HomeMy WebLinkAbout06030055 Sewer
CLAY TOWNSHIP REGIONAL WASTE DISTRICT
SANITARY SEWER PERMIT
.~
[ ] Conditional Permit [x] Final Permit
~
INDIVIDUAL LOTS/EXISTING BUILDINGS
Project Title:
Michigan Road
Location:
Aberdeen Bend
Owner/Builder:
Silverthorne Homes
Lot# 26
Street address: 12836 Birkenstock St
City: Westfield
" , Interceptor Charges Paid:
Zip: 46074
PRe "~
County: Hamilton
E[)((Fee:1650.00
" AppIi6atioi1'fee7"10O:00"
--~~~
, "
PLEASE NOTE: Installation of buiiding sewer shall be per the specifications of the Clay Township
Regionai Waste District (see reverse) and any conditions noted below. All installations shall be inspected by District
personnel during "open trench" phase and before backfilling with sand or stone to six inches above the pipe. NO
footing or foundation drains, or other sources of ground or stormwater, shall be permitted to enter the District's
sanitary sewer system. The District will assume no Iiabilitv for drains which are below the orade level of the
nearest downstream manhole nor for laterals which are extended beneath drivewavs or sidewalks. The
permit holder (property owner, d.eveloper or buiiper) will be responsible for damages to the District's sewer system.
This includes damages to manholes, castings, manhole lids and the like; caused by construction activity on the
building site which is the subject of this permit.
Inspections by the District are MANDATORY and shall be arranged by contacting the District's office at 844-9200
24 hours in advance. All new construction will be placed on billing six months after connection has been made or
when water is connected, whichever comes first.
QThe District reserves the right to inspect all sump pump connections to ensure no illegal
n ctions have been made.
~ave received a copy of Ordinance No. 9-13-99 and agree to follow all District standards. Building
~'] crawl space [ ] slab or [. x] basement that [ x ]will be finished with grinder pump installed to
comply with elevation requirements [ ]rough-in plumbing with orinder pump installed during construction,
[ ] rough-in plumbing only and orinder pump will not be installed during construction, [ ] no plumbing in
the basement. (Please check appropriate box.)
Conditional Permit Terms:
- [] NO CONNECTION to the sewer until further notification.
[ ] Certificate of Insurance must be on file with CTRWD listed as certificate holder.
[ ] 48 hours notice before work starts on manhole core drilling or cuts of active lines
and District inspector must inspect all work before covered.
[ ] All District fees will be paid in full.
[ ] Approval pending Districts review of plans. .
[ ] Copies of approved permits from appropriate county or city agencies for work in
the right-of-way"road cuts or" are required.
[ ] No occupancy until further notification
[ ]
All Conditions have been met and final permit issued
2005.
By signing below, I attest that I am familiar with the District's specifications and agree to accept responsibility for 'all
work done under this permit.
~~~~ ccr~
~ r/ er SignBtu
< \-x,~~ 24la-v>I~
Printed N e
842-1875
Phone
Per~it i;sued ihi~~8th.~ day of Mardi;2006: -...-" = ~ ~~ ves 2 site plans submitted ,~"-~" -"--~ ~ ',.
Permit is valid for ONE- YEAR from the date issued.
~ )
Permit valid only with CTRWD seal in red ink.
Candy J. Feltner
Director of Administration & Customer Service
sv
Please note chan es on lateral s ecification as of Janua
Penn it-rev .01 ~ 13-06cf