HomeMy WebLinkAboutGN100.2#0
of
15
Date:
Sheet:
Revision:
www.caseindy.com
99 E. Carmel Drive, Suite 100
Carmel, Indiana 46032
317.846.2600 317.846.2601(f)
These drawings have been
prepared by Case Design &
Remodeling solely for its use andshould not be reproduced or relied
upon by any other parties.
Dimensions shown or scaled are
subject to change per actual job
condition and must be verified.
Materials are to be supplied as
specified as equal or standard
when not uniquely specified.Installed materials may vary in
appearance from drawings.
Reference manufacturer's product
data for actual appearance and
specifications.Young ResidenceJohn and Melissa1076 Saratoga CircleCarmel, Indiana 46280Approved By:
Date:
G002
PERMIT
Maggie Smith
Senior Designer
msmith@caseindy.com
Craig Dice
Architectural Designer
cdice@caseindy.com
GENERAL / CONSTRUCTION NOTES
DDEEMMOOLLIITTIIOONN NNOOTTEESS
GENERALGENERAL
REMOVE AND HAUL EXISTING NORTH EXTERIOR WALL OF EXISTING BACK PORCH, INCLUDING ALL SIDING, FRAMING, SLIDING DOORS, & TRIM. PROVIDE TEMPORARY BRACING & SHORING AS NECESSARY
REMOVE & HAUL EXISTING EXTERIOR WALL BETWEEN EXISTING BACK PORCH & EXISTING LIVING ROOM COMPLETE, INCLUDING ALL SIDING, FRAMING, SLIDING DOORS, DRYWALL, & TRIM
REMOVE & HAUL MINIMUM AMOUNT OF EXISTING WOOD DECKING & RAILING AS NECESSARY TO ALLOW FOR ACCESS FOR FOUNDATION / CONCRETE SLAB WORK
REMOVE AND HAUL THE FOLLOWING WINDOWS AND DOORS: SLIDING DOOR ON EXISTING LIVING ROOM AND EXISTING PORCH, AND BREAKFAST NOOK WINDOW
REMOVE AND HAUL EXISTING CONCRETE SLAB & COMPACTED FILL AS NECESSARY
REMOVE AND SALVAGE KITCHEN CABINETS AND COUNTERTOPS FOR REUSE IN GARAGE
REMOVE AND HAUL KITCHEN BACKSPLASH
REMOVE AND HAUL KITCHEN SINK
SALVAGE KITCHEN FAUCET
REMOVE AND SALVAGE APPLIANCES PER H.O.
DEMO WALLS PER PLANS
DEMO WALL ABOVE MASTER BEDROOM DOORWAY TO CREATE NEW NOOK IN MASTER BEDROOM
REMOVE AND HAUL KITCHEN CEILING LIGHT FIXTURES
REMOVE AND HAUL EXISTING FIREPLACE
REMOVE AND SALVAGE THERMOSTAT IN LIVING ROOM TO BE RELOCATED
CUT SLAB TO BRING ELECTRICAL TO ISLAND
REMOVE AND HAUL BASE AND SHOE AS NEEDED
REMOVE AND HAUL FLOORING IN KITCHEN, LIVING ROOM, DINING ROOM, FRONT CLOSET AND THROUGH HALLWAY TO GARAGE/BACK BEDROOM; REMOVE AND HAUL ALL SHOE FOR LISTED AREAS
WINDOWS:WINDOWS:
REMOVE AND HAUL THE FOLLOWING WINDOWS: MAIN KITCHEN SINK WINDOW,MASTER BEDROOM, DINING ROOM WINDOWS (2) AND TRANSOM (1), OFFICE WINDOW, AND FRONT BEDROOM WINDOW
REMOVE AND HAUL EXISTING CASINGS FOR ALL WINDOWS TO BE REPLACED
GENERALGENERAL
FURNISH AND INSTALL NEW R-10 2"THICK RIGID INSULATION, DOWN TO 24", ON INSIDE FACE OF EXISTING FOUNDATION WALL OF EXISTING BACK PORCH
FURNISH & INSTALL NEW 4"T MIN. CAST-IN-PLACE CONCRETE FLOOR SLAB OVER COMPACTED FILL; NEW CONCRETE SLAB TO BE SMOOTH FINISH AND FLUSH WITH EXISTING HOUSE CONCRETE SLAB
FURNISH & INSTALL NEW EXTERIOR WALL CONSISTING OF TREATED 2X4 BOTTOM PLATE, 2X4 WALL STUDS @ 16"O/C, R-19 KRAFT-FACED BATT INSULATION, 7/16" OSB EXTERIOR SHEATHING, & FIBER CEMENT SIDING TO
MATCH EXISTING
FURNISH & INSTALL NEW TREATED WOOD DECKING & TREATED WOOD RAILING TO MATCH EXISTING TO REPLACE REMOVED AMOUNT TO ACCESS FOUNDATION
FRAME NEW KITCHEN WALL PER PLANS
PATCH AND REPAIR DRYWALL WALLS AND CEILINGS FROM ROUGH ELECTRICAL AND PLUMBING RELOCATIONS
FRAME FOR AND INSTALL NEW WINDOW IN KITCHEN; INSTALL NEW CASING AND JAMB TO MATCH EXISTING
INSTALL NEW SINK WINDOW IN EXISTING LOCATION; REPLACE JAMB/CASING AS NEEDED
FRAME FOR AND INSTALL NEW BACK SLIDING DOOR AND (2) FLANKING WINDOWS TO BACK DECK
MODIFY WALL FRAMING AS NEEDED TO INSTALL NEW VENT TO EXTERIOR FOR MICROWAVE OVER THE RANGE
FRAME NEW WALL WITH DOORWAY IN MASTER BEDROOM FOR NEW CLOSET DOOR; MODIFY EXISTING SHELVING TO FIT NEW DEPTH OF CLOSET WALL
FRAME NEW WALL ABOVE MASTER BEDROOM DOORWAY FOR NEW NOOK
CUT AND PATCH SLAB FOUNDATION FOR BRINGING ELECTRICAL TO NEW ISLAND
FURNISH AND INSTALL NEW CABINETRY PER PLANS; INCLUDES ACCESSORIES (ROLL OUT TRAYS, UTENSIL DIVIDERS, MIXER LIFT UP, DOOR LIFT UP, SPICE DRAWER, UTENSIL PULL OUT--SEE PLANS FOR LOCATIONS)
FURNISH AND INSTALL NEW COUNTERTOPS WITH LEDGE EDGE
FURNISH AND INSTALL NEW 3X6 GLOSS TILE ON HORIZONTAL BRICK LAY
FURNISH AND INSTALL NEW BASEBOARDS AS NEEDED TO MATCH EXISTING
FURNISH AND INSTALL NEW SHOE MOLDING THROUGHOUT WORKSPACE WHERE NEW FLOORING IS INSTALLED
PPRROOPPOOSSEEDD NNOOTTEESS
3.24.22
Dawn Ashburn
Project Developer
dashburn@caseindy.com
4.01.22#1
8.02.22#2
08/11/22