed and pass testing. *
[x ] NO CONNECTION to the sewer until further notification. .
. [ ] Certificate of Insurance must be on file with CTRWD listed as certificate holder.
[ ] 48 hours notice before work starts on manhole core drilling or cuts of active lines
and District inspector must inspect all work before covered.
[ ] All District fees will be paid in full.
[ ] Approval pending Districts review of plans.
[ ] Copies of approved permits from appropriate county or city agencies for work in
the right-of-way road cuts or are required.
[ ]. No occupancy until further notification
[ ]
All Conditions' have been met and final permit issued
2005.
By signing below, I atlest that I am familiar with the District's specifications and agree to accept responsibility for all
;Ou7]JetC wade,catalys-r- 317 $36- ;\902:)
~Builder/owner Signature Phone
X .W"le- (vl, LJ2D(/~
I Printed Name
Permit issued this 5th day of January, 2006.
ves 2 site plans submitted
Permit is valid for ONE- YEAR from the date issued.
'r~? -=~
~andY J. Feltner
Director of Administration & Customer Service
~
Permit valid only with CTRWD seal in red ink.
Permit-rev.9/21/05sv