HomeMy WebLinkAboutWood River Line/Carmel/Illinois St
,
APPROVED AS TO FORM BY ~.
PIPELINE RELOCATION REIMBURSEMENT AGREEMENT
12.inch Pipeline Relocation
ILLINOIS STREET. CARMEL, HAMILTON COUNTY, IN
. THIS AGREEMENT made and entered into this I It/... . day of 0 ~ ~ j . , 2006;
by and between The City of Carmel, having an office at One Civic Squa e, Carmel, Indiana,
46032 hereinafter called "Carmel"; and Wood River Pipe Lin~aFR~!lRY LLC, having an office
at 5002 Buckeye Road, Emmaus, Pennsylvania 18049, hereinafter called "Wood River";
WITNESSETH:
WHEREAS, Wood River owns and operates a twelve-inch (12") pipeline which traverses
property in Section 26, Township 18 North, Range 3 East, situated in Hamilton County,
Indiana; said property being subject to an easement held by Wood River and;
WHEREAS, Carmel plans to construct a roadway through the aforementioned property and
such roadway will require the relocation of Wood River's twelve-inch (12") pipeline;
NOW, THEREFORE, in consideration of the parties' respective obligations hereunder, the
parties, intending to be legally bound, agree to the following:
1. Relocation Proiect: Wood River agrees to relocate the existing twelve-inch (12")
pipeline for the purpose of accommodating Carmel's proposed property improvements
in accordance with Wood River's design arid specifications and with all applicable
requirements of state and federal law, subject to the further terms and conditions of this
Agreement. Wood River shall cause such reiocation to be completed provided the
following conditions have been fulfilled: [i] Carmel shall provide to Wood River, its.
contractors or agents sufficient property improvement plans and details which provide
sufficient data for Wood River to develop its pipeline relocation plans in accordance
with Wood River's typical pipeline installation specifications; Iii] Carmel shall provide to
Wood River, its contractors or agents, professional land surveying services for Wood
River to develop its design and perform construction; [IIi] Carmel has satisfied the
Obligation to Reimburse Relocation Costs referred to in Paragraph 2 below; .
2. Wood River has estimated the total project costs at $594,275. Reimbursement shall be
made in two payments as follows: [i] The first payment being 50% of the estimate total
project costs which is $297,137.50 due at the execution of this Agreement; [ii] The
second payment being the balance for the work performed under the Agreement due at
the completion of pipeline relocation project. At that time, Wood River shall tally the
costs for the work under the Agreement and submit an invoice to Carmel for the
balance. Carmel agrees to pay said invoice withifl 30 days of receipt;
3. Bids/Contracts for Relocation Proiect: Wood River reserves the right to seiect the
contractor of its choice to perform the pipeline relocation work;
/'
4. Existino Pioeline: Wood River's existing pipeline shall be removed from the property
and disposed of by Wood River. Any monies received from such .disposal shall be
credited to Carmel's account;
5. Abandonment: Should Carmel for any reason determine to cease or change its
roadway plans such that the continuance of this pipeline relocation project as originally
planned is not necessary or if there is a material change in conditions, then in any such
event, Carmel shall. notify Wood River in writing. Subsequently, Carmel and Wood
River shall determine whether to complete or terminate this pipeline relocation project.
Following such determination, Wood River shall terminate or complete the project, as
. required, and upon such completion or termination, the provision of Paragraph 2 herein'
shall remain intact and be In full force. and effect. in the event of termination, any pipe,
fittings, or appurtenances purchased by Wood River and not used for this pipeline
relocation project shall become the property of Wood River and a credit issued for the
same to 'Carmel's account;
6. Covenants to Run with Land: The rights and covenaht herein contained shall be
binding upon and inure to the benefit of the parties hereto and their successors and
assigns; ,
7. Schedule: Upon execution of this Agreement, Wood River agrees to complete the
relocation of its tweive-inch.(12") pipeline\ withi!) five (5) months following the date of
execution (provided reimbursement as per Paragraph 2 above is made in a timely
fashion). Factors beyond the control of either party (including, but not limited to,
inclement weather, rock removal, etc.) may cause delays to the project's schedule.
Such delays are considered reasonable and normal and shall cause no penalty to either
party. Also, because Wood River is a service-oriented company, its product
transportation schedule takes precedence over the schedule of the purge and tie-in of
the relocated pipeline into the existing pipeline. Every effort will be made to schedule.
. downtime of the active pipeline for the tie-in of the relocated pipeline once the relocated'
. pipeiine is complete; however, Wood River shall bear no penalty or costs if downtime
conflicts with Carmel's property improvement schedule. Carmel shall bear the cost of
contractor(s)' downtime charges associated with such scheduling conflicts, if any;
8. Additional Requirements: Carmel, its successors or assigns, shall satisfy the additional
requirements as shown on Exhibit "C". Failure to. satisfy the requirements directly
related to the execution of this pipeline relocation project may result in delays tothe
project schedule.
9. Easement: Easements to provide for the 12-inch pipeline's relocation route shall be
acquired by Wood River. The cost for such acquisitions (labor, consideration, .
recordation, title & survey [if not provided by Carmel]) are part of this Agreement: Any
and all pipeline relocation easement agreements will include a provision for the 10catiC?n,
operation, maintenance, etc., of an eight-inch (8") pipeline in the event Wood River
reactivates its eight-inch (8") pipeline at some point in the future. .
- 2-
<:,<~OP'
"
IN WITNESS THEREOF;' Carmel and Wood River have caused this Agreement to be
executed by their proper officers, effective as of the date and year first above written.
WITNESS:
, CITY OF CARMEL
5c(\(1( a m.j ~I1SO'C\
Print:
By 04# /~
P ri rrt?'
Its:
y
Print'
13'J'
fr-,"~
::t:t6
~.. ~ , 4JoJ-;s <::r-<>
'VV\.~'.
, .
Print:
Prin:
5TATEOF iMI~f\a.'
\ \ I 55:
COUNTY OF:::qIUU kvYl ),
On this "2>[ d day of i\k C0\
, ..... ,
personally came .ht't'l<, ~a.IM,...d. as ~Io-r - W.mbW and
Lcv'i J B\s"r. I M.M:} ~Y\n &i...14as ~ff'-be.(~..... 12:,fl vJ of City of Carmel, to me '
known, who, being duly sworn, did depose and say that they executed the foregoing .
instrument and that they signed their names as authorized and empoweredage_nt!l~of'aJ:1d,~or "
, the company described herein and for the purposes herein set forth.",,:;; :".~" "'-'::"~I; -''::>,
-:;i;'-~ ~-~ - .:;~-..~~
~ /.;..~0'~--'", ~
i a...~~" _ : =
'," ',." I ':' ',',''1(:, : :;:'
,.. Notary Publ ~ \ ,.: .2
..5cy\(}..[B "IY\ ~ h()~dY\"'--,--~,,-,--- ~.::.::
1;;:1:: C1~~~~"m~""~'J'
, 2006, before me, a Notary Public,
-3-
r,
./"
WOOD RIVER PIPE LINES 6ElMP t t1" LLC
A Delaware Limited Liability Company
'" ..'t.~
aJ} 0 M/1 W
Print: C<2>\\-ea" '<=oeO
~~"t ,1[i?c:~ ~
Its: Assistant Secretary
STATE OF Pennsylvania
55:
COUNTY OF Lehigh
On this \ \ day of ~, 2006, before me, a Notary Public,
personally came Roy R. Haase. Jr. as Assistant Secretary of Wood River
Pipe Lines CeR'lJ3a~y LLC, to me known, who, being duly sworn, did depose and say that he
executed the foregoing instrument and that he signed his name as an authorized and
empowered agent of and for Wood River Pipe Lines €>SR'lIiQRY LLC, a Delaware limited liability
company, described herein and for the purposes herein set forth.
c~
Notary Public -
COMMONWEA!,.TH OF PENI'!~YLVAN1A
Notarial Seal
COlleen Ford. NotaIy Public
lJilpet' MIllord l\vp.. Lehlgtl CountY
My 'Commlsslon ExpInl8 Nov. 20. 2006
Member, p""nsylvanla ~a\lon of_
THIS INSTRUMENT PREPARED BY: Slephen C. Muther, ESQ., Buckeye Pipe Line Co., LLC, 5002 Buckeye Road, Emmaus, PA 18049
.4.
,...r.Y
~ 'f,
EXHIBIT "A"
WOOD PIPE LINE>COMPANY, LLC
OUTSIDE SERVICE COSTS
COST ESTIMATE FOR THE
RELOCATION OF. 12-INCH PIPELINE TO ACCOMMODATE
. IlliNOIS STREET
CARMEL, HAMilTON COUNTY, INDIANA
March 28,2006
PRELIMINARY ENGINEER/NG SERVICES
ENGINEERING CONSULTANT
$
40,625
CONSTRUCTION SERVICES
ENGINEERING CONSULTANT
$
21,875
~.
. PIPELINE CONTRACTOR'
Lay~ 2,000' of 12" Pipeline
Hydrotest pipe
Assist with Nitrogen Purge
Tie-in
Remove old pipe
Clean up ,
Cathodic Protection
Contract Inspection
ROW Fees and Damages
Hydrotest Water Disposal
Nitrogen Contractor
Vac Truck Service
. Pipe Removal J Grouting
Radiography
$
250,000
$
$
$
$
$
$
. $
18,200
50,000
5,250
21,000
4,344
26,250
TOTAL OUTSIDE SERVICES
396.919
. 437.544
MA TERIALS
Line Pipe, 12.75" dla, 0.375" W.T., Pritec coated,:t 2,000'
Pipe Bend,-Factory Cold Bend Elbow, 12" Die, 0.500" W.T.
Miscellaneous Valves, Fittings, and Materials
$ 74,725
$
$ 12,000
$ 86.725
$ 524,269
TOTAL MATERIALS.
ESTIMATE TOTAL "A":
<
~. .';
/
",'7?""
EXHIBIT "B"
WOOD PIPE LINe5l::0MPAm-, LLC
INTERNAL LABOR AND EXPENSE
COST ESTIMATE FOR THE
RELOCATION OF 12-INCH PIPELINE TO ACCOMMODATE
ILLINOIS STREET
CARMEL, HAMILTON COUNTY,INDIANA
March 28, 2006
PRELIMINARY ENGINEERING
BUCKEYE PIPE LINE CO _ MANPOWER
Engineering
Right of Way Department
Operations
BUCKEYE PIPE LINE CO. - EXPENSES
Engineering
Right of Way Department
Operations
BUCKEYE PIPE LINE CO. -- EQUIPMENT
Pick Up ~- Operations
Internal Labor Overhead:
$ 5,769
$ 1,960
$ 2,138
$ 9,856
$ 8,346
S 18,203
$ 2,925
$ 1,500
$ 750
$ 5,175
$ 750
$ 24,128
1,578
$ 25,705
Administrative Overhead: 6.54%
TOTAL INTERNAL LABOR AND EXPENSES
CONSTRUCTION ENGINEERING
BUCKEYE PIPE LINE CO. _ MANPOWER
Engineering
Right of Way Department
Operations
BUCKEYE PIPE LINE CO. - EXPENSES
Engineering
Right of Way Department
Operations
BUCKEYE PIPE LINE CO. - EQUIPMENT
Pick Up .. Operations
$ 3,106
$ 1,300
$ 12,113
$ 16,519
$ 13,988
$ . 30,507
$ 1,575
$ 1,000
$ 4,250
S 6,825
$ 4,250
$ 41,582
2,719
$ 44,301
$ 70,007
$ 594,275
Internal Labor Overhead:
Adm inlstrative Overhead: 6.54 %
TOTAL INTERNAL LABOR AND EXPENSES
ESTIMATE TOTAL "B":
ESTIMATE TOTAL FOR PROJECT:
I '" .. '.i-
.,6-
;'
EXHIBIT "cn
WOOD RIVER PIPE L1N~LLC
ADDITIONAL REQUIREMENTS FOR THE
RELOCA TION OF 12-INCH PIPELINE TO ACCOMMODATE
ILLINOIS STREET
CARMEL, HAMILTON COUNTY, INDIANA
MARCH 28, 2006
1. The pipeline installation work will be accomplished via standard trenching.
2. One road crossing of the existing unused roadway will be required and includes removal
of a 10 feet wide strip of existing asphalt pavement (no saw cutting and no replacement of
existing pavement).
. 3. Buckeye's pipeline contractor shall not be required to replace existing features such as
sidewalks or curbing, road pavement or any iandscaping features, should removal of any
of these existing features be required for pipeline relocation,
4. No traffic controls are required of Buckeye's pipeline contractor.
. 5. The new pipe will generally be installed with 4 feet of cover except under the road where
there will be 5 feet of cover to the topof finished pavement.
6. Buckeye's pipeline contractor will backfill and compact the trenches to existing grade.
7. Carmel's road contractor will not work above the existing pipelines until tie-in. of the new
lines is complete and the old pipe is removed or abandoned in place, unless specifically
authorized by Buckeye's field inspector.
S. Buckeye does not have to obtain a separate E&S permit; I.e., Buckeye will fall under the
Carmel's road construction permit.
9. There will be no permit fees charged to Buckeye.
10. No allowance above the generai contingency has been included in the estimate (see
Exhibits A and B) for unforeseen conditions such as rock, contaminated soils,
groundwater, etc. . .
'. 11. The schedule is based on the line pipe and fittings required for the relocation are in-stock
at the time of procurement. If they are not in-stock, then typical lead times for this material
range from 6 weeks to 20 weeks depending on the steel mill. This will increase the project
duration beyond the estimated five (5) months. .