HomeMy WebLinkAboutInsituform Technologies, USA, LLC/Utilities/$399,774.40/Agreement on 36-Inch Sewer Lining ProjectAGREEMENT BETWEEN OWNER AND CONTRACTOR
This Agreement is made this 17th day of August 2022, by and between City of JAQ "
Carmel, Indiana, Board of Public Works and Safety, One Civic Square, Carmel,
Indiana 46032 ("Owner") and Insituform Technologies USA, LLC ("Contractor"), for
the project known as 36-Inch Sewer Lining to be constructed on the site located in
City of Carmel, Indiana (the "Project').
Owner:
City of Carmel, Indiana
Board of Public Works and Safety
One Civic Square
Carmel, IN 46032
Contractor:
Insituform Technologies USA, LLC
580 Goddard Avenue
Chesterfield, MO 63005
Project:
2022 36-Inch Sewer Lining
Enqineer:
Jones & Henry Engineers, Ltd.
1980 E 116th St., Suite 260
Carmel, Indiana 46032
The Owner and Contractor agree as follows:
Article 1. Contract Documents. The Contract Documents consist of this Agreement,
the Drawings and the Specifications identified herein, and written modifications issued
after execution of this Agreement. The Contract Documents form the Contract for
Construction and represent the entire and integrated agreement between the parties
hereto and supersede any and all prior negotiations, representations or agreements,
either written or oral. The Contract Documents shall not be construed to create a
contractual relationship of any kind (1) between Owner and any subcontractor or (2)
between any persons or entities other than Owner and Contractor.
A. Conflicts/Order of Precedent. Contractor shall promptly call to the
attention of Owner any discrepancy or conflict in the Drawings or Specifications that
affect its Work. In the event of conflict or discrepancies between and among the
Contract Documents, figure dimensions shall take precedence over scale
measurements, large scale details shall take precedence over small scale plans or
drawings, and plans or drawings of a later date shall take precedence over those of an
earlier date and Part 4 of the technical specifications title "Special Provisions" shall
take precedence over Parts 1, 2 or 3. Any part of the Work shown on the Drawings
but not specifically mentioned in the Specifications, or vice versa, shall be considered
as part of the Work as though included in both. In the event of an inconsistency or
Agreement Between Owner and Contractor
A-1
conflict between the Drawings and Specifications, or within either document not
clarified by addendum, the better quality or greater quantity of Work shall be provided.
Likewise, the Work to be undertaken by Contractor shall include all incidental work
necessary as customarily done for the completion of the Project even though it may
not be specifically described in the Specifications or Drawings.
B. Contractor's Review of Contract Documents. Contractor has carefully
studied and compared the Contract Documents with each other and with information
furnished by Owner and has reported to Owner all errors, inconsistencies or omissions.
Contractor shall have no rights against Owner for errors, inconsistencies or omissions
in the Contract Documents unless Contractor recognized such error, inconsistency or
omission and reported it prior to the date of this Agreement. Contractor shall perform
no construction activity knowing it involves a recognized error, inconsistency or
omission in the Contract Documents. Contractor warrants and represents to Owner
that the Drawings and Specifications for the Work are suitable and adapted for said
Work and guarantees the sufficiency of said Drawings and Specifications for their
intended purpose and agrees that it will perform the Work and complete the same to
the satisfaction of Owner.
C. Enumeration of Contract Documents. An enumeration of the Contract
Documents, other than Modifications, is:
1.1 Request for Quotes Letter
1.2 This Agreement Including Exhibits D through H
1.3 Contractor's Quote
1.4 SRF Requirement Packet
1.5 General Conditions
1.6 Specifications, consisting of all sections listed in Table of Contents
thereof with the general title:
2022 36-Inch Sewer Lining
(The Specification are Not attached to this Agreement due to volume.)
1.7 Reference Drawings
1.8 Addenda numbers 1 to 2 inclusive.
1.9 The following which may be delivered or issued after the Effective Date
of the Agreement and are not attached hereto: All Written Amendments
and other documents amending, modifying, or supplementing the
Contract Documents pursuant to paragraphs 3.4 of the General
Conditions.
There are no Contract Documents other than those listed above in this Article 1. The
Contract Documents may only be amended, modified or supplemented as provided in
paragraphs 3.4 of the General Conditions.
Article 2. The Work. The intent of the Agreement is to provide for the construction
and completion in every detail of the work described. Contractor shall provide all
materials, labor, tools, equipment, supplies, safety equipment, transportation and
supervision necessary to perform, and shall perform, the work in a good and
y oT Uarmel
Agreement Between Owner and Contractor
Itbd
workmanlike manner and in accordance with the Contract Documents (as hereinafter
defined) or reasonably inferable by Contractor as necessary to produce the results
intended by the Contract Documents and generally described as 2022 36-Inch Sewer
Lining (all hereinafter called the "Work"):
A. Supervision and Construction Procedures. Contractor shall
supervise and direct the Work using Contractor's best skill and attention. Contractor
shall be solely responsible for and have control over construction means, methods,
techniques, sequences and procedures and for coordinating all portions of the Work.
Contractor shall be responsible to Owner for the acts and omissions of Contractor's
employees, subcontractors, material suppliers, laborers, equipment lessors and all
other persons performing portions of the Work. Contractor shall be responsible for the
inspection of Work performed under the Contract Documents to determine that the
Work is in proper condition to receive subsequent Work.
B. Subcontractors. Before construction commences, Contractor shall
furnish in writing to Owner the names of all persons or entities proposed for each
principal portion of the Work and their respective contract sums. Contractor shall not
contract with a proposed person or entity to whom Owner has made a reasonable
objection. Contractor shall not change a subcontractor, person or entity previously
selected if Owner makes reasonable objection to such change.
1. By appropriate agreement, Contractor shall require each subcontractor,
to the extent of the Work to be performed by the subcontractor, to be bound to
Contractor by the terms of the Contract Documents, and to assume toward Contractor
all the obligations and responsibilities which Contractor, by the Contract Documents,
assumes toward Owner. Each subcontract shall preserve and protect the rights of
Owner under the Contract Documents with respect to the Work to be performed by the
subcontractor so that subcontracting thereof will not prejudice_ such rights. Contractor
shall make available to each proposed subcontractor, prior to the execution of the
subcontract, copies of the Contract Documents to which the subcontractor will be
bound. Each subcontract for a portion of the Work is contingently assigned by
Contractor to Owner, however, such assignment is effective only after termination of
this Agreement by Owner for cause pursuant to Article 15 of the General Conditions
and only for those subcontracts which Owner accepts by notifying the subcontractor in
writing.
2. Contractor along with its Subcontractors shall assure harmonious labor
relations at and adjacent to the Project and site so as to prevent any delays, disruptions
or interference to the Work. Contractor shall prevent strikes, sympathy strikes,
slowdowns, work interruptions, jurisdictional disputes or other labor disputes resulting
for any reason whatsoever from the acts or failure to act of the employees of Contractor
or any of its subcontractors, material suppliers, or other such persons or entities.
Contractor agrees that it will bind and require all of its subcontractors, material
suppliers and other such persons or entities to agree to all of the provisions of this
paragraph. If Contractor or any of its subcontractors, material suppliers or other such
persons or entities fail to fulfill any of the covenants set forth in this paragraph,
Contractor will be deemed to be in default and substantial violation of the Contract
Documents.
Agreement Between Owner and Contractor
A-3
C. Contractor's Representations. Contractor represents and warrants
the following to Owner as a material inducement to Owner to execute this Agreement,
which representations and warranties shall survive the execution and delivery of this
Agreement, any termination of this Agreement, and the final completion of the Work:
1. Contractor is able to furnish the tools, materials, supplies, equipment and
labor required to complete the Work and perform its obligations hereunder and has
sufficient experience and competence to do so;
2. Contractor has examined and carefully studied the Contract Documents
(including the Addenda enumerated herein) and the other related data identified in the
Documents including "technical data."
3. Contractor has visited the site of the Project and is familiar with the local
conditions under which the Work is to be performed and has correlated observations
with the requirements of the Contract Documents; and
4. Contractor is familiar with and is satisfied as to all federal, state and local
Laws and Regulations that may affect cost, progress, performance and furnishing of
the Work.
5. Contractor possesses a high level of experience and expertise in the
business administration, construction and superintendence of projects of the size,
complexity and nature of the Project involving, among other things, the Work to be
performed hereunder, and will perform the Work with the care, skill and diligence of
such a contractor.
6. Contractor represents and warrants and the Owner awards this
Agreement upon the express warranty of the Contractor that he has not, nor has any
other member, representative, agent, or officer of the firm, company, corporation or
partnership represented by the Contractor:
a. employed or retained any company or person, to solicit or secure this
Agreement;
b. entered into or offered to enter into any combination, collusion, or
agreement to receive or pay and that the Contractor has not received or
paid, any fee, commission, percentage, or any other consideration,
contingent upon or resulting from the award of and the execution of this
Agreement, excepting such consideration and subject to the terms and
conditions expressed upon the face of the within Agreement.
7. Contractor has carefully studied all reports of explorations and tests of
subsurface conditions at or contiguous to the site and all drawings of physical
conditions in or relating to existing surface or subsurface structures at or contiguous to
the site (except Underground Facilities) which have been identified in the Special
Conditions as provided in paragraph 4.2.1 of the General Conditions. Contractor
accepts the determination set forth in paragraph 4.2 of the General Conditions of the
extent of the "technical data" contained in such reports and drawings upon which
Contractor is entitled to rely as provided in paragraph 4.2 of the General Conditions.
Agreement Between Owner and Contractor
A-4
Contractor acknowledges that such reports and drawings are not Contract Documents
and may not be complete for Contractor's purposes. Contractor acknowledges that
Owner and Engineer do not assume responsibility for the accuracy or completeness of
information and data shown or indicated in the Contract Documents with respect to
Underground Facilities at or contiguous to the site. Contractor has obtained and
carefully studied (or assumes responsibility for having done so) all such additional
supplementary examinations, investigations, explorations, tests, studies and data
concerning conditions (surface, subsurface and Underground Facilities) at or
contiguous to the site or otherwise which may affect cost, progress, performance or
furnishing of the Work or which relate to any aspect of the means, methods,
techniques, sequences and procedures of construction to be employed by Contractor
and safety precautions and programs incident thereto. Contractor does not consider
that any additional examinations, investigations, explorations, tests, studies or data are
necessary for the performance and furnishing of the Work at the Contract Price, within
the Contract Times and in accordance with the other terms and conditions of the
Contract Documents.
For a breach or violation of this representation, the Owner shall have the right to cancel
this Agreement without liability and to recover, at the election of the Owner, any and
all monies or other consideration paid hereunder.
8. Contractor has correlated the information known to Contractor,
information and observations obtained from visits to the site, reports and drawings
identified in the Contract Documents and all additional examinations, investigations,
explorations, tests, studies and data with the Contract Documents.
9. Contractor has given Engineer written notice of all conflicts, errors,
ambiguities or discrepancies that Contractor has discovered in the Contract
Documents and the written resolution thereof by Engineer is acceptable to Contractor,
and the Contract Documents are generally sufficient to indicate and convey
understanding of all terms and conditions for performing and furnishing of the Work.
Article 3. Engineer. The Project has been designed by Jones & Henry Engineers,
Ltd., who is hereinafter referred to as Engineer and who is to act as the Owner's
representative, assume all duties and responsibilities, and have the rights and authority
assigned to Engineer in the Contract Documents in connection with completion of the
Work all in accordance with the Contract Documents.
Article 4. Date of Commencement and Completion. Contractor shall commence
its Work promptly upon receipt of written notice from Owner to proceed with the Work,
and Contractor shall achieve Substantial Completion within ninety (90) days after the
Contract Time commences to run as provided in paragraph 2.3 of the General
Conditions, subject to adjustments authorized by Owner ("Contract Time"). The Work
shall be completed and ready for final payment in accordance with paragraph 14.7.2
of the General Conditions within One Hundred and Twenty (120) days after the date
when the Contract Time commences to run. The term "day" as used in the Contract
Documents shall mean calendar day unless otherwise specifically defined. Time limits
stated in the Contract Documents are of the essence of this Agreement. By executing
this Agreement, Contractor confirms that the Contract Time is a reasonable period for
performing the Work. Contractor shall not knowingly, except by agreement or
M., CILY Of Callne!
Agreement Between Owner and Contractor
A-5
instruction of Owner in writing, prematurely commence operations on the site or
elsewhere prior to the effective date of insurance required by Article 5 of the General
Conditions.
A. Commencement. It is not incumbent upon Owner to notify Contractor
when to begin (other than the notice to proceed), cease or resume Work, to give early
notice of the rejection of faulty Work, nor in any way to superintend so as to relieve
Contractor of responsibility or of any consequence of neglect or carelessness by
Contractor or its subordinates. All materials and labor shall be furnished at such time
as shall be for the best interest of all trades concerned, to the end that the combined
Work of all may be properly and fully completed in accordance with the progress
schedule.
B. Overtime. Owner, if it deems it reasonably necessary, may direct
Contractor to work overtime, in addition to any overtime required to meet the progress
schedule and, if so directed, Contractor shall Work said overtime. Provided that
Contractor is not in default under any of the terms or provisions of the Contract
Documents, Contractorwill be reimbursed for such actual additional wages paid, if any,
at rates which have been approved by Owner plus taxes imposed by law on such
additional wages, worker's compensation insurance and levies on such additional
wages if required to be paid by Contractor. If, however, the progress of the Work or of
the Project be delayed by any fault or neglect or act or failure to act of Contractor or
any of its officers, agents, servants or employees, then Contractor shall, in addition to
all of the other obligations imposed by this Agreement upon Contractor in such cases,
and at its own cost and expense, work such overtime as may be necessary to make
up for all time lost and to avoid delay in the completion of the Work and of the Project.
If, after written notice is given, Contractor refuses to work overtime required to make
up lost time or to avoid delay in the completion of the Work and of the Project, Owner
may hire others to perform the Work and deduct the cost from Contractor's Contract
Sum.
C. Delay. Should the progress of the Work or of the Project be delayed by
any fault or neglect or act or failure to act of Contractor or any of its officers, agents,
servants or employees so as to cause any additional cost, expense, liability or damage
to Owner, or any damages or additional costs or expenses for which Owner may or
shall become liable, Contractor shall and does hereby agree to compensate Owner for
and indemnify them against all such costs, expenses, damages and liability.
D. Excusable Delay. If Contractor is delayed, suspended, accelerated,
interfered with, or otherwise hindered (collectively referred to as "hindrance" or
"hindrances") at any time in the progress, performance or completion of any portion or
portions of the whole of the Work contemplated by the Contract Documents as a result
of flood, cyclone, hurricane, tornado, earthquake or other similar catastrophe, or as the
result of acts of God, the public enemy, acts of the Government, or fires, epidemics,
quarantine restrictions, strikes or labor disputes, freight embargoes or unusual delay
in transportation, unavoidable casualties, or abnormal weather or on account of any
acts or omissions of Owner or others engaged by it (except as herein provided), or by
their employees, agents or representatives, or by changes ordered in the Work by
Owner which are not required to correct problems or discrepancies in Contractor's
Work, or by any other causes which Contractor could not reasonably control or
circumvent, and which are not due to any fault, neglect, act or omission on Contractor's
Agreement Between Owner and Contractor
A-6
part, and the risks of which are not otherwise assumed by Contractor pursuant to the
provisions of the Contract Documents, then the Contract Time for completion of the
portion or portions of the Work directly affected by such hindrance shall, upon timely
written request of Contractor, be extended by a period equivalent to the time lost by
reason of the aforesaid causes by Change Order approved and signed by Owner.
All claims for an extension of the Contract Time shall be based on written notice
delivered to Owner and Engineer within twenty-one (21) days of the
commencement of the event or occurrence giving rise to the claim. Such notice
must set forth (a) the cause of the hindrance, (b) a description of the portion or
portions of the Work affected thereby, and (c) all details pertinent thereto,
including supporting data and the specific number of days requested. It is a
condition precedent to the consideration or validity of all claims for an extension
of the Contract Time that such claims be made in writing and delivered in strict
accordance with all applicable time limits provided above. Otherwise, such
claims shall be waived, invalid and unenforceable as against Owner.
E. No Damages for Delay. Contractor agrees that, whether or not any
hindrances shall be the basis for an extension of the Contract Time, it shall have no
claim against Owner for an increase in the Contract Sum, nor a claim against Owner
for a payment or allowance of any kind for damage, loss or expense resulting from
hindrances, except for acts constituting intentional and unjustified or unreasonable
interference, disruption or delay by Owner with Contractor's performance of its Work
when such acts continue after Contractor's written notice to Owner of such
interference, disruption or delay. Owner's exercise of its rights under the Contract
Documents, including but not limited to, its rights regarding changes in the Work,
regardless of the extent or number of such changes, performance of separate work or
carrying out Contractor's Work by Owner, directing overtime or changes in the
sequence of the Work, withholding payment or otherwise exercising its rights under
the provisions of this Agreement shall not be construed as intentional or unjustified
interference with Contractor's performance of the Work.
F. Liquidated Damages. Owner and Contractor recognize that time is of
the essence of this Agreement and that Owner will suffer financial loss if the Work is
not completed within the times specified in Article 4, plus any extensions allowed in
accordance with Article 12 of the General Conditions. They also recognize the delays,
expense and difficulties involved in proving the actual loss suffered by Owner if the
Work is not completed on time. Accordingly, instead of requiring any such proof,
Owner and Contractor agree that as liquidated damages for delay (but not as a penalty)
Contractor shall pay Owner FIVE HUNDRED DOLLARS 500.00 for each day that
expires after the time specified in Article 4 for Substantial Completion until the Work is
otherwise substantially complete. After Substantial Completion, if Contractor shall
neglect, refuse orfail to complete the remaining Work within the time specified in Article
4 for completion and readiness for final payment or any proper extension thereof
granted by Owner, Contractor shall pay Owner FIVE HUNDRED DOLLARS ($500.00)
for each day that expires after the time specified in Article 4 for completion and
readiness for final payment.
Article 5. Contract Sum. Owner agrees to pay Contractor for the timely and proper
performance of the Work, subject to additions and deductions provided therein and in
accordance with the Contract Documents in current funds based on the quote prices
Agreement Between Owner and Contractor
A-7
as set forth in the conformed copy of the Contractor's quote attached hereto as Exhibit
A, the sum of three -hundred -ninety -nine -thousand -seven -hundred -seventy -four -
dollars -and -forty -cents ($399,774.40) ("Contract Sum").
The Contract Sum, including authorized adjustments, is the total amount
payable by Owner to Contractor for performance of the Work under the Contract
Documents. In determining the Contract Sum, Contractor has taken into account the
level of completeness of the Contract Documents and has exercised its best skill and
efforts to make (1) appropriate judgments and inferences in connection with the
requirements of the Contract Documents, and (2) all inquiries to clarify the Contract
Documents as necessary to calculate and establish the Contract Sum. The Contract
Sum may be changed only by Change Order.
Article 6. Contract Payments. All payments provided herein are subject to funds as
provided by Owner and the laws of the State of Indiana. Contractor shall submit
Applications for Payment in accordance with Article 14 of the General Conditions.
Based on Applications for Payment properly submitted to Engineer by Contractor, the
Applications for Payment will be processed by Engineer as provided in the General
Conditions.
A. Progress Payments; Retainage: Owner shall make monthly progress
payments on account of the Contract Price on the basis of Contractor's Applications
for Payment as recommended by Engineer, no more often than monthly during
construction as provided below. Each Application for Payment shall be based on the
schedule of values established in paragraph 2.7 of the General Conditions (and in the
case of Unit Price Work based on the number of units properly completed) or, in the
event there is no schedule of values, as provided in the General Requirements. Such
Application for Payment shall be supported by such data substantiating Contractor's
right to payment as Owner may require, such as copies of requisitions from
subcontractors and material suppliers.
1. Owner reserves the right to inspect the Project and approve the progress
of Work completed to the date of the Application for Payment. If requested by Owner
prior to making said payment, Contractor shall submit to Owner an Affidavit and partial
Waiver of Lien, and/or partial waivers from subcontractors and material suppliers, in
form and content satisfactory to Owner, stipulating that all costs for labor and materials
incurred in the previous month have been paid to subcontractors, material suppliers,
laborers and equipment lessors. An Application for Payment shall not include requests
for payment of amounts Contractor does not intend to pay to a subcontractor or
material supplier.
a. Prior to Substantial Completion, progress payments will be made in an
amount equal to the percentage indicated below, but, in each case, less
the aggregate of payments previously made and less such amounts as
Engineer shall determine, or OWNER may withhold, in accordance with
paragraph 14.2.2.5 of the General Conditions.
b. Progress payment will be made for ninety percent (90%) of Work
completed (with the balance being held as retainage). If Work is fifty
percent (50%) complete as determined by Engineer, and if the character
and progress of the Work has been satisfactory to Owner and Engineer,
Agreement Between Owner and Contractor
A-8
Owner, at its sole discretion and without obligation, on recommendation
of Engineer, may determine that as long as the character and progress
of the Work remain satisfactory, there will be no additional retainage on
account of Work completed in which case the remaining progress
payments prior to Substantial Completion will be in an amount equal to
one hundred percent (100%) of the Work properly completed.
C. Progress payment will be made for ninety percent (90%) of invoice price
for materials and equipment not incorporated in the Work (but delivered,
suitably stored and accompanied by documentation satisfactory to
Owner as provided in paragraph 14.4 of the General Conditions).
B. Payment of Subcontractors. The Contractor agrees to assume and does
assume full and exclusive responsibility for the payment of subcontractors in
compliance with Ind. Code § 36-1-12-13. The obligation of the surety shall not in any
way be affected by the bankruptcy, insolvency, or breach of contract of the Contractor.
1. The making of an incorrect certification by the Contractor shall be
considered a substantial breach of contract on the part of the Contractor. Based on a
breach of contract, the Owner may, in addition to all other remedies, withhold all
payments not yet made and recover all payments previously made less that amount
which has actually been paid to subcontractors by the Contractor. The obligation is
hereby created on the part of the Contractor to return all such payments previously
made in such case.
2. Upon receipt of a progress payment, Contractor shall pay promptly all
valid bills and charges for materials, equipment, labor and other costs in connection
with or arising out of the Work and will hold Owner free and harmless from and against
all liens and claims of liens for such materials, equipment, labor and other costs, -or
any of them, filed against the Project or the site, or any part thereof, and from and
against all expenses and liability in connection therewith including, but not limited to,
court costs and attorneys' fees. Should any lien or claim of lien be filed of record
against the Project or the site, or should Owner receive notice of any claim or of any
unpaid bill in connection with the Work, Contractor shall forthwith either pay or
discharge the same and cause the same to be released of record or shall furnish
Owner with appropriate indemnity in form and amount satisfactory to Owner.
C. Withholding of Payment. If any claim or lien is made or filed with or
against Owner, the Project, the real estate, or contract proceeds by any person
claiming that Contractor or any subcontractor or any person for whom Contractor is
liable has failed to make payment for labor, services, materials, equipment, taxes or
other items or obligations furnished or incurred for or in connection with the Work, or if
at any time there shall be evidence of such non-payment or of any claim or lien which
is chargeable to Contractor, or if Contractor or any subcontractor or other person for
whom Contractor is liable causes damages to the Work, or if Contractor fails to perform
or is otherwise in default under any of the terms or provisions of the Contract
Documents, Owner shall have the right to retain from any payment then due or
thereafter to become due an amount which it deems sufficient to (1) satisfy, discharge
and/or defend against such claim or lien or any action which may be brought or
judgment which may be recovered thereon, (2) make good any such non-payment,
Agreement Between Owner and Contractor
A-9
damage, failure or default, and (3) compensate Owner for and indemnify him against
any and all losses, liability, damages, costs, and expenses, including attorneys' fees
and disbursements which may be sustained or incurred in connection therewith.
Owner shall have the right to apply and charge against Contractor so much of the
amount retained as may be required for the foregoing purposes. If the amount retained
is insufficient therefor. Contractor shall be liable for the difference.
1. If Owner withholds any payment, partial or final, from Contractor, Owner
may, but shall not be obligated or required to, make direct or joint payment on behalf
of Contractor for any part or all of such sums due and owing to said subcontractors,
material suppliers, equipment lessors and/or laborers for their labor, materials or
equipment furnished to the Project, not to exceed the Contract Sum remaining due and
owing to Contractor, and charge all such direct payments against the Contract Sum;
provided, however, that nothing contained in this paragraph shall create any personal
liability on the part of Owner to any subcontractor, material supplier, equipment lessor
or laborer, or any direct contractual relationship between Owner and them.
D. Substantial Completion. Upon Substantial Completion of the Work in
accordance with Article 14 of the General Conditions, the Owner shall pay the
Contractor an amount sufficient to increase total payments to Contractorto ninety-eight
percent (98%) of the Contract Sum (with the balance being retainage), less such
amounts as Engineer shall determine, or Owner may withhold, in accordance with
paragraph 14.4 of the General Conditions.
E. Final Payment. Upon final completion and acceptance of the Work in
accordance with paragraph 14.7.2 of the General Conditions, Owner shall pay the
remainder of the Contract Sum as recommended by Engineer as provided in said
paragraph 14.7.2.
1. When the Contractor completes the work in accordance with the Contract
Documents and in an acceptable matter as determined by the Engineer, the Contractor
will prepare a final estimate for the work performed and will furnish the Engineer with
a copy of the final estimate. Final payment shall not become due until Contractor
submits (a) an affidavit that payrolls, bills for materials and equipment, and other
indebtedness connected with the Work for which Owner or Owner's property might be
responsible or encumbered (less amounts withheld by Owner) have been paid or
otherwise satisfied, (2) a certificate evidencing that insurance required by the Contract
Documents will remain in force after final payment is currently in effect and will not be
canceled or allowed to expire until at least 30 days' prior written notice has been given
to Owner, (3) a written statement that Contractor knows of no substantial reason that
the insurance will not be renewable to cover the period required by the Contract
Documents, (4) consent of surety, if any, to final payment, and (5) if required by Owner,
other data establishing payment or satisfaction of obligations, such as receipts,
releases and waivers of liens, claims, security interests or encumbrances.
2. The Engineer, acting on behalf of the Owner, will then certify to the
Owner's duly appointed representative the balance due "the Contractor and the
certificate will be deemed evidence of final acceptance of the completed Agreement
by the Owner. Owner shall make final payment to the Contractor within one hundred
twenty (120) days after final acceptance and completion of the Agreement. However,
final payment may not be made on any amount that is in dispute, but final payment
Agreement Between Owner and Contractor
A-10
may be made on the part of the Contract Sum or those amounts not in dispute. For
each day after one hundred twenty (120) days, the Owner will pay to the Contractor
interest for late payment of money due to the Contractor. However, interest will not be
paid for those days that the delay in payment is not directly attributable to the Owner.
The annual percentage rate of interest that the Owner shall pay on the unpaid balance
is eight percent (8%).
3. Acceptance of final payment by Contractor shall constitute a waiver of
claims by Contractor except those previously made in writing and identified by
Contractor as unsettled at the time of final payment.
Article 7. Termination and Suspension. The Agreement may be terminated by the
Owner or the Contractor as provided in Article 15 of the General Conditions. The Work
may be suspended by the Owner as provided in Article 15 of the General Conditions.
Article 8. Interest. Unless otherwise expressly provided in the Contract Documents,
payments due to Contractor under the terms of the Contract Documents and unpaid
shall bear no interest and Contractor shall be entitled to no interest, statutory or
otherwise. If the right to interest is expressly provided in the Contract Documents, then
such interest shall apply only with respect to liquidated and non -disputed payments,
and shall accrue from and after the thirtieth (30th) day following Owner's receipt of a
statement of account by Contractor demanding such payment and containing an
express statement by Contractor of its intention to assess such interest. In the event
Owner is entitled to withhold payment under the Contract Documents, or in the event
of a good faith dispute between Owner and Contractor, no interest shall accrue.
Article 9. Owner's, Contractor's and Engineer's Representations.
9.1 The Owner's Representative is:
Mr. John Duffy, Utility Director
30 W Main Street Suite 220
Carmel, Indiana 46032
9.2 The Contractor's Representative is:
Ursula Youngblood, Contracting & Attesting Officer
580 Goddard Avenue
Chesterfield, MO 63005
Article 10. Miscellaneous.
A. GOVERNING LAW. This Agreement shall be governed by the laws of
the State of Indiana.
B. Terms used in this Agreement which are defined in Article 1 of the
General Conditions will have the meanings indicated in the General Conditions.
C. No assignment by a party hereto of any rights under or interests in the
Contract Documents will be binding on another party hereto without the prior written
Agreement Between Owner and Contractor
A-11
consent of the party sought to be bound; and, specifically but without limitation, moneys
that may become due and moneys that are due may not be assigned without such
consent (except to the extent that the effect of this restriction may be limited by law),
and unless specifically stated to the contrary in any written consent to an assignment
no assignment will release or discharge the assignor from any duty or responsibility
under the Contract Documents.
D. SUCCESSORS AND ASSIGNS. Owner and Contractor respectively
bind themselves, their successors, assigns and legal representatives to the other party
hereto in respect to covenants, agreements and obligations contained in the Contract
Documents. Neither party to this Agreement shall assign this Agreement without the
written consent of the other. If either party attempts to make such an assignment
without such consent, that party shall nevertheless remain legally responsible for all
obligations under this Agreement.
E. Any provision or part of the Contract Documents held to be void or
unenforceable under any Law or Regulation shall be deemed stricken, and all
remaining provisions shall continue to be valid and binding upon Owner and
Contractor, who agree that the Contract Documents shall be reformed to replace such
stricken provision or part thereof with a valid and enforceable provision that comes as
close as possible to expressing the intention of the stricken provision.
F. WRITTEN NOTICE. Written notice shall be deemed to have been duly
served if delivered in person to the individual or to an officer of the corporation for which
it was intended, or if delivered at or sent by registered or certified mail to the last
business address known to the party giving notice.
G. RIGHTS AND REMEDIES. Duties and obligations imposed by the
Contract Documents and rights and remedies available thereunder shall be in addition
to and not a limitation of duties, obligations, rights and remedies otherwise imposed or
available by law. No act or failure to act by Owner or Contractor shall constitute a
waiver of a right or duty afforded them under this Agreement, nor shall such action or
failure to act constitute approval of or acquiescence in a thereunder.
Article 11. Dispute Resolution.
A. Mediation. The parties shall endeavor to resolve their claims by
mediation which, if the parties mutually agree, shall be administered by the American
Arbitration Association in accordance with its Construction Industry Mediation
Procedures in effect on the date of the Agreement. The parties shall share the
mediator's fee and any filing fees equally. The mediation shall be held in the place
where the Project is located, unless another location is mutually agreed upon.
Agreements reached in mediation shall be enforceable as settlement agreements in
any court having jurisdiction thereof.
B. Litigation. In the event of any litigation between the Owner and
Contractor that arises out of or relates to this Agreement or the Project, the "prevailing
party" in such litigation shall be entitled to recover its attorneys' fees incurred in the
litigation. For the purposes of this paragraph, the term "prevailing party" shall mean
the party that recovers all or substantially of the relief requested in its pleadings, and
includes attorneys' fees incurred in the collection or enforcement of any judgment. The
parties agree that the exclusive and sole venue for any claim arising out of or relating
,.nfqewt
i y e aame
Agreement Between Owner and Contractor
A-12
to the Contract shall be any court of competent jurisdiction located in Hamilton County,
Indiana.
IN WITNESS WHEREOF, Owner and Contractor have signed five (5) copies of this
Agreement. One counterpart each has been delivered to Owner, Contractor and
Engineer. All portions of the Contract Documents have been signed or identified by
Owner and Contractor or identified by Engineer on their behalf.
r q e aame
Agreement Between Owner and Contractor
A-13
DocuSign Envelope ID: 6A9F830C-961C-41CA-88AD-8D607A5F8670
This Agreement will be effective on August 17, 2022 (which is the Effective Date of this
Agreement as defined in the General Conditions).
City of Carmel, Indiana
Owner
It's Board of Works & Public
By Safety
DocuSigned by:
e�ft`V�'rd, Presiding Officer
DocuSigned by:
°1 fie, Member
DocuSigned by:
o ,'Member
Dxuftmd by:
S K Wo4�
Attest
8/17/2022
Address forgiving notices
One Civic Square
Carmel, IN 46032
INSITUFORM TECHNOLOGIES USA, LLC.
Contractor
By dlsmla-� IA4�-
UrsulYoungb 1 ng Attesting Officer
[corporate seal]
Attest,�� ,
Jana ae
us, Contracting &Attesting Officer
Address for giving notices
580 Goddard Avenue
Chesterfield, MO 63005
License
No. not applicable
Agent for service of process:
A-14
not applicable
—CITY Tcuffw--
Agreement Between Owner and Contractor
INSTRUCTIONS FOR EXECUTING AGREEMENT
If the Contractor is a corporation, the following certificate should be executed by an
officer of the firm other than the Agreement signee:
certify that I am the Contractinq & Attesting Officer of the
limited liability company
corporation named as Contractor hereinabove; that
Ursula J. Youngblood
who signed the foregoing
Agreement on behalf of the Contractor was then
Contractinq & Attesting Officer
Limited Liability Company
of said Corperat4on;
that said Agreement was duly signed for and in behalf of
Limited Liability Company
said Gorporation by authority of its governing body, and is
within the scope of its corporate powers.
Jana L use, Contracting & Attesting Officer
(Corporate Seal)
If the Agreement is signed by the secretary of the corporation, the above certificate
should be executed by some other officer of the corporation, under the corporate seal.
In lieu of the foregoing certificate there may be attached to the Agreement copies so
much of records of the corporation as will show the official character and authority of
the officers signing, duly certified by the secretary or assistant secretary under the
corporate seal to be true copies.
The full name and business address of the Contractor should be inserted and the
Agreement should be signed with his official signature. The name of the signing party
or parties should be typewritten or printed under all signatures, o the Agreement.
If the Contractor should be operating as a partnership, ekt partner should sign the
Agreement. If the Agreement be not signed by each partner, there should be attached
to the Agreement a duly authenticated power of attorney evidencing the signer's
(signers') authority to sign such contract for and in behalf of the partnership.
Agreement Between Owner and Contractor
A-15
If the Contractor be an individual, the trade name (if the Contractor be operating under
a trade name) should be indicated in the Agreement and the Agreement should be
signed by such individual. If signed by one other than the Contractor, there should be
attached to the Agreement a duly authenticated power of attorney evidencing the
signer's authority to execute such Agreement for and in behalf of the Contractor.
Agreement Between Owner and contractor
A-16
580 Goddard Avenue
Chesterfield, MO 63005
78
Fm, A E G I 0 Nr Phone: (636) 898-8000
Insituform Fax: (636egion' Corn
1nvw.eegion.com
Stronger. Safer. Infrastructure: !
INSITUFORM TECHNOLOGIES USA, LLC
PRESIDENT APPONTMENT OF
CONTRACTING AND ATTESTING OFFICERS
The undersigned, being the President of Insituform Technologies USA, LLC, a Delaware Limited
Liability Company (the "Company"), and pursuant to the authority set forth in the Limited Liability
Company Operating Agreement of the Company, hereby determines that:
Christlanda Adkins, Janet Hass, Jana Louse, Diane Partridge, Whittney Schulte, and Ursula
Youngblood are appointed as Contracting and Attesting Officers of the Company, each with the
authority, individually and in the absence of the others, subject to the control of the Board of
Managers of the Company, to: (i) certify and attest to the signature of any officer of the
Company; (ii) enter into and bind the Company to perform pipeline rehabilitation activities of the
Company and all matters related thereto, including the maintenance of one or more offices and
facilities of the Company; (iii) execute and to deliver documents on behalf of the Company; and
(iv) take such other action as is or may be necessary and appropriate to carry out the project,
activities and work of the Company.
2.. Any person previously appointed or serving as a Contracting and Attesting Officer of the
Company prior to the date hereof and who is not named above is hereby removed from any such
appointment.
Dated: March 25, 2022
w
Burt . Ke. i
President
�M AEGION'
Stronger. Safer. Infrastructure:
Insifuform
INSUITUFORM TECHNOLOGIES USA, LLC
BOARD OF MANAGERS AND OFFICERS
(Current as of October 1, 2021)
BOARD OFMANAGERS
Robert Tullman
Member Board of Managers
Monts, M. Bolles
Member Board of Managers
Timothy J. Gallagher
Member, Board of Managers
OFFICERS
Name
Office
Ralph E. Western
President
David F. Morris
Executive Vice President & Chief Financial Officer
Monts. M. Bolles
Executive Vice President, Chief Legal Officer, Chief HR Officer
& Secretary
Kent W. Bartholomew
Sr. Vice President & Assistant Secretary
John L. Heggemann
Sr. Vice President
Donald E. Hake
Sr. Vice President & Treasurer
Dennis Pivin
Vice President — Safety
CONTRACTING AND ATTESTING OFFICERS
Christlanda Adkins
Gina Gurrieri
Janet Hass
Jana Lause
Diane Partridge
Whittney Schulte
Ursula Youngblood
Business Address for Board of Managers and Officers:
17988 Edison Avenue
Chesterfield, MO 63005
EXHIBIT D
CONTRACTOR'S AFFIDAVIT AND WAIVER OF LIENS AND CLAIMS
(_) FINAL (_) PARTIAL (_) PAYMENT TO FOLLOW
OWNER: City of Carmel, Indiana Department PROJECT:
of Public Works.
CONTRACTOR: CONTRACT DATE:
being duly sworn states that he or she is the of
CONTRACTOR, which was awarded Contract No. with the OWNER in accordance with the
contract terms and conditions to install and/or furnish certain materials and labor as follows:
("Work") for the Project,
DOES HEREBY STATE, WARRANT AND REPRESENT ON BEHALF OF THE CONTRACTOR the following:
PARTIAL WAIVER That the balance due from OWNER is the sum of ($ ).
() Receipt of which is hereby acknowledged; or
() Payment of which has been promised as the sole consideration for this AFFIDAVIT AND WAIVER OF LIENS
AND CLAIMS and which is given to and for said amount effective upon receipt of such payment.
FINAL WAIVER That the final balance due from OWNER is the sum of ($ ).
() Receipt of which is hereby acknowledged; or
() Payment of which has been promised as the sole consideration for this AFFIDAVIT AND WAIVER OF LIENS
AND CLAIMS which is given to and for said amount effective upon receipt of such payment.
THEREFORE, through the date hereof. Contractor waives and releases the Owner and Project of all liens or claims,
including, but not limited to, claims for materials, equipment, labor, superintendence and other services or Work
performed or furnished by Contractor and further affirms that no other party has any claim or right to lien on account of
any materials, equipment, labor, superintendence and other services or Work performed or furnished to or for
Contractor for the Project. Contractor agrees to indemnify, defend and hold the Owner and Project harmless, including
costs and attorneys' fees, from and against any and all claims or liens for any subcontractors, materials, supplies,
equipment or labor furnished for, in connection with or incorporated into the Project by, through or under Contractor
through the date hereof. This Affidavit and Waiver of Liens is given to induce Owner to pay the amount indicated
above. Contractor represents that all employees, subcontractors or materialmen have been paid or will be paid from
these funds.
That through the date hereof, all Affidavits and Waiver of Liens and Claims are true, correct and unconditional and that
there is no claim either legal or equitable to defeat the validity of said Affidavits and Waiver of Liens and Claims. That
the following are the names of all parties who have furnished material or labor, or both, for said Work and all parties
having contracts or subcontracts for specific portions of said Work or for material used in the construction thereof and
the amount due or to become due to each, and that the items mentioned include all labor and material required to
complete said Work according to Project plans and specifications:
1
2
3
4
5
6
7
CONTRACTOR
TYPE OF
WORK
AMOUNT OF
CONTRACT
TOTAL
RETAINED
NET
PREVIOUSLY
PAID
NET
AMOUNT
THIS
PAYMENT
BALANCE
TO
BECOME
DUE
TOTAL
AMOUNT OF ORIGINAL CONTRACT
WORK COMPLETED TO DATE
EXTRAS TO CONTRACT
LESS RETAINAGE
TOTAL CONTRACT & EXTRAS
NET AMOUNT EARNED
CREDITS TO CONTRACT
NET PREVIOUSLY PAID
ADJUSTED TOTAL CONTRACT
NET AMOUNT OF THIS PAYMENT
BALANCE TO BECOME DUE
2022 36-Inch Sewer Lining A-22 CITY OF CARMEL
This instrument has been executed as of the day of , 20_
CONTRACTOR:
STATE OF
COUNTY
OF
INDIANA
M
Name:
Title:
Sworn to and subscribed before me the undersigned authority on this
, 20_
Notary Public, State
of
Printed Name of
Notary
[ SEAL]
My Commission Expires:
day of
2022 36-Inch Sewer Lining A-22 CITY OF CARMEL
EXHIBIT E
SUBCONTRACTOR AFFIDAVIT AND WAIVER OF LIENS AND CLAIMS
(_) FINAL (_) PARTIAL (_) PAYMENT TO FOLLOW
OWNER: City of Carmel, Indiana Department PROJECT:
of Public Works.
SUBCONTRACTOR: CONTRACT DATE:
being duly sworn states that he or she is the of
SUBCONTRACTOR, which entered into a contract in writing with ("CONTRACTOR") who was
awarded Contract No. with the OWNER in accordance with the contract terms and conditions
to install and/or furnish certain materials and labor as follows:
("Work") for the Project,
DOES HEREBY STATE, WARRANT AND REPRESENT ON BEHALF OF THE SUBCONTRACTOR the following:
PARTIAL WAIVER That the balance due from CONTRACTOR is the sum of ($ 1.
() Receipt of which is hereby acknowledged; or
() Payment of which has been promised as the sole consideration for this AFFIDAVIT AND WAIVER OF LIENS
AND CLAIMS and which is given to and for said amount effective upon receipt of such payment.
FINAL WAIVER That the final balance due from CONTRACTOR is the sum of ($ 1.
() Receipt of which is hereby acknowledged; or
() Payment of which has been promised as the sole consideration for this AFFIDAVIT AND WAIVER OF LIENS
AND CLAIMS which is given to and for said amount effective upon receipt of such payment.
THEREFORE, through the date hereof, Subcontractor waives and releases the Owner, Contractor and Project of all
liens or claims, including, but not limited to, claims for materials, equipment, labor, superintendence and other services
or Work performed or furnished by Subcontractor and further affirms that no other party has any claim or right to lien
on account of any materials, equipment, labor, superintendence and other services or Work performed or furnished to
or for Subcontractor for the Project. Subcontractor agrees to indemnify, defend and hold the Owner, Contractor and
Project harmless, including costs and attorneys' fees, from and against any and all claims or liens for any sub -
subcontractors, materials, supplies, equipment or labor furnished for, in connection with or incorporated into the Project
by, through or under Subcontractor through the date hereof. This Affidavit and Waiver of Liens is given to induce
Contractor to pay the amount indicated above. Subcontractor represents that all employees, subcontractors or
materialmen have been paid or will be paid from these funds.
That through the date hereof, all Affidavits and Waiver of Liens and Claims are true, correct and unconditional and that
there is no claim either legal or equitable to defeat the validity of said Affidavits and Waiver of Liens and Claims. That
the following are the names of all parties who have furnished material or labor, or both, for said Work and all parties
having contracts or subcontracts for specific portions of said Work or for material used in the construction thereof and
the amount due or to become due to each, and that the items mentioned include all labor and material required to
complete said Work according to Project plans and specifications:
1
2
3
4
5
6
7
SUBCONTRACTOR
TYPE OF
WORK
AMOUNT
OF
CONTRACT
TOTAL
RETAINED
NET
PREVIOUSLY
PAID
NET
AMOUNT
THIS
PAYMENT
BALANCE
TO
BECOME
DUE
TOTAL
AMOUNT OF ORIGINAL CONTRACT
EXTRAS TO CONTRACT
TOTAL CONTRACT & EXTRAS
CREDITS TO CONTRACT
ADJUSTED TOTAL CONTRACT
WORK COMPLETED TO DATE _
LESS RETAINAGE
NET AMOUNT EARNED
NET PREVIOUSLY PAID
NET AMOUNT OF THIS PAYMENT
BALANCE TO BECOME DUE
2022 36-Inch Sewer Lining CITY OF CARMEL
A-24
This instrument has been executed as of the day of , 20.
CONTRACTOR:
Name:
Title:
STATE OF INDIANA
COUNTY
OF
Sworn to and subscribed before me the undersigned authority on this
, 20_
Notary Public, State
of
Notary
[ SEAL]
My Commission Expires:
Name of
day of
2022 36-Inch Sewer Lining CITY OF CARMEL
A-24
EXI Illil I I
CHANGE ORDER
Change Order No
Date:
Contract Date:
Name of Project: 2022 36-Inch Sewer Lining
Owner:
Contractor:
The following changes are hereby made to the Agreement:
Description of Change in Work:
Justification:
Original Contract Price:
Previous Changes to Contract Price:
Current Contract Price adjusted by previous
Change Order(s):
The Contract Price due to this Change
Order will be (increased)(decreased) by:
The new Contract Price including this
Change Order will be:
Change to Contract Time:
H
The Contract Time will be (increased)(decreased) by
The date for completion of all work will be
Requested by:
(Owner)
calendar days.
(Date)
Recommended by:
(Consulting Engineer) (Date)
Accepted by:
(Contractor) (Date)
Approved by:
(Name and Title)
One Copy — Owner
One Copy — Contractor
One -Copy- Ertgineer
2022 36-Inch Sewer Lining A-25 CITY OF CARMEL
Change Order Form
EXHIBIT G
CONFINED SPACE
REQUIREMENT ACKNOWLEDGEMENT
The undersigned hereby warrants and represents that they are familiar with and have
reviewed the OSHA requirements concerning entry into confined spaces.
The undersigned hereby further warrants and represents that they have made all
employees, agents, or independent contractors including, but not limited to
subcontractors employed by them who will be working on the site familiar with these
requirements.
The undersigned hereby further warrants and represents that all employees, agents, or
independent contractors including, but not limited to subcontractors employed by them
who will be working on the site will comply with all requirements concerning entry into
confined spaces including, but not limited to, additional requirements which might be
imposed pursuant to state and federal regulations.
rsa,k � tiounaGPi '
JrsuIAJ. YoungbIoLdJ Si ature
Contracting & Attesting Officer
580 Goddard Avenue
Chesterfield MO 63005
Company (Address)
2022 36-Inch Sewer Lining CITY OF CARMEL
A-26
Exhibit H
Clause and Affidavit to be added to Contract
For Services to be provided to
CITY OF CARMEL, INDIANA
(as required by Indiana SEA 590, effective July 1, 2011)
VERIFICATION OF WORK ELIGIBILITY STATUS
I. Ursula J. Youngblood for INSITUFORM TECHNOLOGIES USA, LLC. (hereinafter called
"Contractor") understands and agrees that it is required to enroll in and verify the work
eligibility status of all employees hired after the date of this contract through the E-Verify
program. This requirement shall be waived if the E-Verify program ceases to exist. For the
purposes of this paragraph, the "E-Verify program" means the electronic verification of work
authorization program of the Illegal Immigration Reform and Immigration Responsibility Act
of 196 (P.L. 104-208), Division C, Title IV, s. 403(a), as amended, operated by the United
States Department of Homeland Security or a successor work authorization program
designated by the United States Department of Homeland Security or other federal agency
authorized to verify the work authorization status of newly hired employees under the
Immigration Reform and Control Act of 1986 (P.L. 99-603).
2. An authorized representative of the Contractor has signed the affidavit below concerning
the employment of unauthorized aliens.
AFFIDAVIT CONCERNING EMPLOYMENT
OF UNAUTHORIZED ALIENS
I am a duly authorized officer of INSITUFORM TECHNOLOGIES USA, LLC.
(hereinafter called "Contractor") and I hereby certify that as of the date of this Affidavit,
Contractor does not employ any "unauthorized aliens" as that term is defined in 8 U.S.C. 1324a
(h)(3).
I AFFIRM UNDER THE PENALTIES FOR PERJURY THAT THE FOREGOING
REPRESENTATIONS ARE TRUE.
Dated: 8August 2022 2I � L�I� /S4
Signature f L/ jk
Ursula J. Youngblood, Contracting & Attesting Officer
Printed Name
8 U.S.C. 1324a(h)(3) Definition of unauthorized alien
As used in this section, the term "unauthorized alien" means with respect to the employment
of an alien at a particular time, that the alien is not at that time either
(A) An alien lawfully admitted for permanent residence, or
_ (B) Authorized to he sn emnloynd by this chapter or bv the Attorne , General
NOTICE TO PROCEED
Dated 2022
TO:
ADDRESS:
PROJECT: 36-Inch Sewer Lining
OWNER's CONTRACT NO.:
CONTRACT FOR: City of Carmel, Indiana
You are notified that the Contract Times under the above contract will commence to run on
.2022. By that date, you are to start performing your obligations under the Contract
Documents. In accordance with Article 4 of the Agreement the dates of Substantial Completion
and completion and readiness for final payment are . 2022 and .2022.
Before you may start Work at the site, paragraph 2.5 of the General Conditions provides
that you must deliver to the Owner (with copies to ENGINEER and other identified additional
insureds) certificates of insurance which you are required to purchase and maintain in
accordance with the Contract Documents.
Also before you may start any Work at the site, you must
M
cc: Project Engineer
John Duffy
City of Carmel, Indiana
(OWNER)
(AUTHORIZED SIGNATURE
Utility Director
(TITLE)
Notice to Proceed
SRF REQUIREMENTS
This project is funded by the Indiana State Revolving Fund (SRF). The Contractor shall comply with all
SRF requirements written or referenced in the following included documents.
�. vow �acn'eir
a. Attachment A: Form WH-347
b. Attachment B: Required Provisions Related to Davis -Bacon Act and Related Acts
c. Attachment C: Required Contract Provisions Related to Wage -Fringe Benefit
Certification
d. Attachment D: IFA Wage -Fringe Benefit Certification Form
e. Attachment E: Required Contract Provision Related to Suspension and
Debarment
2. Certification of Nonsegregated Facilities
3. Notice of Workers Nondiscrimination in Employment
4.
form
5. Davis -Bacon wage rates (te beissaed by adderrdaj
2022 36-Inch Sewer Lining
SRF Requirements
INDIANA STATE REVOLVING FUND LOAN PROGRAM
DBE PACKET
This packet lists required contract conditions that apply to all Clean Water and Drinking Water
State Revolving Fund projects and contains forms that must be used in the procurement process.
This packet must be physically included in all bidding and contract documents.
This project is being financed in whole or in part by the Indiana State Revolving Fund Loan
Programs. The loan recipient is required to comply with the following federal and state laws, rules
and regulations and must ensure that their contractor(s) also comply with these regulations, laws and
rules.
1. Title VI of the Civil Rights Act of 1964 (P.L 88-352), the Rehabilitation Act of 1973 (P.L. 93-
1123, 87 Stat. 355, 29 U.S.C. Sec. 794), the Older Americans Amendments of 1975 (P.L. 94-
135 Sec. 303, 89 Stat. 713, 728, 42 U.S.C. Sec. 6102), and subsequent regulations, ensures
access to facilities or programs regardless of race, color, national origin, sex, age or handicap.
2. Executive Orders 11246, as amended by Executive Orders 11375 and 12086 and subsequent
regulations. Prohibits employment discrimination on the basis of race, color, religion, sex or
national origin. Inclusion of the seven clauses in Section 202 of E. O. 11246 as amended by E.
O. 11375 and 12086 are required in all project related contracts and subcontracts over $10,000.
3. 40 CFR Part 33 Participation by Disadvantaged Business Enterprises in Procurement under
Environmental Protection Agency (EPA) Financial Assistance Agreements
4. Executive Orders 11625, 12138 and 12432; 40 CFR part 33; Section 129 of P. L. 100-590
Small Businesses Reauthorization & Amendment Act of 1988; Public Law 102-389 (42 U.S.C.
437d); a 1993 appropriations act ("EPA's 8% statute"); Public Law 101-549, Title X of the
Clean Air Acts Amendments of 1990 (42 U.S.C. 7601 note) ("EPA's 10% statute").
Encourages recipients to award construction, supply and professional service contracts to
minority and women's business enterprises (MBEIWBE) and small businesses and requires
recipients to utilize affirmative steps in procurement.
5. Executive Order 12549 and 40 CFR Part 32, Subparts B and C. Prohibits entering into
contracts or sub -contracts with individuals or businesses who are debarred or suspended.
Borrowers are required to check the status of all contractors (construction and professional
services) and must require contractors to check the status of subcontractors for contracts
expected to be equal to or over $25,000 via this Internet address: www.sam.aov
6. Indiana Code 36-1-12-12, Requires the board to withhold final payment to contractor until the
contractor has paid the subcontractors, material suppliers, laborers, or those furnishing services
7. Indiana Code 36-1-12-13.1, requires performance and payments bonds equal to 100% of the
contract price if the cost of the public work is estimated to be more than $200,000.
Equal Employment
Inclusion of these seven clauses (excerpt from Executive Order No. 11246, Section 202 as amended by
Executive Order 11375 and 12086) is required in all CWSRF and DWSRF project related contracts
and subcontracts over $10,000:
During the performance of this contract, the contractor agrees as follows:
The contractor will not discriminate against any employee or applicant for employment because
of race, color, religion, sex or national origin. The contractor will take affirmative action to
ensure that applicants are employed, and that employees are treated during employment, without
regard to their race, color, religion, sex, or national origin. Such action shall include, but not be
limited to the following: employment, upgrading, demotion, or transfer; recruitment or
recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and
selection for training, including apprenticeship. The contractor agrees to post in conspicuous
places, available to employees and applicants for employment, notices to be provided by the
contracting officer setting forth the provisions of this nondiscrimination clause.
2. The contractor will, in all solicitations or advertisements for employees placed by or on behalf
of the contractor, state that all qualified applicants will receive consideration for employment
without regard to race, color, religion, sex, or national origin.
The contractor will send to each labor union or representative of workers with which he has a
collective bargaining agreement or other contract or understanding, a notice, to be provided by
the agency contracting officer, advising the labor union or worker's representative of the
contractor's commitments under Section 202 of Executive Order No. 11246 of September 24,
1965, and shall post copies of the notice in conspicuous places available to employees and
applicants for employment.
4. The contractor will comply with all provisions of Executive Order No. 11246 of Sept. 24, 1965,
and all of the rules, regulations, and relevant orders of the Secretary of Labor.
5. The contractor will furnish all information and reports required by Executive Order No. 11246
of Sept. 24, 1965, and by the rules, regulations and orders of the Secretary of Labor, or pursuant
thereto, and will permit access to his books, records, and accounts by the contracting agency and
the Secretary of Labor for purposes of investigation to ascertain compliance with such rules,
regulations, and orders.
6. In the event of the contractor's noncompliance with the nondiscrimination clauses of this
contract or with any of such rules, regulations, or orders, this contract may be cancelled,
terminated or suspended in whole or in part and the contractor may be declared ineligible for
further Government contracts in accordance with procedures authorized in Executive Order No.
11246 of Sept. 24, 1965, and such other sanctions may be imposed and remedies invoked as
provided in Executive Order No. 11246 of Sept. 24, 1965, or by rule, regulation, or order of the
Secretary of Labor, or as otherwise provided by law.
The contractor will include the provisions of paragraphs (1) through (7) in every subcontract or
purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued
pursuant to Section 204 of Executive Order No. 11246 of Sept. 24, 1965, so that such provisions
will be binding upon each subcontractor or vendor. The contractor will take such action with
respect to any subcontract or purchase order as may be directed by the Secretary of Labor as a
2
means of enforcing such provisions including sanctions for noncompliance: Provided, however,
that in the event the contractor becomes involved in, or is threatened with, litigation with a
subcontractor or vendor as a result of such direction, the contractor may request the United
States to enter into such litigation to protect the interests of the United States.
-Bisadvantaged-Busittew En
with -Efforts-
Borrowe r grime contractors must follow, document, and in
documentation of their
good faith efforts to mee Re MI�1 BE goals as listed below to ensure that Disadvantage Business
Enterprises (DBEs) have the opportunity top ' ' ne n the project by increasing DBE awareness of
procurement efforts and outreach. In order to become a certi ie er this rule, an eligible
entity must submit an application that can be found by visiting: httns://www.in.eov ' ealtr1cbe
ontracts and subcontracts to be awarded to MBEs and WBEs and their
participation in the Contractor's aggrega a on all construction work for the
subject project are as follows:
MBFs 7 %-
0
—T. re made aware of contracting opportunities to the fullest extent practicable
through outreach and recrut me ; ' lacing DBEs on solicitation lists and
soliciting them whenever they are potential sources.
rmation on forthcoming opportunities available to DBEs and arrange time frames for
contracts and esta schedules, where the requirements permit, in a way that
encourages and facilitates participation the competitive process. This includes,
whenever possible, posting solicitation for bids or proposa s um of 30 calendar days
before the bid or proposal closing date.
C-onsidgr in the contracting process whether firms competing for large contracts could be
subcontracte wi s will include dividing total requirements when economically
feasible into smaller tasks or quantities ximum participation by DBEs in the
competitive process. Encourage contracting with a consortm hen a contract is too
large for one of these firms to handle individually.
nce of the Small Business Administration and the Minority Business
Development Agency of the U. S. Departmen o
awards subcontracts, require the prime contractor to take the steps in
numbers 1 through
Rea uired Contract Conditions
must be included in all procurement contracts entered into by the loan recipient for all
SRF projects:
1. The prime cont or must pay its subcontractor for satisfactory performance no more than 30
days from the prime c actor's receipt of payment from the loan recipient.
2. The prime contractor must notify loan recipient in writing prior to the termination of any
DBE subcontractor for convenience by rime contractor.
3. If a DBE subcontractor fails to complete work un a subcontract for any reason, the prime
contractor must employ the six good faith efforts if solicr ' a replacement subcontractor.
4. The prime contractor must employ the six good faith efforts even if rime contractor has
achieved its fair share objectives.
5. Each procurement contract signed must include the Following term and condition:
"The contractor shall not discriminate on the basis of race, color, national origin or sex in
the performance of this contract. The contractor shall carry out applicable requirements
of 40 CFR Part 33 in the award and administration of contracts awarded under EPA
financial assistance agreements. Failure by the contractor to carry out these requirements
is a material breach of this contract which may result in the termination of this contract
or other legally available remedies."
\ {
((
fla !
f
z
\ \\ )\
!;! 9
G){ �
g
.
- �
z
\\{ g
k \
fi\,
-
k
! !
:
-- ;3iT _:
\§§
._! -
\ /
§
-
)
)
\
_#
G ! #\
/
q ! !!
f
\tr�(
0
/
0 /
`
/ (( `�
_
f!
\){
_
§
o
'0 - §
`
-
i{!E -
)
~
/
\j\ -
))!
\ ;{
2
]
03
E
)
:0
all?
/E\
/
j \
\
�(
q
\
§«
r�
o�
F
UQoo
QN
Z
00
U�
Z
0
WH
FO
r
a
JF
N ~
IIIXLLL
Y~
o
Wf
f
1a-NW
N>W
N
�Z
U
rw
O�
a
u
LL a
°UW
p
ODUO
�Sw
w
w
OF
X
LL
�ON
W
LLow
F
JUZ
J�J
a
w
3 �
mmo
cam,
' N aJ
_Ti
LU N N v o m C� L
d E
'c«« C�Km K ='moo
-� g
S°'l�
O
y
'
VEvp
Kc
-
me8tTmN'Ey
2«
wocE
v N eOO.
Lmc
'E
am
_S.N°
LBv
m y 0 Nry
y
N N r:
a U
'p N-6 01 pCq1 O N
L C O LL r
m
m
DNQo
N u .d. m y
ta' S '9 �aiE
° m�0
E M c 2
E v v j u N z u° QN
O 3
N
m ij 6�
"C N 2 m L' 2
N O eo
:0,
� ap
O U C m � � W� X b
yi L
N
O ° n O C n O C
O n^
L O
5 wm
ioi cmam
L o
'J s a8aw a .mw.!°1a>
m� a @vnc
rn vL
56g
N C,�
v o._Jin
c�0a
QEm
mEC" NJD Q mo
v'0S.mn
'
n m
�
n nn H
12
�Ea
0
Dm N
o2'bd
—�n
mDGo
mE._Q:2 vcJ
m o Lry
E0mvw
'N nUCN
LN ❑ a
N Cy y-LN
?
�ry`pJ
Cm U
'O° md m
6 N LU16° = m
N C mm
DC
O m
C
m12 ° LL y v
L
Cp W m
mJ N xO
C U nWW «Po
n
p C'''dpppN
C S W. N C J m O) N
iy
'�pV
ie
CD=�
LLmC_ �g
'-' N m
N
C L
m of.:
T m .'wN
nE�rn
O
m C C« Z D m d
N O L dC L K m d m E
po --
c«N nE'�. W 5«Lv
0o
E°�jv`�i
$=��°O TE�� w
n E
y mm
c n m� m n m« 3❑
N `. @ o L)
L mo �'nN vn nn%
a v oM� s m u m nin
U1
Attachment B
Required Contract Provisions Related to Davis -Bacon Act and Related Acts
Provisions substantially like the following shall be included in each procurement contract for
the actual construction, attention and/or repair, including painting and decorating. The SRF
Applicant shall remain responsible for compliance with applicable law (including Davis Bacon
and related Acts). Such SRF Applicant has been encouraged to consult with its advisors and
counsel regarding such matters and, in any event, understands that the use of the following does
not relieve the SRF Applicant from its obligation to comply with applicable law (including Davis
Bacon and related Acts) and related provisions of any financial assistance agreement entered into
with the Indiana Finance Authority, nor will the State Revolving Fund Loan Programs, the
Indiana Finance Authority or the State of Indiana be responsible for or limited by any SRF
Applicant's use of the following provision.
(1) Minimum wages.
(i) All laborers and mechanics employed or working upon the site of the work will be paid
unconditionally and not less often than once a week, and without subsequent deduction or rebate
on any account (except such payroll deductions as are permitted by regulations issued by the
Secretary of Labor under the Copeland Act (29 CFR part 3) ), the full amount of wages and bona
fide fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not
less than those contained in the wage determination of the Secretary of Labor which is attached
hereto and made a part hereof, regardless of any contractual relationship which may be alleged to
exist between the contractor and such laborers and mechanics.
Contributions made or costs reasonably anticipated for bona fide fringe benefits under section
I (b)(2) of the Davis -Bacon Act on behalf of laborers or mechanics are considered wages paid to
such laborers or mechanics, subject to the provisions of paragraph (1)(iv) of this section; also,
regular contributions made or costs incurred for more than a weekly period (but not less often
than quarterly) under plans, funds, or programs which cover the particular weekly period, are
deemed to be constructively made or incurred during such weekly period. Such laborers and
mechanics shall be paid the appropriate wage rate and fringe benefits on the wage determination
for the classification of work actually performed, without regard to skill, except as provided in
Section (4). Laborers or mechanics performing work in more than one classification may be
compensated at the rate specified for each classification for the time actually worked therein:
Provided, That the employer's payroll records accurately set forth the time spent in each
classification in which work is performed. The wage determination (including any additional
classification and wage rates conformed under paragraph (1)(ii) of this section) and the Davis -
Bacon poster (WH-1321) shall be posted at all times by the contractor and its subcontractors at
the site of the work in a prominent and accessible place where it can be easily seen by the
workers.
(ii)(A) The ]SRF Applicant], on behalf of EPA, shall require that any class of laborers or
mechanics, including helpers, which is not listed in the wage determination and which is to be
employed under the contract shall be classified in conformance with the wage determination.
The EPA award official shall approve an additional classification and wage rate and fringe
benefits therefore only when the following criteria have been met:
(1) The work to be performed by the classification requested is not performed by a classification
in the wage determination; and
(2) The classification is utilized in the area by the construction industry; and
(3) The proposed wage rate, including any bona fide fringe benefits, bears a reasonable
relationship to the wage rates contained in the wage determination.
(B) If the contractor and the laborers and mechanics to be employed in the classification (if
known), or their representatives, and the [SRF Applicant] agree on the classification and wage
rate (including the amount designated for fringe benefits where appropriate), a report of the
action taken shall be sent by the [SRF Applicant] to the State award official. The State award
official will transmit the report, to the Administrator of the Wage and Hour Division,
Employment Standards Administration, U.S. Department of Labor, Washington, DC 20210. The
Administrator, or an authorized representative, will approve, modify, or disapprove every
additional classification action within 30 days of receipt and so advise the State award official or
will notify the State award official within the 30-day period that additional time is necessary.
(C) In the event the contractor, the laborers or mechanics to be employed in the classification or
their representatives, and the and the [SRF Applicant] do not agree on the proposed
classification and wage rate (including the amount designated for fringe benefits, where
appropriate), the award official shall refer the questions, including the views of all interested
parties and the recommendation of the State award official, to the Administrator for
determination. The Administrator, or an authorized representative, will issue a determination
within 30 days of receipt and so advise the contracting officer or will notify the contracting
officer within the 30-day period that additional time is necessary.
(D) The wage rate (including fringe benefits where appropriate) determined pursuant to
paragraphs (1)(ii)(B) or (C) of this section, shall be paid to all workers performing work in the
classification under this contract from the first day on which work is performed in the
classification.
(iii) Whenever the minimum wage rate prescribed in the contract for a class of laborers or
mechanics includes a fringe benefit which is not expressed as an hourly rate, the contractor shall
either pay the benefit as stated in the wage determination or shall pay another bona fide fringe
benefit or an hourly cash equivalent thereof.
(iv) If the contractor does not make payments to a trustee or other third person, the contractor
may consider as part of the wages of any laborer or mechanic the amount of any costs reasonably
anticipated in providing bona fide fringe benefits under a plan or program, provided, that the
Secretary of Labor has found, upon the written request of the contractor, that the applicable
standards of the Davis -Bacon Act have been met. The Secretary of Labor may require the
contractor to set aside in a separate account assets for the meeting of obligations under the plan
or program.
(2) Withholding. The [SRF Applicant], shall upon written request of the EPA Award Official
or an authorized representative of the Department of Labor, withhold or cause to be withheld
from the contractor under this contract or any other Federal contract with the same prime
contractor, or any other federally -assisted contract subject to Davis -Bacon prevailing wage
requirements, which is held by the same prime contractor, so much of the accrued payments or
advances as may be considered necessary to pay laborers and mechanics, including apprentices,
trainees, and helpers, employed by the contractor or any subcontractor the full amount of wages
required by the contract. In the event of failure to pay any laborer or mechanic, including any
apprentice, trainee, or helper, employed or working on the site of the work, all or part of the
wages required by the contract, the (Agency) may, after written notice to the contractor, sponsor,
applicant, or owner, take such action as may be necessary to cause the suspension of any further
payment, advance, or guarantee of funds until such violations have ceased.
(3) Payrolls and basic records.
(i) Payrolls and basic records relating thereto shall be maintained by the contractor during the
course of the work and preserved for a period of three years thereafter for all laborers and
mechanics working at the site of the work. Such records shall contain the name, address, and
social security number of each such worker, his or her correct classification, hourly rates of
wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or
cash equivalents thereof of the types described in section I (b)(2)(B) of the Davis -Bacon Act),
daily and weekly number of hours worked, deductions made and actual wages paid. Whenever
the Secretary of Labor has found under 29 CFR 5.5(a)(1)(iv) that the wages of any laborer or
mechanic include the amount of any costs reasonably anticipated in providing benefits under a
plan or program described in section I (b)(2)(B) of the Davis -Bacon Act, the contractor shall
maintain records which show that the commitment to provide such benefits is enforceable, that
the plan or program is financially responsible, and that the plan or program has been
communicated in writing to the laborers or mechanics affected, and records which show the costs
anticipated or the actual cost incurred in providing such benefits. Contractors employing
apprentices or trainees under approved programs shall maintain written evidence of the
registration of apprenticeship programs and certification of trainee programs, the registration of
the apprentices and trainees, and the ratios and wage rates prescribed in the applicable programs.
(ii)(A) The contractor shall submit weekly, for each week in which any contract work is
performed, a copy of all payrolls to the [SRF Applicant], that is, the entity that receives the sub -
grant or loan from the State capitalization grant recipient. Such documentation shall be available
on request of the State recipient or EPA. As to each payroll copy received, the [SRF Applicant]
shall provide written confirmation in a form satisfactory to the State indicating whether or not
the project is in compliance with the requirements of 29 CFR 5.5(a)(1) based on the most recent
payroll copies for the specified week. The payrolls shall set out accurately and completely all of
the information required to be maintained under 29 CFR 5.5(a)(3)(i), except that full social
security numbers and home addresses shall not be included on the weekly payrolls. Instead the
payrolls shall only need to include an individually identifying number for each employee (e.g.,
the last four digits of the employee's social security number). The required weekly payroll
information may be submitted in any form desired. Optional Form WH-347 is available for this
purpose from the Wage and Hour Division Web site at
http://www.dol.gov/esa/whd/forms/wh347instr.htm or its successor site. The prime contractor is
responsible for the suhmiseinn of conies of Payrolls by all subcontractors. Contractors and
subcontractors shall maintain the full social security number and current address of each covered
worker, and shall provide them upon request to the [SRF Applicant] for transmission to the
State or EPA if requested by EPA, the State, the contractor, or the Wage and Hour Division of
the Department of Labor for purposes of an investigation or audit of compliance with prevailing
wage requirements. It is not a violation of this section for a prime contractor to require a
subcontractor to provide addresses and social security numbers to the prime contractor for its
own records, without weekly submission to the [SRF Applicant].
(B) Each payroll submitted shall be accompanied by a "Statement of Compliance," signed by the
contractor or subcontractor or his or her agent who pays or supervises the payment of the persons
employed under the contract and shall certify the following:
(1) That the payroll for the payroll period contains the information required to be provided under
§ 5.5(a)(3)(ii) of Regulations, 29 CFR part 5, the appropriate information is being maintained
under § 5.5 (a)(3)(i) of Regulations, 29 CFR part 5, and that such information is correct and
complete;
(2) That each laborer or mechanic (including each helper, apprentice, and trainee) employed on
the contract during the payroll period has been paid the full weekly wages earned, without
rebate, either directly or indirectly, and that no deductions have been made either directly or
indirectly from the full wages earned, other than permissible deductions as set forth in
Regulations, 29 CFR part 3; and
(3) That each laborer or mechanic has been paid not less than the applicable wage rates and
fringe benefits or cash equivalents for the classification of work performed, as specified in the
applicable wage determination incorporated into the contract.
(C) The weekly submission of a properly executed certification set forth on the reverse side of
Optional Form WH-347 shall satisfy the requirement for submission of the "Statement of
Compliance" required by paragraph (3)(ii)(B) of this section.
(D) The falsification of any of the above certifications may subject the contractor or
subcontractor to civil or criminal prosecution under section 1001 of title 18 and section 231 of
title 31 of the United States Code.
(iii) The contractor or subcontractor shall make the records required under paragraph (3)(i) of
this section available for inspection, copying, or transcription by authorized representatives of
the State, EPA or the Department of Labor, and shall permit such representatives to interview
employees during working hours on the job. If the contractor or subcontractor fails to submit the
required records or to make them available, the Federal agency or State may, after written notice
to the contractor, sponsor, applicant, or owner, take such action as may be necessary to cause the
suspension of any further payment, advance, or guarantee of funds. Furthermore, failure to
submit the required records upon request or to make such records available may be grounds for
debarment action pursuant to [SRF Applicant].
(4) Apprentices and trainees.
(i) Apprentices. Apprentices will be permitted to work at less than the predetermined rate for
the work they performed when they are employed pursuant to and individually registered in a
bona fide apprenticeship program registered with the U.S. Department of Labor, Employment
and Training Administration, Office of Apprenticeship Training, Employer and Labor Services,
or with a State Apprenticeship Agency recognized by the Office, or if a person is employed in
his or her first 90 days of probationary employment as an apprentice in such an apprenticeship
program, who is not individually registered in the program, but who has been certified by the
Office of Apprenticeship Training, Employer and Labor Services or a State Apprenticeship
Agency (where appropriate) to be eligible for probationary employment as an apprentice. The
allowable ratio of apprentices to journeymen on the job site in any craft classification shall not be
greater than the ratio permitted to the contractor as to the entire work force under the registered
program. Any worker listed on a payroll at an apprentice wage rate, who is not registered or
otherwise employed as stated above, shall be paid not less than the applicable wage rate on the
wage determination for the classification of work actually performed. In addition, any
apprentice performing work on the job site in excess of the ratio permitted under the registered
program shall be paid not less than the applicable wage rate on the wage determination for the
work actually performed. Where a contractor is performing construction on a project in a
locality other than that in which its program is registered, the ratios and wage rates (expressed in
percentages of the journeyman's hourly rate) specified in the contractor is or subcontractor's
registered program shall be observed. Every apprentice must be paid at not less than the rate
specified in the registered program for the apprentice's level of progress, expressed as a
percentage of the journeymen hourly rate specified in the applicable wage determination.
Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship
program. If the apprenticeship program does not specify fringe benefits, apprentices must be
paid the full amount of fringe benefits listed on the wage determination for the applicable
classification. If the Administrator determines that a different practice prevails for the applicable
apprentice classification, fringes shall be paid in accordance with that determination. In the
event the Office of Apprenticeship Training, Employer and Labor Services, or a State
Apprenticeship Agency recognized by the Office, withdraws approval of an apprenticeship
program, the contractor will no longer be permitted to utilize apprentices at less than the
applicable predetermined rate for the work performed until an acceptable program is approved.
(ii) Trainees. Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less
than the predetermined rate for the work performed unless they are employed pursuant to and
individually registered in a program which has received prior approval, evidenced by formal
certification by the U.S. Department of Labor, Employment and Training Administration. The
ratio of trainees to journeymen on the job site shall not be greater than permitted under the plan
approved by the Employment and Training Administration. Every trainee must be paid at not
less than the rate specified in the approved program for the trainee's level of progress, expressed
as a percentage of the journeyman hourly rate specified in the applicable wage determination.
Trainees shall be paid fringe benefits in accordance with the provisions of the trainee program.
If the trainee program does not mention fringe benefits, trainees shall be paid the full amount of
fringe benefits listed on the wage determination unless the Administrator of the Wage and Hour
Division determines that there is an apprenticeship program associated with the corresponding
journeyman wage rate on the wage determination which provides for less than full fringe benefits
for apprentices. Any employee listed on the payroll at a trainee rate who is not registered and
participating in a training plan approved by the Employment and Training Administration shall
be pair% not ess than the lip app acaable wage rate on the wage determi�� onR«onatinn for the rlassiFnafion of
10
work actually performed. In addition, any trainee performing work on the job site in excess of
the ratio permitted under the registered program shall be paid not less than the applicable wage
rate on the wage determination for the work actually performed. In the event the Employment
and Training Administration withdraws approval of a training program, the contractor will no
longer be permitted to utilize trainees at less than the applicable predetermined rate for the work
performed until an acceptable program is approved.
(iii) Equal employment opportunity. The utilization of apprentices, trainees and journeymen
under this part shall be in conformity with the equal employment opportunity requirements of
Executive Order 11246, as amended, and 29 CFR part 30.
(5) Compliance with Copeland Act requirements. The contractor shall comply with the
requirements of 29 CFR part 3, which are incorporated by reference in this contract.
(6) Subcontracts. The contractor or subcontractor shall insert in any subcontracts the clauses
contained in 29 CFR 5.5(a)(1) through (10) and such other clauses as the governing federal
agency may by appropriate instructions require, and also a clause requiring the subcontractors to
include these clauses in any lower tier subcontracts. The prime contractor shall be responsible
for the compliance by any subcontractor or lower tier subcontractor with all the contract clauses
in 29 CFR 5.5.
(7) Contract termination: debarment. A breach of the contract clauses in 29 CFR 5.5 may be
grounds for termination of the contract, and for debarment as a contractor and a subcontractor as
provided in 29 CFR 5.12.
(8) Compliance with Davis -Bacon and Related Act requirements. All rulings and interpretations
of the Davis -Bacon and Related Acts contained in 29 CFR parts 1, 3, and 5 are herein
incorporated by reference in this contract.
(9) Disputes concerning labor standards. Disputes arising out of the labor standards provisions
of this contract shall not be subject to the general disputes clause of this contract. Such disputes
shall be resolved in accordance with the procedures of the Department of Labor set forth in 29
CFR parts 5, 6, and 7. Disputes within the meaning of this clause include disputes between the
contractor (or any of its subcontractors) and Subrecipient(s), State, EPA, the U.S. Department of
Labor, or the employees or their representatives.
(10) Certification of eligibility.
(i) By entering into this contract, the contractor certifies that neither it (nor he or she) nor any
person or Finn who has an interest in the contractor's firm is a person or firm ineligible to be
awarded Government contracts by virtue of section 3(a) of the Davis -Bacon Act or 29 CFR
5.12(a)(1).
(ii) No part of this contract shall be subcontracted to any person or firm ineligible for award of a
Government contract by virtue of section 3(a) of the Davis -Bacon Act or 29 CFR 5.12(a)(1).
(iii) The penalty for making false statements is prescribed in the U.S. Criminal Code, 18 U.S.C.
(11) Overtime requirements. No contractor or subcontractor contracting for any part of the
contract work which may require or involve the employment of laborers, mechanics, watchmen
and guards shall require or permit any such laborer, mechanic, watchman or guard in any
workweek in which he or she is employed on such work to work in excess of forty hours in such
workweek unless such laborer, mechanic, watchman or guard receives compensation at a rate not
less than one and one-half times the basic rate of pay for all hours worked in excess of forty
hours in such workweek.
(12) Violation; liability for unpaid wages; liquidated damages. In the event of any violation of
the clause set forth in the above paragraph (11) of this section the contractor and any
subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such
contractor and subcontractor shall be liable to the United States (in the case of work done under
contract for the District of Columbia or a territory, to such District or to such territory), for
liquidated damages. Such liquidated damages shall be computed with respect to each individual
laborer, mechanic, watchman or guard employed in violation of the clause set forth in the above
paragraph (11) of this section, in the sum of $10 for each calendar day on which such individual
was required or permitted to work in excess of the standard workweek of forty hours without
payment of the overtime wages required by the clause set forth in the above paragraph (11) of
this section.
(13) Withholding for unpaid wages and liquidated damages. The [SRF Applicant], upon
written request of the EPA Award Official or an authorized representative of the Department of
Labor, shall withhold or cause to be withheld, from any moneys payable on account of work
performed by the contractor or subcontractor under any such contract or any other Federal
contract with the same prime contractor, or any other federally -assisted contract subject to the
Contract Work Hours and Safety Standards Act, which is held by the same prime contractor,
such sums as may be determined to be necessary to satisfy any liabilities of such contractor or
subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in the
above paragraph (12) of this section.
(14) Subcontracts. The contractor or subcontractor shall insert in any subcontracts the clauses
set forth in paragraphs (11) through (14) of this section and also a clause requiring the
subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall
be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses
set forth in paragraphs (11) through (14) of this section.
(b) In addition to the clauses contained in paragraph (13), above, in any contract subject only to
the Contract Work Hours and Safety Standards Act and not to any of the other statutes cited in
29 CFR 5.1, the [SRF Applicant] shall insert a clause requiring that the contractor or
subcontractor shall maintain payrolls and basic payroll records during the course of the work and
shall preserve them for a period of three years from the completion of the contract for all
laborers, mechanics, watchmen and guards working on the contract. Such records shall contain
the name and address of each such employee, social security number, correct classifications,
hourly rates of wages paid, daily and weekly number of hours worked, deductions made, and
actual wages paid. Further, the [SRF Applicant] shall insert in any such contract a clause
providing hat the records to be maintained under this paragraph shall be made available by the
contractor or subcontractor for inspection. con_, v _in¢, or transcription by authorized representatives
12
of the (write the name of agency) and the Department of Labor, and the contractor or
subcontractor will permit such representatives to interview employees during working hours on
the job.
[29 CFR 5.51
13
Attachment C
Required Wage/Fringe Benefit Certification
A provision substantially like the following shall be included in each contract between SRF
Applicant and a contractor for work related to the Project. A copy of the Wage/Fringe Benefit
Certification referenced in the below provision is attached hereto. Additional copies may be
obtained from the Indiana Finance Authority.
Davis -Bacon Wage/Fringe Benefit Certification
(a) Every contractor and subcontractor furnishing work on the Project shall complete a
Wage/Fringe Benefit Certification on the form approved by the Indiana Finance Authority and
submit this certification to the Labor Standards Administrator prior to commencing work on the
Project.
(b) The Contractor shall require the substance of this provision to be included in all contracts
with subcontractors.
14
a
n
r.
c
0-1
r
M
v�
y_ oc
-E a
N
Uo
r
W �
r C
d u
m a
� a
c a
'C E
LL V
N a
RF
J
J
F
fU
W
O
w
IL
P.
a
D
f6
6
C
a
u
d
�
U
m
a
m
0
T
a
�
J
U
D
D
Q
>
O
T
O `
�
O
o �
y C
O
dU
d
m
rn
c
c
l
in
0
O m
N c
o
>m
> T
a
m 10
n
d
a
0
m
U N
�
l0
a�
m
F
c
0
N
u
y
d
a
d
d
m'
rn
d�
C
41
LL
a
m
u
a
Q
�
a
@„
E
3
p
NO
LL
m
0
U
N
U
d
F
0
e
a
T
a
a
ery
U
d
is
N
N
�
V
E
Attachment E
Required Contract Provision Related to Suspension and Debarment
A provision substantially like the below shall be included in each procurement contract related
to the Project. The SRF Applicant shall remain responsible for compliance with applicable
law (including Suspension, Debarment, and Other Responsibility Matters). Such SRF
Applicant has been encouraged to consult with its advisors and counsel regarding such
matters and, in any event, understands that the use of the following does not relieve the SRF
Applicant from its obligation to comply with applicable law (including Suspension,
Debarment, and Other Responsibility Matters) and related provisions of any financial
assistance agreement entered into with the Indiana Finance Authority, nor will the State
Revolving Fund Loan Programs, the Indiana Finance Authority or the State of Indiana be
responsible for or limited by any SRF Applicant's use of the following provision.
Contractor shall fully comply with Subpart C of 2 CFR Part 180 and 2 CFR Part 1532, entitled
"Responsibilities of Participants Regarding Transactions (Doing Business with Other Persons)."
Contractor is responsible for ensuring that any lower tier covered transaction as described in
Subpart B of 2 CFR Part 180 and 2 CFR Part 1532, entitled "Covered Transactions," includes a
term or condition requiring compliance with Subpart C. Contractor is responsible for further
requiring the inclusion of a similar term or condition in any subsequent lower tier covered
transactions. Contractor may access the Excluded Parties List System at www.epls.gov. This
term and condition supersedes EPA Form 5700-49, "Certification Regarding Debarment,
Suspension, and Other Responsibility matters."
16
U.S. ENVIRONMENTAL PROTECTION AGENCY
CERTIFICATION OF NONSEGREGATED FACILITIES
(Applicable to federally assisted construction contracts and related subcontracts exceeding
$10,000 which are not exempt from the Equal Opportunity clause.)
The federally assisted construction contractor certifies that he does not maintain or
provide for his employees any segregated facilities at any of his establishments, and that he does
not permit his employees to perform their services at any location, under his control, where
segregated facilities are maintained. The federally assisted construction contractor certifies
further that he will not maintain or provide for his employees any segregated facilities at any of
his establishments, and that he will not permit his employees to perform their services at any
location, under his control, where segregated facilities are maintained. The federally assisted
construction contractor agrees that a breach of this certification is a violation of the Equal
Opportunity clause in this contract. As used in this certification, the term segregated facilities
means any waiting rooms, work areas, rest rooms and other storage or dressing areas, parking
lots, drinking fountains, recreation or entertainment areas, transportation, and housing facilities
provided for employees which are segregated by explicit directive or are in fact segregated on the
basis of race, creed, color, or nation origin, because of habit, local custom, or otherwise. The
federally assisted construction contractor agrees that (except where he has obtained identical
certifications from proposed subcontractors for specific time periods) he will obtain identical
certifications from proposed subcontractors prior to the award of subcontracts exceeding $10,000
which are not exempt from the provisions of the Equal Opportunity clause, and that he will retain
such certification in his files.
(%emu ,CB Ali leG 111 8 August 2022
Signa re / k__/ Date
Ursula J. Youngblood Contracting & Attesting Officer
Name and Title of Signer (Please type)
INSITUFORM TECHNOLOGIES USA, LLC.
Firm Name
NOTE: The penalty for making false statements in offers is prescribed in 18 U.S.C. 1001.
OEE-1 (11/79)
NOTICE TO LABOR UNIONS OR OTHER ORGANIZATIONS OF WORKERS
NONDISCRIMINATION IN EMPLOYMENT
(Name of union or organization of workers)
The undersigned currently holds contract(s) with City of Carmel Indiana
(Name of Applicant)
involving funds or credit of the U.S. Government or (a) subcontract(s) with a prime contractor
holding such contract(s).
You are advised that under the provisi ons of the above contract(s) or subcontract(s) and in
accordance with Executive Order 11246, as amended, dated September 24, 1965, as amended, the
undersigned is obl iged not to discri mi nate agai nst any employee or appl i cant for employment
because of race, color, creed, or national origin. This obligation not to discriminatein employment
i ncl udes, but i s not I i mited to, the fol Iowi ng:
HIRING, PLACEMENT, UPGRADING, TRANSFER, OR DEMOTION,
RECRUITMENT, ADVERTISING, OR SOLICITATION FOR
EMPLOYMENT, TRAINING DURING EMPLOYMENT, RATES OF PAY OR
OTHER FORMS OF COMPENSATION, SELECTION FOR TRAINING
INCLUDING APPRENTICESHIP, LAYOFF OR TERMINATION.
This notice i s furnished you pursuant to the provisions of the above oontract(s) or subcontract(s)
and Executive Order 11246, as amended.
Copi es of this notice wi I I be posed by the undersigned i n conspicuous places avai I able to
employees or appl icants for empl oyment.
INSITUFORM TECHNOLOGIES USA, LLC.
(Contractor or Subcontractor)
8 Auciust 2022
(Date)
OEE-2 (11179)
BIBBER'S BBE STATUS FORM
\Afterheotice of Award is issued, the Contractor shall fill in and submit the form below specifying the
WBE status on the Contractor and all subcontractors.
Prime Con actor Name
CONTACT PERSO
E-MAIL ADDRESS
MAILING ADDRESS
Phone#
DBE/MBE/WBE status (please
rovide applicable details)
Subcontractor Name
CONTACT PERSON
E-MAIL ADDRESS
MAILING ADDRESS
P one#
DBE/MBE/WBE status (please provide applicable details)
Subcontractor Name
CONTACT PERSON
E-MAIL ADDRESS
MAILING ADDRESS I Phone;
DBE/MBE/WBE status (please provide applicable details)
Attach additional pages as necessary for all subcontractors.
"General Decision Number: IN20220006 07/29/2022
Superseded General Decision Number: IN20210006
State: Indiana
Construction Types: Heavy and Highway
Counties: Adams, Allen, Bartholomew, Benton, Blackford,
Boone, Brown, Carroll, Cass, Clark, Clay, Clinton, Crawford,
Daviess, Dearborn, Decatur, DeKalb, Delaware, Dubois, Elkhart,
Fayette, Floyd, Fountain, Franklin, Fulton, Gibson, Grant,
Greene, Hamilton, Hancock, Harrison, Hendricks, Henry, Howard,
Huntington, Jackson, Jasper, Jay, Jefferson, Jennings, Johnson,
Knox, Kosciusko, Lagrange, Lawrence, Madison, Marion, Marshall,
Martin, Miami, Monroe, Montgomery, Morgan, Newton, Noble, Ohio,
Orange, Owen, Parke, Perry, Pike, Posey, Pulaski, Putnam,
Randolph, Ripley, Rush, Scott, Shelby, Spencer, Starke,
Steuben, Sullivan, Switzerland, Tippecanoe, Tipton, Union,
Vanderburgh, Vermillion, Vigo, Wabash, Warren, Warrick,
Washington, Wayne, Wells, White and Whitley Counties in Indiana.
* EXCEPT LAKE, LAPORTE, PORTER AND ST. JOSEPH COUNTIES HEAVY
AND HIGHWAY CONSTRUCTION PROJECTS
Note: Contracts subject to the Davis -Bacon Act are generally
required to pay at least the applicable minimum wage rate
required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered
contracts entered into by the federal government that are
subject to the Davis -Bacon Act itself, but do not apply to
contracts subject only to the Davis -Bacon Related Acts,
including those set forth at 29 CFR 5.1(a)(2)-(60).
If the contract is entered 1. Executive Order 14026 I
1 into on or after January 30, 1 generally applies to the 1
12022, or the contract is I contract. I
I renewed or extended (e.g., an 1. The contractor must pay
I option is exercised) on or I all covered workers at 1
after January 30, 2022: 1 least $15.00 per hour (or 1
1 1 the applicable wage rate 1
1 1 listed on this wage 1
I I determination, if it is 1
1 I higher) for all hours 1
I 1 spent performing on the I
I I contract in 2022. 1
I I
I If the contract was awarded on 1. Executive Order 13658 1
l or between January 1, 2015 and I generally applies to the I
1January 29, 2022, and the I contract. I
I contract is not renewed or 1. The contractor must pay alll
extended on or after January 1 covered workers at least 1
130, 2022: 1 $11.25 per hour (or the I
I I applicable wage rate listed I
I I on this wage determination, I
I I if it is higher) for all I
I I hours spent performing on I
I I that contract in 2022. 1
1 1
The applicable Executive Order minimum wage rate will be
adjusted annually. If this contract is covered by one of the
Executive Orders and a classification considered necessary for
performance of work on the contract does not appear on this
wage determination, the contractor must still submit a
conformance request.
Additional information on contractor requirements and worker
protections under the Executive Orders is available at
https://www.dol.gov/agencies/whd/government-contracts.
Modification
Number Publication Date
0
01/07/2022
1
02/04/2022
2
02/18/2022
3
02/25/2022
4
03/04/2022
5
04/01/2022
6
04/15/2022
7
04/22/2022
8
04/29/2022
9
05/06/2022
10
05/13/2022
11
05/27/2022
12
06/03/2022
13
06/10/2022
14
06/17/2022
is
07/01/2022
16
07/08/2022
17
07/15/2022
18
07/29/2022
ASBE0008-004 03/01/2022
DEARBORN, FAYETTE, FRANKLIN, OHIO, RIPLEY SWITZERLAND AND UNION
COUNTIES
Rates Fringes
Asbestos Workers/Insulator
(Includes application of all
insulating materials,
protective coverings,
coatings & finishings to all
types of mechanical systems) ..... $ 32.33 20.19
HAZARDOUS MATERIAL HANDLER
(Includes preparation,
wettings, stripping, removal,
scrapping, vacuuming, bagging
& disposing of all insulation
materials, whether they
contain asbestos or not, from
mechanical systems) .............. $ 25.00 13.70
ASBE0017-008 06/01/2022
NEWTON COUNTY:
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR ........................ $ 52.80 32.30
HAZARDOUS MATERIAL HANDLER
(INCLUDES PREPARATION,
WETTING, STRIPPING REMOVAL
SCRAPPING, VACUUMING, BAGGING
AND DISPOSAL OF ALL
INSULATION MATERIALS, WHETHER
THEY CONTAIN ASBESTOS OR NOT,
FROM MECHAINCAL SYSTEMS) ......... $ 38.85 24.60
ASBE0018-005 06/01/2021
BROWN, BARTHOLOMEW, BENTON, BOONE, CARROLL, CASS, CLAY,
CLINTON, DECATUR, DELAWARE, ELKHART. FOUNTAIN, FULTON, GREENE,
HAMILTON, HANCOCK, HENDRICKS, HENRY, HOWARD, JASPER, JOHNSON,
KOSCIUSKO, LAGRANGE, MARSHALL, MADISON, MARION, MONROE,
MONTGOMERY, MORGAN, OWEN, PARKE, PULASKI, PUTNAM, RUSH, SHELBY,
STARKE, TIPPECANOE, TIPTON, VERMILLION, VIGO, WARREN and WHITE
Counties
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR (includes
application of all insulating
materials, protective
coverings, coatings and
finishings to all types of
mechanical systems) .............. $ 33.90 21.38
HAZARDOUS MATERIAL HANDLER
(includes preparation,
wettings, stripping, removal,
scrapping, vacuuming, bagging
& disposing of all
insulation materials, whether
they contain asbestos or not,
from mechanical systems) ......... $ 23.00 14.40
ASBE0037-004 04/02/2021
DAVIESS, DUBOIS, GIBSON, KNOX, MARTIN, PIKE, POSEY, SPENCER,
SULLIVAN, VANDERBURGH AND WARRICK COUNTIES
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR (includes
application of all insulating
materials protective
coverings, coatings an
finishes to all types of
mechanical systems. Also the
application of firestopping,
material openings and
penetrations in walls,
floors, ceilings, curtain
walls and all lead abatement.) ... $ 32.00 21.89
HAZARDOUS MATERIAL HANDLER
(Includes preparation,
wetting, stripping, removal,
scrapping, vacuuming, bagging
and disposing of all
insulation materials, whether
they contain asbestos or not,
from mechanical systems) ......... $ 23.00 14.40
ASBE0041-002 07/01/2021
ADAMS, ALLEN, BLACKFORD, DE KALB, GRANT, HUNTINGTON, JAY,
MIAMI, NOBLE, STEUBEN, WABASH, WELLS AND WHITLEY COUNTIES:
Rates Fringes
ASBESTOS WORKER/HEAT& FROST
INSULATOR (includes
application of all insulating
materials, protective
coverings, coatings and
finishings to all types of
mechanical systems) .............. $ 30.05 21.49
HAZARDOUS MATERIAL HANDLER
(includes preparation,
wettings, stripping, removal,
scrapping, vaccuming, bagging
& disposing of all insulation
materials, whether they
contain asbestos or not, from
mechanical systems) .............. $ 23.00 14.40
ASBE0051-003 03/01/2022
CLARK, CRAWFORD. FLOYD, HARRISON, JACKSON, JEFFERSON, JENNINGS,
LAWRENCE, ORANGE, PERRY, SCOTT, and WASHINGTON Counties
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR (Includes
application of all insulating
materials, protective
coverings, coatings and
finishings to all types of
mechanical systems) .............. $ 27.10 18.38
HAZARDOUS MATERIAL HANDLER
(includes preparation,
wettings, stripping, removal,
scrapping, vaccuming, bagging
& disposing of all insulation
materials, whether they
contain asbestos or not, from
mechanical systems) .............. $ 19.80 13.30
ASBE0079-002 07/01/2017
RANDOLPH AND WAYNE COUNTIES
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR (Includes
application of all insulating
materials, protective
coverings, coatings &
finishings to all types of
mechanical systems) .............. $ 22.25 8.89
HAZARDOUS MATERIAL HANDLER
(Includes preparation,
wetting, stripping, removal,
scrapping, vacuuming, bagging
& disposing of all insulation
materials, whether they
contain asbestos or not, from
mechanical systems)) ............. $ 25.00 13.70
B R I N 0003-00106/01 /2021
INDIANAPOLIS
BOONE, HANCOCK, HENDRICKS, JOHNSON, MARION, MONTGOMERY, MORGAN
and SHELBY COUNTIES
Rates Fringes
Bricklayer, Stone Mason,
Pointer, Caulking ................
$ 33.59 15.89
TERRAllO FINISHER ................
$ 20.74 11.98
TERRAllO WORKER/SETTER ........... $ 33.36 15.74
Tile & Marble Finisher ...........
$ 21.69 11.99
Tile, Marble Setter ..............
$ 32.61 15.73
BRIN0004-004 06/01/2021
FORT WAYNE
ADAMS, ALLEN, DEKALB, HUNTINGTON, NOBLE, STEUBEN, WELLS AND
W H ITLEY COUNTIES:
Rates Fringes
BRICKLAYER (STONE MASON,
MARBLE MASONS, POINTER,
CLEANER, AND CAULKER) ............ $ 31.50 18.96
Terrazzo Grinder Finisher ........ $ 28.00 14.84
Terrazzo Worker Mechanic ......... $ 32.37 18.76
Tile Setter & Marble Mason
Mechanic ......................... $ 28.00 16.36
Tile, Marble & Terrazzo
Finisher ......................... $ 25.00 13.78
BRIN0004-005 06/01/2020
CRAWFORD, DUBOIS, PERRY, POSEY, SPENCER, VANDERBURGH, and
WARRICK Counties
Rates Fringes
BRICKLAYER ....................... $ 30.00
14.71
TILE FINISHER ....................
$ 20.31
12.00
TILE SETTER ......................
$ 27.19
13.85
BRIN0004-009 06/01/2021
BARTHOLOMEW, BROWN, DEARBORN, DECATUR, JENNINGS, MONROE, OHIO,
OWENS, RIPLEY and SWITZERLAND COUNTIES
Rates Fringes
Bricklayer, Stonemason ........... $ 30.53 15.95
TERRAllO FINISHER ................ $ 21.69 11.99
TERRAllO WORKER/SETTER ........... $ 33.36 15.74
Tile & Marble Finisher ........... $ 21.69 11.99
Tile, Marble Setter .............. $ 32.61 15.73
BRIN0004-010 06/01/2021
CLARK, FLOYD, and HARRISON Counties
Rates Fringes
BRICKLAYER
BRICKLAYERS, STONEMASONS
AND CEMENT MASONS ........... $ 29.57 15.10
BRIN0004-015 06/01/2021
TERRE HAUTE
CLAY, DAVIESS, GIBSON, GREENE, KNOX, MARTIN, PARKE, PIKE,
PUTNAM, SULLIVAN, VERMILLION and VIGO COUNTIES
Rates Fringes
BRICKLAYER
BRICKLAYERS, STONE MASONS
and POINTER/
CLEANER/CAULKER............. $ 33.59
15.97
CEMENT MASON (Greene and
Sullivan Counties) .......... $ 27.78
11.02
CEMENT MASON (REMAINING
COUNTIES) ................... $ 33.59
15.97
TERRAZO FINISHER ............ $ 20.74
11.98
TERRAZZO WORKER ............. $ 33.36
15.74
TILE LAYER, MARBLE MASON,
MOSAIC WORKER ............... $ 32.61
15.73
BRIN0004-016 06/01/2021
MUNCIE
BLACKFORD, DELAWARE, FAYETTE, FRANKLIN, HAMILTON, HENRY, JAY,
MADISON, RANDOLPH, RUSH, TIPTON, UNION and WAYNE COUNTIES
Rates Fringes
Bricklayer, Stonemason,
Pointer, Caulker & Cleaner ....... $ 31.75 18.07
TERRAllO FINISHER ................ $ 20.74 11.98
TERRAllO WORKER/SETTER ........... $ 33.36 15.74
Tile & Marble Finisher ........... $ 20.74 11.98
Tile & Marble Setter, Mosaic
Worker ........................... $ 32.61 15.73
BRIN0006-001 06/01/2021
JASPER, NEWTON & STARKE COUNTIES
Rates Fringes
BRICKLAYER (Including
Stonemason, and Pointer,
Caulker & Cleaner) ............... $ 38.85 27.17
Tile, Marble & Terrazzo Worker ... $ 37.05 21.64
B R I N 0011-00106/01/2021
LAFAYETTE
BENTON, CARROLL, CLINTON, FOUNTAIN, TIPPECANOE, WARREN and
WHITE COUNTIES
Rates Fringes
Bricklayer, Stonemason,
Pointer, Caulker & Cleaner ....... $ 30.75 18.97
TERRAllO FINISHER ................ $ 21.69 11.99
TERRAllO WORKER/SETTER ........... $ 33.36 15.74
Tile & Marble Finisher ........... $ 21.69 11.99
Tile & Marble Setter; Mosaic
Worker ........................... $ 32.61 15.73
BRIN0018-002 06/01/2021
CASS, ELKHART, FULTON, GRANT, HOWARD, KOSCUISKO, LAGRANGE,
MARSHALL, MIAMI, PULASKI, WABASH
Rates Fringes
Bricklayer, Caulker, Cleaner,
Pointer .......................... $ 31.11 18.40
CARP0002-023 04/01/2022
DEARBORN, JACKSON, JENNINGS, OHIO, RIPLEY AND SWITZERLAND
COUNTIES
Rates Fringes
CARPENTER ........................ $ 26.95 26.11
CARP0133-001 04/01/2021
BOONE, CLAY, FOUNTAIN, MONROE, MONTGOMERY, MORGAN, OWEN,
PARKE, PUTNAM, VERMILLION AND VIGO COUNTIES
Rates Fringes
CARPENTER ........................ $ 28.71 23.36
CARP0133-003 04/01/2021
HAMILTON, HANCOCK, HENDRICKS, JOHNSON (Townships of Clark, Camp
Atterbury north of Hospital Road, Pleasant, White River), and
MARION Counties
Rates Fringes
CARPENTER ........................ $ 29.82 23.36
----------------------------------------------------------------
CARP0175-004 04/01/2021
CLARK, FLOYD, HARRISON, JEFFERSON,SCOTT AND WASHINGTON COUNTIES
Rates Fringes
CARPENTER ........................ $ 25.82 25.59
----------------------------------------------------------------
CARP0215-002 04/01/2022
BENTON, CARROLL, CLINTON, PULASKI, TIPPECANOE, WARREN AND WHITE
COUNTIES
Rates Fringes
CARPENTER ........................ $ 30.53 23.04
----------------------------------------------------------------
CA R P02 24-01104/01/ 2021
CRAWFORD, DUBOIS, PERRY, PIKE, POSEY, SPENCER, VANDERBURGH AND
WARRICK COUNTIES:
Rates Fringes
CARPENTER ........................ $ 25.89 25.52
----------------------------------------------------------------
CARP0224-012 04/01/2021
DAVIESS, GIBSON, GREENE, KNOX, LAWRENCE, MARTIN, ORANGE AND
SULLIVAN COUNTIES:
Rates Fringes
CARPENTER ........................ $ 26.24 25.57
CARP0232-003 04/01/2022
ALLEN, DEKALB, LAGRANGE, NOBLE, STEUBEN and WHITLEY COUNTIES
Rates Fringes
CARPENTER ........................ $ 29.14 23.87
----------------------------------------------------------------
CARP0301-001 04/01/2022
BARTHOLOMEW, BROWN,(Camp Atterbury south of Hospital Road),
DECATUR, FRANKLIN, JOHNSON (Townships of Blue River, Franklin,
Hensley, Needham, Nineveh, Union), RUSH AND SHELBY COUNTIES
Rates Fringes
CARPENTER ........................ $ 29.26 23.87
----------------------------------------------------------------
CARP0413-003 04/01/2022
ADAMS, CASS, ELKHART, FULTON, GRANT, HOWARD, HUNTINGTON,
KOSCIUSKO, MARSHALL, MIAMI, TIPTON, WABASH AND WELLS COUNTIES:
Rates Fringes
CARPENTER ........................ $ 29.46 23.70
----------------------------------------------------------------
CARP0999-001 06/01/2017
JASPER, NEWTON, AND STARKE COUNTIES
Rates Fringes
CARPENTER ........................ $ 37.56 26.42
----------------------------------------------------------------
CARP1016-00104/01/2022
BLACKFORD, DELAWARE, FAYETTE, HENRY, JAY, MADISON, RANDOLPH,
UNION AND WAYNE COUNTIES
Rates Fringes
CARPENTER ........................ $ 29.56 24.01
CARP1076-004 04/01/2016
HAMILTON and MARION Counties, and the following Townships in
JOHNSON County: Camp Atterbury (North of Hospital Rd.), Clark,
Pleasant, and White River
Rates Fringes
MILLWRIGHT....................... $ 26.81 19.28
CARP1076-005 06/01/2017
JASPER, NEWTON, PULASKI, and STARKE Counties
Rates Fringes
MILLWRIGHT ....................... $ 37.66 26.42
CARP1076-006 06/01/2018
BARTHOLOMEW, BLACKFORD, BOONE, BROWN, CLAY, DECATUR, DELAWARE,
FAYETTE, FOUNTAIN, FRANKLIN, HAMILTON, HANCOCK, HENDRICKS,
HENRY, JAY, JOHNSON, MADISON, MARION, MONROE, MONTGOMERY,
MORGAN, OWEN, PARKE, PUTNAM, RANDOLPH, RUSH, SHELBY, UNION,
VERMILLION, VIGO, AND WAYNE COUNTIES
Rates Fringes
MILLWRIGHT....................... $ 28.18 22.39
CARP1080-001 04/01/2021
GIBSON, GREENE, POSEY, SULLIVAN, VANDERBURGH and WARRICK
COUNTIES
Rates Fringes
MILLWRIGHT
ZONE 1
POSEY, VANDERBURGH and
WARRICK COUNTIES ........... $ 30.92 24.83
ZONE
GIBSON, GREENE AND
SULLIVAN COUNTIES .......... $ 29.64 25.77
ELEC0016-003 04/01/2022
CRAWFORD, DAVIESS, DUBOIS, GIBSON, LAWRENCE, MARTIN, ORANGE,
PERRY, PIKE, POSEY, SPENCER, VANDERBURGH, WARRICK
Rates Fringes
ELECTRICIAN ...................... $ 40.88 18.62
ELEC0016-006 08/31/2020
CRAWFORD, DAVIESS, DUBOIS, GIBSON, LAWRENCE, MARTIN, ORANGE,
PERRY, PIKE, POSEY, SPENCER, VANDERBURGH, WARRICK
Rates Fringes
ELECTRICIAN (Communication
Technician Only) ................. $ 29.15 15.40
ELEC0071-006 01/02/2019
DEARBORN, OHIO, and SWTIZERLAND COUNTIES
Rates Fringes --
Line Construction:
Equipment Operator .......... $ 33.62 13.46
Groundman................... $ 24.17 11.38
Lineman & Cable Splicers .... $ 38.27 14.48
ELEC0153-003 06/01/2021
ELKHART, KOSCIUSKO and MARSHALL COUNTIES
Rates Fringes
Communication Technician ......... $ 26.50 18.33
ELECTRICIAN ...................... $ 36.50 25.98
Includes the installation, operation, inspection,
modification, maintenance and repair of systems used for
the transmission and reception of signals of any nature,
for any purpose, including but not limited to , sound and
voice transmission/transference systems, communication
systems that transmit or receive information and /or
control systems, television and video systems,
micre-processor controlled fire alarm systems, and security
systems and the performance of any task directly related to
such installation or service. The scope of work shall
exclude the installation of electrical power wiring and the
installation of conduit raceways exceeding fifteen (15)
feet in length.
ELECO212-002 11/30/2021
DEARBORN, OHIO, and SWITZERLAND COUNTIES
Rates Fringes
ELECTRICIAN (Communication
Technician Only) ................. $ 25.95 12.27
ELECO212-009 06/07/2022
DEARBORN, OHIO, and SWITZERLAND COUNTIES
Rates Fringes
ELECTRICIAN ...................... $ 33.29 20.05
ELEC0305-003 05/01/2022
ADAMS, ALLEN, DE KALB, HUNTINGTON, LAGRANGE, NOBLE, STEUBEN,
WELLS, and WHITLEY COUNTIES
Rates Fringes
ELECTRICIAN ...................... $ 35.71 10.14+26.14%
ELEC0305-004 08/31/2020
ADAMS, ALLEN, DE KALB, HUNTINGTON, LAGRANGE, NOBLE, STEUBEN,
WELLS, and WHITLEY COUNTIES
Rates Fringes
ELECTRICIAN (Communication
Technician Only) ................. $ 29.25 16.85
ELEC0369-005 05/31/2021
CLARK, FLOYD, HARRISON, JACKSON, JEFFERSON, SCOTT, and
WASHINGTON Counties
Rates Fringes
ELECTRICIAN ...................... $ 33.85 18.72
ELEC0481-003 03/31/2022
BARTHOLOMEW, BOONE, DECATUR, HAMILTON, HANCOCK, HENDRICKS,
JENNINGS, JOHNSON, MADISON, MARION, MONTGOMERY, MORGAN, PUTNAM,
RIPLEY, RUSH AND SHELBY COUNTIES
Rates Fringes
ELECTRICIAN ...................... $ 38.20 25.56
ELEC0481-004 01/01/2021
BARTHOLOMEW, BOONE, DECATUR, HAMILTON, HANCOCK, HENDRICKS,
JENNINGS, JOHNSON, MADISON, MARION, MONTGOMERY, MORGAN, PUTNAM,
RIPLEY, RUSH AND SHELBY COUNTIES
Rates Fringes
ELECTRICIAN (Communication
Technician Only) ................. $ 30.64 17.22
ELEC0531-002 05/31/2021
JASPER, PULASKI, and STARKE COUNTIES
Rates Fringes
ELECTRICIAN ...................... $ 41.50 28.26
ELEC0531-003 05/28/2018
JASPER, PULASKI, and STARKE COUNTIES
Rates Fringes
ELECTRICIAN (Communication
Technician Only) ................. $ 27.64 13.23
ELEC0538-005 01/01/2022
FOUNTAIN, VERMILLION, and WARREN Counties
Rates Fringes
ELECTRICIAN ...................... $ 37.80 22.66
------------------------------ ----------------------------------
ELEC0538-009 09/01/2018
FOUNTAIN, VERMILLION, and WARREN Counties
Rates Fringes
ELECTRICIAN (Communication
Technician Only) ................. $ 32.82 16.28
----------------------------------------------------------------
ELEC0668-001 06/01/2019
BENTON, CARROLL, CASS, FULTON, TIPPECANOE and WHITE COUNTIES
Rates Fringes
ELECTRICIAN (Communication
Technician Only) ................. $ 28.90 14.53
.................. ----........... -------------------------------
ELEC0668-002 01/01/2022
BENTON, CARROLL, CASS, FULTON, TIPPECANOE and WHITE COUNTIES
Rates Fringes
ELECTRICIAN ...................... $ 36.17 21.40
FOOTNOTE: a. PAID HOLIDAYS: New Years Day, Memorial Day,
July 4th, Labor Day, Veterans Day Thanksgiving Day and
Christmas Day
ELEC0697-003 08/31/2021
NEWTON COUNTY
Rates Fringes
ELECTRICIAN (Communication
Technician Only) ................. $ 35.75 28.77
ELEC0697-006 06/01/2022
NEWTON COUNTY
Rates Fringes
ELECTRICIAN ...................... $ 45.25 30.13
ELEC0702-003 12/30/2019
DUBOIS, GIBSON, PERRY, PIKE, POSEY, SPENCER AND VANDERBURGH
COUNTIES
Rates Fringes
Line Construction:
GROUNDMAN, Class A .......... $ 28.58 29%+ 7.75
GROUNDMAN-EQUIPMENT
OPERATOR (All other
equipment) .................. $ 36.35 29%+ 7.75
HEAVY -EQUIPMENT OPERATOR
(All crawler type
equipment D-4 and larger) ... $ 41.49 29%+7.75
LINEMAN .....................$50.63 29%+7.75
ELEC0725-007 06/01/2021
BROWN, CLAY, GREENE, KNOX, MONROE, OWEN, PARKE, SULLIVAN AND
VIGO COUNTIES
Rates Fringes
Communication Technician ......... $ 29.56 15.96
Includes the installation, operation, inspection,
maintenance, repair and service of radio, television,
recording, voice sound and vision production and
reproduction apparatus, equipment and appliances used for
domestic, commercial, education, entertainment and private
telephone systems.
ELEC0725-014 10/01/2021
BROWN, CLAY, GREENE, KNOX, MONROW, OWEN, PARKE, SULLIVAN AND
VIGO COUNTIES
Rates Fringes
ELECTRICIAN ...................... $ 39.00 21.01
----------------------------------------------------------------
ELEC0855-002 06/01/2018
BLACKFORD, DELAWARE, FAYETTE, FRANKLIN, HENRY, JAY, RANDOLPH,
UNION and WAYNE Counties
Rates Fringes
ELECTRICIAN (Communication
Technician Only) ................. $ 27.64 14.15
----------------------------------------------------------------
ELEC0855-004 06/01/2021
BLACKFORD, DELAWARE, FAYETTE, FRANKLIN, HENRY, JAY, RANDOLPH,
UNION and WAYNE Counties
Rates Fringes
ELECTRICIAN ...................... $ 33.57 19.03
----------------------------------------------------------------
ELEC0873-001 06/01/2021
CLINTON, GRANT, HOWARD, MIAMI, TIPTON, AND WABASH COUNTIES
Rates Fringes
ELECTRICIAN (Communication
Technician Only) ................. $ 30.08 17.23
----------------------------------------------------------------
ELEC0873-002 03/01/2022
CLINTON, GRANT, HOWARD, MIAMI, TIPTON AND WABASH COUNTIES:
Rates Fringes
ELECTRICIAN ...................... $ 36.59 20.12
------------------------------------------------------------
ELEC1393-001 12/02/2020
REMAINING COUNTIES
Rates
Line Construction:
EQUIPMENT OPERATOR 1:
Diggers, 5th wheel type
trucks, crawler type, D-4
and smaller, bucket trucks
and live boom type line
trucks ...................... $ 32.91
EQUIPMENT OPERATOR 3
(Backhoes over 1/2 yard
bucket capacity, cranes
rated at 15 ton or more
Fringes
29%+6.75
capacity) 95%J.L. rate ..... $ 39.19 29%+6.75
GROUNDMAN TRUCK DRIVER ...... $ 26.14 29%+6.75
GROUNDMAN................... $ 25.04 29%+6.75
LINEMAN ..................... $ 41.61 29%+6.75
ENG10103-003 04/01/2021
f I CAI [0 7I t! [ellJ � 17 4:T�1:ii111 � 17_1 i! RII� I I i I t'[�lil N;� I ills- i [iI
ADAMS, ALLEN, BENTON, BLACKFORD, CARROLL, CASS, CLINTON,
DEKALB, DELAWARE, FAYETTE, GRANT, HAMILTON, HANCOCK, HENRY,
HOWARD, HUNTINGTON, JAY, JOHNSON, MADISON, MARION, MIAMI,
RANDOLPH, RUSH, SHELBY, STEUBEN, TIPPECANOE, TIPTON, UNION,
WABASH, WAYNE, WELLS, WHITE AND WHITLEY COUNTIES
Rates Fringes
Power equipment operators:
GROUP 1
..................... $ 37.75
20.21
GROUP 2
..................... $ 36.03
20.21
GROUP 3
..................... $ 35.11
20.21
GROUP 4
..................... $ 33.61
20.21
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Air compressors in manifold with throttle valve;
Asphalt plant engineer; Auto grade or similar type machine;
Auto patrol; Backhoe or farm -type tractor, 45 hp and over;
Ballast regulator (RR); Bituminous mixer; Bituminous paver;
Bituminous plant engineer; Bulldozer; Caisson drilling
machine; Cherry picker, 15 ton or over; Chip spreader;
Concrete mixer 21 cu. ft. or over; Core drilling machine;
Crane or derrick with any attachment (including clamshell,
dragline, shovel, backhoe, etc.); Dredge engineer; Dredge
operator; Drilling machine on which the drill is an integral
part; Earth mover, rubber -tired (paddle wheel, 616, 631,
TS-24 or similar type); Earth mover, rubber -tired, tandem
($0.50 per hour additional for each bowl); Elevating
grader; Fork lift, 10 ton or over; P.C.C. formless paver
post driver; Highlift shovel, 1 1/2 cu. yd. or over; Hoist,
2 drums and over; Helicopter, crew; Hydraulic boom truck;
keystone, skimmer scoop; Loader, self-propelled (belt,
chain, wheel); Locomotive operator, Mechanic; Mucking
machine; Panel board concrete plant, central mix type;
Paver, Hetherington; Pile driver, skid or crawler; Road
paving mixer; Rock breaking plant; Rock crushing plant,
portable; Roller (asphalt, waterbound macadam, bituminous
macadam, brick surface); Roller with dozer blade; Root
rake, tractor -mounted; Self-propelled widener; Stump
remover, tractor -mounted; Surface heater and planer; Tandem
push tractor ($0.50 per hour additional); Tractor, boom;
Winch or hoe head; Tractor, push; Tractor with scoop;
Tractor -mounted spreader; Tree mover; Trench machine, over
24""; Tug boat operator; Well drilling machine; Winch truck
with A -frame
GROUP 2: Air compressor with throttle valve or clever
brooks -type combination; Backfiller; Backhoe on farm -type
tractor, under 45 hp; Bull float; Cherry picker under 15
ton; Chip spreader, self-propelled; Concrete pump; Concrete
mesh depressor, independently
operated; Concrete spreader, power -driven; End loader under 1
1/2 cu. yd.; Excavating loader, portable; Finishing machine
and bull float; Gunite machine; Head greaser; Mesh or steel
placer; Multiple tamping machine (RR); P.C.C. concrete belt
placer; Pull grader, power control; Refrigerating machine,
freezing operation; Ross carrier; Sheepfoot roller
(self-propelled); Tamper (multiple vibrating, asphalt,
waterbound macadam, bituminous macadam, brick surface);
Trench machine, 24"" and under; Tube float; Welder
GROUP 3: Assistant plant engineer; Base paver (Jersey or
similar type machine); Concrete finishing machine; Concrete
mixer, less than 21 cu. ft.; Curb machine; Farm tractor,
including farm tractor with all attachments except backhoe
and including high lift end loaders of 1 cu. yd. capacity
or less; Fire tender on boiler; Hoist, 1 drum; Operator, 5
pieces of minor equipment; Paving breaker; Power broom,
self-propelled; Roller, earth and sub -base material; Slurry
seal machine; Spike machine (RR); Tamper (multiple
vibrating, earth and sub -base material); Throttle valve and
fire tender combination on horizontal or upright boiler;
Tractaire with drill; Tractor, 50 h.p. or over; Well point
system; Widener, APSCO or similar type
GROUP 4: Air compressor; Assistant to engineer, oiler;
Automatic dry batch plant; Bituminous distributor;
Bituminous patching tamper; Belt spreader; Broom and belt
machine; Chair cart, self-propelled; Coleman -type screen;
Conveyor, portable; Digger post hole, power -driven; Fork
lift, under 10 ton; Form grader; Form tamper, motor -driven;
Generator; Hetherington driver; Hydra seeder; Operator, 1
through 4 pieces of minor equipment; Outboard or inboard
motorboat; Power curing spraying machine; Power saw,
concrete, power -driven; Pug mill; Pull broom, power -type;
Seaman tiller; Straw blower or brush mulcher; Striping
machine paint, motor -driven; Sub grader; Tractaire,
tractor, below 50 h.p.; Truck crane oiler, driver;
Spreader; Water pump; Welding machine, 2 of 300 amps or over
ENG10150-009 04/01/2021
HEAVY, HIGHWAY AND RAILROAD CONSTRUCTION
ELKHART, FULTON, JASPER, KOSCIUSKO, LAGRANGE, MARSHALL, NEWTON,
NOBLE, PULASKI, and STARKE COUNTIES
Rates Fringes
POWER EQUIPMENT OPERATOR
GROUP 1.....................
$ 31.85
30.85
GROUP 2.....................
$ 30.25
30.85
GROUP 3.....................
$ 28.95
30.85
GROUP 4.....................
$ 27.55
30.85
GROUPS .....................
$ 24.30
30.85
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Air compressors in manifold with throttle valve;
Asphalt plant engineer; Auto grade or similar type machine;
Auto patrol; Automatic Sub -Grade; Backhoe or farm type
tractor, 45 hp and over; Ballast regulator (RR); Barrier
Wall Machine; Batch Plants (Concrete & Asphalt); B
ituminous mixer; Bituminous paver; Bituminous plant
engineer; Boring Machine; Bulldozer; Caisson drilling
machine; Cherry picker, 15 ton or over; Chip spreader;
Concrete mixer, 21 cu. ft, or over; Concrete Belt Placer;
Concrete Paver; Concrete Pump (Truck Mounted); Concrete Saw
(track mounted); Concrete Spreader (power driven); Core
drilling machine; Crane or derrick with any attachment
(including clamshell, dragline, shovel, backhoe, etc.);
Curb Machine; Gutter Machine; Dredge engineer; Dredge
operator; Drilling machine on which the drill is an
integral part; Earthmover, rubber -tired (paddle wheel, 616,
631, TS-24 or similar type); Earthmover, rubber -tired,
tandem (.50 per hr. additional for each bowl); Elevating
Grader; Forklift (10 ton or over); P.C.C. Formless Paver;
Gradall; Gravel Processing Plant (portable); Operator of
Guard Rail Post Driver; Highlift Shovel 1-1/2 cu.yd, or
over) Frame; Hoist (2 drum & over); Helicopter crew;
Hydraulic boom truck; Hydraulic Excavator; Loaded -Self
propelled (belt chain wheel); Laser Screed; Locomotive
operator; Mechanic; Mucking machine; P.C.C. Concrete Belt
Placer; Panel board concrete plant (central mix type);
Paver (Hetherington); Pavement Breaker; Pile driver, skid
or crawler; Road paving mixer; Rock breaking plant; Rock
crushing plant (portable); Roller (asphalt, waterbound
macadam, bituminous macadam, brick surface); Roller with
dozer blade; Road Widener; Root rake (tractor -mounted);
Roto Mill Grinder; Self-propelled widener, Stump remover;
Surface heater and planer; Tandem push tractor ($0.50 per
hour additional); Tractor, boom; Winch or hoe head; Tractor
(push); Tractor with scoop; Tractor -mounted spreader; Tree
mover; Trench machine, over 24""; Tug boat operator; Well
drilling machine; Widener (Apsco or similar type); Winch
truck with A -frame
GROUP 2: Air compressor with throttle valve or Clever Brooks
type combination; Backfiller; Farm type tractor (under 45
H.P.); Cherry picker under 15 ton; Chip spreader
(self-propelled); Concrete pump (trailer type); Concrete
mesh depressor, independently operated; End loader under 1
1/2 cu. yd.; Excavating loader (portable); Finishing
machine and bull float; Gunite machine; Hydraulic Power
unit; Head greaser; Mesh or
steel placer; Multiple tamping backhoe on machine (RR); Bull
float (bidwell Machine); Refrigerating machine -operation;
Ross Carrier; Sheepfoot roller (self-propelled);
Tamper -Multiple Vibrating (Asphalt, Waterbound, Macadam,
Bituminous Macadam, Brick Surface); Trench machine (24"" and
under); Tube float; Water Pull/Wagon; Welder
GROUP 3: Plant engineer; Base paver (Jersey or similar type
machine); Concrete finishing machine; Concrete mixer, less
than 21 cu. ft.; Curb machine; Farm tractor, including farm
tractor with all attachments except backhoe and including
high lift end loaders of 1 cu. yd. capacity or less;
Fireman, on boiler; Hoist, 1 drum; Operator, 3-5 pieces of
minor equipment; Paving breaker; Power broom,
self-propelled; Roller, earth and sub -base material; Power
Saw -Concrete (Power Driven); Slurry seal machine; Spike
machine (RR); Sub -surface Material Distributor; Tamper
(multiple vibrating, earth and sub -base material); Throttle
valve; Throttle Valve and fireman combination on horizontal
or upright boiler; Tractaire with drill; Well Point
GROUP 4: Air compressor; Assistant to engineer, oiler;
Bituminous patching tamper; Belt spreader; Broom and belt
machine; Chair cart, self-propelled; Coleman -type screen;
Conveyor, portable; Deck -hand Digger post hole,
power -driven; Forklift, under 10 ton; Form grader; Form
tamper, motor -driven; Generator; Hetherington driver; Hydra
seeder; Mechanic heater; Operator, 2 pieces of minor
equipment; Outboard or inboard motor boat; Power curing
spraying machine; Pug mill; Pull broom, power type; Seaman
tiller, Skid steer loader over 3/4 cu. yd.; Straw blower or
brush mulcher; Striping machine paint, motor -driven;
Sub -grader; Tractaire; Tractor, below 50 h.p.; Truck crane
oiler; Spreader, Water pump
GROUP 5: Skid steer loader under 3/4 cu. yds
ENG10150-039 06/01/2021
UNDERGROUND & UTILITY CONSTRUCTION:
JASPER, NEWTON, PULASKI AND STARKE COUNTIES:
Rates Fringes
POWER EQUIPMENT OPERATOR
GROUP 1.....................
$ 42.00
39.68
GROUP 2.....................
$ 41.20
39.68
GROUP 3.....................
$ 36.90
39.68
GROUP 4.....................
$ 34.70
39.68
GROUPS .....................
$ 29.25
39.68
POWER EQUITMENT OPERATOR CLASSIFICATIONS
GROUP 1: Asphalt plants (construction), Asphalt plant
(permanent), Auto Patrol (Maintainer), Automatic Dry
Batch Plant, Automated Concrete Placer, Automated
Sub -Grader, Automated Slip Form Paver, Automated Finish
Machine, Combination Backhoe Front, End Loader Machine
(1/2 cu. yd.), Backhoe bucket or over or with attachments),
Combination backhoe 1 cu yd, Backhoe bucket or over or with
attachments, Ballast Regulator (RR), Belt Loader
(stationary), Boring Machine (road), Bulldozer, Concrete
Mixer(27 cu. ft. or over), Concrete Pump (truck mounted),
Concrete Breaker (truck mounted and self-propelled), Core
Drilling Machine, Cranes and Backhoes (all attachments),
Cranes, Hammerhead, Creter Crane, Crushers (concrete, rock,
recycling, etc.), Derricks, Derricks (traveling), Dredge
Operator, Formless Curb and Gutter Machine (36 inches and
over), Formless Curb and Gutter Machine under 36 inches,
Gradall and Machines (of a like nature), Guardrail Post
Driver (truck mounted), Lead Greaser, Helicopter, Highlift
Shovel (3 yd. and over), Hoist (1 drum), Hoist (2, and 3
drums), Hydraulic Power Units (grouting, piledriving and
extracting) Hydro orwater blaster (self-propelled),
Locomotive Operators, Mechanic, Welder, Mucking Machine,
Panelboard Concrete Plant (central mix type), Paver
(Hetherington), Pile Driver (Skid or Crawler), Road Paving
Mixer, Rock Drill Crawler or Skid Rig, Rock Drill (truck
Mounted), Ross Carrier, Roto Mill Grinder (36"" and over),
Roto mill grinder (less than 36""), Throttle Valve and
Compressor or Clever Brooks Type Combination, Throttle
Valve and Fireman Combination or Horizontal or Upright
Boiler, Tournapull or similar type equipment, Tractor
(boom), Tractor Drawn Belt Loader with attached Pusher
(requires two engineers), Trench Machine, Tug Boat
Operator, Wheel Excavator, Winch Tractor with ""a"" frame,
Scoops, Turnapull or similar types machine used in Tandem
(add $1.00 to class I hourly rate for each machine attached
there to).
GROUP 2: Combination Backhoe Front End Loader Machine with
less than 1/2 cu. yd., Backhoe Bucket or with attachments,
Bituminous Mixer, Bituminous Paver, Bridge Deck Finisher,
Concrete Mixer (less than 27 cu. ft.), Compressor and
throttle valve, Compressor (common receiver 3), Greaser,
Highlift Shovels (under 3 cu. yds.), Jersey Spreader or
Base Paver, Pavement Bump Grinder (self-propelled), Roller
(Asphalt, waterbound, Macadam, Bituminous Macadam, Brick
Surface, Sheepfoot Roller (self- propelled with blade),
Surface Heater and Planer, Tamper (mutiple vibrating,
asphalt waterbound macadam, bituminouus macadam, brick
surface), Tractor (push), Tractor with scoop, Widener,
Apsco or similar type.
GROUP 3: Back Filler, Bituminous Distributor, Broom and Belt
Machine, Bull Float, Compressor (common receiver 2),
Concrete cutter wheel type (rockwell), Concrete Finishing
Machine, Concrete Spreader (power driven), Digger, Post
Hole (power driven), Finishing Machine and Bull Float,
Forklift, Form Grader, Form Tamper (motor driven),
Hydraulic (boom truck) when used for hauling materials,
Laser screed, Mutiple Tamping Machine, Paving Breaker,
Roller (earth and subbase material), Roller sheepfoot
(self-propelled), Sub -grader, Tamper, Mutipile Vibrating
(earth and subbase material), Tractaire with Drill, Tractor
(with all drawn attachements except backhoe and including
Highlift, Endloader of 1 cu. yd. capacity and less.
GROUP 4: Air Compressors, Conveyor (all), Fireman on Boiler,
Generator, Grout Machine, Power curing Spraying Machine
(self-propelled), Broom (self-propelled), Seaman Tiller,
Skid steer loaders, Spike Machine (RR), Stripping Machine
(paint, self-propelled), Throttle Valve, Welding Machine,
Well Points System.
GROUP 5: Deck Hand, Hetherington Driver, Mechanical Heater
(1 to 5), Outboard or Inboard Motor Boat, Oiler, Power Saw
(Concrete Power Driven), Water Pump, Grasscutter.
ENG10181-014 04/O1/2022
HEAVY AND HIGHWAY CONSTRUCTION:
BARTHOLOMEW, BROWN, CLARK, CRAWFORD, DEARBORN, DECATUR, DUBOIS,
FLOYD, FRANKLIN, GIBSON, HARRISON, JACKSON, JEFFERSON,
JENNINGS, LAWRENCE, MARTIN, OHIO, ORANGE, PERRY, PIKE, POSEY,
RIPLEY, SCOTT, SPENCER, SWITZERLAND, VANDERBURGH, WARRICK, and
WASHINGTON COUNTIES
Rates Fringes
Power equipment operators:
GROUP A ..................... $ 39.50 18.56
GROUP B..................... $ 36.85 18.56
GROUP C..................... $ 34.72 18.56
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP A: Air compressor in manifold with throttle valve;
Asphalt plant engineer; Auto grade or similar type machine;
Bituminous mixer; Bituminous paver; Bituminous plant
engineer; Bulldozer; Caisson drilling machine; Cherry
picker, all; Ballast regulator (RR); Chip spreader,
self-propelled; Cold grinder or similar type equipment;
Concrete mixer, 21 cu. ft. or over; Concrete pump,
truck -mounted; Core drilling machine; Crane or derrick with
any attachment (including clamshell, dragline, shovel,
backhoe, etc.); Dredge operator; Drilling machine on which
the drill is an integral part; Earth mover, rubber -tired,
tandem 0.50 per hour additional; Elevating grader;
Endloader, Hi- lift shovel; P.C.C. formless paver; Gradall;
Gravel processing plant, portable; Guardrail post driver
operator; Head greaser; Hi -lift shovel, endloader; Hoist (2
drums and over); Helicopter crew; Hydraulic boom truck,
Keystone, Skimmer Scoop; Loader, self-propelled (belt,
chain wheel); Locomotive operator; Mechanic; Mucking
machine; Multi -bank drill operator; Panel board concrete
plant, central mix type; Paver, Hetherington; Pile driver,
skid or crawler; Road paving mixer; Rock breaking plant;
Rock crushing plant, portable; Roller (asphalt, waterbound,
macadam, bituminous macadam, brick surface); Roller, with
dozer blade; Root rake, tractor -mounted; Stump remover,
tractor- mounted; Surface heater and planer; Tandem push
tractor, $0.50 per hour additional; Tractor, boom winch or
hoe head; Tractor, push; Tractor with scoop;
Tractor -mounted spreader; Tree mover; Trench machine, over
24""; Tug boat operator; Welder; Well drilling machine;
Self-propelled widener.
GROUP B: Air compressor with throttle valve or clever
brooks -type combination; Backfiller, base paver, Jersey or
similar type machine; Bull float; Concrete finishing
machine; Concrete mesh depressor, independently operated;
Concrete spreader, power- driven; Dredge engineer;
Excavator loader, portable; Fire tender on boiler;
Forklift, regardless of ton; Hoists, 1 drum; Mesh or steel
placer; Minor equipment operator, 5 pieces; Multiple
tamping machine (RR); P.C.C. concrete placer, Paving
breaker; Power broom, self-propelled;
Pull grader, power -controlled; Refrigerating machine,
freezing operation; Roller, earth and sub- base material;
Ross carrier (Straddle buggy); Sheepfoot roller,
self-propelled without blade; Tamper, multiple\vibrating
(asphalt, waterbound macadam, bituminous macadam, brick
surface); Tamper, multiple vibrating (earth and sub -base
material); Trench machine, 24"" and under; Tube float; Well
point system; Widener, Apsco or similar type; Winch truck
with A -frame.
GROUP C: Air compressor, oiler; Automatic dry batch plant;
Bituminous distributor; Bituminous patching tamper; Belt
spreader; Broom and belt machine; Brush burner; Chair cart,
self- propelled; Coleman -type screen; Cold grinder oiler;
Concrete mixer, less than 21 cu. ft.; Conveyor, portable;
Curb machine; Deckhand; Digger (post hole, power -driven);
Farm tractor, including farm tractor with all attachments
(except backhoe, Hi- lift endloaders); Form grader; Form
tamper, motor -driven; Generator; Gunite machine;
Hetherington driver; Hydra seeder; Mechanical heater; Minor
equipment operator, 1 through 4 pieces; Curing spraying
machine; Power saw, concrete (power -driven); Pug mill pull
broom, power type; Seaman tiller; Slurry seal machine;
Spike machine; Straw blower or brush mulcher, Stripping
machine (paint, motor -driven); Sub grader; Throttle valve;
Tractaire with drill; Truck crane and multi -drill oiler,
driver, Spreader; Water pump.
ENG10181-015 04/O1/2022
SEWER WATERLINE & UTILITY CONSTRUCTION:
BARTHOLOMEW, BROWN, CLARK, CRAWFORD, DEARBORN, DECATUR, DUBOIS,
FLOYD, FRANKLIN, GIBSON, HARRISON, JACKSON, JEFFERSON,
JENNINGS, LAWRENCE, MARTIN, OHIO, ORANGE, PERRY, PIKE, POSEY,
RIPLEY, SCOTT, SPENCER, SWITZERLAND, VANDERBURGH, WARRICK, and
WASHINGTON COUNTIES
Rates Fringes
Power equipment operators:
GROUP A ..................... $ 39.50 19.28
GROUP B..................... $ 36.85 19.28
SEWER WATERLINE & UTILITY CONSTRUCTION
GROUP A: A -frame winch truck; Air compressor 900 cu. ft. and
over; Air tugger; Autograde (CMI); Auto patrol; Backhoe;
Ballast regulator (RR); Batch plant (electrical control
concrete); Bending machine (pipe); Bituminous plant
(engineer); Bituminous plant; Bituminous mixer travel
plant; Bituminous paver; Bituminous roller; Buck hoist;
Bulldozer; Cableway; Chicago boom; Clamshell; Concrete
mixer, 21 cu. ft. or over; Concrete paver, concrete pump,
crete; Crane; Craneman; Crusher plant; Derrick; Derrick
boat; Dinky; Dope pots (pipeline); Dragline; Dredge
operator; Dredge engineer; Drill operator; Elevator grader;
Elevator; Ford hoe, or similar type equipment; Forklift;
Formless paver; Gantry crane; Gradall; Grademan; Hopto;
Hough loader or similar type; Hydro crane; Motor crane;
Mucking machine; Multiple tamping machine (RR); Overhead
crane; Pile driver; Pulls; Push dozer; Push boats; Roller
(sheep foot); Ross Carrier; Scoop; Shovel; Side boom; Swing
crane; Trench machine; Welder (heavy duty; Truck -mounted
concrete pump; Truck -mounted drill; Well point; Whirleys.
GROUP B: Air compressor, up to 900 cu. ft.; Brakeman; Bull
float; Concrete mixer, over 10S and under 21S; Concrete
spreader or puddler; Deck engine; Electric vibrator
compactor (earth or rock); Finishing machine; Fireman;
Greaser, on grease facilities servicing heavy equipment;
Material pump; Motor boats; Portable loader; Post hole
digger; Power broom; Rock roller; Roller, wobble wheel
(earth and rock); Spike machine (RR); Seaman tiller;
Spreader rock; Sub grader; Tamping machine; Welding
machine; Widener, Apsco or similar type: Bituminous
distributor; Cement gun; Concrete saw; Conveyor; Deckhand
oiler; Earth roller; Form grader; Generator; Guard rail
driver; Heater; JLG lifts; Oiler; Paving joint machine;
Power traffic signal; Scissor lift; Steam Jennyu; Truck
crane oiler; Vibrator; Water pump.
ENG10841-011 04/01/2020
HEAVY, HIGHWAY AND UTILITY CONSTRUCTION
BOONE, CLAY, DAVIESS, FOUNTAIN, GREENE, HENDRICKS, KNOX,
MONROE, MONTGOMERY, MORGAN OWEN, PARKE, PUTNAM, SULLIVAN,
VERMILLIAN, VIGO, and WARREN COUNTIES
Rates Fringes
Power equipment operators:
GROUP 1..................... $ 33.75 23.00+a
GROUP 2..................... $ 27.50 23.00+a
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Air Compressor Over 600 CU FT, Air Compressors (2),
Compressors hooked in Manifold, Asphalt Plant Engineer,
Auto Grade and/or C.M.I. or similar type Machine, Auto
Patrol, Motor Patrol, Power Blade, Aspco Paver, Asphalt
Planer, Asphalt Rollers, Asphalt Paver Operator, Concrete
or Asphalt Milling Machine, Self Propelled Widener, Backhoe
and/or Pavement Breaker Attachment, Self Propelled Pavement
Breaker, Ballast Regulator (R.R), Bituminous Mixer,
Bituminous Paver, Bituminous Plant Engineer, Bulk Cement
Plant Engineer, Bulldozer, One Drum Hoist with Tower or
Boom, Cableways, Tower Machines, Back Filler, Boom Tractor,
Boom or Winch Truck, Winch or Hydraulic Boom Truck, Boring
Machine, Bolier Operator, Brush Mulcher, Bull Float,
Finishing Machine, Power Cranes, Overhead Cranes, Truck
cranes, Piledriver, Skid or Crawler, Guard Rail Post
Driver, Tower Cranes, Hydro Crane, Cherry Picker,
Draglines, Derricks, Shovels, Clam, Gradalls, Two Drum
Machine, Concrete or Asphalt Curb Machine, Self Propelled,
Concrete Mixers with Skid, Tournamixer, Concrete Pump
(Truck or Skid Mounted), Concrete Plant Engineer, Soil
Cement Machine, Formless Paver, Concrete Spreader, Span Saw
(and similar types), Chip Spreader, Mesh Placer, Dredging
Equipment or Dredge Engineer or Dredge Operator, Tug Boat
Operator, Marine Scoops, Ditching Machine with Dual
Attachment, Standard or Dinkey Locomotives, Drilling
Machine, including Well Testing, Caissons, Shaft or any
similar type Drilling Machine (Well Point Systems), 4 Point
Life System (Power Lift or similar type), Mud Cat, Mucking
Machine, Sull-Air, Mechanics, Welder, Head Equipment
Greaser, Tournapull, Tractor Operating Scoops, Push
Tractors, Large Rollers on Earth, Loaders (Track or Rubber
Mounted), or similar type Machine, Lull, Tournadozer,
Scoopmobiles, Elevating Machines, Power Broom (Self
Propelled), Power Sub Grader, Hydra Ax, Farm Tractor with
Attachments, Soil Stabilizer (Seaman Tiller, Bo mag, Rago
Gator and similar types of equipment), Tree Mover, Stump
Remover, Root Rake, Hydra Seeder, Straw Blower,
Refrigerating Machine, Freezing Operator, Chair Cart -Self
Propelled, Helicopter Crew (3), Ross Carrier or Straddle
Buggy or similar Machine, Rock Crusher Plant, Gravel
Processing Machine, Pipe Cleaning Machine, Pipe Wrapping
Machine, Pipe Bending Machine, Pug Mill, Concrete Bump
Grinder Machine, Power Curing Spray Machine, Forklift
(except when used for landscaping), Snooper Truck Operator.
GROUP 2: Air Compressor 600 cu. ft. and under, Air Tugger,
Air Valves, Assistant Concrete Plant Engineer, Assistant
Asphalt Plant Engineer, Asphalt Plant Fireman, Bulk Cement
Plant Equipment Greaser, Concrete Mixers without Skips,
Curbing Machine, Concrete Saw (Self Propelled),
Conveyors,Cement Blimps, Ditching Machine under 6"",
Distributor Operator On trucks, Deck Hands, Elevators when
used for hoisting material, Engine Tenders, Fork Lift (when
used for landscaping), Farm Tractor, Fireman, Fireman on
Paint or Dope Pots, Form Tamper, Form Grader, Flex Plane,
Generators (two to four), or Welding Machines or Water
Pumps, within 400 feet, Gunite Machine, Machine Mounted
Post Hole Digger, Mude Jack, One Drum Machines without
Tower or Boom, One Water Pump, One Welding Machine,
Outboard or Inboard Motor Boat, Pull Broom (Power Type,
Siphons and Pulsometer, Switchman, Striping and or Painting
Machine (motor driven), Slurry Seal Machine, Track lack,
Temporary Heat, Throttle Valve, Tube Float, Tractaire,
Wagon Drill, Multiple Tamping Machine (R.R.), Spike Machine
(R.R.), Mechanical Heaters, Brush Burner, Vacuum Truck
(Super Sucker and similar types).
FOOTNOTES:
A. Employees operating booms from 149Ft. to 199 Ft.
including jib, shall receceive an additional seventy-five
Cents (.75) per hour above the rate. Employees operating
booms over 199 Ft. including jib, shall receive an
additional one dollar and twenty- five cents ($1.25) per
hour above the regular rate.
B. Employees operating scoops, pulls, or tractors hooked in
tandem shall receive an additional one dollar ($1.00) per
hour above the regular rate.
C. Employees operating scoops, pulls, or tractors pulling
any other hauling unit in tandem shall receive an
additional one dollar ($1.00) per hour above the regular
rate.
D. Underground work -Employees working in tunnels, shafts,
etc. shall be paid a thirty percent (30%) premium above the
wage rate.
I R 0 N 0022-00106/01/2021
BARTHOLOMEW, BENTON, BOONE, BROWN, CARROLL, CASS, CLAY,
CLINTON, DAVIESS (REMAINDER OF COUNTY), DECATUR (W 3/4),
DELAWARE (REMAINDER OF COUNTY), FAYETTE (W 1/3),
FOUNTAIN,FRANKLIN (NW TIP), FULTON (REMAINDER OF COUNTY), GRANT
(REMAINDER OF COUNTY), GREENE, HAMILTON, HANCOCK, HENDRICKS,
HENRY, HOWARD, JACKSON, JASPER (SOUTHEASTERN 1/2), JENNINGS
(NORTHWEST 2/3), JOHNSON, KNOX (REMAINDER OF COUNTY), LAWRENCE,
MADISON, MARION, MARTIN (NW 2/3), MIAMI (REMAINDER OF COUNTY),
MONROE, MONTGOMERY, MORGAN, NEWTON (SOUTHERN 1/2), OWEN, PARKE,
PULASKI (REMAINDER OF COUNTY), PUTNAM, RANDOLPH (SW TIP), RUSH
(REMAINDER OF COUNTY), SHELBY, SULLIVAN, TIPPECANOE, TIPTON,
VERMILLION, VIGO, WAYNE, WARREN AND WHITE COUNTIES:
Rates Fringes
IRONWORKER ....................... $ 33.90 24.70
The following holidays shall be observed: New Year's Day,
Memorial Day, Independence Day, Labor Day, Thanksgiving Day
and the day after Thanksgiving and Christmas Day. Any
holiday which occurs on a Sunday shall be observed the
following Monday, unless the legal observance of these
holidays is changed by law.
IRON0044-010 06/O1/2022
DEARBORN, DECATUR (REMAINDER OF COUNTY), FAYETTE (REMAINDER OF
COUNTY), FRANKLIN (REMAINDER OF COUNTY), JEFFERSON (REMAINDER
OF COUNTY), JENNINGS (REMAINDER OF COUNTY), OHIO, RIPLEY, RUSH
(SOUTHEASTERN TIP), SWITZERLAND, AND UNION (SOUTHERN 1/3)
Rates Fringes
Ironworkers:
FENCE ERECTORS .............. $ 30.28 22.30
ORNAMENTAL .................. $ 31.87 22.30
STRUCTURAL, MACHINERY
MOVERS, RIGGERS ............. $ 31.87 22.30
IRON0070-002 06/O1/2022
CLARK, CRAWFORD, FLOYD, HARRISON, JACKSON (SOUTHERN 3/4);
JEFFERSON (EXCLUDING NORTHEASTERN TIP); JENNINGS (SOUTHERN
3/4), LAWRENCE (SOUTHERN 2/3), MARTIN (SOUTHEASTERN 2/3),
ORANGE, PERRY (EASTERN 3/4); SCOTT AND WASHINGTON COUNTIES:
Rates Fringes
IRONWORKER ....................... $ 31.79 24.62
IRON0070-016 06/O1/2022
DEARBORN, DECATUR (REMAINDER OF COUNTY), FAYETTE (SE CORNER),
FRANKLIN (S 3/4), OHIO, RIPLEY (REM. OF COUNTY), SWITZERLAND
(REMAINDER OF COUNTY) and JENNINGS (NE TIP) COUNTIES
Rates Fringes
IRONWORKER (Reinforcing) ......... $ 31.79 24.62
IRON0103-001 04/01/2021
DAVIESS (S 1/2), DUBOIS, GIBSON, KNOX (S 1/2), MARTIN (SW 1/3),
PERRY (W 1/4), PIKE, POSEY, SPENCER, VANDERBURGH, AND WARRICK
Rates Fringes
IRONWORKER ....................... $ 30.00 25.66
IRON0147-004 06/01/2021
ADAMS, ALLEN, BLACKFORD, DEKALB, DELAWARE (NORTHEASTTHIRD OF
COUNTY), FULTON (EASTERN PART), GRANT (EXCLUDING SOUTHWEST
PORTION), HUNTINGTON, JAY, MIAMI (NORTHEAST HALF), NOBLE
(EXCLUDING NORTHEAST TIP), STEUBEN, WABASH, WELLS, and WHITLEY
COUNTIES
Rates Fringes
IRONWORKER ....................... $ 30.35 24.22
IRON0290-004 06/01/2022
FAYETTE (NE 1/4), RANDOLPH (S. PART OF COUNTY EXCLUDING
WINCHESTER BUT INCLUDING UNION CITY) UNION (NORTHERN 2/3) AND
WAYNE (REMAINDER OF COUNTY) COUNTIES
Rates Fringes
Ironworkers: ..................... $31.59 24.40
IRON0292-005 06/01/2022
ELKHART, FULTON (North 2/3), KOSCIUSKO (Remainder of County),
LAGRANGE (West 1/3), MARSHALL, MIAMI (Northwestern Tip), NOBLE
(Northwestern Tip), PULASKI (Northeast Half), and STARKE
COUNTIES
Rates Fringes
IRONWORKER ....................... $ 33.62 24.25
IRON0395-002 06/O1/2022
JASPER (NORTHERN 1/2), NEWTON (NORTHERN 1/2), PULASKI
(NORTHWESTERN TIP) COUNTIES
Rates Fringes
IRONWORKER
IRONWORKERS ................. $ 43.00 37.24
SHEETER..................... $ 41.75 34.54
LABO0041-003 04/01/2022
HEAVY & HIGHWAY CONSTRUCTION
NEWTON COUNTY
Rates Fringes
LABORERS
Group 1..................... $ 31.74 23.63
Group 2..................... $ 32.04 23.63
Group 3..................... $ 32.74 23.63
LABORERS CLASSIFICATIONS (HEAVY AND HIGHWAY)
GROUP 1: Construction Laborer, Carpenter Tender, Fence
Erector, Grade Checker, Guard Rail Erector, Continuous
Steel Rod or Mat Installer, Wire Mesh Layer, Joint Man
(Mortar, Mastic, and all other types), Lighting Installer
(Permanent or Temporary), Lineman for Automatic Grade Maker
on Paving Machines, Mortar Man, Multi -Plant Erector,
Rip -rap Installer (all Products and Materials), Road
Marking and Delineation Laborer, Setting and Placing of all
Precast Concrete Products, Sing Installation including
supporting structure, Spraying of all Epoxy, Curing
Compound, or Like Material, Flagperson, Air Tool, Power
Tool Operator, Asphalt Raker Man, Batch Truck Dumper,
Bridge Hand Rail ERector, Handler (bulk or bag cement),
Chain Saw Man, Concrete Puddler, Concrete Rubber, Concrete
Saw Operator, Core Drill Operator, Eye Level, Hand Blade
Operator Hydro Seeder Man, Motor Driven Georgia Buggy
Operator, Power Driven Compactor or Taper Operator, Power
Saw Operator, Pump Crete Assembly Man, Sreed Man or Screw
Man on Asphalt Paver, Regar Installer, Sandblaster Man,
Sealer Applicator for Asphalt (toxic), Setting and Placing
pre -stressed on Pre -cast Concrete Structural Members, Side
Rail Setters (for Sidewalk, Side Ditches, Radii, and
Pavement), Spreader Box Tender (manua or power driven),
Straw Blower Man, Subsureface Drain and Culvert Pipe Layer,
Concrete Conveyor, Horizonal Boring and Jackman and
Sheetman, Pipe Greade Man, Winch and Windless Operator
Conduit Installer, Sod Layer
GROUP 2: Cutting Torch Burner, Laser Beam Aligner, Manhole
Erector, Sewer Pipe Layer, Water Line Installer, Temporary
or Permanent Welders (electric or Oxy Acetylene)
GROUP 3: Air Track and Wagon Drillman, Dynamite and Powder
Man, Concrete Barrier Rail Form Setter, Concrete Saw Joint
Control Cutting
LAB00041-005 04/01/2022
UTILITY CONSTRUCTION
JASPER & NEWTON COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................
$ 31.74 23.63
GROUP 2.....................
$ 32.04 23.63
GROUP 3.....................
$ 32.74 23.63
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer; Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LABO0041-006 04/01/2022
HEAVY & HIGHWAY CONSTRUCTION
JASPER & STARKE COUNTIES
Rates Fringes
LABORERS
Group 1..................... $ 28.97 23.63
Group 2..................... $ 29.27 23.63
Group 3.....................$29.97 23.63
LABORERS CLASSIFICATIONS (HEAVY AND HIGHWAY)
GROUP 1: Construction Laborer, Carpenter Tender, Fence
Erector, Grade Checker, Guard Rail Erector, Continuous
Steel Rod or Mat Installer, Wire Mesh Layer, Joint Man
(Mortar, Mastic, and all other types), Lighting Installer
(Permanent or Temporary), Lineman for Automatic Grade Maker
on Paving Machines, Mortar Man, Multi -Plant Erector,
Rip -rap Installer (all Products and Materials), Road
Marking and Delineation Laborer, Setting and Placing of all
Precast Concrete Products, Sing Installation including
supporting structure, Spraying of all Epoxy, Curing
Compound, or Like Material, Flagperson, Air Tool, Power
Tool Operator, Asphalt Raker Man, Batch Truck Dumper,
Bridge Hand Rail ERector, Handler (bulk or bag cement),
Chain Saw Man, Concrete Puddler, Concrete Rubber, Concrete
Saw Operator, Core Drill Operator, Eye Level, Hand Blade
Operator Hydro Seeder Man, Motor Driven Georgia Buggy
Operator, Power Driven Compactor or Taper Operator, Power
Saw Operator, Pump Crete Assembly Man, Sreed Man or Screw
Man on Asphalt Paver, Regar Installer, Sandblaster Man,
Sealer Applicator for Asphalt (toxic), Setting and Placing
pre -stressed on Pre -cast Concrete Structural Members, Side
Rail Setters (for Sidewalk, Side Ditches, Radii, and
Pavement), Spreader Box Tender (manua or power driven),
Straw Blower Man, Subsureface Drain and Culvert Pipe Layer,
Concrete Conveyor, Horizonal Boring and Jackman and
Sheetman, Pipe Greade Man, Winch and Windless Operator
Conduit Installer, Sod Layer
GROUP 2: Cutting Torch Burner, Laser Beam Aligner, Manhole
Erector, Sewer Pipe Layer, Water Line Installer, Temporary
or Permanent Welders (electric or Oxy Acetylene)
GROUP 3: Air Track and Wagon Drillman, Dynamite and Powder
Man, Concrete Barrier Rail Form Setter, Concrete Saw Joint
Control Cutting
LABO0081-003 04/01/2022
UTILITY CONSTRUCTION
STARKE COUNTY
Rates Fringes
Laborers:
GROUP 1.....................
$ 28.97 23.63
GROUP 2.....................
$ 29.27 23.63
GROUP 3.....................
$ 29.97 23.63
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector, Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer; Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LABO0120-003 04/01/2022
UTI LITTY CONSTRUCTION
MARION & SHELBY COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................
$ 27.40 17.22
GROUP 2.....................
$ 27.90 17.22
GROUP 3.....................
$ 28.40 17.22
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer; Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LAB00204-003 04/01/2022
UTILITY CONSTRUCTION
CLAY, FOUNTAIN, GREENE, HENDRICKS, OWEN, PARKE, PUTNAM,
SULLIVAN, VERMILLION, VIGO, & WARREN COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................
$ 27.40 17.22
GROUP 2.....................
$ 27.90 17.22
GROUP 3.....................
$ 28.40 17.22
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer; Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LAB00213-003 04/01/2022
UTILITY CONSTRUCTION
ADAMS, ALLEN, DEKALB, HUNTINGTON, NOBLE, STEUBEN, WABASH,
WELLS, & WHITLEYCOUNTIES
Rates Fringes
Laborers:
GROUP 1.....................
$ 27.40 17.22
GROUP 2.....................
$ 27.90 17.22
GROUP 3.....................
$ 28.40 17.22
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer, Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LAB00274-005 04/01/2022
UTILITY CONSTRUCTION
BENTON, BOONE, CARROLL, CASS, CLINTON, FULTON, HOWARD, MIAMI,
MONTGOMERY, PULASKI, TIPPECANOE, TIPTON, and WHITE COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................
$ 27.40 17.22
GROUP 2.....................
$ 27.90 17.22
GROUP 3.....................
$ 28.40 17.22
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer, Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LABOO561-015 04/01/2022
UTILITY CONSTRUCTION
DAVIESS, DUBOIS, GIBSON, KNOX, PIKE, POSEY, SPENCER,
VANDERBURGH, & WARRICK COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................
$ 27.40 17.22
GROUP 2.....................
$ 27.90 17.22
GROUP 3.....................
$ 28.40 17.22
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer; Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LAB00645-005 04/01/2022
UTILITTY CONSTRUCTION
ELKHART COUNTY
Rates Fringes
Laborers:
GROUP 1.....................
$ 27.40 17.22
GROUP 2.....................
$ 27.90 17.22
GROUP 3.....................
$ 28.40 17.22
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker, Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer; Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LAB00645-006 04/01/2022
UTILITY CONSTRUCTION
KOSCIUSKO, LAGRANGE, & MARSHALL COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................
$ 27.40 17.22
GROUP 2.....................
$ 27.90 17.22
GROUP 3.....................
$ 28.40 17.22
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper, Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer, Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LABO0741-007 04/01/2022
UTILITY CONSTRUCTION
BARTHOLOMEW, BROWN, DEARBORN, DECATUR, FRANKLIN, JACKSON,
JENNINGS, JOHNSON, LAWRENCE, MARTIN, MONROE, MORGAN, OHIO,
ORANGE & RIPLEY COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................
$ 27.40 17.22
GROUP 2.....................
$ 27.90 17.22
GROUP 3.....................
$ 28.40 17.22
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer; Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); Tying and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LAB00795-004 04/01/2022
D1d 111uKUailtlrzyl[.1.�
CLARK, CRAWFORD, FLOYD, HARRISON, JEFFERSON, PERRY, SCOTT,
SWITZERLAND, & WASHINGTON COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................
$ 27.40 17.22
GROUP 2.....................
$ 27.90 17.22
GROUP 3.....................
$ 28.40 17.22
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector,
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer; Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer; Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
LAB00999-001 04/01/2020
HEAVY AND HIGHWAY CONSTRUCTION
ALL COUNTIES EXCEPT: Jasper, Newton, & Starke
Rates Fringes
Laborers:
GROUP 1.....................
$ 25.10 16.17
GROUP 2.....................
$ 25.40 16.17
GROUP 3.....................
$ 26.10 16.17
LABORERS CLASSIFICATIONS
GROUP 1: Building and Construction Laborers; Scaffold
Builders (other than for Plasterers); Mechanic Tenders;
Window Washers and cleaners; Waterboys and Toolhousemen;
Roofers Tenders; Railroad Workers; Masonry Wall Washers
(interior and exterior); Cement Finisher Tenders; Carpenter
Tenders; All Portable Water pumps with discharge up to (3)
inches; Plaster Tenders; Mason Tenders; Flag & Signal
Person.
GROUP 2: Waterproofing; Handling of Creosot Lumber or like
treated material (excluding railroad material); Asphalt
Rakers and Lutemen; Kettlemen; Air Tool Operators and all
Pneumatic Tool Operators; Air and Electric Vibrators and
Chipping Hammer Operators; Earth Compactors Jackmen and
Sheetmen working Ditches deeper than (6) ft.in depth;
Laborers working in ditches (6) ft.in depth or deeper;
Assembly of Unicrete Pump; Tile Layers (sewer or field) and
Sewer Pipe Layer (metallic or non-metallic); Motor driven
Wheelbarrows and Concrete Buggies; Hyster Operators; Pump
Crete Assemblers; Core Drill Operators; Cement, Lime or
Silica Clay Handlers (bulk or bag); Handling of Toxic
Materials damaging to clothing; Pneumatic Spikers; Deck
Engine and Winch Operators; Water Main and Cable Ducking
(metallic and non-metallic); Screed Man or Screw Operator
on Asphalt Paver; Chain and Demolition Saw Operators;
Concrete Conveyor Assemblers.
GROUP 3: Water Blast Machine Operator; Mortar Mixers; Welders
(Acetylene or electric); Cutting Torch or Burner; Cement
Nozzle. Laborers; Cement Gun Operator; Scaffold Builders
when Working for Plasterers. Dynamite Men; Drillers - Air
Track or Wagon Drilling for explosives Hazardous and Toxic
material handler, asbestos removal or handler.
LABO1112-003 04/01/2022
UTILITY CONSTRUCTION
BLACKFORD, DELAWARE, FAYETTE, GRANT, HAMILTON, HANCOCK, HENRY,
JAY, MADISON, RANDOLPH, RUSH, UNION & WAYNE COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................
$ 27.40 17.22
GROUP 2.....................
$ 27.90 17.22
GROUP 3.....................
$ 28.40 17.22
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade
checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker
on paving machines; Mortar man; Multi -plate erector;
Rip -rap installer (all products and materials); Road
marking and delineation laborer; Setting and placing of all
precast concrete products; Sign installation including
supporting structure; Spraying of all epoxy, curing
compound, or like material; sod layer; Air tool, power
tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail
erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro
seeder man; Motor -driven Georgia buggy operator;
Power -driven compactor or tamper operator; Power saw
operator; Pumperete assembly man; Screed man or screw man
on asphalt paver; Rebar installer, Sandblaster man; Sealer
applicator for asphalt (toxic); Setting and placing
prestressed or precast concrete structural memebers; Side
rail setter (for sidewalks, side ditches, radii, and
pavements); Spreader box tender (manual or power -driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete
conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass
operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole
erector; Sewer pipe layer; Water line installer, temporary
or permanent; Welder (electric or exy-acetylene) in
connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of
utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail
form setter; Dynamite and powder man; General leadman;
Concrete Saw Joint Control cutting
PAIN0012-006 05/01/2020
COMMERCIALAND INDUSTRIAL
DEARBORN, OHIO, RIPLEYAND SWITZERLAND COUNTIES:
Rates Fringes
PAINTER
Bridges, Lead Abatement ..... $ 26.30 11.35
Brush & Roller,
Paperhanger, Drywall Taping.$ 25.30 11.35
Sandblasting, Waterblasting.$ 26.05 11.35
Spray ....................... $ 25.80 11.35
PAIN0027-005 06/01/2021
NEWTON COUNTY, West of Highway #41
Rates Fringes
GLAZIER..........................$47.83 39.84
* PAIN0047-005 06/01/2022
BARTHOLOMEW, BOONE, BROWN, DECATUR, HAMILTON, HANCOCK,
HENDRICKS, JACKSON, JENNINGS, JOHNSON, LAWRENCE, MARION,
MARTIN, MONROE, MORGAN, ORANGE, AND SHELBY COUNTIES
Rates Fringes
PAINTER
BRIDGE WORK
Concrete/Masonry Bridges ... $ 26.44 13.30
Steel Bridges .............. $ 30.50 14.50
NON -BRIDGE WORK
Brush, Roller .............. $ 28.10 15.81
Spray and Sand -Blasting .... $ 29.10 15.81
* PAIN0080-00106/01/2022
BENTON, CARROLL, CASS, CLINTON, FOUNTAIN, MONTGOMERY TIPPECANOE
AND WARREN COUNTIES
Rates Fringes
PAINTER
Brush and Roller ............ $ 27.13 17.43
Spray and Sandblasting ...... $ 27.18 17.43
* PAIN0091-007 06/01/2022
ELKHART, FULTON, KOSCIUSKO AND MARSHALL COUNTIES
Rates Fringes
PAINTER
Brush & Roller, Drywall
Taping & Finishing,
Vinyl/Paper Hanging ......... $ 28.75 17.00
Spray ....................... $ 29.25 17.00
* PAIN0118-005 06/01/2022
CLARK, CRAWFORD, FLOYD, HARRISON JEFFERSON, SCOTT AND
WASHINGTON COUNTIES
Rates Fringes
Painters:
Heavy Construction
Brush, Roller &
Paperhanger ................
$ 22.20 14.07
Spray, Sandblast &
Waterblast.................
$ 23.45 13.19
Highway Construction
&
Railroad Bridges
Brush, Roller&
Paperhanger ................
$ 29.81 14.58
Spray, Sandblast &
Waterblast.................
$ 30.81 14.58
PAIN0156-001 04/01/2020
DAVIESS, DUBOIS, GIBZSON, KNOX, PERRY, PIKE, POSSEY, SPENCER,
VANDERBURGH, AND WARRICK COUNTIES
Rates Fringes
Painters:
BRUSH & ROLLER OF MASTICS,
CREOSOTES, KEWINCH KOATE,
& COAL TAR EPDXY ............ $ 28.60 17.53
BRUSH & ROLLER .............. $ 27.60 17.53
DRYWALL FINISHERS ........... $ 27.85 17.53
SPRAY of MASTICS
CREOSOTES, KWINCH KOATE,
COALTAR EPDXY .............. $ 29.60 17.53
SPRAY, SANDBLAST, POWER
TOOLS, WATERBLAST & STEAM
CLEANING .................... $ 28.60 17.53
FOOTNOTE A:
All Structures over 40? $0.75/ hour above base wage
All Structures over75? $1.50/ hour above base wage
All Structures over 100? $2.50/ hour above base wage
* PAIN0197-001 06/01/2022
CLAY, GREENE, OWEN, PARKE, PUTNAM, SULLIVAN, VERMILLION AND
VIGO COUNTIES:
Rates Fringes
Painters:
Brush & Roller.............. $ 28.50 13.70
Sandblasting ................ $ 30.50 13.70
Spray & Pot Man ............. $ 29.00 13.70
FOOTNOTE A: $1.00 premium for work on structures over 40 ft.
above floor/ground level
$2.00 premium for work on structures over 100 ft
above floor/ground level
PAIN0387-004 11/01/2021
DEARBORN, FRANKLIN, OHIO, RIPLEY, and SWITZERLAND COUNTIES
Rates Fringes
GLAZIER .......................... $ 27.93 16.82
* PAIN0460-004 06/01/2022
JASPER, NEWTON, PULASKI, STARKE AND WHITE COUNTIES
Rates Fringes
Painters:
Brush & Roller
Building ................... $ 37.10 27.68
Brush and Roller
Heavy and Highway .......... $ 37.10 27.68
Drywall Taping & Finishing..$ 37.98 27.68
* PAIN0469-002 06/01/2022
ADAMS, ALLEN, DEKALB, GRANT, HUNTINGTON, LAGRANGE, NOBLE,
STEUBEN, WABASH, WELLS, and WHITLEY COUNTIES
Rates Fringes
Painters:
Brush, Roller,
Paperhanger, & Drywall
Finishing ................... $ 23.77 14.74
Lead Abatement .............. $ 27.66 14.30
Spray & Sandblast Pot
Tenders and Ground
Personnel ................... $ 24.86 14.30
Spray, Sandblast, Power
Tools, Waterblast, & Steam
Cleaning .................... $ 24.86 14.30
* PAIN0669-001 05/01/2022
BLACKFORD, DELAWARE, FAYETTE, FRANKLIN, HENRY, HOWARD, JAY,
MADISON, MIAMI, RANDOLPH, RUSH, TIPTON, UNION and WAYNE COUNTIES
Rates Fringes
Painters:
Brush; Roller;
Paperhanging; Drywall
Finishers ................... $ 22.70 15.29
Spray/W aterblasti ng;
Sandblasting ................ $ 23.70 15.29
PAIN1165-014 07/01/2021
CLARK, CRAWFORD, DAVIESS, DUBOIS, FLOYD, GIBSON, HARRISION,
JEFFERSON, KNOX, MARTIN, ORANGE, PERRY, PIKE, POSEY, SCOTT,
SPENCER, VANDERBURGH, WARRICK AND WASHINGTON
Rates Fringes
GLAZIER .......................... $ 30.45 17.25
PAIN1165-017 07/01/2021
ADAMS, ALLEN, BLACKFORD, DE KALB, GRANT, HUNTINGTON, JAY,
NOBLE, STEUBEN, WABASH, WELLS AND WHITLEY COUNTIES
Rates Fringes
GLAZIER .......................... $ 27.42 15.55
PAIN1165-018 07/01/2021
JASPER and NEWTON (East of Highway #41) COUNTIES
Rates Fringes
GLAZIER .......................... $ 38.18 25.53
PAIN1165-019 07/01/2021
ELKHART, FULTON, KOSCIUSKO, LAGRANGE, MARSHALL, PULASKI, and
STARKE COUNTY
Rates Fringes
GLAZIER .......................... $ 29.81 17.68
PAIN1165-022 01/01/2021
BARTHOLOMEW, BENTON, BOONE, BROWN, CARROLL, CASS, CLAY,
CLINTON, DECATUR, DELEWARE, FAYETTE, FOUNTAIN, GREENE, HAM I LTON,
HANCOCK, HENDRICKS, HENRY, HOWARD, JACKSON, JENNINGS, JOHNSON,
LAWRENCE, MADISON, MARION, MIAMI, MONROE, MONTGOMERY, MORGAN,
OWEN, PARKE, PUTNAM, RANDOLPH, RUSH, SHELBY, SULLIVAN,
TIPPECANOE, TIPTON, UNION, VIGO, VERMILLION, WARREN, WAYNE, and
WHITE COUNTIES
Rates Fringes
GLAZIER .......................... $ 29.61 17.42
PLAS0075-001 06/01/2017
CLAY, OWEN, PARKE, PUTNAM, VERMILLION AND VIGO COUNTIES:
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 25.75 13.50
----------------------------------------------------------------
PLAS0075-002 06/01/2017
GREENE and SULLIVAN COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 28.50 13.50
-----------------------------------------------------------•---
PLAS0101-001 06/01/2018
ELKHART, FULTON AND MARSHALL COUNTIES; PULASKI COUNTY (SOUTHERN
1/2):
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 31.50 14.30
----------------------------------------------------------------
PLASO101-008 06/01/2014
ADAMS, ALLEN, DEKALB, HUNTINGTON, KOSCIUSKO, LAGRANGE, NOBLE,
STEUBEN, WELLS AND WHITLEY COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 23.38 11.94
PLASTERER ........................ $ 25.69 11.75
----------------------------------------------------------------
PLASO438-003 06/01/2018
PULASKI (NOTHERN 2/3), JASPER (N. EASTERN PORTION OF WEST TO
BUT NOT INCLUDING WHEATFIELD), ALL OF STARKE COUNTY
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 36.01 25.40
----------------------------------------------------------------
PLAS0692-002 06/01/2016
AREA #46
BARTHOLOMEW, BOONE, BROWN, CLARK, CLAY, CRAWFORD, DAVIESS,
DUBOIS, GIBSON, HENDRICKS, JACKSON, JEFFERSON, JENNINGS,
JOHNSON, KNOX, LAWRENCE, MARION, MARTIN, MONROE, MORGAN,
ORANGE, OWEN, PARKE, PERRY, PIKE, POSEY, PUTNAM, SCOTT, SHELBY,
SPENCER, VANDERBURGH, VERMILLION, VIGO and WARRICK COUNTIES
Rates Fringes
PLASTERER ........................ $ 25.04 13.23
PLAS0692-008 05/01/2017
BARTHOLOMEW, BROWN, CLARK, DEARBORN, FLOYD, JACKSON, JEFFERSON,
JENNINGS, LAWRENCE, OHIO, ORANGE, RIPLEY, SCOTT, SHELBY,
SWITZERLAND, and WASHINGTON Counties
Rates Fringes
CEMENT MASON/CONCRETE FINISHER
AREA #821................... $ 24.18 13.49
PLAS0692-009 04/01/2020
AREA#83
BLACKFORD, DELAWARE, GRANT, HAMILTON (Northern Part), HANCOCK
(Northern Part), JAY, MADISON, TIPTON, and WABASH COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 26.00 15.54
PLASTERER ........................ $ 25.49 11.95
P LAS0692-01104/O1/2020
AREA #83
DECATUR, FAYETTE, FRANKLIN, HENRY, RANDOLPH, RUSH, UNION and
WAYNE COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 26.00 15.54
PLASTERER ........................ $ 25.49 11.95
PLAS0692-015 06/01/2016
AREA #121
BENTON, CARROLL, CASS, CLINTON, FOUNTAIN, HOWARD, MIAMI,
MONTGOMERY, TIPPECANOE, WARREN, WHITE and VERMILLION (Northern
Part) COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 26.10 17.30
PLASTERER ........................ $ 27.71 16.40
PLAS0692-018 06/01/2017
AREA #165
NEWTON COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 38.88 23.73
PLAS0692-022 06/01/2017
Southward on Rt. No. 49 to the JASPER, BENTON and WHITE County
lines, including the City Limits of Wheatfield, Rensselaer and
Remington, Indiana. To the West, the boundary of NEWTON County
Rates Fringes
CEMENT MASON/CONCRETE FINISHER
AREA #406................... $ 33.35 19.09
PLAS0692-023 06/01/2018
AREA #532
BOONE, HAMILTON (SOUTH HALF OF COUNTY NORTH TO NEW ROUTE
INDIANA #32 INCLUDING NOBLESVILLE); HANCOCK COUNTY (SOUTHERN
AND WESTERN PART OF HANCOCK COUNTY, NORTH TO BUT NOT INCLUDING
FORTVILLE); HENDRICKS, JOHNSON, MARION and MORGAN COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 26.45 18.11
Slip Form Shift Work ........ $ 27.45 18.11
Swinging/Suspended Scaffold.$ 26.70 18.11
PLAS0692-027 04/01/2020
AREA #566
CRAWFORD, DAVIESS, DUBOIS, GIBSON, HARRISON, KNOX, MARTIN,
PERRY, PIKE, POSEY, SPENCER, VANDERBURGH and WARRICK COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER ... $ 28.30 18.31
PLUM0136-003 04/O1/2022
BROWN, DAVIESS, DUBOIS, GIBSON, JACKSON, LAWRENCE, MARTIN,
MONROE, ORANGE, OWEN, PERRY, PIKE, POSEY, SPENCER, VANDERBURGH,
WARRICK, and WASHINGTON Counties
Rates Fringes
Plumbers and Pipefitters......... $ 40.07 19.11
PLUM0157-002 07/O1/2022
BENTON, CARROLL, CLINTON, FOUNTAIN, MONTGOMERY, TIPPECANOE,
WARREN AND WHITE COUNTIES:
Rates Fringes
Plumbers and Pipefitters......... $ 39.73 20.85
PLUM 0166-00106/01/202 2
ADAMS, ALLEN, BLACKFORD, DE KALB, GRANT, HUNTINGTON, NOBLE,
STEUBEN, WABASH, WELLS, and WHITLEY COUNTIES
Rates Fringes
Plumber and Steamfitter.......... $ 39.26 17.81
PLUM0166-002 06/01/2022
ELKHART, KOSCIUSKO, and LAGRANGE COUNTIES
Rates Fringes
PLUMBER .......................... $ 39.26 17.81
----------------------------------------------------------------
PLU M0172-00106/01/2022
JASPER (S of the N. Side of the City of Rensselear), MARSHALL,
PULASKI and STARKE COUNTIES
Rates Fringes
Plumber, Pipefitter,
Steamfitter ...................... $ 38.54 21.79
-------------------------------------- -------------------------
PLUM0210-003 09/01/2020
JASPER (to the City of Rensselaer) and NEWTON COUNTIES
Rates Fringes
PLUMBER .......................... $ 42.07 25.16
----------------------------------------------------------------
PLUM0392-006 06/01/2018
DEARBORN, OHIO, RIPLEY, AND SWITZERLAND COUNTIES
Rates Fringes
Plumbers and Pipefitters......... $ 32.01 19.67
----------------------------------------------------------------
PLUM0440-002 06/04/2022
BARTHOLOMEW, BOONE, HAMILTON, HANCOCK, HENDRICKS, HOWARD,
JOHNSON AND MARION COUNTIES; MIAMI COUNTY (SOUTH OF A STRAIGHT
LINE WHERE ROUTE 218 ENTERS W. BOUNDARY); MORGAN, SHELBY and
TIPTON COUNTIES
Rates Fringes
Plumbers and Pipefitters......... $ 41.57 18.99
----------------------------------------------------------------
PLUM0440-004 06/01/2018
FAYETTE, FRANKLIN, HENRY, RANDOLPH, RUSH, UNION and WAYNE
COUNTIES
Rates
Fringes
Plumber and Steamfitter..........
$ 37.67 16.79
------------------------------------- ---------------------------
P L U M 0502-00108/O1/2016
CLARK, FLOYD AND HARRISON COUNTIES
Rates
Fringes
PLUMBER/PIPEFITTER...............
$ 32.00 20.13
----------------------------------------------------------------
PLUM0597-004 06/01/2018
JASPER (Excluding the city limits
of Rensselear), AND NEWTON
(Entire County)
Rates Fringes
PIPEFITTER ....................... $ 48.50 31.12
------------------------------------------------------------
ROOF0023-004 06/O1/2021
ADAMS, ALLEN, DEKALB, ELKHART, FULTON, HUNTINGTON, KOSCIUSKO,
LAGRANGE, MARSHALL, MIAMI, NOBLE, PULASKI, STARKE, STEUBEN,
WABASH, WELLS, and WHITLEY COUNTIES
Rates Fringes
ROOFER
COMPOSITION ................. $ 30.50 19.03
SLATE & TILE ................ $ 32.00 19.03
----------------------------------------------------------------
ROOF0026-002 06/01/2021
JASPER AND NEWTON COUNTIES
Rates Fringes
ROOFER ........................... $ 39.59 22.07
ROOF0042-002 08/01/2021
DEARBORN, OHIO and RIPLEY COUNTIES
Rates Fringes
ROOFER ........................... $ 28.85 17.05
ROO F0075-00105/01/2021
FAYETTE, RANDOLPH, UNION, and WAYNE Counties
Rates Fringes
ROOFER
Composition ................. $ 24.38 20.09
Slate & Tile ................ $ 24.60 20.09
ROOF0075-002 05/01/2021
CLINTON COUNTY
Rates Fringes
ROOFER
Composition,.- ::.:...........$ 24.38 20.09
Slate & Tile ................ $ 24.60 20.09
ROOF0106-006 04/01/2021
CRAWFORD, DAVIESS, DUBOIS, GIBSON KNOX, MARTIN, ORANGE PERRY,
PIKE, POSEY, SPENCER, VANDERBURGH AND WARRICK
Rates Fringes
ROOFER
COMPOSITION ................. $ 31.00 18.43
SLATE & TILE ................ $ 30.80 16.52
ROOF0119-002 09/01/2021
BARTHOLOMEW, BLACKFORD, BOONE, BROWN, DECATUR, DELAWARE,
FRANKLIN, GRANT, HAMILTON, HANCOCK, HENDRICKS, HENRY, HOWARD,
JACKSON, JAY, JENNINGS, JOHNSON, LAWRENCE, MADISON, MARION,
MONROE, MONTGOMERY, MORGAN, PUTNAM, RUSH, SHELBY, and TIPTON
Counties
Rates Fringes
ROOFER ........................... $ 27.80 11.75
----------------------------------------------------------------
ROOF0147-002 04/01/2018
CLARK, FLOYD, HARRISON JEFFERSON, SCOTT, SWITZERLAND, and
WASHINGTON Counties
Rates Fringes
ROOFER ........................... $ 24.43 10.20
----------------------------------------------------------------
ROOF0150-002 07/O1/2021
CLAY, GREENE, OWEN, PARKE, SULLIVAN, VERMILLION AND VIGO
COUNTIES
Rates Fringes
ROOFER ........................... $ 28.50 16.50
----------------------------------------------------------------
SHEE0020-003 07/01/2021
Rates Fringes
Sheet metal worker (HVAC Duct
Work) ............................ $ 32.71 25.82
----------------------------------------------------------------
SHEE0020-010 07/01/2021
BARTHOLOMEW, BOONE, BROWN, DECATUR, DELAWARE, FAYETTE,
FRANKLIN, HAMILTON, HANCOCK, HENDRICKS, HENRY, JACKSON,
JENNINGS, JOHNSON, LAWRENCE, MADISON, MARION, MONROE,
MONTGOMERY, MORGAN, ORANGE, RIPLEY, RUSH, SHELBY, TIPTON, UNION
AND WASHINGTON COUNTIES
Rates Fringes
SHEET METALWORKER ............... $ 37.46 23.83
-------------------------------- —------------------ ------------
SHEE0020-011 07/01/2020
CLINTON COUNTY
Rates Fringes
SHEET METAL WORKER ............... $ 33.31 25.51
SHEE0020-024 07/01/2020
CLAY, GREENE, MARTIN, OWEN, PARKE, PUTNAM, SULLIVAN,
VERMILLION, and VIGO COUNTIES
Rates Fringes
Sheet metal worker ............... $ 35.71 21.95
TEAM0135-003 04/O1/2021
REMAINING COUNTIES
Rates Fringes
TRUCK DRIVER
GROUP 1.....................
$ 31.16
17.27
GROUP 2.....................
$ 31.21
17.27
GROUP 3.....................
$ 31.26
17.27
GROUP 4.....................
$ 31.31
17.27
GROUPS .....................
$ 31.36
17.27
GROUP 6.....................
$ 31.26
17.27
GROUP 7.....................
$ 31.46
17.27
GROUP 8.....................
$ 31.46
17.27
GROUP 9.....................
$ 31.56
17.27
GROUP10.....................
$ 31.01
17.27
GROUP11.....................
$ 31.56
17.27
GROUP12.....................
$ 31.66
17.27
TRUCK DRIVER CLASSIFICATIONS
GROUP 1: Single/batches axle straight trucks; Batch trucks,
wet or dry 3 (34E) axle or less; Single axle Grease and
maintenance truck
GROUP 2: Single axle fuel and water trucks
GROUP 3: Single axle ""dog -legs"", and tandem truck or dog-
legs; Winch trucks or A -frames when used for transportation
purposes; Drivers on batch trucks, wet or dry over 3 (34E)
batches and tandem axle grease and maintenance truck
GROUP 4: Tandem axle fuel trucks; tandem axle water trucks;
butuminous distributors (two -man)
GROUP 5: Tandem trucks over 15 tons payload; Single axle semi
trucks; Farm tractors hauling material; Mixer trucks (all
types); Trucks pulling tilt -top trailer single axle; Single
axle low- boys; Truck -mounted pavement breakers
GROUP 6: Tandem trucks or ""dog -legs""; Semi -water Truck;
Sprinkler Truck; Heavy equipment -type water wagons, 5,000
gallons and under; butuminous distributors (one-man)
GROUP 7: Tri-axle trucks; Tandem axle semi trucks; Equipment
when not self -loaded or pusher loaded, such as Koehring or
similar dumpsters, track trucks, Euclid bottom dump and hug
bottom dump, tournatrailers, tournarockers, Acey wagons or
for similar equipment (12 cu yds or less); Mobile mixer
truck; Tandem Axle trucks pulling tilt -top trailer; Tandem
- Axle lowboy; Tri- Axle batch Truck; Tri-Axle grease and
maintenance truck
GROUP 8: Tandem -tandem semi trucks; Truck mechanics and
welders; Heavy equipment -type water wagon over 5,000
gallons; Tri-Axle Trucks pulling tilt -top trailer;
Low -boys, tandem -tandem axle
GROUP 9: Low -boys, tandem tri-axle; Acey wagons up to and
including 3 buckets; Equipment when not self -loaded or
pusher loaded, such as koehring or similar dumpsters, Track
Trucks, Euclid bottom dump and hug bottom dump,
Tournatrailers, Tournarockers, Acey wagons or for similar
equipment (over 12 cu yds.)
GROUP 10: Pick-up trucks
GROUP 11: Helpers; Greasers; Tire men; Batch board tenders;
Warehouseman
GROUP 12: Acey wagon (over 3 buckets); Quad Axle Trucks;
Articulating Dump
WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave
for Federal Contractors applies to all contracts subject to the
Davis -Bacon Act for which the contract is awarded (and any
solicitation was issued) on or after January 1, 2017. If this
contract is covered by the ED, the contractor must provide
employees with 1 hour of paid sick leave for every 30 hours
they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their
own illness, injury or other health -related needs, including
preventive care; to assist a family member (or person who is
like family to the employee) who is ill, injured, or has other
health -related needs, including preventive care; or for reasons
resulting from, or to assist a family member (or person who is
like family to the employee) who is a victim of, domestic
violence, sexual assault, or stalking. Additional information
on contractor requirements and worker protections under the EO
is available at
https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification
and wage rates that have been found to be prevailing for the
cited type(s) of construction in the area covered by the wage
determination. The classifications are listed in alphabetical
order of ""identifiers"" that indicate whether the particular
rate is a union rate (current union negotiated rate for local),
a survey rate (weighted average rate) or a union average rate
(weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed
in dotted lines beginning with characters other than ""SU"" or
""UAVG"" denotes that the union classification and rate were
prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of
the union which prevailed in the survey forthis
classification, which in this example would be Plumbers. 0198
indicates the local union number or district council number
where applicable, i.e., Plumbers Local 0198. The next number,
005 in the example, is an internal number used in processing
the wage determination. 07/O1/2014 is the effective date of the
most current negotiated rate, which in this example is July 1,
2014.
Union prevailing wage rates are updated to reflect all rate
changes in the collective bargaining agreement (CBA) governing
this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that
no one rate prevailed for this classification in the survey and
the published rate is derived by computing a weighted average
rate based on all the rates reported in the survey for that
classification. As this weighted average rate includes all
rates reported in the survey, it may include both union and
non -union rates. Example: SULA2012-007 5/13/2014. SU indicates
the rates are survey rates based on a weighted average
calculation of rates and are not majority rates. LA indicates
the State of Louisiana. 2012 is the year of survey on which
these classifications and rates are based. The next number, 007
in the example, is an internal number used in producing the
wage determination. 5/13/2014 indicates the survey completion
date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a
new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate
that no single majority rate prevailed for those
classifications; however, 100% of the data reported for the
classifications was union data. EXAMPLE: UAVG-OH-0010
08/29/2014. UAVG indicates that the rate is a weighted union
average rate. OH indicates the state. The next number, 0010 in
the example, is an internal number used in producing the wage
determination. 08/29/2014 indicates the survey completion date
for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of
each year, to reflect a weighted average of the current
negotiated/CBA rate of the union locals from which the rate is
based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can
be:
an existing published wage determination
a survey underlying a wage determination
a Wage and Hour Division letter setting forth a position on
a wage determination matter
a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests
for summaries of surveys, should be with the Wage and Hour
National Office because National Office has responsibility for
the Davis -Bacon survey program. If the response from this
initial contact is not satisfactory, then the process described
in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal
process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an
interested party (those affected by the action) can request
review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the
interested party's position and by any information (wage
payment data, project description, area practice material,
etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an
interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISIO"
GENERAL CONDITIONS
GENERAL CONDITIONS
TABLE OF CONTENTS
ARTICLE1 - DEFINITIONS...................................................................................................................................................................................GC-4
ARTICLE 2 - PREMLIMINARY MATTERS........................................................................................................................................................GC-5
2.1 Delivery of Bonds and Evidence of Insurance..................................................................................................................................................GC-5
2.2 Commencement of Contract Times: Notice to Proceed....................................................................................................................................GC-5
2.3 Startine the Work..............................................................................................................................................................................................GC-5
2.4 Before Startine Construction.............................................................................................................................................................................GC-6
2.5. Before Startine Construction............................................................................................................................................................................
GC-6
2.6 Preconstruction Conference...............................................................................................................................................................................GC-6
2.7 Initially Acceptable Schedules ................. .........................................................................................................................................................
GC-6
AITI ]CLE 3 - CONTRACT DOCUMENTS: INTENT, AMENDING REUSE...................................................................................................GC-6
3.1 Intent ..................................................................................................................................................................................................................GC-6
3.2 Reference Standards..........................................................................................................................................................................................GC-6
3.3 Reporting and Resolving Discrepancies............................................................................................................................................................GC-7
3.3.2 Resolving..................................................................................................................................................................................................GC-7
3.4 Amending and Supplementing Contract Documents........................................................................................................................................GC-7
3.5 Reuse of Documents..........................................................................................................................................................................................GC-7
ARTICLE 4 - AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS ...................................................................GC-7
4.1 Availability of Lands.........................................................................................................................................................................................GC-7
4.2 Subsurface and Physical Conditions.................................................................................................................................................................GC-8
4.2.1 Reports and Drawings: ..............................................................................................................................................................................
GC.8
4.2.1.2 Physical Conditions: . .............................................................................................................................................................................
GC-8
4.2.2. Limited Reliance by CONTRACTOR Authorized, Technical Data: .......................................................................................................
GC-8
4.3 Differing Subsurface or Physical Conditions....................................................................................................................................................GC-8
4.3.2 ENGINF.ER's Review: ...........................................................................................................................................................
.................. GC-8
4.3.3. Possible Contract Documents Cha......................................................................................................................................................GC-8
4.3.4 Possible Price and Times Adjustment s.....................................................................................................................................................GC-8
4.4 Physical Conditions -Underground Facilities.....................................................................................................................................................GC-9
4.4.1 Shown or Indicated: ..................................................................................................................................................................................
GC-9
4.5 Reference Points................................................................................................................................................................................................GC-9
4.6 Asbestos PCRs Petroleum Hazardous {Paste or Radioactive Material.........................................................................................................GC-9
ARTICLE 5 - BONDS, INSURANCE AND INDEMNIFICATION...................................................................................................................GC-10
5.1 Performance. Payment and Other Bonds: ......................................................................................................................................................
GC-110
5.2. Licensed Sureties and Insurers......................................................................................................................................................................GC-10
5.3 Certificates of Insurance.................................................................................................................................................................................GC-10
5.4 CONTRACTOR's Liability Insurance...........................................................................................................................................................GC-10
A. Workers Compensation/F.mplover's Liability: ..........................................................................................................................................GC-II
B. Commercial General Liability: ...................................................................................................................................................................
GC-1 I
C. Commercial Automobile Liability (Owned. Leased. Hired/Non-Owned): .................................................................................................
GC -I 1
5.5 OWNER's Liability Insurance.........................................................................................................................................................................GC-I1
5.6 Property Insurance...........................................................................................................................................................................................GC-12
5.7. Waiver of Rights ........................................... ..................................................................................................................................................
GC-12
5.8 Receipt and Application of Insurance Proceeds..............................................................................................................................................
GC-12
5.9 Accentance of Bonds and Insurance; Option to Replace'........................................................... ....................................................................
GC-13
5.10 Partial Utilization -Property Insurance...........................................................................................................................................................GC-13
5.11 Indemnification..............................................................................................................................................................................................GC-13
ARTICLE 6 - CONTRACTOR'S RESPONSIBILITIES.....................................................................................................................................GC-13
6.1 Supervision and Superintendence....................................................................................................................................................................GC-13
6.2 labor. Materials and Equipment ....................................................................................................................................................................GC-13
6.3 Services. Materials and Equipment.................................................................................................................................................................GC-13
6.4 Progress Schedule...........................................................................................................................................................................................GC-14
6.5 Substitutes and "Or -Equal" Items...................................................................................................................................................................GC-14
6.5. 1.1"Or-Eguaf':..........................................................................................................................................................................................GC-14
6.5.1.2 S'ubstivae Gents:...................................................................................................................................................................................GC-14
6.6 Concerning Subcontractors. Suppliers and Others ....... ................................................ ...................................................................................
GC- 15
6.7 Patent Fees and Royalties................................................................................................................................................................................GC-15
6.8 Permits.............................................................................................................................................................................................................GC-15
6.9 Lmvs and Regulations.....................................................................................................................................................................................GC-15
6.10 Taxes..............................................................................................................................................................................................................GC-16
6.11 Use of Site and Other Areas..........................................................................................................................................................................GC-16
6.11.1 Limitations on Use of Site and Other Areas.........................................................................................................................................GC-16
6.12 Record Documents........................................................................................................................................................................................GC-16
6.13 Safety and Protection ............................ ...
-
GC-] (Quote Form)
6.14 Safety Representative....................................................................................................................................................................................GC-16
6.15 Hazard Communication Programs................................................................................................................................................................GC-16
6.16 Emergencies..................................................................................................................................................................................................GC-17
6.17 Shoo Drawings and Samoles.........................................................................................................................................................................GC-17
6,17.1.1 Shoo Drawings...................................................................................................................................................................................GC-17
6.17.3 Submittal Procedures............................................................................................................................................................................GC-17
6.17.4 ENGINEER's Review...........................................................................................................................................................................GC-17
6.17.5 Resubmittal Procedures.........................................................................................................................................................................GC-17
6.18 Continuing the Work.....................................................................................................................................................................................GC-17
6.19 CON I RAC'fOR's General Warranty and Guarantee....................................................................................................................................GC-17
ARTICLE7 - OTHER WORK...............................................................................................................................................................................GC-18
7.1 Related Work at Site........................................................................................................................................................................................GC-18
7.2 Coordination....................................................................................................................................................................................................GC-19
ARTICLE 8 - OWNER'S RESPONSIBILITIES..................................................................................................................................................GC-19
8.1 Communication to Contractor.........................................................................................................................................................................GC-19
8.2 Replacement of ENGINEER...........................................................................................................................................................................GC-19
8.3 Famish Data....................................................................................................................................................................................................GC-19
8.4 Lands and Easements; Reports and Tests........................................................................................................................................................GC-19
8.5 Insurance..........................................................................................................................................................................................................GC-19
8.6 Change Orders.................................................................................................................................................................................................GC-19
8.7 Inspections. Tests and Approvals....................................................................................................................................................................GC-19
8.8. Limitations on Owner's Responsibilities.......................................................................................................................................................GC-19
8.10 Undisclosed Hazardous Environmental Condition.......................................................................................................................................GC-19
ARTICLE 9-ENGINEER'S STATUS DURING CONSTRUCTION...............................................................................................................GC-19
9.1 O W NER's Representative...............................................................................................................................................................................GC-
19
9.2 Visits to Site: ...................................................................................................................................................................................................
GC-19
9.3 Proiect Representative.....................................................................................................................................................................................GC-19
9.3.2 Duties and Responsibilities.....................................................................................................................................................................GC-19
9.3.4 Clarifications and Interpretations............................................................................................................................................................GC-21
9.4 Authorized Variations in Work.......................................................................................................................................................................GC-21
9.5 Reiecting Defective Work...............................................................................................................................................................................GC-21
9.6 Shop Drawings, Change Orders and Par ments...............................................................................................................................................GC-21
9.7 Determinations for Unit Prices........................................................................................................................................................................GC-21
9.8 Decisions on Disputes.....................................................................................................................................................................................GC-21
9.9 tations on Engineer's Authority and Responsibilities.............................................................................................................................GC-21
ARTICLE 10 - CHANGES IN THE WORK.........................................................................................................................................................GC-22
10.1 Authorized Changes in the Work..................................................................................................................................................................GC-22
10.2 Unauthorized Changes in the Work..............................................................................................................................................................GC-22
10.3 Execution of Change Orders.........................................................................................................................................................................GC-22
10.4 Notification to Surety....................................................................................................................................................................................GC-22
ARTICLE I I- COST OF THE WORK; ALLOWANCES AND UNIT PRICES..............................................................................................GC-22
11.1 Cost of the Work...........................................................................................................................................................................................GC-22
11.2 Allowances....................................................................................................................................................................................................GC-24
11.3 Unit Price Work.............................................................................................................................................................................................GC-24
ARTICLE 12 - CHANCES OF CONTRACT PRICE AND TIMES..................................................................................................................GC-24
12.1 Change of Contract Price...............................................................................................................................................................................GC-24
12.2 Changes of ContractTime.............................................................................................................................................................................GC-24
12.3 Delays............................................................................................................................................................................................................GC-25
ARTICLE 13 - TEST AND INSPECTIONS; CORRECTION, REMOVAL OF WORK................................................................................CC-25
13.1 Notice of Defects...........................................................................................................................................................................................GC-25
13.2 Access to Work..............................................................................................................................................................................................GC-25
13.3 Tests and Inspections.....................................................................................................................................................................................GC-25
13.4 Uncovering Work..........................................................................................................................................................................................GC-25
13.5 OWNER May Stop the Work........................................................................................................................................................................GC-25
13.6 Correction or Removal of Defective Work ................................................... ................................................................................................
GC-26
13.7 Correction Period...........................................................................................................................................................................................GC-26
13.8 Acceptance of Defective Work.....................................................................................................................................................................GC-26
13.9 OWNER Alnv Correct Defective Work..........................................................................................................................................................GC-26
ARTICLE 14 - PAYMENTS TO CONTRACTOR AND COMPLETION........................................................................................................GC-26
14.1 Schedule of ValUes.......................... ..............................................................................................................................................................
GC-26
14.2 Application for Progress Payment.................................................................................................................................................................GC-26
14.2.2 Review of Applications for Progress Payment.....................................................................................................................................GC-27
14.3 CONTRACTOR'S Warranty of "I itle........... ..................................................................................................................................................
GC-27
14.4 Substantial Completion.................................................................................................................................................................................GC-27
14.5 Partial Utilization ...........................................................................................................................................................................................GC-28
� Ana
GC-2 (Quote Form)
14.7 Final Payment................................................................................................................................................................................................GC.28
14.7.2 Final Payment and Acceptance.............................................................................................................................................................GC-29
14.8 Final Completion Delayed.............................................................................................................................................................................GC-29
14.9 Waiver of Claims...........................................................................................................................................................................................GC-29
ARTICLE 15 - SUSPENSION OF WORK AND TERMINATION ............................................
....................................................................... GC-29
15.1 OWNER May Suspend Work.......................................................................................................................................................................GC-29
15.2 OWNER's Right to Terminate for Cause......................................................................................................................................................GC-29
15.3 OWNER'S Right to Terminate for Convenience ..........................................................................................................................................GC-30
15.4 CONTRACTOR May Stop Work or Terminate...........................................................................................................................................GC-30
ARTICLE16 - DISPUTE RESOLUTION............................................................................................................................................................GC-30
ARTICLE 17 -MISCELLANEOUS.......................................................................................................................................................................GC-30
17.1 Giving Notice ................................................................................................................................................................................................GC-30
17.2 Computation of Time ...................................................................................................................................................................................GC-30
17.3 Notice of Claim.............................................................................................................................................................................................GC-30
17.4 Cumulative Remedies....................................................................................................................................................................................GC-30
17.5 Professional Fees and Court Costs Included.................................................................................................................................................GC-30
GC-3 (Quote Form)
Part B - GENERAL CONDITIONS City of Cannel
ARTICLE I
DEFINITIONS
Wherever used in these General Conditions or in the other Contract
Documents the following terms have the meanings indicated which
are applicable to both the singular and plural thereof:
LL Addenda -Written or graphic instruments issued prior to the
opening of Quotes which clarify, correct or change the Bidding
Requirements or the Contract Documents.
1.2. Agreement -The written contract between OWNER and
CONTRACTOR covering the Work to be performed; other Contract
Documents are attached or incorporated by reference into the
Agreement and made a part thereof as provided therein.
1.3. Application for Payment -The form accepted by ENGINEER
which is to be used by CONTRACTOR in requesting progress or
final payments and which is to be accompanied by such supporting
documentation as is required by the Contract Documents, including
Affidavit and Waiver of Claims or Liens.
1.4. Asbestos -Any material that contains more than one percent
asbestos and is friable or is releasing asbestos fibers into the air above
current action levels established by the United States Occupational
Safety and Health Administration.
1.5. Bid -The offer or proposal (also referred to as Quote) of the
Contractor (also referred to as Contractor) submitted on the
prescribed form setting forth the prices for the Work to be performed.
1.6. Bidding Documents- The Notice to Contractors, the Proposal,
including Quote Form, and the proposed Contract Documents
(including all Addenda issued prior to receipt of Quotes).
1.7. Bidding Requirements -The Advertisement/ Notice to
Contractors, Instructions to Contractors, and the Quote form.
1.8. Bonds -Quote, Performance and Payment bonds and other
instruments of security.
1.9. Change Order -A document recommended by ENGINEER,
which is signed by CONTRACTOR and OWNER and authorizes an
addition, deletion or revision in the Work, or an adjustment in the
Contract Price or the Contract Times, issued on or after the Effective
Date of the Agreement.
1.10. Contract Documents -The Agreement, Addenda (which pertain
to the Contract Documents), CONTRACTOR's Quote (including
documentation accompanying the Quote and any post Quote
documentation submitted prior to the Notice of Award) when
attached as an exhibit to the Agreement, the Notice to Proceed, the
Bonds, these General Conditions, the Special Conditions, the
Specifications and the Drawings as the same me more specifically
identified in the Agreement, together with all Written Amendments,
Change Orders, Work Change Directives, Field Orders and
ENGINEER's written interpretations and clarifications issued
pursuant to paragraphs 3.4., 3.4.2.1, and 3.4.2.3 on or after the
Effective Date of the Agreement. Shop Drawing submittals approved
pursuant to paragraphs 6.17.4.1 and 6.17.4.2 and the reports and
drawings refered to in paragraphs 4.2.1.1 and 4.2.2.2 are not
Contract Documents.
1.11. Contract Price -The moneys payable by OWNER to
CONTRACTOR for completion of the Work in accordance with the
Contract Documents as stated in the Agreement (subject to the
provisions of paragraph 11.3 in the case of Unit Price Work).
1.12. Contract Times -The numbers of calendar days or the dates
stated in the Agreement: (i) to achieve Substantial Completion, and
(ii) to complete the Work so that it is ready for final payment as
evidenced by ENGINEER's written recommendation of final
payment in accordance with paragraph 14.7.2.1.
1.13. CONTRACTOR -The person, firm or corporation with whom
OWNER has entered into the Agreement.
1.14. Defective -An adjective which when modifying the word Work
refers to Work that is unsatisfactory, faulty or deficient, in that it does
not conform to the Contract Documents, or does not meet the
requirements of any inspection, reference standard, test or approval
referred to in the Contract Documents, or has been damaged prior to
ENGINEER's recommendation of final payment (unless
responsibility for the protection thereof has been assumed by
OWNER, at Substantial Completion in accordance, with paragraph
14.4 or 14.5).
1.15. Drawings -The drawings which show the scope, extent and
character of the Work to be furnished and performed by
CONTRACTOR and which have been prepared or approved by
ENGINEER and are referred to in the Contract Documents. Shop
drawings are not Drawings.
1.16. Effective Date of the Agreement -The date indicated in the
Agreement on which it becomes effective, but if no such date is
indicated it means the date on which the Agreement is signed and
delivered by the last of the two parties to sign.
1.17. ENGINEER -The person, firm or corporation named as such in
the Agreement.
L 18. ENGINEER's Consultant -A person, firm or corporation having
a contract with ENGINEER to furnish services as ENGINEER's
independent professional associate or consultant with respect to the
Project and who is identified as such in the Special Conditions.
1.19. Field Order -A written order issued by ENGINEER which
orders minor changes in the Work in accordance with paragraph 9.5
but which does not involve a change in the Contract Price or the
Contract Times.
1.20. General Requirements -Sections of Division I of the
Specifications.
1.21. Hazardous Waste -The term Hazardous Waste shall have the
meaning provided in Section 1004 of the Solid Waste Disposal Act
(42 USC Section 6903) as amended from time to time.
1.22. Laws and Regulations; Laws or Regulations -Any and all
applicable laws, rules, regulations, ordinances, codes and orders of
any and all governmental bodies, agencies, authorities, and courts
having jurisdiction over the work.
1.23. Liens -Liens, charges, security interests or encumbrances upon
real property or personal property.
1.24. Milestone -A principal event specified in the Contract
Documents relating to an intermediate completion date or time prior
to Substantial Completion of all the Work.
1.25. Notice ofAward-The written notice by OWNER to the apparent
successful Contractor stating that upon compliance by the apparent
successful Contractor with the conditions precedent enumerated
therein, within the time specified, OWNER will sign and deliver the
Agreement.
1.26. Notice to Proceed -A written notice given by OWNER to
CONTRACTOR (with a copy to ENGINEER) fixing the date on
which the Contract Times will commence to run and on which
GC-4 (Quote Form)
CONTRACTOR shall start to perform CONTRACTOR'S obligations
under the Contract Documents.
1.27. OWNER -The public body or authority corporation, association,
firm or person with whom CONTRACTOR has entered into the
Agreement -and for whom the Work is to he provided.
1.28. Partial Utilization -Use by OWNER of a substantially
completed part of the Work for the purpose for which it is intended
(or a related purpose) prior to Substantial Completion of all the
Work.
1.29. PCBs -Polychlorinated biphenyls.
1.30. Petroleum -Petroleum, including crude oil or any fraction
thereof which is liquid at standard conditions of temperature and
pressure (60 degrees Fahrenheit and 14.7 pounds per square inch
absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse,
gasoline, kerosene, and oil mixed with other non -Hazardous Wastes
and crude oils.
1.31. Project -The total construction of which the Work to be
provided under the Contract Documents may he the whole, or a part
as indicated elsewhere in the Contract Documents.
1.32. Radioactive Material -Source, special nuclear, or byproduct
material as defined by the Atomic Energy Act of 1954 (42 USC
Section 2911 et seq.) as amended from time to time.
1.33. Resident Project Representative -The authorized representative
of ENGINEER who may be assigned to the site or any part thereof as
defined in the Special Conditions.
1.34. Samples -Physical examples of materials, equipment, or
workmanship that are representative of some portion of the Work and
which establish the standards by which such portion of the Work will
bejudged.
1.35. Shop Drmvings-All drawings.. diagrams, illustrations, schedules_
and other data or information which are specifically prepared or
assembled by or for CONTRACTOR and submitted by
CONTRACTOR to illustrate some portion of the Work.
1.36. Specifications -those portions of the Contract Documents
consisting of written technical descriptions of materials, equipment,
construction systems, standards and workmanship as applied to the
Work and certain administrative details applicable thereto.
1.37. Subcontractor -An individual, firm or corporation having a
direct contract with CONTRACTOR or with any other Subcontractor
for the performance of a part of the Work at the site.
1.38. Substantial Completion -The Work (or a specified part thereof)
has progressed to the point where, in the opinion of ENGINEER as
evidenced by ENGINEER's definitive certificate of Substantial
Completion, it is sufficiently complete, in accordance with the
Contract Documents, so that the Work (or specified part) can be
utilized for the purposes for which it is intended; or if no such
certificate is issued, when the Work is complete and ready for final
payment as evidenced by ENGINEER's written recommendation of
final payment in accordance with paragraph 14.17.2. The terms
"substantially complete" and "substantially completed" as applied to
all or part of the Work refer to Substantial Completion thereof.
1.39. Special Conditions -The part of the Contract Documents which
amends or supplements these General Conditions based on project or
work specific requirements.
1.40. Supplier -A manufacturer, fabricator, supplier. distributor,
materialman or vendor having a direct contract with CONTRACTOR
or with any Subcontractor to furnish materials or equipment to be
incorporated in the Work by CONTRACTOR or any Subcontractor.
1.41. Underground Facilities -All pipelines, conduits, ducts, cables,
wires, manholes, vaults, tanks, tunnels or other such facilities or
attachments, and any encasements containing such facilities which
have been installed underground to furnish any of the following
services or materials: electricity, gases, steam, liquid petroleum
products, telephone or other communications, cable television,
sewage and drainage removal, traffic or other control systems or
water.
1.42. Unit Price Work -Work to be paid for on the basis of unit prices
as an amount stated in the Quote as a price per unity of measurement
for materials, equipment or services or a scope of work as described
in the Bidding Documents.
1.43. Work -The entire completed construction or the various
separately identifiable parts thereof required to be furnished under the
Contract Documents. Work includes and is the result of performing
or furnishing labor and furnishing and incorporating materials and
equipment into the Construction, and performing or furnishing
services and furnishing documents, all as required by the Contract
Documents.
1.44. Work Change Directive -A written directive to CONTRACTOR,
issued on or after the Effective Date of the Agreement and signed by
OWNER and recommended by ENGINEER, ordering an addition,
deletion or revision in the Work, or responding to differing or
unforeseen physical conditions under which the Work is to be
performed as provided in paragraph 4.2 or 4.3 or to emergencies
under paragraph 6.16. A Work Change Directive will not change the
Contract Price or the Contract Times, but is evidence that the parties
expect that the change directed or documented by a Work Change
Directive will be incorporated in a subsequently issued Change Order
following negotiations by the parties as to its effect, if any, on the
Contract Price. or Contract Times as provided in paragraph 10.1.2.
1.45. Written Amendment -A written amendment of the Contract
Documents, signed by OWNER and CONTRACTOR on or after the
Effective Date of the Agreement and normally dealing with the
nonengineering or nontechnical rather than strictly construction -
related aspects of the Contract Documents.
ARTICLE 2
PRELIMINARY MATTERS
2.1 Delivery of Bonds and Evidence of Insurance
2.1.1 When CONTRACTOR delivers the executed Agreements to
OWNER, CONTRACTOR shall also deliver to OWNER such Bonds
as CONTRACTOR maybe required to furnish in accordance with
paragraph 5.1 of the General Conditions or Agreement.
2.1.2 OWNER will furnish to CONTRACTOR copies of the Contract
Documents. As many copies will be furnished as are available from
the printings made for bidding purposes. Additional copies will be
furnished upon request at the cost of reproduction.
2.2 Commencement of Contract Times: Notice to Proceed
2.2.1 The Contract Times will commence to run on the day indicated
in the Notice to Proceed. A Notice to Proceed may be given at any
time within thirty (30) days after the Effective Date of the
Agreement.
2.3 Starting the Work
2.3.1 CONTRACTOR shall start to perform the Work on the date
when the Contract Times commence to run, but no Work shall be
GC-5 (Quote Form)
done at the site prior to the date on which the Contract Times
commence to run.
2.4 Before Starting Construction
2.4.1 Before undertaking each part of the Work, CONTRACTOR
shall carefully study and compare the Contract Documents and check
and verify pertinent figures shown thereon and all applicable field
measurements. CONTRACTOR shall promptly report in writing to
ENGINEER any conflict, error, ambiguity or discrepancy which
CONTRACTOR may discover and shall obtain a written
interpretation or clarification from ENGINEER before proceeding
with any Work affected thereby; however, CONTRACTOR shall not
be liable to OWNER or ENGINEER for failure to report any conflict,
error, ambiguity or discrepancy in the Contract Documents, unless
CONTRACTOR knew or reasonably should have known thereof.
2.4.2 Within ten (10) days after the Effective Date of the Agreement
(unless otherwise specified in the General Requirements),
CONTRACTOR shall submit to ENGINEER for review:
2.4.2.1 a preliminary progress schedule indicating the times (numbers
of calendar days or dates) for starting and completing the various
stages of the Work, including any Milestones specified in the
Contract Documents;
2.4.2.2 N/A
2.4.2.3 N/A.
2.4.2.3.1 Mobilization for CONTRACTOR and any tier of
subcontractor(s) shall be considered collectively and shall not exceed
10 percent (100%) of the Contract Price. Mobilization shall be those
costs associated with the initiation of the Project and sitework,
including but not limited to, transporting of personnel, equipment,
materials, supplies, incidental items; establishment of the field
offices, temporary facilities necessary for the project, bonds and
insurances, submittal requirements,_ permits, field supervision, final
cleanup and demobilization. Mobilization- does not include such
items as, contract negotiations and Quote preparation. Where the
Work is covered by Unit Price and no item has been included for
mobilization, then this Work is considered incidental to the Work and
will not be paid separately.
2.4.3.1.2. Where the work is covered by Unit Prices, and item(s) for
mobilization, as described in 2.4.3.1 have been included, the
maximum allowable amount shall be ten percent (10%) of the
aggregate of all items excluding mobilization. Where mobilization is
included in multiple items, then the aggregate amount of all
mobilization items shall not exceed the allowable ten percent (10%).
2.4.3.2 Costs for submittal requirements, field office and supervision,
where identified separately in the schedule of values shall be
considered for payment monthly. When the cost is a lump sum as
submitted in accordance with 2.4, the monthly cost shall be
established by dividing the lump sum by the number of monthly
estimates based on the original Contract Time. No adjustments shall
be made for any Contract Time extensions.
2.4.3.3 Mobilization shall be included in the progress payments, in
accordance with the schedule of values and Unit Prices. When the
mobilization and inventory, has progressed to an amount equal to
fifty percent (50%) of the Contract Price. The remaining
mobilization payment will be paid as part of the final payment.
2.4.4 N/A.
2.5. Before Starting Construction.
2.5.1 Before any Work at the site is started, CONTRACTOR shall
deliver to the OWNER and ENGINEER, with copies to each
additional insured identified in the General or Special Conditions,
certificates of insurance (and other evidence of insurance which
OWNER or any additional insured may reasonably request) which
CONTRACTOR is required to purchase and maintain in accordance
with paragraphs 5.4 and 5.6.
2.6 N/A
2.71nitially Acceptable Schedules
2.7.1 Unless otherwise provided in the Contract Documents, at least
ten (10) days before submission of the first Application for Payment
a conference attended by CONTRACTOR, ENGINEER and others as
appropriate will be held to review for acceptability to ENGINEER as
provided below the schedules submitted in accordance with
paragraph 2.4.2, CONTRACTOR shall have an additional ten (10)
days to make corrections and adjustments and to complete and
resubmit the schedules. No progress Payment shall be made to
CONTRACTOR until the schedules are submitted to and acceptable
to ENGINEER as provided below.
2.7.1.1 The progress schedule will be acceptable to ENGINEER as
providing an orderly progression of the Work to completion within
any specified Milestones and the Contract Times, but such
acceptance will neither impose on ENGINEER responsibility for the
sequencing, scheduling or progress of the Work nor interfere with or
relieve CONTRACTOR from CONTRACTOR's full responsibility
therefor.
ARTICLE 3
CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE
3.1 Intent
3.1.1 The Contract Documents comprise the entire agreement
between OWNER and CONTRACTOR concerning the work. The
Contract Documents are complementary; what is called for by one is
as binding as if called for by all. The Contract Documents will be
construed in accordance with the law of the place of the Project.
3.1.2 It is the intent of the Contract Documents to describe a
functionally complete Project (or part thereof) to be constructed in
accordance with the Contract Documents. Any Work, materials or
equipment that may reasonably be inferred from the Contract
Documents or from prevailing custom or trade usage as being
required to produce the intended result will be furnished and
performed whether or not specifically called for. When words or
phrases which have a well-known technical or constmction industry
or trade meaning are used to describe Work, materials or equipment,
such words or phrases shall be interpreted in accordance with that
meaning.
Work, excluding mobilization and inventory, has progressed to an
amount equal to five percent (5%) or more of the Contract Price, then 3.1.3 Clarifications and interpretations of the Contract Documents
an amount of not more than fifty percent (50%) of the mobilization shall be issued by ENGINEER as provided in paragraph 9.3.4.
cost will be considered for inclusion in the progress payment. Prior 3.2 Reference Standards
to the established five percent (50/6), Owner may consider payment on
invoices for bonds and insurances and permits; this amount shall be 3.2.1 Standards, Specifications, Codes, Laws and Regulations.
subtracted from the total amount for mobilization. Not more than 3.2.1.1. Reference to standards, specifications, manuals or codes of
forty percent (40 /a) of the mobilization cost will be considered for any technical society, organization or association, or to the Laws or
inclusion in the -progre.gspayments onon the ` mk W a:^^
GC-6 (Quote Form)
Regulations of any governmental authority, whether such reference
be specific or by implication, shall mean the latest standard,
specification, manual, code or Laws or Regulations in effect at the
time of opening of Quotes (or, on the Effective Date of the
Agreement if there were no Quotes), except as may be otherwise
specifically stated in the Contract Documents.
3.3 Reporting and Resolving Discrepancies
3.3.1 Reporting
3.3.1.1. If, during the performance of the Work, CONTRACTOR
discovers any conflict, error, ambiguity or discrepancy within the
Contract Documents or between the Contract Documents and any
provision of any such Law or Regulation applicable to the
performance of the Work or of any such standard, specification,
manual or code or of any instruction of any Supplier referred to in
paragraph 6.3.2, CONTRACTOR shall report it to ENGINEER in
writing at once, and, CONTRACTOR shall not proceed with the
Work affected thereby (except in an emergency as authorized by
paragraph 6.16) until an amendment or supplement to the Contract
Documents has been issued by one of the methods indicated in
paragraph 3.4; provided, however, that CONTRACTOR shall not be
liable to OWNER or ENGINEER for failure to report any such
conflict, error, ambiguity or discrepancy unless CONTRACTOR
knew or reasonably should have known thereof.
3.3.2 Resolving
3.3.2.1. Except as otherwise specifically stated in the Contract
Documents or as may be provided by amendment or supplement
thereto issued by one of the methods indicated in paragraph 3.4, the
provisions of the Contract Documents shall take precedence in
resolving any conflict, error, ambiguity or discrepancy between the
provisions of the Contract Documents and:
3.3.2.1.1. the provisions of any such standard, specification, manual,
code or —instruction (whether or not specifically incorporated by
reference in the Contract Documents); or
3.3.2.1.2. the provisions of any such Laws or Regulations applicable
to the performance of the Work. (unless such an interpretation of the
provisions of the Contract Documents would result in violation of
such Law or Regulation).
3.3.2.1.3 No provision of any such standard, specification, manual,
code or instruction shall be effective to change the duties and
responsibilities of OWNER, CONTRACTOR or ENGINEER or any
of their subcontractors, consultants, agents, or employees from those
set forth in the Contract Documents, nor shall it be effective to assign
to OWNER, ENGINEER or any of ENGINEER's Consultants, agents
or employees any duty or authority to supervise or direct the
furnishing or performance of the Work or any duty or authority to
undertake responsibility inconsistent with the previsions of paragraph
9.9 or any other provision of the Contract Documents.
3.3.3. Whenever in the Contract Documents the terms "as ordered,"
"as directed," "as required," "as allowed," "as approved" or terms of
like effect or import are used, or the adjectives "reasonable,"
"suitable," "acceptable," "proper" or "satisfactory" or adjectives of
like effect or import are used to describe a requirement, direction,
review or judgment of ENGINEER as to the Work, it is intended that
such requirement, direction, review or judgment will be solely to
evaluate, in general, the completed Work for compliance with the
requirements of and information in the Contract Documents and
conformance with the design concept of the completed Project as a
functioning whole as shown or indicated in. the Contract Documents
(unless there is a specific statement indicating otherwise). The use of
any such term or adjective shall not be effective to assign to
ENGINEER any duty or authority to supervise or direct the
furnishing or performance of the Work or any duty or authority to
undertake responsibility contrary to the provisions of paragraph 9.9
or any other provision of the Contract Documents.
3.4 Amending and Supplementine Contract Documents
3.4.1 The Contract Documents may be amended to provide for
additions, deletions and revisions in the Work or to modify the terms
and conditions thereof in one or more of the following ways:
3.4.1.1 a formal Written Amendment,
3.4.1.2 a Change Order (pursuant to paragraph 10.3), or
3.4.1.3 a Work Change Directive (pursuant to paragraph 10.1).
3.4.2 In addition, the requirements of the Contract Documents may
be supplemented, and minor variations and deviations in the Work
may be authorized, in one or more of the following ways:
3.4.2.1 a Field Order (pursuant to paragraph 9.4),
3.4.2.2 ENGINEER's approval of a Shop Drawing or Sample
(pursuant to paragraphs 6.17.4.1 and 6.17.4.2), or
3.4.2.3 ENGINEER's written interpretation or clarification (pursuant
to paragraph 9.3.4).
3.5 Reuse of Documents
3.5.1 CONTRACTOR, and any Subcontractor or Supplier or other
person or organization performing or furnishing any of the Work
under a direct or indirect contract with OWNER (i) shall not have or
acquire any title to or ownership rights in any of the Drawings,
Specifications or other documents (or copies of any thereof) prepared
by or bearing the seal of ENGINEER or ENGINEER's Consultant,
and (ii) shall not reuse any of such Drawings, Specifications, other
documents or copies on extensions of the Project or any other project
without writtenconsentof OWNER and ENGINEER and specific
written verification or adaption by ENGINEER.
ARTICLE 4
AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL
CONDITIONS; REFERENCE POINTS
4.1 Availability of Lands
4.1.1 OWNER shall furnish, as indicated in the Contract Documents
the lands upon which the Work is to be performed, rights -of -way and
easements for access thereto, and such other lands which are
designated for the use of CONTRACTOR. OWNER shall identify
any encumbrances or restrictions not of general application but
specifically related to use of lands so furnished with which
CONTRACTOR will have to comply in performing the Work.
Easements for permanent structures or permanent changes in existing
facilities will be obtained and paid for by OWNER, unless otherwise
provided in the Contract Documents. If CONTRACTOR and
OWNER are unable to agree on entitlement to or the amount or
extent of any adjustments in the Contract Price or the Contract Times
as a result of any delay in OWNER's furnishing these lands, rights -
of -way or easements, CONTRACTOR may make a claim therefor as
provided in Article 12.
4.1.2 CONTRACTOR shall provide for all additional lands and
access thereto that may be required for temporary construction
facilities or storage of materials and equipment.
4.1.3 The OWNER shall provide permanent easements and
temporary construction easements as shown on the Drawings for
buried pipelines across private property. If the easements obtained are
GC-7 (Quote Form)
additional easements required. There will be no additional
compensation made for obtaining these easements, damages to
private property outside easements, or additional cost to the
CONTRACTOR because of the easements or lack thereof.
4.2 Subsurface and Physical Conditions
4.2.1 Reports and Drawings: Reference is made to the Special
Conditions for identification of:
4.2.1.1 Subsurface Conditions: Those reports of explorations and
tests of subsurface conditions at or contiguous to the site that have
been utilized by ENGINEER in preparing the Contract Documents;
are detailed in the Special Conditions, the following reports of
explorations and tests of subsurface conditions at the site of the
Work. The technical data contained in such reports) upon which
CONTRACTOR may rely are the boring method, plan and logs; level
of subsurface water; laboratory test methods and results, if any; and
similar factual data, all as of the dates made.
4.2.1.2 Physical Conditions: Those drawings of physical conditions
in or relating to existing surface or subsurface structures at or
contiguous to the site (except Underground Facilities) that have been
utilized by ENGINEER in preparing the Contract Documents are
detailed in the Special Conditions.
4.2.1.3 The following drawings of physical conditions in or relating
to existing surface and sub -surface structures (except Underground
Facilities) which are at or contiguous to the site of the Work:
4.2.1.3.1 Copies of the reports listed in paragraph 4.2.1.1. and
Drawings listed in paragraph 4.2.1.2. may be examined at the
ENGINEER's office during normal working hours as defined in the
Special Conditions. These reports and drawings are not part of the
Contract Documents, but the technical data contained therein upon
which the CONTRACTOR is entitled to rely as provided in
paragraph 4.2. and as identified and established above are
incorporated therein by reference. CONTRACTOR is not entitled to
rely upon other information and data utilized by ENGINEER and
ENGINEER's Consultants in the preparation of Drawings and
Specifications.
4.2.2. Limited Reliance by CONTRACTOR Authorized, Technical
Data CONTRACTOR may rely upon the general accuracy of the
"technical data" contained in such reports and drawings, but such
reports and drawings are not Contract Documents. Such "technical
data" is identified in the Special Conditions, Except for such reliance
on such "technical data," CONTRACTOR may not rely upon or
make any claim against OWNER, ENGINEER or any of
ENGINEER's Consultants with respect to:
4.2.2.1. the completeness of such reports and drawings for
CONTRACTOR's purposes, including, but not limited to, any aspects
of the means, methods, techniques, sequences and procedures of
construction to be employed by CONTRACTOR and safety
precautions and programs incident thereto, or
4.2.2.2 other data, interpretations, opinions and information contained
in such reports or shown or indicated in such drawings, or
4.2.2.3 any CONTRACTOR interpretation of or conclusion drawn
from any "technical data" or any such data, interpretations, opinions
or information.
4.3 Differing Subsurface or Physical Conditions
4.3.1 If CONTRACTOR believes that any subsurface or physical
condition at or contiguous to the site that is uncovered or revealed
either:
4.3.1.1 is of such a nature as to establish that any "technical data" on
which CONTRACTOR is entitled to rely as provided in paragraphs
4.2 is materially inaccurate, or
4.3.1.2 is of such a nature as to require a change in the Contract
Documents, or
4.3.1.3 differs materially from that shown or indicated in the Contract
Documents, or
4.3.1.4 is of an unusual nature, and differs materially from conditions
ordinarily encountered and generally recognized as inherent in Work
of the character provided for in the Contract Documents;
then CONTRACTOR shall promptly, but in no case less than forty-
eight (48) hours after becoming aware thereof and before further
disturbing conditions affected thereby or performing any Work in
connection therewith (except in an emergency as permitted by
paragraph 6.16), notify OWNER and ENGINEER in writing about
such condition. CONTRACTOR shall not further disturb such
conditions or perform any Work in connection therewith (except as
aforesaid) until receipt of written order to do so.
4.3.2 ENGINEER's Review: ENGINEER will promptly review the
pertinent conditions, determine the necessity of OWNER's obtaining
additional exploration or tests with respect thereto and advise
OWNER in writing (with a copy to CONTRACTOR) of
ENGINEER's findings and conclusions.
4.3.3. Possible Contract Documents Channe If ENGINEER
concludes that a change in the Contract Documents is required as a
result of a condition that meets one or more of the categories in
paragraph 4.2, a Work Change Directive or a Change Order will be
issued as provided in Article 10 to reflect and document the
consequences of such change.
4.3.4 Possible Price and Times Adjustments
4.3.4J An equitable adjustment intheContract Price or in the
Contract Times, or both, will be allowed to the extent that the
existence of such uncovered or revealed condition causes an increase
or decrease in CONTRACTOR's cost of, or time required for
performance of, the Work; subject, however, to the following:
4.3.4.1.1 such condition must meet any one or more of the categories
described in paragraphs 4.2.3.1 through 4.3.1.4 inclusive;
4.3.4.1.2 a change in the Contract Documents pursuant to paragraph
4.3.3 will not be an automatic authorization of nor a condition
precedent to entitlement to any such adjustment;
4.3.4.1.3 with respect to Work that is paid for on a Unit Price Basis,
any adjustment in Contract Price will be subject to the provisions of
paragraphs 9.7 and 11.3.
4.3.4.2 CONTRACTOR shall not be entitled to any adjustment in the
Contract Price or Times if,
4.3.4.2.1 CONTRACTOR knew of the existence of such conditions
at the time CONTRACTOR made a final commitment to OWNER in
respect of Contract Price and Contract Times by the submission of a
Quote or becoming bound under a negotiated Contract; or
4.3.4.2.2 the existence of such condition could reasonably have been
discovered or revealed as a result of any examination, investigation,
exploration, test or study of the site and contiguous areas required by
the Bidding Requirements or Contract Documents to be conducted by
or for CONTRACTOR prior to CONTRACTOR's making such final
commitment; or
4.3.4.2.3 CONTRACTOR failed to give the written notice within the
time and ae rem,ired by naraaranh a 3,1
GC-8 (Quote Form)
4.3.4.3 If OWNER and CONTRACTOR are unable to agree on
entitlement to or as to the amount or length of any such equitable
adjustment in the Contract Price or Contract Times, a claim may be
made as provided in Article 12. However, OWNER, ENGINEER
and ENGINEER's Consultants shall not be liable to CONTRACTOR
for any claims, costs, losses or damages sustained by
CONTRACTOR on or in connection with any other project or
anticipated Project.
4.4 Physical Conditions -Underground Facilities
4.4.1 Shown or Indicated: The information and data shown or
indicated in the Contract Documents with respect to existing
Underground Facilities at or contiguous to the site is based on
information and data famished to OWNER or ENGINEER by the
owners of such Underground Facilities or, by others. Unless it is
otherwise expressly provided in the Special Conditions:
4.4.1.1. OWNER and ENGINEER shall not be responsible for the
accuracy or completeness of any such information or data; and
4.4.1.2. The cost of all of the following will be included in the
Contract Price and CONTRACTOR shall have full responsibility for
(i) reviewing and checking all such information and data, (ii) locating
all Underground facilities shown or indicated in the Contract
Documents, (iii) coordination of the Work with the owners of such
Underground Facilities during construction, and (iv) the safety and
protection of all such Underground Facilities as provided in
paragraph 6.13 and repairing any damage thereto resulting from the
Work.
4.3.2. Not Shown or Indicated
4.3.2.1 If an Underground Facility is uncovered or revealed at or
contiguous to the site which was not shown or indicated in the
Contract Documents, CONTRACTOR shall promptly, and in no case
later than forty-eight (48) hours after becoming aware thereof and
before further disturbing conditions affected therebyor-performing
any Work in connection therewith (except in an emergency as
required by paragraph 6.16), identify the owner of such Underground
Facility and give written notice to that owner and to OWNER and
ENGINEER. ENGINEER will promptly review the Underground
Facility and determine the extent, if any, to which a change is
required in the Contract Documents to reflect and document the
consequences of the existence of the Underground Facility.
4.3.2.2 If ENGINEER concludes that a change in the Contract
Documents is required, a Work Change Directive or a Change Order
will be issued as provided in Article 10 to reflect and document such
consequences. During such lime, CONTRACTOR shall be
responsible for the safety and protection of such Underground
Facility as provided in paragraph 6.13 CONTRACTOR shall be
allowed an increase in the Contract Price or an extension of the
Contract Times, or both, to the extent that they are attributable to the
existence of any Underground Facility that was not shown or
indicated in the Contract Documents and that CONTRACTOR did
not know of and could not reasonably have been expected to be
aware of or to have anticipated. If OWNER and CONTRACTOR are
unable to agree on entitlement to or the amount or length of any such
adjustment in Contract Price or Contract Times, CONTRACTOR
may make a claim therefor as provided in Article 12. However,
OWNER, ENGINEER and ENGINEER's Consultants shall not be
liable to CONTRACTOR for any claims, costs, losses or damages
incurred or sustained by CONTRACTOR on or in connection with
any other project or anticipated project.
4.5.1 OWNER shall provide engineering surveys to establish
reference points for construction which in ENGINEER's judgment
are necessary to enable CONTRACTOR to proceed with the Work.
CONTRACTOR shall be responsible for laying out the Work; shall
protect and preserve the established reference points and shall make
no changes or relocations without the prior written approval of
OWNER. CONTRACTOR shall report to ENGINEER whenever any
reference point is lost or destroyed or requires relocation because of
necessary changes in grades or locations, and shall be responsible for
the accurate replacement or relocation of such reference points by
professionally qualified personnel.
4.6 Asbestos, PCBs. Petroleum, Hazardous Waste or Radioactive
Material
4.6.1 OWNER shall be responsible for any Asbestos, PCBs,
Petroleum, Hazardous Waste or Radioactive Material uncovered or
revealed at the site which was not shown or indicated in Drawings or
Specifications or identified in the Contract Documents to be within
the scope of the Work and which may present a substantial danger to
persons or property exposed thereto in connection with the Work at
the site. OWNER shall not be responsible for any such materials
brought to the site by CONTRACTOR, Subcontractor, Suppliers or
anyone else for whom CONTRACTOR is responsible.
4.6.2. CONTRACTOR shall immediately: (i) stop all Work in
connection with such hazardous condition and in any area affected
thereby (except in an emergency as required by paragraph 6.16), and
(ii) notify OWNER and ENGINEER (and thereafter confirm such
notice in writing) OWNER shall promptly consult with ENGINEER
concerning the necessity for OWNER to retain a qualified expert to
evaluate such hazardous condition or take corrective action, if any.
4.6.3 CONTRACTOR shall not be required to resume Work in
connection with such hazardous condition or in any such affected
area until after OWNER has obtained any required permits related
thereto and delivered to CONTRACTOR special written notice; (i)
specifying that such condition and any affected area is or has been
rendered safe for the resumption of Work, or (ii) specifying any
special conditions under which such Work may be resumed safely. If
OWNER and CONTRACTOR cannot agree as to entitlement to or
the amount or extent or an adjustment, if any, in Contract Price or
Contract Times as a result of such Work stoppage or such special
conditions under which Work is agreed by CONTRACTOR to be
resumed, either party may make a claim therefor as provided in
Article 12.
4.6.4 If after receipt of such, special written notice CONTRACTOR
does not agree to resume such Work based on a reasonable belief it is
unsafe, or does not agree to resume such Work under such special
conditions, then OWNER may order such portion of the Work that is
in connection with such hazardous condition or in such affected area
to be deleted from the Work. If OWNER and CONTRACTOR
cannot agree as to entitlement to or the amount or extent (if an
adjustment, if any, in Contract Price or Contract Times as a result of
deleting such portion of the Work, then either party may make a
claim therefor as provided in Article 12. OWNER may have such
deleted portion of the Work performed by OWNER's own forces or
others in accordance with Article 7.
4.6.5 To the fullest extent permitted by Laws and Regulations,
OWNER shall indemnify and hold harmless CONTRACTOR,
Subcontractors, ENGINEER, ENGINEER's Consultants and the
officers, directors, employees, agents, other consultant and
Subcontractors of each and any of them from and against all claims,
4.5 Reference Points costs, losses and damages arising out, of or resulting from such
hazardous condition, provided that: (i) any such claim, cost, loss or
damage is attributable to bodily injury, sickness, disease or death, or
GC-9 (Quote Form)
to injury to or destruction of tangible property (other than the Work
itself), including the loss of use resulting therefrom, and (if) nothing
in this subparagraph 4.6.5 shall obligate OWNER to indemnify any
person or entity from and against the, consequences of that person's
or entity's own negligence.
4.6.6 To the fullest extent permitted by the Laws and Regulations,
CONTRACTOR shall indemnify and hold harmless the OWNER and
ENGINEER, and the officers, directors, partners, employees, agents,
consultants, and subcontractors of each and any of them from and
against all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute
resolution costs) arising out of or relating to a Hazardous
Environmental Condition created by CONTRACTOR or by anyone
for whom CONTRACTOR is responsible. Nothing in this paragraph
4.6.6 shall obligate CONTRACTOR to indemnify any individual or
entity from and against the consequences of that individual's own
negligence.
4.6.7 The provisions of paragraphs 4.2 and 4.3 are not intended to
apply to Asbestos, PCBs, Petroleum, Hazardous Waste or
Radioactive Material uncovered or revealed at the she,
ARTICLE 5
BONDS, INSURANCE AND INDEMNIFICATION.
5.1 N/A.
5.2. Licensed Sureties and Insurers
5.2.1. All Bonds and Insurance required by the Contract Documents
to be purchased and maintained by OWNER or CONTRACTOR
shall be obtained, from surety or insurance companies that are duly
licensed or authorized in the jurisdiction in which the Project is
located to issue Bonds or insurance policies for the limits and
coverages so required. Such surety and insurance companies shall
also meet such additional requirements and qualifications as may be
provided in the Special Conditions, if any.
The surety and insurance companies providing any coverages on this
Project shall have and maintain during the term of this Agreement a
minimum A.M. Best (Best's Key Rating Guide) rating classification
of "A.".
5.3 Certificates of Insurance
5.3.1 CONTRACTOR shall deliver to OWNER, with copies to each
Additional Insured identified in the Special Conditions, certificates of
insurance (and other evidence of insurance requested by OWNER or
any other additional insured) which CONTRACTOR is required to
purchase and maintain in accordance with paragraph 5.4.
5.3.2. The CONTRACTOR shall file policies and/or certificates of
insurance, in duplicate, for all coverages required with the OWNER
and the ENGINEER, naming the OWNER and the ENGINEER as
Certificate Holders. Addresses of OWNER and ENGINEER must
also be shown.
5.3.3 The certificate of insurance shall show that all coverages are
provided on an occurrence basis and shall indicate the aggregate limit
available for this Project as of the date the certificate is issued.
Binders will be accepted as evidence of coverage_for only the first
ninety (90) days and cannot be renewed or extended beyond that
time.
5.3.4. All insurance policies and certificates of insurance must
include a provision stating a minimum thirty (30) days' prior written
notice will be provided to the OWNER and ENGINEER for any
The CONTRACTOR shall cease operations upon the occurrence of
any such cancellation, non renewal, material change, or reduction of
coverage, and shall not resume operations until satisfactory
replacement insurance is provided, coverage is effective and
certificates of insurance are received.
5.4 CONTRACTOR's Liability Insurance
5.4.1 CONTRACTOR shall purchase and maintain such liability and
other insurance as is required for the Work being performed and
Tarnished and that will provide protection from claims which may
arise out of or result from CONTRACTOR's performance and
furnishing of the Work and CONTRACTOR's other obligations
under the Contract Documents whether it is to be performed or
furnished by CONTRACTOR, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform or
furnish any of the Work, or by anyone for whose acts any of them
may be liable which are applicable to the Work to be performed,
including:
5.4.1.1 claims under workers' compensation disability benefits and
other similar employee benefit acts which are applicable to the Work
to be performed including private entities performing Work at the site
and exempt from the coverage on account of number of employees or
occupation, which entities shall maintain voluntary compensation
coverage at the same limits specified for the mandatory coverage for
the duration of the Project. In case any such Work is sublet, the
CONTRACTOR shall require the Subcontractor to provide insurance
for all employees of the Subcontractor engaged in such Work unless
such employees are covered by the coverage afforded by the
CONTRACTOR's insurance.
5.4.1.1.1 If any Work under this Agreement involves activities within
the scope of the United States Long Shoremen's and Harbor
Worker's Act and/or the Jones Act, coverage for such exposure shall
be provided with a minimum limit of $1,000,000 per occurrence.
5.4.1.2 claims for damages because of bodily injury, occupational
sickness or disease or death of CONTRACTOR's employees, or
persons or entities excluded by statute from the requirements of
5.4.1.1, but required by the Contract Documents to provide the
insurance required therein;
5.4.1.3 claims for damages because of bodily injury, sickness or
disease or death of any person other than CONTRACTOR's
employees;
5.4.1.4 claims for damages insured by customary personal injury
liability coverage which are sustained: (i) by any person as a result of
an offense directly or indirectly related to the employment of such
person by CONTRACTOR or (ii) by any other person for any other
reason;
5.4.1.5 claims for damages, other than to the Work itself because of
injury to or destruction of tangible property wherever located,
including loss of use resulting therefrom;
5.4.1.6 claims for bodily injury or property damage arising out of
completed operations; and
5.4.1.7 claims involving contractual liability insurance applicable to
the CONTRACTOR'S obligations under the indemnification
requirements of paragraph 5.11 of the General Conditions.
5.4.2 Contractor shall purchase and maintain commercial general
liability and commercial automobile liability insurance during the
entire term of this Agreement. The policies shall he based on terms
commonly referred to in the insurance industry as an occurrence
coverage foot (Claims made policy forms are not acceptable.)
GC-10 (Quote Form)
5.4.2.1 The certificate of insurance for commercial general liability
insurance shall indicate the amount of the aggregate limit remaining
for this Project as of the date of the certificate.
5.4.2.2 The commercial general liability coverage shall include
premises coverage, products and completed operations coverage,
personal injury coverage, coverage for explosion, collapse, and
underground coverages, broad form property damage and contractual
liability coverage to satisfy the indemnification clause in its entirety
included in paragraph 5.11 of the General Conditions.
5.4.2.3 The commercial general liability policy must contain the
following definition of "insured contract":
"That part of any other contract or agreement
pertaining to your business (including an indemnification of a
municipality in connection with work performed for a
municipality) under which you assume the tort liability of another
party to pay for "bodily injury" or "property damage" to a third
person or organization. Tort liability means a liability that
would be imposed by law in the absence of any contract or
agreement."
5.4.2.4 The certificate of insurance shall include this specific
language on the certificate of insurance confirming this definition of
an insured contract or a certified copy of the policy is to be submitted
which includes this definition of an insured contract.
5.4.3 The CONTRACTOR shall purchase and maintain commercial
automobile liability coverages for any owned or leased vehicles.
Non -owned and hired auto liability coverages shall also be included.
5.4.4 This policy shall cover the total Project and include explosion,
collapse, and underground coverages for the entire Work provided by
the CONTRACTOR and Subcontractors.
5.4.5 The policy shall stipulate that the "designated CONTRACTOR"
includes the CONTRACTOR and all Sub -contractors engaged in the
Work.
5.4.6 The original policy shall be submitted to and filed with the
OWNER or its designated representative.
5.4.7. Minimum Limits of Insurance:
5.4.7.1 The minimum limits of liability for all coverages in each of
the proceeding paragraphs above shall be as follows, unless otherwise
specifically required by Law or by the Special Conditions (whichever
is greater). Coverages shall be maintained without interruption from
the date of commencement of the Work until date of final payment
and termination of any coverage required to be maintained after final
payment.
A. Workers Comnensation/Emolover's Liabilitv:
Coverage A (Worker's Compensation) - Statutory
Coverage B (Employer's Liability) - $1,000,000 / each accident;
$1,000,000 Disease -each employee; $1,000,000 Disease -policy limit.
This coverage to be valid in all states covered for the Contract Work.
B. Commercial General Liability:
General Aggregate (except Products/Completed Operations) -
$2,000,000;
Bodily Injury & Property Damage - $2,000,000 Combined Single
Limit/Per Occurrence;
Personal/Advertising Injury $2,000,000/occurrence;
Products/Completed Operations General Aggregate - $2,000,000;
Coverage to include exposures listed in 5.4.2.2;
Coverage includes Contractual Liability and Broad Form Property
Damage including Completed Operations;
Coverage to apply on a "Per Project" basis in order that coverage will
not be diminished by unrelated work.
C. Commercial Automobile Liability (Owned. Leased. Hired/Non-
Owned):
Bodily Iniury & Prooertv Damage - $5,000,000 / occurrence
All coverages provided above shall be endorsed to include the
OWNER, ENGINEER and all Consultants as listed in the Special
Conditions as Additional Insured except for A (Worker's
Compensation) and will stipulate that this coverage is primary
respecting any other coverages the OWNER, ENGINEER or
Consultants might have. The additional insured endorsement will
include "Completed Operations" of the CONTRACTOR (and any
Subcontractor). The coverage requirements apply to all
CONTRACTOR'S, Subcontractors, Sub -subcontractors and
Suppliers; CONTRACTOR is responsible to verify these
requirements for each and every one of its Subcontactors, Sub -
subcontractors and Suppliers.
5.4.7.2 If a commercial umbrella liability policy is used to satisfy the
minimum limits of liability requirements, the combined limits must
equal these minimum limits of liability.
5.4.7.3 If the aggregate liability limits required by this Agreement for
any policy subsequently fall below the aggregate limits required by
this Agreement for this Project, immediate steps shall be taken to
effect reinstatement of the minimum aggregate liability limits
required by this Agreement. A revised certificate of insurance, in
compliance with paragraph 5.3.2, is required to confirm compliance
with this requirement. Any additional premiums resulting from such
reinstatement shall be at no additional cost to OWNER.
5.4.7.4 Upon specific request by OWNER or ENGINEER, the
original policy shall be filed with the OWNER or his designated
representative within thirty (30) days of request.
5.4.7.5 With respect to products and/or completed operations
insurance coverage, will remain in effect for at least three (3) years
after final payment (and CONTRACTOR shall famish OWNER, and
each other insured identified in the General Conditions to whom a
certificate of insurance has been issued, evidence satisfactory to
OWNER and any such other insured or additional insured of
continuation of such insurance at final payment and three (3) year
thereafter).
5.4.8.1 These coverage requirements and minimum coverage limits
are to provide the minimum acceptable insurance coverages and their
existence does not in any way limit or reduce the CONTRACTOR'S
or Subcontractor's indemnity obligations under the Contract
Documents.
5.4.8.2 No representation or warranty is made by the OWNER or
ENGINEER regarding the sufficiency or adequacy of the insurance
requirements, coverages or limits stated in the Contract Documents.
The CONTRACTOR and Subcontractors are advised to consult with
their respective insurance agents or professional advisors to
determine their coverage needs and requirements.
5.5 OWNER's Liability Insurance.
5.5.1 In addition to the insurance required to be provided by
CONTRACTOR under paragraph 5.4, OWNER, at OWNER's option,
may purchase and maintain at OWNER's expense OWNER's own
GC-11 (Quote Form)
liability insurance as will protect OWNER against claims which may
arise from operations under the Contract Documents.
5.6 Property Insurance
5.6.1 CONTRACTOR shall purchase and maintain property
insurance / builder's risk insurance upon the Work at the site of the
Project in the amount of the full replacement cost thereof, except for
the errors and omissions of the ENGINEER.
5.6.1.1 The CONTRACTOR shall purchase and maintain special
form coverage and include demolition occasioned by enforcement of
Laws and Regulations; earthquake; water damage; and such other
perils as may be specifically required by the General Conditions
Builders Risk Property Insurance upon the Work at the site to the full
insurable replacement cost value thereof, including underground
pipelines. The CONTRACTOR shall also purchase and maintain
special form coverage and include demolition occasioned by
enforcement of Laws and Regulations; earthquake; water damage;
and such other perils as may be specifically required by the General
Conditions on any property, whether real property or personal
property, whether or not it is located at the site or in transit, in which
the OWNER and/or ENGINEER have an insurable interest as
evidenced by current Estimates, or other terms of this Agreement,
and include the interests of OWNER, CONTRACTOR,
Subcontractors of any tier, ENGINEER, ENGINEER'S Consultants
and any other persons or entities identified in the General Conditions,
each of whom is deemed to have an insurable interest and shall be
listed as an additional insured.
5.6.1.2 This coverage is to be provided on a separate Builders Risk
completed value policy, with special form coverage. This insurance
shall:
5.6.1.2.1 include expense incurred in the repair or replacement of any
insured property (including, but not limited to, fees and charges of
ENGINEERS and architects);
5.6.1.2.2 cover materials, property, and equipment in transit for
incorporation in the Work or stored at the site or at another location
prior to being incorporated in the Work;
5.6.1.2.3. be maintained in effect until final payment and settlement
is made unless otherwise agreed to in writing by OWNER,
CONTRACTOR, and ENGINEER with thirty (30) days written
notice to each other additional insured to whom a certificate of
insurance has been issued prior to the cessation of such coverage.
5.6.2 CONTRACTOR shall purchase and maintain such boiler and
machinery insurance or additional property insurance as may be
required by the Special Conditions or Laws and Regulations which
will include the interests of OWNER. CONTRACTOR,
Subcontractors, ENGINEER, ENGINEER's Consultants and any
other persons or entities identified in the Special Conditions each of
whom is deemed to have an insurable interest and shall be listed as an
insured or additional insured.
5.6.3 All the policies of insurance (and the certificates or other
evidence thereoO required to be purchased and maintained by
OWNER in accordance with paragraphs 5.5 and 5.6 will contain a
provision or endorsement that the coverage afforded will not be
cancelled or materially changed or renewal refused until at least thirty
(30) days' prior written notice has been given to OWNER and
CONTRACTOR and to each other additional insured to whom a
certificate of insurance has been issued and will contain waiver
provisions in accordance with paragraph 5.7.
of any deductible amounts that are identified in the Special
Conditions. The risk of loss within such identified deductible amount,
will be home by CONTRACTOR. Subcontractor or others suffering
any such loss and if any of them wishes properly insurance coverage
within the limits of such amounts, each may purchase and maintain it
at the purchaser's own expense.
5.6.5 If OWNER requests in writing that other special insurance be
included in the property insurance policies provided under paragraphs
5.5 or 5.6, CONTRACTOR shall, if possible, include such insurance,
and the cost thereof will be charged to OWNER by appropriate
Change Order or Written Amendment. Prior to commencement of the
Work at the site, OWNER shall in writing advise CONTRACTOR
whether or not such other insurance is required by OWNER.
5.6.6 The OWNER and ENGINEER (and others if required by
special provisions in the Contract Documents), shall be named as
additional insureds on the insurance. All parties insured shall receive
a certified copy of the insurance policy prior to commencement of
work. The original policy and a copy thereof shall be filed with the
OWNER or his designated representative.
5.7. Waiver of Riehts.
5.7.1. OWNER and CONTRACTOR intend that all policies
purchased in accordance with paragraphs 5.6 will protect OWNER,
CONTRACTOR, Subcontractors and ENGINEER and all other
persons or entities identified in the General Conditions to be listed as
insureds or additional insureds in such policies and will provide
primary coverage for all losses and damages caused by the perils
covered thereby. All such policies shall contain provisions to the
effect that in the event of payment of any loss or damage, the insurers
will have no rights of recovery against any of the insureds or
additional insureds thereunder. OWNER and CONTRACTOR waive
all rights against each other and their respective officers, directors,
employees, and agents for all losses and damages caused by, arising
outof, or resulting from any of the. perils .covered by such policies
and any other property insurance applicable to the Work; and, in
addition, waive all such rights against Subcontractors and
ENGINEER and all other persons or entities identified in the General
Conditions to be listed as insureds or additional insureds under such
policies for losses and damages so caused. None of the above waivers
shall extend to the rights that any party making such a waiver may
have to the proceeds of insurance held by CONTRACTOR as trustee
or otherwise payable under any policy so issued. The property
insurance policies shall be modified to reflect and approve this
waiver of subrogation rights. However, this waiver shall not apply to
losses arising out of errors or omissions of the ENGINEER,
ENGINEER's Consultants or Sub -Consultants, that are not covered
by the Builder's Risk policy.
5.8 Receipt and Application of Insurance Proceeds.
5.8.1 Any insured loss under the policies of insurance required by
paragraph 5.5 will be adjusted with OWNER and made payable to
OWNER as fiduciary for the insureds, as their interests may appear,
subject to the requirements of any applicable mortgage clause and of
paragraph 5.8.2. OWNER shall deposit in a separate account any
money so received, and shall distribute it in accordance with such
agreement as the parties in interest may reach. If no other special
agreement is reached the damaged Work shall be repaired or
replaced, the moneys so received applied on account thereof and the
Work and the cost thereof covered by an appropriate Change Order
or Written Amendment.
5.8.2 OWNER as fiduciary shall have power to adjust and settle any
5.6.4 OWNER shall not be responsible for purchasing and loss with the insurers unless one of the parties in interest shall object
maintaining any property insurance to protect the interests of in writing within fifteen (15) days after the occurrence of loss to
CONTR 4 CTOR. Suboomractors or others On the Work to the extent n%Fldpv-� np H,M� fP M-;— h, 1'. -lace
GC-12 (Quote Form)
OWNER m fiduciary shall make settlement with the insurers in
accordance with such agreement as the parties in interest may reach.
If no such agreement among the parties in interest is reached,
OWNER as fiduciary shall adjust and settle the loss with the insurers
and, if required in writing by any party in interest, OWNER as
fiduciary shall give bond for the proper performance of such duties.
5.9 Acceptance of Bonds and Insurance: Option to Replace:
5.9.1 If OWNER or CONTRACTOR has any objection to the
coverage afforded by or other provisions of the Bonds or insurance
required to he purchased and maintained by the other party in
accordance with Article 5 on the basis of non-conformance with the
Contract Documents, the objecting party shall so notify the other
party in writing within ten (10) days after receipt of the certificates
(or other evidence requested) required by paragraph 2.5. OWNER
and CONTRACTOR shall each provide to the other such additional
information in respect of insurance provided as the other may
reasonably request. If either party does not purchase or maintain all
of the Bonds and insurance required of such party by the Contract
Documents, such party shall notify the other party in writing of such
failure to purchase prior to the start of the Work, or of such failure to
maintain prior to any change in the required coverage. Without
prejudice to any other right or remedy, the other party may elect to
obtain equivalent Bonds or insurance to protect such other party's
interests at the expense of the party who was required to provide such
coverage, and a Change Order shall be issued to adjust the Contract
Price accordingly.
5.10 Partial Utilization -Property Insurance
5.10.1 If the OWNER finds it necessary to occupy or use a portion or
portions of the Work prior to Substantial Completion thereof, such
occupancy shall not commence prior to a time mutually agreed to by
the OWNER and CONTRACTOR and to which the insurance
company or companies providing the property insurance have
consented by endorsement to the policy or policies. This insurance.
shall not be cancelled, reduced, limited, excluded, or lapsed on
account of such partial occupancy. Consent of the CONTRACTOR
and of the insurance company or companies to such occupancy or use
shall not be unreasonably withheld. Coverage shall be maintained by
CONTRACTOR until the OWNER agrees to provide this coverage
or the completion of this and all terms of this agreement, whichever
is later.
5.11 Indemnification
5.11.1 To the fullest extent permitted by Laws and Regulations,
CONTRACTOR shall indemnify and hold harmless OWNER and
ENGINEER and the officers, directors, employees, agents and other
consultants of each and any of them from and against all claims,
costs, losses and damages (including but not limited to all fees and
charges of engineers, architects, attorneys and other professionals and
all court or arbitration or other dispute resolution costs) caused by,
arising out of or resulting from the performance of the Work,
provided that any such claim, cost, loss or damage: (i) is attributable
to bodily injury, sickness, disease or death, or to injury to or
destruction of tangible property (other than the Work itself),
including the loss of use resulting therefrom, and (ii) is caused in
whole or in part by any negligent act or omission of CONTRACTOR,
any Subcontractor; any Supplier, any person or organization directly
or indirectly employed by any of them to perform or furnish any of
the Work or anyone for whose acts any of them may be liable,
regardless of whether or not caused in part by any negligence or
omission of a person or entity indemnified hereunder or whether
liability is imposed upon such indemnified party by Laws and
Regulations regardless of the negligence of any such person or entity.
5.11.2 In any and all claims against OWNER or ENGINEER or any
of their respective consultants, agents, officers, directors or
employees by any employee (or the survivor or personal
representative of such employee) of CONTRACTOR, any
Subcontractor, any Supplier, any person or organization directly or
indirectly employed by any of them to perform or famish any of the
Work, or anyone for whose acts any of them may be liable, the
indemnification obligation under paragraph 5.11 shall not be limited
in any way by any limitation on the amount or type of damages,
compensation or benefits payable by or for CONTRACTOR or any
such Subcontractor, Supplier or other person or organization under
workers' compensation acts, disability benefit acts or other employee
benefit acts.
5.11.3 The indemnification obligations of CONTRACTOR under
paragraph 5.11 shall not extend to the liability of ENGINEER and
ENGINEER's Consultants, officers, directors, employees or agents
caused by the professional negligence, errors or omissions of any of
them.
5.11.4 All representations, indemnifications, warranties and
guarantees made in, required by or given in accordance with the
Contract Documents, as well as all continuing obligations indicated
in the Contract Documents, will survive final payment, completion
and acceptance of the Work and termination or completion of the
Agreement.
ARTICLE 6
CONTRACTOR'S RESPONSIBILITIES
6.1 Supervision and Sungrintendence
6.1.1 CONTRACTOR shall supervise, inspect and direct the Work
competently and efficiently, devoting such attention thereto and
applying such skills and expertise as may be necessary to perform the
Work in accordance with the Contract Documents. CONTRACTOR
shall be solely responsible for the means, methods, techniques,
sequences and procedures of construction, but CONTRACTOR shall
not be responsible for the negligence of others in the design or
specification of a specific means, method, technique, sequence or
procedure of construction which is shown or indicated in and
expressly required by the Contract Documents. CONTRACTOR shall
be responsible to see that the completed Work complies with the
Contract Documents.
6.1.2 CONTRACTOR shall keep on the Work at all times during its
progress a competent resident superintendent, who shall not be
replaced without written notice to OWNER and ENGINEER except
under extraordinary circumstances. The superintendent will be
CONTRACTOR's representative at the site and shall have authority
to act on behalf of CONTRACTOR. All communications to the
superintendent shall be as binding as if given to CONTRACTOR.
6.2 Labor, Materials and Equipment
6.2.1 CONTRACTOR shall provide competent. suitably qualified
personnel to survey, layout and construct the Work as required by the
Contract Documents. CONTRACTOR shall at all limes maintain
good discipline and order at the site.
6.2.2 Except as otherwise required for the safety or protection of
persons or the Work or property at the site or adjacent thereto, and
except as otherwise indicated in the Contract Documents, all Work at
the site shall be performed during regular working hours and
CONTRACTOR will not permit overtime work or the performance
of Work on Saturday, Sunday or any legal holiday without OWNER's
written consent given after prior written notice to ENGINEER.
6.3
GC-13 (Quote Form)
6.3.1 Unless otherwise specified in the Contract Documents,
CONTRACTOR shall famish and assume full responsibility for all
materials, equipment, labor, transportation, construction equipment
and machinery, tools, appliances, fuel, power, light, heat, telephone,
water, sanitary facilities, temporary facilities and all other facilities
and incidentals necessary for the famishing, performance, testing,
start-up and completion of the Work.
6.3.2 All materials and equipment shall be of good quality and new,
except as otherwise provided in the Contract Documents. All
warranties and guarantees specifically called for by the Specifications
shall expressly run to the benefit of OWNER. If required by
ENGINEER, CONTRACTOR shall famish satisfactory evidence
(including reports of required tests) as to the kind and quality of
materials and equipment. All materials and equipment shall be
applied, installed, connected, erected, used, cleaned and conditioned
in accordance with instructions of the applicable Supplier, except as
otherwise provided in the Contract Documents.
6.4 Progress Schedule
6.4.1 CONTRACTOR shall adhere to the progress schedule
established in accordance with paragraph 2.9 as it may be adjusted
from time to time as provided below:
6.4.1.1 CONTRACTOR shall submit to ENGINEER for acceptance
(to the extent indicated in paragraph 2.7) proposed adjustments in the
progress schedule that will not change the Contract Times (or
Milestones). Such adjustments will conform generally to the progress
schedule then in effect and additionally will comply with any
provisions of the General Requirements applicable thereto.
6.4.1.2 Proposed adjustments in the progress schedule that will
change the Contract Times (or Milestones) shall be submitted in
accordance with the requirements of paragraph 12.2. Such
adjustments may only be made by a Change Order or Written
Amendment in accordance with Article 12.
6.5 Substitutes and "Or-Emal" Items
6.5.1 Whenever an item of material or equipment is specified or
described in the Contract Documents by using the name of a
proprietary item or the name of a particular Supplier, the
Specification or description is intended to establish the type, function
and quality required. Unless the Specification or description contains
or is followed by words reading that no like equivalent or `or -equal"
item or no substitution is permitted, other items of material or
equipment or material or equipment of other Suppliers may be
accepted by ENGINEER under the following circumstances:
6.5.1.1 "Or-Eauar': If in ENGINEER's sole discretion an item of
material or equipment proposed by CONTRACTOR is functionally
equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by ENGINEER
as an `or -equal" item, in which case review and approval of the
proposed item may, in ENGINEER's sole discretion, be
accomplished without compliance with some or all of the
requirements for acceptance of proposed substitute items.
6.5.1.2 Substitute /fetus: If in ENGINEER's sole discretion an item of
material or equipment proposed by CONTRACTOR does not qualify
as an `or -equal" item under subparagraph 6.5.1.1, it will be
considered a proposed substitute item.
6.5.1.2.1 CONTRACTOR shall submit sufficient information. as
provided below to allow ENGINEER to determine that the item of
material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor.
6.5.1.2.2 The procedure for review by the ENGINEER will include
the following as supplemented in the General Requirements and as
ENGINEER may decide is appropriate under the circumstances.
6.5.1.2.3 Requests for review of proposed substitute items of material
or equipment will not be accepted by ENGINEER from anyone other
than CONTRACTOR.
6.5.1.2.4 If CONTRACTOR wishes to furnish or use a substitute item
of material or equipment, CONTRACTOR shall first make written
application to ENGINEER for acceptance thereof, certifying that the
proposed substitute will: (i) perform adequately the functions and
achieve the results called for by the general design, (ii) be similar in
substance to that specified and (iii) be suited to the same use as that
specified.
6.5.1.2.5 The application will state: (i) the extent, if any, to which the
evaluation and acceptance of the proposed substitute will prejudice
CONTRACTOR's achievement of Substantial Completion on time,
(ii) whether or not acceptance of the substitute for use in the Work
will require a change in any of the Contract Documents (or in the
provisions of any other direct contract with OWNER for work on the
Project) to adapt the design to the proposed substitute and (III)
whether or not incorporation or use of the substitute in connection
with the Work is subject to payment of any license fee or royalty.
6.5.1.2.6 All variations of the proposed substitute from that specified
will: be identified in the application and available maintenance, repair
and replacement service will be indicated.
6.5.1.2.7 The application will also contain an itemized estimate of all
costs or credits that will result directly or indirectly from acceptance
of such substitute, including costs of redesign and claims of other
CONTRACTORS affected by the resulting change, all of which will
be considered by ENGINEER in evaluating the proposed substitute.
ENGINEER may require CONTRACTOR to famish additional data
about the proposed substitute.
6.5.1.2.8 CONTRACTOR's Expense: All data to he provided by
CONTRACTOR in' support of any proposed `or -equal" or substitute
item will be at CONTRACTOR's expense.
6.5.2. Substitute Construction Methods or Procedures: If a specific
means, method, technique, sequence or procedure of construction is
shown or indicated in and expressly required by the Contract
Documents, CONTRACTOR may furnish or utilize a substitute
means, method, technique, sequence or procedure of construction
acceptable to ENGINEER. CONTRACTOR shall submit sufficient
information to allow ENGINEER, in ENGINEER's sole discretion, to
determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. The procedure for review by
ENGINEER will be similar to that provided in subparagraph 6.5.1.2.
6.5.3. ENGINEER's Evaluation: ENGINEER will be allowed a
reasonable time within which to evaluate each proposal or submittal
made pursuant to paragraphs 6.5.1.2 and 6.5.2. ENGINEER will be
the sole judge of acceptability. No "or -equal" or substitute will be
ordered, installed or utilized without ENGINEER's prior written
acceptance which will be evidenced by either a Change Order or an
approved Shop Drawing.
6.5.4 OWNER may require CONTRACTOR to famish at
CONTRACTOR's expense a special performance guarantee or other
surety with respect to any "or -equal" or substitute.
6.5.5 ENGINEER will record time required by ENGINEER and
ENGINEER's Consultants in evaluating substitutes proposed or
submitted by CONTRACTOR pursuant to paragraphs 6.5.1.2 and
6.5.2 and in making changes in the Contract Documents (or in the
GC-14 (Quote Form)
provisions of any other direct contract with OWNER for work. on the
Project) occasioned thereby.
6.5.6 Whether or not ENGINEER accepts a substitute item so
proposed or submitted by CONTRACTOR, CONTRACTOR shall
reimburse OWNER for the charges of ENGINEER and ENGINEER's
Consultants for evaluating each such proposed substitute item.
6.6 Concerning Subcontractors. Suppliers and Others
6.6.LCONTRACTOR shall not employ any Subcontractor, Supplier
or other person or organization (including those acceptable to
OWNER and ENGINEER as indicated in paragraph 6.6.2), whether
initially or as a substitute, against whom OWNER or ENGINEER
may have reasonable objection. CONTRACTOR shall not be
required to employ any Subcontractor, Supplier or other person or
organization to furnish or perform any of the Work against whom
CONTRACTOR has reasonable objection.
6.6.2 If the General or Special Conditions require the identity of
certain Subcontractors, Suppliers or other persons or organizations
(including those who are to furnish the principal items of materials or
equipment) to be submitted to OWNER in advance of the specified
date prior to the Effective Date of the Agreement for acceptance by
OWNER and ENGINEER, and if CONTRACTOR has submitted a
list thereof in accordance with the General or Special Conditions,
OWNER's or ENGINEER's acceptance (either in writing or by failing
to make written objection thereto by the date indicated for acceptance
or objection in the bidding documents or the Contract Documents) of
any such Subcontractor, Supplier or other person or organization so
identified may be revoked on the basis of reasonable objection after
due investigation, in which case CONTRACTOR shall submit an
acceptable substitute, the Contract Price will be adjusted by the
difference in the cost occasioned by such substitution and an
appropriate Change Order will be issued or Written Amendment
signed. No acceptance by OWNER or ENGINEER of any such
Subcontractor,. Supplier or other person.. or_organizationshall
constitute a waiver of any right of OWNER or ENGINEER to reject
defective Work.
6.6.3 CONTRACTOR shall be fully responsible to OWNER and
ENGINEER for all acts and omissions of the Subcontractors,
Suppliers and other persons and organizations performing or
furnishing any of the Work under a direct or indirect contract with
CONTRACTOR just as CONTRACTOR is responsible for
CONTRACTOR's own acts and omissions. Nothing in the Contract
Documents shall create for the benefit of any such Subcontractor,
Supplier or other person or organization any contractual relationship
between OWNER or ENGINEER and any such Subcontractor,
Supplier or other person or organization, nor shall it create any
obligation on the part of OWNER or ENGINEER to payor to see to
the payment of any moneys due any such Subcontractor, Supplier or
other person or organization except as may otherwise be required by
Laws and Regulations.
6.6.4 CONTRACTOR shall be solely responsible for scheduling and
coordinating the Work of Subcontractors, Suppliers and other persons
and organizations performing or furnishing any of the Work under a
direct or indirect contract with CONTRACTOR.
6.6.5 CONTRACTOR shall require all Subcontractors, Suppliers and
such other persons and organizations performing or furnishing any of
the Work to communicate with the ENGINEER through
CONTRACTOR.
account of the particular Sub -contractor's, Supplier's, other person's,
or other organization's work.
6.6 The divisions and sections of the Specifications and the
identifications of any Drawings shall not control CONTRACTOR in
dividing the Work among Subcontractors or Suppliers or delineating
the Work to be performed by any specific trade.
6.6.7 All Work performed for CONTRACTOR by a Subcontractor or
Supplier will be pursuant to an appropriate agreement between
CONTRACTOR and the Subcontractor or Supplier which
specifically binds the Subcontractor or Supplier to the applicable
terms and conditions of the Contract Documents for the benefit of
OWNER and ENGINEER. Whenever any such agreement is with a
Subcontractor or Supplier who is listed as an additional insured on
the property insurance provided in paragraph 5.5 or 5.6, the
agreement between the CONTRACTOR and the Subcontractor
or/Supplier will contain provisions whereby the Subcontractor or
Supplier waives all rights against OWNER, CONTRACTOR and
ENGINEER and all other additional insureds for all losses and
damages caused by, arising out of or resulting from any of the perils
covered by such policies and any other property insurance applicable
to the Work. If the insurers on any such policies require separate
waiver forms to be signed by any Subcontractor or Supplier,
CONTRACTOR will obtain the same.
6.7 Patent Fees and Royalties
6.7.1 CONTRACTOR shall pay all license fees and royalties and
assume all costs incident to the use in the performance of the Work or
the incorporation in the Work of any invention, design, process,
product or device which is the subject of patent rights or copyrights
held by others. If a particular invention, design, process, product or
device is specified in the Contract Documents for use in the
performance of the Work and if to the actual knowledge of OWNER
or ENGINEER its use is subject to patent rights or copyrights calling
for the paymentof any license fee or royalty to others, theexistence
of such rights shall be disclosed in the Contract Documents.
6.7.2 To the fullest extent permitted by Laws and Regulations,
CONTRACTOR shall indemnify and hold harmless OWNER and
ENGINEER and the officers, directors, employees, agents and other
consultants of each and any of them from and against all claims,
costs, losses and damages arising out of or resulting from any
infringement of patent rights or copyrights incident to the use in the
performance of the Work or resulting from the incorporation in the
Work of any invention, design, process, product or device not
specified in the Contract Documents.
6.8 Permits
6.8.1 Unless otherwise provided in the Special Conditions,
CONTRACTOR shall obtain and pay for all construction permits and
licenses. OWNER shall assist CONTRACTOR, when necessary, in
obtaining such permits and licenses. CONTRACTOR shall pay all
governmental charges and inspection fees necessary for the
prosecution of the Work, which are applicable at the time of opening
of Quotes, or, if there are no Quotes, on the Effective Date of the
Agreement. CONTRACTOR shall pay all charges of utility owners
for connections to the Work, and OWNER shall pay all charges of
such utility owners for capital costs related thereto such as plant
investment fees.
6.9 Laws and Regulations
6.6.5.1 OWNER or ENGINEER may famish to any such 6.9.1. CONTRACTOR shall give all notices and comply with all
Subcontractor, Supplier, or other person or organization, to the extent Laws and Regulations applicable to furnishing and performance of
practicable, information about amounts paid to CONTRACTOR in the Work. Except where otherwise expressly required by applicable
accordance with CONTRACTOR'c pnlicatinnc for Payment on Laws and Regulations, neither OWNER nor ENGINEER shall be
GC-15 (Quote Form)
responsible for monitoring CONTRACTOR's compliance with any
Laws or Regulations.
6.9.2. if CONTRACTOR performs any Work knowing or having
reason to know that it is contrary to Laws or Regulations,
CONTRACTOR shall bear all claims, costs, losses and damages
caused by, arising out of or resulting therefrom; however, it shall not
be CONTRACTOR's primary responsibility to make certain that the
Specifications and Drawings are in accordance with Laws and
Regulations, but this shall not relieve CONTRACTOR of
CONTRACTOR'S obligations under paragraph 3.3.2.
6.10 Taxes
6.10.1 Contractor shall pay all sales, consumer, use, and other similar
taxes required to be paid by CONTRACTOR in accordance with the
Laws and Regulations of the place of the Project which are applicable
during the performance of the Work.
6.11 Use of Site and Other Areas
6.11.1 Limitations on Use of Site and Other Areas
6.11.1.1 CONTRACTOR shall confine construction equipment, the
storage of materials and equipment and the operations of workers to
the site and land and areas identified in and permitted by the Contract
Documents and other land and areas permitted by Laws and
Regulations, rights -of -way, permits and easements, and shall not
unreasonably encumber the premises with construction equipment or
other materials or equipment. CONTRACTOR shall assume full
responsibility for any damage to any such land or area, or to the
owner or occupant thereof or of any adjacent land or areas, resulting
from the performance of the Work.
6.11.1.2 Should any claim be made by any such owner or occupant
because of the performance of the Work, CONTRACTOR shall
promptly settle with such other party by negotiation or otherwise
resolve the claim by y arbitration or other dispute resolution proceeding
or at law.
6.11.1.3 CONTRACTOR shall, to the fullest extent permitted by
Laws and Regulations, indemnify and hold harmless OWNER,
ENGINEER, ENGINEER's Consultant and anyone directly or
indirectly employed by any of them from and against all claims,
costs, losses and damages arising out of or resulting from any claim
or action, legal or equitable, brought by any such owner or occupant
against OWNER, ENGINEER or any other party indemnified
hereunder to the extent caused by or based upon CONTRACTOR's
performance of the Work.
6.11.2 During the progress of the Work, CONTRACTOR shall keep
the premises free from accumulations of waste materials, rubbish and
other debris resulting from the Work. At the completion of the Work,
CONTRACTOR shall remove all waste materials, rubbish and debris
from and about the premises as well as all tools, appliances,
construction equipment and machinery and surplus materials.
CONTRACTOR shall leave the site clean and ready for occupancy
by OWNER at Substantial Completion of the Work. CONTRACTOR
shall restore to original condition all property not designated for
alteration by the Contract Documents.
6.11.3 CONTRACTOR shall not load nor permit any part of any
structure to be loaded in any manner that will endanger the structure,
nor shall CONTRACTOR subject any part of the Work or adjacent
property to stresses or pressures that will endanger it.
6.12 Record Documents
6.12.1 CONTRACTOR shall maintain in a safe place at the site one
record copy of all Drawings, Specifications, Addenda, Written
and written interpretations and clarifications (issued pursuant to
paragraph 9.3.4) in good order and annotated to show all changes
made during construction. These record documents together with all
approved Samples and a counterpart of all approved Shop Drawings
will he available to ENGINEER for reference. Upon completion of
the Work, these record documents, Samples and Shop Drawings will
be delivered to ENGINEER for OWNER.
6.13 Safety and Protection
6.13.1 CONTRACTOR shall be responsible for initiating,
maintaining and supervising all safety precautions and programs in
connection with the Work. CONTRACTOR shall take all necessary
precautions for the safety of, and shall provide the necessary
protection to prevent damage, injury or loss to:
6.13.1.1 all persons on the Work site or who may be affected by the
Work;
6.13.1.2 all the Work and materials and equipment to be incorporated
therein, whether in storage on or off the site; and
6.13.1.3 other property at the site or adjacent thereto, including trees,
shrubs, lawns, walks, pavements roadways, structures, utilities and
Underground Facilities not designated for removal, relocation or
replacement in the course of construction.
6.13.2 CONTRACTOR shall comply with all applicable Laws and
Regulations of any public body having jurisdiction for safety of
persons or property or to protect them from damage, injury or loss;
and shall erect and maintain all necessary safeguards for such safety
and protection. CONTRACTOR shall notify owners of adjacent
property and of Underground Facilities and utility owners when
prosecution of the Work may affect them, and shall cooperate with
them in the protection, removal, relocation and replacement of their
property.
6.13.3 All damage, injury or loss to any property referred to in
paragraph 6.13.1.2 or 6.13.1.3 caused, directly or indirectly, in whole -
or in part, by CONTRACTOR, any Subcontractor, Supplier or any
other person or organization directly or indirectly employed by any of
them to perform or furnish any of the Work or anyone for whose acts
any of them may be liable, shall be remedied by CONTRACTOR
(except damage or loss attributable to the fault of Drawings or
Specifications or to the acts or omissions of OWNER or ENGINEER
or ENGINEER's Consultant or anyone employed by any of them or
anyone for whose acts any of them may be liable, and not
attributable, directly or indirectly, in whole or in part, to the fault or
negligence of CONTRACTOR or any Subcontractor, Supplier or
other person or organization directly or indirectly employed by any of
them).
6.13.1.4 CONTRACTOR's duties and responsibilities for safety and
for protection of the Work shall continue until such time as all the
Work is completed and ENGINEER has issued a notice to OWNER
and CONTRACTOR in accordance with paragraph 14.7.2 that the
Work is acceptable (except as otherwise expressly provided in
connection with Substantial Completion).
6.14 Safety Representative
6.14.1 CONTRACTOR shall designate a qualified and experienced
safety representative at the site whose duties and responsibilities shall
be the prevention of accidents and the maintaining and supervising of
safety precautions and programs.
GC-6. l5 Hazard Communication Programs
6.15.1 CONTRACTOR shall be responsible for coordinating any
exchange of material safety data sheets or other hazard
GC-16 (Quote Form)
exchanged between or among employers at the site in accordance
with Laws or Regulations.
6.16 Emergencies
6.16.1 In emergencies affecting the safety or protection of persons or
the Work or property at the site or adjacent thereto, CONTRACTOR,
without special instruction or authorization from OWNER or
ENGINEER, is obligated to act to prevent threatened damage, injury
or loss. CONTRACTOR shall give ENGINEER prompt written
notice if CONTRACTOR believes that any significant changes in the
Work or variations from the Contract Documents have been caused
thereby. If ENGINEER determines that a change in the Contract
Documents is required because of the action taken by
CONTRACTOR in response to such an emergency, a Work Change
Directive or Change Order will be issued to document the
consequences of such action.
6.17 Shot) Drawings and Samples
6.17.1. CONTRACTOR shall submit Shop Drawings to ENGINEER
for review and approval in accordance with the accepted schedule of
Shop Drawings and Sample submittals (see paragraph 2.7).
6.17.1.1 Shop Drawings
6.17.1.1.1 All submittals will be identified as ENGINEER may
require and in the number of copies specified in the General
Requirements.
6.17.1.1.2 The data shown on the Shop Drawings will be complete
with respect to quantities, dimensions, specified performance and
design criteria, materials and similar data to show ENGINEER the
materials and equipment CONTRACTOR proposes to provide and to
enable ENGINEER to review the information for the limited
purposes required by paragraph 6.17.4.
6.17.1.2 Samples: CONTRACTOR shall also submit Samples to
ENGINEER for .review and approval in accordance with said
accepted schedule of Shop Drawings and Sample submittals.
6.17.1.2.1 Each Sample will be identified clearly as to material,
Supplier, pertinent data such as catalog numbers and the use for
which intended and otherwise as ENGINEER may require to enable
ENGINEER to review the submittal for the limited purposes required
by paragraph 6.17.4. The numbers of each Sample to be submitted
will be as specified in the Specifications.
6.17.2 Where a Shop Drawing or Sample is required by the Contract
Documents or the schedule of Shop Drawings and Sample
submissions accepted by ENGINEER as required by paragraph 2.7,
any related Work performed prior to ENGINEER's review and
approval of the pertinent submittal will be at the sole expense and
responsibility of CONTRACTOR.
6.17.3 Submittal Procedures
6.17.3.1 Before submitting each Shop Drawing or Sample,
CONTRACTOR shall have determined and verified:
6.17.3.1.1 all field measurements, quantities, dimensions, specified
performance criteria, installation requirements, materials, catalog
numbers and similar information with respect thereto,
6.17.3.1.2 all materials with respect to intended use, fabrication,
shipping, handling, storage, assembly and installation pertaining to
the performance of the Work, and
6.17.3.1.3 all information relative to CONTRACTOR'S sole
responsibilities in respect of means, methods, techniques, sequences
and procedures of construction and safety precautions and programs
incident thereto.
6.17.3.1.4 shall also have reviewed and coordinated each Shop
Drawing or Sample with other Shop Drawings and Samples and with
the requirements of the Work and the Contract Documents.
6.17.3.2 Each submittal will bear a stamp or specific written
indication that CONTRACTOR has satisfied CONTRACTOR's
obligations under the Contact Documents with respect to
CONTRACTOR'S review and approval of that submittal.
6.17.3.3 Al the time of each submission, CONTRACTOR shall give
ENGINEER specific written notice of such variations, if any, that the
Shop Drawing or Sample submitted may have from the requirements
of the Contract Documents, such notice to be in a written
communication separate from the submittal; and, in addition, shall
cause a specific notation to be made on each Shop Drawing and
Sample submitted to ENGINEER for review and approval of each
such variation.
6.17.4 ENGINEER's Review
6.17.4.1 ENGINEER will review and approve Shop Drawings and
Samples in accordance with the schedule of Shop Drawings and
Sample submittals accepted by ENGINEER as required by paragraph
2.7. ENGINEER's review and approval will be only to determine if
the items covered by the submittals will, after installation or
incorporation in the Work, conform to the information given in the
Contract Documents and be compatible with the design concept of
the completed Project as a functioning whole as indicated by the
Contract Documents.
6.17.4.2 ENGINEER's review and approval will not extend to means,
methods, techniques, sequences or procedures of construction (except
where a particular means, method, technique, sequence or procedure
of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto.
The review and approval of a separate item as such will not indicate
approval of the assembly in which the item functions.
6.17.4.3 ENGINEER's review and approval of Shop Drawings or
Samples shall not relieve CONTRACTOR from responsibility for
any variation from the requirements of the Contract Documents
unless CONTRACTOR has in writing called ENGINEER's attention
to each such variation at the time of submission as required by
paragraph 6.17.3.3 and ENGINEER has given written approval of
each such variation by specific written notation thereof incorporated
in or accompanying the Shop Drawing or Sample approval; nor will
any approval by ENGINEER relieve CONTRACTOR from
responsibility for complying with the requirements of paragraph
6.17.3.1.
6.17.5 Resubmittal Procedures
6.17.5.1 CONTRACTOR shall make corrections required by
ENGINEER, and shall return the required number of corrected copies
of Shop Drawings and submit as required new Samples for review
and approval. CONTRACTOR shall direct specific attention in
writing to revisions other than the corrections called for by
ENGINEER on previous submittals.
6.18 Continuing the Work
6.18.1 CONTRACTOR shall carry on the Work and adhere to the
progress schedule during all disputes or disagreements with
OWNER. No Work shall be delayed or postponed pending resolution
of any disputes or disagreements, except as permitted by paragraph
15.4 or as OWNER and CONTRACTOR may otherwise agree in
writing.
6.19 CONTRACTOR's General Warranty and Guarantee
GC-17 (Quote Form)
6.19.1 CONTRACTOR warrants and guarantees to OWNER that all
Work will be in accordance with- the Contract Documents and will
not be defective. ENGINEER and its Related Entities shall be
entitled to rely on representation of CONTRACTOR's warranty and
guarantee.
6.19.2 CONTRACTOR's warranty and guarantee hereunder excludes
defects or damage caused by:
6.19.2.1 abuse, modification or improper maintenance or operation
by persons other than CONTRACTOR, Subcontractors or Suppliers;
or
6.19.2.2 normal wear and tear under normal usage.
6.19.3 CONTRACTOR's obligation to perform and complete the
Work in accordance with the Contract Documents shall be absolute.
None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of
CONTRACTOR' obligation to perform the Work in accordance with
the Contract Documents:
6.19.3.1 observations by ENGINEER;
6.19.3.2 recommendation of any progress or final payment by
ENGINEER;
6.19.3.3 the issuance of a certificate of Substantial Completion or any
payment by OWNER to CONTRACTOR under the Contract
Documents;
6.19.3.4 use or occupancy of the Work or any part thereof by
OWNER;
6.19.3.5 any review and approval of a Shop Drawing or Sample
submittal or the issuance of a notice of acceptability by ENGINEER
pursuant to paragraph 14.7.2;
6.19.3.6. any inspection, test or approval by others; or
6.19.3.7 any correction of defective Work by OWNER.
other work. CONTRACTOR shall not endanger any work of others
by cutting, excavating or otherwise altering their work and will only
cut or alter their work with the written consent of ENGINEER and
the others whose work will be affected. The duties and
responsibilities of CONTRACTOR under this paragraph are for the
benefit of such utility owners and other contractors to the extent that
there are comparable provisions for the benefit of CONTRACTOR in
said direct contracts between OWNER and such utility owners and
other contractors.
7.1.3 If the proper execution or results of any part of
CONTRACTOR's Work depends upon work performed by others
under this Article 7, CONTRACTOR shall inspect such other work
and promptly report to ENGINEER in writing any delays, defects or
deficiencies in such other work that render it unavailable or
unsuitable for the proper execution and results of CONTRACTOR's
Work. CONTRACTOR's failure so to report will constitute an
acceptance of such other work as fit and proper for integration with
CONTRACTOR'S Work except for latent or nonapparent defects and
deficiencies in such other work.
7.2 Coordination
7.2.1 If OWNER contracts with others for the performance of other
work on the Project at the site, the following will be set forth in
Special Conditions:
7.2.1.1 the person, firm or corporation who will have authority and
responsibility for coordination of the activities among the various
prime CONTRACTORS will be identified;
7.2.1.2 the specific matters to be covered by such authority and
responsibility will he itemized; and
7.2.1.3 the extent of such authority and responsibilities will he
provided.
7.2.2 Unless otherwise provided in the Special Conditions, OWNER
shall have sole authority and responsibility In respect of such
coordination.
ARTICLE 7
7.3.2 Should CONTRACTOR cause damage to the Work or property
OTHER WORK
of any separate contractor at the site, or should any claim arising out
7.1 Related Work at Site
of CONTRACTOR's performance of the Work at the site be made by
any separate contractor against CONTRACTOR, OWNER and
7.1.1 OWNER may perform other work related to the Project at the
ENGINEER, or any other person, CONTRACTOR shall promptly
site by OWNER's own forces, or let other direct contracts therefor
attempt to settle with such other contractor by agreement, or to
which shall contain General Conditions similar to these, or have other
otherwise resolve the dispute. CONTRACTOR shall, to the fullest
work performed by utility owners. If the fact that such other work is
extent permitted by Laws and Regulations, indemnify and hold
to be performed was not noted in the Contract Documents, then:
OWNER and ENGINEER harmless from and against all claims,
damages, losses and expenses (including, but not limited to, fees of
7.1.1.1 written notice thereof will be given to CONTRACTOR prior
engineers, architects, attorneys and other professionals and court
to starting any such other work, and
costs) arising directly, indirectly or consequentially out of any action,
7.1.1.2 CONTRACTOR may make a claim therefor as provided in
legal or equitable, brought by any separate CONTRACTOR against
Article 12 if CONTRACTOR believes that such performance will
OWNER or ENGINEER to the extent based on a claim arising out of
involve additional expense to CONTRACTOR or requires additional
CONTRACTOR's performance of the Work. Should a separate
time and the parties are unable to agree as to the amount or extent
contractor cause damage to the Work or property of CONTRACTOR
thereof.
or should the performance of Work by any separate contractor at the
site give rise to any other claim, CONTRACTOR shall not institute
7.1.2 CONTRACTOR shall afford each other contractor who is a
any action, legal or equitable, against OWNER or ENGINEER or
party to such a direct contract and each utility owner (and OWNER,
permit any action against any of them to be maintained and continued
if OWNER is performing the additional work with OWNER's
in its name or for its benefit in any court or before any arbiter which
employees) proper and safe access to the site and a reasonable
seeks to impose liability on or to recover damages from OWNER or
opportunity for the introduction and storage of materials and
ENGINEER on account of any such damage or claim. If
equipment and the execution of such other work and shall properly
CONTRACTOR is delayed at any time in performing or furnishing
connect and coordinate the Work with theirs. Unless otherwise
Work by any act or neglect of a separate contractor, and OWNER
provided in the Contract Documents, CONTRACTOR shall do all
and CONTRACTOR are unable to agree as to the extent of any
cutting, fitting and patching of the Work that may be required to
adjustment in Contract Time attributable thereto, CONTRACTOR
make its several parts come together properly and integrate with such
may make a claim for an extension of time in accordance with Article
GC-18 (Quote Form)
12. An extension of the Contract Time shall be CONTRACTOR's
exclusive remedy with respect to OWNER or ENGINEER for any
delay, disruption, interference, or hindrance caused by any separate
CONTRACTOR.
ARTICLE 8
OWNER'S RESPONSIBILITIES
8.1 Communication to Contractor
8.1.1 Except as otherwise provided in these General Conditions,
OWNER shall issue all communications to CONTRACTOR through
ENGINEER.
8.2 Replacement of ENGINEER
8.2.1 In case of termination of the employment of ENGINEER,
OWNER shall appoint an ENGINEER against whom
CONTRACTOR makes no reasonable objection, whose status under
the Contract Documents shall be that of the former ENGINEER.
8.3 Furnish Data
8.3.1 OWNER shall furnish the data required of OWNER under the
Contract Documents promptly and shall make payments to
CONTRACTOR promptly when they are due as provided in
paragraphs 14.2 and 14.3.
8.4 Lands and Easements: Reports and Tests
8.4.1 OWNER's duties in respect of providing lands and easements
and providing Engineering surveys to establish reference points are
set forth in paragraphs 4.1 and 4.6. Paragraph 4.2 refers to OWNER's
identifying and making available to CONTRACTOR copies of
reports of explorations and tests of subsurface conditions at the site
and drawings of physical conditions in existing structures at or
contiguous to the site that have been utilized by ENGINEER in
preparing the Contract Documents.
8.5 Insurance
8.5.1 Owner's responsibilities, if any, in respect to purchasing and
maintaining liability and property insurance are set forth in Article 5.
8.6 Change Orders
8.6.1 OWNER is obligated to execute Change Orders as indicated in
paragraph 10.3.
8.7 Inspections, Tests and Approvals
8.7.1 OWNER's responsibility in respect of certain inspections, tests
and approvals is set forth in paragraph 13.3
8.8. Limitations on Owner's Resnonsibilities
8.8.1 The OWNER shall not supervise, direct or have control or
authority over, nor be responsible for, CONTRACTOR's means,
methods, techniques, sequences or procedures of constmction or the
safety precautions and: programs incident thereto, or for any failure
of CONTRACTOR to comply with Laws and Regulations applicable
to the famishing or performance of the Work. OWNER will not be
responsible for CONTRACTOR's failure to perform or furnish the
Work in accordance with the Contract Documents.
8.10 Undisclosed Hazardous Environmental Condition
8.10.1 OWNER'S responsibility in respect of undisclosed Asbestos,
PCBs, Petroleum, Hazardous Waste or Radioactive Materials
uncovered or revealed at the site is set forth in paragraph 4.6.
ARTICLE 9
9.1 OWNER's Representative
9.1.1 ENGINEER will be OWNER's representative during the
construction period. The duties and responsibilities and the
limitations of authority of ENGINEER as OWNER's representative
during construction are set forth in the Contract Documents and shall
not be extended without written consent of OWNER and
ENGINEER.
9.2 Visits to Site:
9.2.1 ENGINEER will make visits to the site at intervals appropriate
to the various stages of construction as ENGINEER deems necessary
in order to observe as an experienced and qualified design
professional the progress that has been made and the quality of the
various aspects of CONTRACTOR's executed Work. Based on
information obtained during such visits and observations,
ENGINEER will endeavor for the benefit of OWNER to determine,
in general, if the Work is proceeding in accordance with the Contract
Documents. ENGINEER will not be required to make exhaustive or
continuous on -site inspections to check the quality or quantity of the
Work. ENGINEER's efforts will be directed toward providing
OWNER a greater degree of confidence that the completed Work will
conform generally to the Contract Documents. On the basis of such
visits and on -site observations, ENGINEER will keep OWNER
informed of the progress of the Work and will endeavor to guard
OWNER against defective Work.
9.2.2 ENGINEER's visits and on -site observations are subject to all
the limitations on ENGINEER's authority and responsibility set forth
in paragraph 9.9, and particularly, but without limitation, during or as
a result of ENGINEER's on -site visits or observations of
CONTRACTOR's Work ENGINEER will not supervise, direct,
control or have authority over or be responsible for
CONTRACTOR's means, methods, techniques, sequences or
procedures of construction, or the safety precautions and programs
incident thereto, or for any failure of CONTRACTOR to comply with
Laws and Regulations applicable to the furnishing or performance of
the Work.
9.3 Project Representative
9.3.1 If OWNER and ENGINEER agree, ENGINEER will famish a
Resident Project Representative to assist ENGINEER in providing
more continuous observation of the Work. The responsibilities and
authority and limitations thereon of any such Resident Project
Representative and assistants will be as provided in paragraph 9.9
and in the Special Conditions. If OWNER designates another
representative or agent to represent OWNER at the site who is not
ENGINEER's Consultant, agent or employee, the responsibilities and
authority and limitations thereon of such other person will be as
provided in the Special Conditions.
9.3.2 Duties and Responsibilities
The Resident Project Representative (hereafter referred to as RPR)
will:
9.3.2.1 Schedules: Review the progress schedule, schedule of Shop
Drawing submittals and schedule of values prepared by
CONTRACTOR and consult with ENGINEER concerning
acceptability of the same;
9.3.2.2 Conferences and Meetings: Attend meetings with
CONTRACTOR, such as preconsmaclion conferences, progress
meetings, job conferences and other project -related meetings, and
prepare and circulate copies of minutes thereof;
9.3.2.3 Liaison:
GC-19 (Quote Form)
9.3.2.3.1 Some as ENGINEER's liaison with CONTRACTOR,
working principally through CONTRACTOR's superintendent and
assist in understanding the intent of the Contract Documents; and
assist ENGINEER in serving as OWNER's liaison with
CONTRACTOR when CONTRACTOR' operations affect
OWNER's on -site operations.
9.3.2.3.2 Assist in obtaining from OWNER additional details or
information, when required for proper execution of the Work.
9.3.2.4 Shoo Drawings and Samples:
a. Record date of receipt of Shop Drawings and Samples.
b. Receive Samples which are famished at the site by
CONTRACTOR, and notify ENGINEER of availability of Samples
for examination.
c. Advise ENGINEER and CONTRACTOR of the
commencement of any Work requiring a Shop Drawing or Sample if
the submittal has not been approved by ENGINEER.
5. Review of Work, Rejection of defective Work,
Inspections and Tests:
a. Conduct onsite observations of the Work in progress to
assist ENGINEER in determining if the Work is in general
proceeding in accordance with the Contract Documents.
b. Report to ENGINEER whenever RPR believes that any
Work is unsatisfactory, faulty, or defective or does not conform to the
Contract Documents, or has been damaged, or does not meet the
requirements of any inspection, test, or approval required to be made;
and advise ENGINEER of Work that RPR believes should be
corrected or rejected or should be recovered for observation, or
requires special testing, inspection, or approval.
c. Verify that tests, equipment and systems start-ups and
operating and maintenance training are conducted in the presence of
appropriate personnel and that CONTRACTOR maintains adequate
records thereof; and observe, record, and report to ENGINEER
appropriate details relative to the test procedures and startups.
d. Accompany visiting inspectators representing public or
other agencies having jurisdiction over the Project, record the results
of these inspections, and report to ENGINEER.
6. Interpretation of Contract Documents: Reports to
ENGINEER when clarifications and interpretations of the Contract
Documents are needed and transmit to CONTRACTOR clarifications
and interpretations as issued by ENGINEER.
7. Modifications: Consider and evaluate CONTRACTOR's
suggestions for modifications in Drawings or Specifications and
report with RPR's recommendations to ENGINEER. Transmit to
CONTRACTOR decisions as issued by ENGINEER.
8. Records:
9.3.2.4.1 Maintain at the job site orderly files for correspondence,
reports of job conferences, Shop Drawings and samples,
reproductions of original Contract Documents including all Work
Directive Changes, Addenda, Change Orders, Field Orders,
additional Drawings issued subsequent to the execution of the
Contract, ENGINEER's clarifications and interpretations of the
Contract Documents, progress reports, and other Project related
documents.
9.3.2.4.2 Keep a diary or log book, recording CONTRACTOR hours
on the job site, weather conditions, data relative to questions of Work
Directive Changes, Change Orders or changed conditions, list of job
site visitors. dailv activities_ decicinnc �h�...., fl.. t., ., 1 ..-A
specific observations in more detail as in the case of observing test
procedures; and send copies to ENGINEER.
9.3.2.5 Record names, addresses, and telephone numbers of all
CONTRACTORS, Subcontractors and major suppliers of material
and equipment.
9.3.2.6. Reports:
9.3.2.6.1 Furnish ENGINEER periodic reports as required of progress
of the Work and of CONTRACTOR's compliance with the progress
schedule and schedule of Shop Drawing and Sample submittals.
9.3.2.6.2 Consult with ENGINEER in advance of scheduled major
tests, inspections, or start of important phases of the Work.
9.3.2.6.3 Draft Proposed Change Orders and Work Directive
Changes, obtaining backup material from CONTRACTOR, and
recommend to ENGINEER Change Orders, Work Directive Changes,
and Field Orders.
9.3.2.6.4 Report immediately to ENGINEER and OWNER upon the
occurrence of any accident.
9.3.2.7 Payment Requests: Review Applications for Payment with
CONTRACTOR for compliance with the established procedure for
their submission and forward with recommendations to ENGINEER,
noting particularly the relationship of the payment requested to the
schedule of values, Work completed, and materials and equipment
delivered at the site but not incorporated in the Work.
9.3.2.8 Certificates, Maintenance and Operation Manuals: During the
course of the Work, verify that certificates, maintenance and
operation manuals, and other data required to be assembled and
furnished by CONTRACTOR are applicable to the items actually
installed and in accordance with the Contract Documents, and have
this material delivered to ENGINEER for review and forwarding to
OWNER prior to final payment for the Work.
9.3.2.9 Completion:
9.3.2.9.1 Before ENGINEER issues a Certificate of Substantial
Completion, submit to CONTRACTOR a list of observed items
requiring completion or correction.
9.3.2.9.2 Conduct final inspection in the company of ENGINEER,
OWNER, and CONTRACTOR and prepare a final list of items to be
completed or corrected.
9.3.2.9.3 Observe that all items on final list have been completed or
corrected and make recommendations to ENGINEER concerning
acceptance.
9.3.3. Limitations of Authority - Resident Project Representative
shall not:
9.3.3.1 authorize any deviation from the Contract Documents or
substitution of materials or equipment, unless authorized by
ENGINEER.
9.3.3.2 exceed limitations of ENGINEER's authority as set forth in
the Contract Documents.
9.3.3.3 undertake any of the responsibilities of CONTRACTOR,
Subcontractors, or CONTRACTOR's superintendent.
9.3.3.4 advise on, issue directions relative to or assume control over
any aspect of the means, methods, techniques, sequences, or
procedures of construction unless such advice or directions are
specifically required by the Contract Documents.
9.3.3.5 advise on, issue directions regarding or assume control over
GC-20 (Quote Form)
9.3.3.6 accept Shop Drawing or Sample submittals from anyone other
than CONTRACTOR.
9.3.3.7 authorize OWNER to occupy the Project in whole or in part.
9.3.3.8 participate in specialized field or laboratory tests or
inspections conducted by others except as specifically authorized by
ENGINEER.
9.3.4 Clarifications and Interuretations
9.3.4.1 ENGINEER will issue with reasonable promptness such
written clarifications or interpretations of the requirements of the
Contract Documents (in the form of Drawings or otherwise) as
ENGINEER may determine necessary which shall be consistent with
the intent of and reasonably inferable from Contract Documents.
Such written clarifications and interpretations will be binding on
OWNER and CONTRACTOR.
9.3.4.2 If OWNER or CONTRACTOR believes that a written
clarification or interpretation justifies an adjustment in the Contract
Price or the Contract Times and the parties are unable to agree to the
amount or extent thereof, if any, OWNER or CONTRACTOR may
make a written claim therefor as provided in Article 12.
9.4 Authorized Variations in Work
9.4.1 ENGINEER may authorize minor variations in the Work from
the requirements of the Contract Documents which do not involve an
adjustment in the Contract Price or the Contract Times and are
compatible with the design concept of the completed Project as a
functioning whole as indicated by the Contract Documents. These
may be accomplished by a Field Order and will be binding on
OWNER and also on CONTRACTOR who shall perform the Work
promptly. If OWNER or CONTRACTOR believes that a Field Order
justifies an adjustment in the Contract Price or the Contract Times
and the parties are unable to agree as to the amount or extent thereof,
OWNER or CONTRACTOR may make a written claim therefor as
provided in Article 12.
9.5 Rejecting Defective Work
9.5.1 ENGINEER will have authority to disapprove or reject Work
which ENGINEER believes to be defective, or that ENGINEER
believes will not produce a completed Project that conforms to the
Contract Documents or that will prejudice the integrity of the design
concept of the completed Project as a functioning whole as indicated
by the Contract Documents. ENGINEER will also have authority to
require special inspection or testing of the Work as provided in
paragraph 13.9 whether or not the Work is fabricated, installed or
completed.
9.6 Shoo Drawings, Change Orders and Payments
9.6.1 In connection with ENGINEER's authority as to Shop Drawings
and Samples, see paragraph 6.17.
9.6.2 In connection with ENGINEER's authority as to Change
Orders, see Articles 10 and 12.
9.6.3 In connection with ENGINEER's authority as to Applications
for Payment, See Article 14.
9.7 Determinations for Unit Prices
9.7.1 ENGINEER will determine the actual quantities and
classifications of Unit Price Work performed by CONTRACTOR.
ENGINEER will review with CONTRACTOR the ENGINEER's
preliminary determinations on such matters before rendering a
written decision thereon (by recommendation of an Application for
Payment or otherwise). ENGINEER'S written decision thereon will
within ten (10) days after the date of any such decision, either
OWNER or CONTRACTOR delivers to the other and to ENGINEER
written notice of intention to appeal from ENGINEER's decision and
formal proceeding is instituted by the appealing party in a foram of
competent jurisdiction to exercise such rights or remedies as the
appealing party may have with respect to ENGINEER's decision,
unless otherwise agreed in writing by OWNER and CONTRACTOR.
9.8 Decisions on Disputes
9.8.1 ENGINEER will be the initial interpreter of the requirements of
the Contract Documents and judge of the acceptability of the Work
thereunder. Claims, disputes and other matters relating to the
acceptability of the Work or the interpretation of the requirements of
the Contract Documents pertaining to the performance and furnishing
of the Work and Claims under Article 12 in respect of changes in the
Contract Price or Contract Times will be referred initially to
ENGINEER in writing with a request for a formal decision in
accordance with this paragraph. Written notice of each such claim,
dispute or other matter will be delivered by the claimant to
ENGINEER and the other party to the Agreement promptly (but in
no event later than thirty (30) days) after the start of the occurrence or
event giving rise thereto, and written supporting data will be
submitted to ENGINEER and the other party within sixty (60) days
after the start of such occurrence or event or thirty (30) days after the
initial required notice, unless ENGINEER allows an additional period
of time for the submission of additional or more accurate data in
support of such claim, dispute or other matter. The opposing party
shall submit any response to ENGINEER and the claimant within
thirty (30) days after receipt of the claimant's last submittal (unless
ENGINEER allows additional time), ENGINEER will render a
formal decision in writing within thirty (30) days after receipt of the
opposing parry's submittal, if any, in accordance with this paragraph.
ENGINEER's written decision on such claim, dispute or other matter
will be final and binding upon OWNER and CONTRACTOR unless
e written notice of intention to appeal from ENGINEER's written
decision is delivered by OWNER or CONTRACTOR to the other and
to ENGINEER within thirty (30) days after the date of such decision
and a formal proceeding is instituted by the appealing party in a
forum of competent jurisdiction to exercise such rights or remedies as
the appealing party may have with respect to such claim, dispute or
other matter in accordance with applicable Laws and Regulations
within thirty (30) days of the date of such decision, unless otherwise
agreed in writing by OWNER and CONTRACTOR.
9.8.2 When functioning as interpreter and judge under paragraphs 9.7
and 9.8, ENGINEER will not show partiality to OWNER or
CONTRACTOR and will not be liable in connection with any
interpretation or decision rendered in good faith. The rendering of a
decision by ENGINEER pursuant to paragraphs 9.7 or 9.8 with
respect to any such claim, dispute or other matter (except any which
have been waived by the making or acceptance of final payment as
provided in paragraph 14.2.2.4) will be a condition precedent to any
exercise by OWNER or CONTRACTOR of payment as provided in
paragraph 14.2.2.2) will be a condition precedent to any exercise by
OWNER or CONTRACTOR of such rights or remedies as either may
otherwise have under the Contract Documents or by Laws or
Regulations in respect of any such claim, dispute or other matter
pursuant to Article 16.
9.9 Limitations on Engineer's Authoritv and Responsibilities
9.9.1 Neither ENGINEER's authority or responsibility under this
Article 9 or under any other provision of the Contract Documents nor
any decision made by ENGINEER in good faith either to exercise or
not exercise such authority or responsibility or the undertaking,
exercise or performance of any authority or responsibility by
GC-21 (Quote Form)
ENGINEER to CONTRACTOR, any Subcontractor, any Supplier,
any other person or organization, or to any surety for or employee or
agent of any of them.
9.9.2 ENGINEER will not supervise, direct, control, or have
authority over, or be responsible for CONTRACTOR's means,
methods, techniques, sequences or procedures of construction, or the
safety precautions and programs incident thereto, or for any failure of
CONTRACTOR to comply with Laws and Regulations applicable to
the furnishing or performance of the Work. ENGINEER will not be
responsible for CONTRACTOR's failure to perform or furnish the
Work in accordance with the Contract Documents.
9.9.3 ENGINEER will not be responsible for the acts or omissions of
CONTRACTOR or of any Subcontractor, any Supplier, or of any
other person or organization performing or furnishing any of the
Work.
9.9.4. ENGINEER's review of the final Application for Payment and
accompanying documentation and all maintenance and operating
instructions, schedules, guarantees, bonds and certificates of
inspection, tests and approvals and other documentation required to
be delivered by paragraph 14.7.1.1 will only be to determine
generally that their content complies with the requirements of, and in
the case of certificates of inspections, tests and approvals that the
results certified indicate compliance with the Contract Documents.
9.9.5. The limitations upon authority and responsibility set forth in
this paragraph 9.9 shall also apply to ENGINEER's Consultants,
Resident Project Representative and assistants.
ARTICLE 10
CHANGES IN THE WORK
10.1 Authorized Changes in the Work
10.1.1 Without invalidating the Agreement and without notice to any
surety, OWNER may; at any time or from time to time, order
additions, deletions or revisions in the Work. Such additions,
deletions or revisions will be authorized by a Written Amendment, a
Change Order, or a Work Change Directive. Upon receipt of any
such document, CONTRACTOR shall promptly proceed with the
Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise
specifically provided).
10.1.2 If OWNER and CONTRACTOR are unable to agree as to the
extent, if any, of an adjustment in the Contract Price or an adjustment
of the Contract Times that should be allowed as a result of a Work
Change Directive, a claim may be made therefor as provided in
Article 12.
10.2 Unauthorized Changes in the Work
10.2.1 CONTRACTOR shall not be entitled to an increase in the
Contract Price or an extension of the Contract Times with respect to
any Work performed that is not required by the Contract Documents
as amended, modified and supplemented as provided in paragraph 3.4
except in the case of an emergency as provided in paragraph 6.16 or
in the case of uncovering Work as provided in paragraph 13.4.
10.3 Execution of Change Orders
10.3.1 OWNER and CONTRACTOR shall execute appropriate
Change Orders recommended by ENGINEER (or Written
Amendments) covering:
10.3.1.1 changes in the Work which are (i) ordered by OWNER
pursuant to paragraph 10.1, (ii) required because of acceptance of
defective Work under paragraph 13.8 or correcting defective Work
under paragraph 13.9, or (iii) agreed to by the parties;
10.3.1.2 changes in the Contract Price or Contract Times which are
agreed to by the parties; and
10.3.1.3. changes in the Contract Price or Contract Times which
embody the substance of any written decision rendered by
ENGINEER pursuant to paragraph 9.8; provided that, in lieu of
executing any such Change Order, an appeal may be taken from any
such decision in accordance with the provisions of the Contract
Documents and applicable Laws and Regulations, but during any
such appeal, CONTRACTOR shall carry on the Work and adhere to
the progress schedule as provided in paragraph 6.18.
10.4 Notification to Surety
10.4.1 If notice of any change affecting the general scope of the
Work or the provisions of the Contract Documents (including, but not
limited to, Contract Price or Contract Times) is required by the
provisions of any Bond to be given to a surety, the giving of any such
notice will be CONTRACTOR's responsibility, and the amount of
each applicable Bond will be adjusted accordingly.
ARTICLE 11
COST OF THE WORK; ALLOWANCES AND UNIT PRICES
11.1 Cost of the Work
11.1.1 The term Cost of the Work means the sum of all costs
necessarily incurred and paid by CONTRACTOR in the proper
performance of the Work. Except as otherwise may be agreed to in
writing by OWNER, such costs shall be in amounts no higher than
those prevailing in the locality of the Project, shall include only the
following items and shall not include any of the costs itemized in
paragraph 11.2:
ILLI.1 Payroll costs for employees in the direct employ of
CONTRACTOR in the performance of the Work under schedules of
job classifications agreed upon by OWNER and CONTRACTOR.
Such employees shall include without limitation superintendents,
foremen and other personnel employed full time at the site, Payroll
costs for employees not employed full time on the Work shall be
apportioned on the basis of their time spent on the Work. Payroll
costs shall include, but not be limited to, salaries and wages plus the
cost of fringe benefits which shall include social security
contributions, unemployment, excise and payroll taxes, workers'
compensation, health and retirement benefits, bonuses, sick leave,
vacation and holiday pay applicable thereto. The expenses of
performing Work after regular working hours, on Saturday, Sunday
or legal holidays, shall be included in the above to the extent
previously authorized by OWNER.
11.1.1.2 Cost of all materials and equipment famished and property
incorporated in the Work, including costs of transportation and
storage thereof, and Suppliers' field services required in connection
therewith. All cash discounts shall accrue to CONTRACTOR unless
OWNER deposits funds with CONTRACTOR with which to make
payments, in which case the cash discounts shall accrue to OWNER.
All trade discounts, rebates and refunds and returns from sale of
surplus materials and equipment shall accrue to OWNER, and
CONTRACTOR shall make provisions so that they may be obtained.
11.1.1.3. Payments made by CONTRACTOR to the Subcontractors
for Work Performed or famished by Subcontractors. If required by
OWNER, CONTRACTOR shall obtain competitive Quotes from
Subcontractors acceptable to OWNER and CONTRACTOR and shall
deliver such Quotes to OWNER who will then determine, with the
advice of ENGINEER, which Quotes, if any, will be accepted. If any
GC-22 (Quote Form)
subcontract provides that the Subcontractor is to be paid on the basis
of Cost of the Work Plus a fee, the Subcontractor's Cost of the Work
and fee shall be determined in the same manner as CONTRACTOR's
Cost of the Work and fee as provided in paragraphs I1.1.1, 11.1.2,
11.1.3 and 11.1.4. All subcontracts shall be subject to the other
provisions of the Contract Documents insofar as applicable.
11.1.1.4 Costs of special consultants (including but not limited to
engineers, architects, testing laboratories, surveyors, attorneys and
accountants) employed for services specifically related to the Work.
11.1.1.5 Supplemental costs including the following;
11.1.1.5.1 The proportion of necessary transportation, travel and
subsistence expenses of CONTRACTOR's employees incurred in
discharge of duties connected with the Work.
11.1.1.5.2 Cost, including transportation and maintenance, of all
materials, supplies, equipment, machinery, appliances, office and
temporary facilities at the site and hand tools not owned by the
workers, which are consumed in the performance of the Work, and
cost less market value of such items used but not consumed which
remain the property of CONTRACTOR.
11.1.1.5.3 Rentals of all construction equipment and machinery and
the parts thereof whether rented from CONTRACTOR or others in
accordance with rental agreements approved by OWNER with the
advice of ENGINEER, and the costs of transportation, loading,
unloading, installation, dismantling and removal thereof, all in
accordance with the terms of said rental agreements. The rental of
any such equipment, machinery or parts shall cease when the use
thereof is no longer necessary for the Work.
11.1.1.5.4 Sales, consumer, use or similar taxes related to the Work,
and for which CONTRACTOR is liable, imposed by Laws and
Regulations.
11.1.1.5.5 Deposits lost for causes other than negligence of
CONTRACTOR, any Subcontractor or anyone directly or indirectly
employed by any of them or for whose acts any of them may be
liable, and royalty payments and fees for permits and licenses.
11.1.1.5.6 Losses and damages (and related expenses) caused by
damage to the Work, not compensated by insurance or otherwise,
sustained by CONTRACTOR in connection with the performance
and furnishing of the Work (except losses and damages within the
deductible amounts of property insurance established by OWNER in
accordance with paragraph 5.6), provided they have resulted from
causes other than the negligence of CONTRACTOR, any
Subcontractor, or anyone directly or indirectly employed by any of
them or for whose acts any of them may be liable. Such losses shall
include settlements made with the written consent and approval of
OWNER. No such losses, damages and expenses shall be included in
the Cost of the Work for the purpose of determining
CONTRACTOR's fee. If, however, any such loss or damage requires
reconstruction and CONTRACTOR is placed in charge thereof,
CONTRACTOR shall be paid for services a fee proportionate to that
stated in paragraph I I.1.3. .
11.1.1.5.7 The cost of utilities, fuel and sanitary facilities at the site.
11.1.1.5.8 Minor expenses such as telegrams, long distance telephone
calls, telephone service at the site, expressage and similar petty cash
items in connection with the Work.
11.1.1.5.9 Cost of premiums for additional Bonds and insurance
required because of changes in the Work.
11.1.2 The term Cost of the Work shall not include any of the
following:
11.1.2.1 Payroll costs and other compensation of CONTRACTOR's
officers, executives, principals (of partnership and sole
proprietorships), general managers, engineers, architects, estimators,
attorneys, auditors, accountants, purchasing and contracting agents,
expediters, timekeepers, clerks and other personnel employed by
CONTRACTOR whether at the site or in CONTRACTOR's principal
or a branch office for general administration of the Work and not
specifically included in the agreed upon schedule of job
classifications referred to in paragraph 11.1.1.1 or specifically
covered by paragraph 11.1.1.4, all of which are to be considered
administrative costs covered by the CONTRACTOR's fee.
11.1.2.2 Expenses of CONTRACTOR's principal and branch offices
other than CONTRACTOR's office at the site.
11.1.2.3 Any part of CONTRACTOR's capital expenses, including
interest on CONTRACTOR's capital employed for the Work and
charges against CONTRACTOR for delinquent payments.
11.1.2.4 Cost of premiums for all Bonds and for all insurance
whether or not CONTRACTOR is required by the Contract
Documents to purchase and maintain the same (except for the cost of
premiums covered by subparagraph 11.1.1.5.9 above).
11.1.2.5 Costs due to the negligence of CONTRACTOR, any
Subcontractor, or anyone directly or indirectly employed by any of
them or for whose acts any of them may be liable, including but not
limited to, the correction of defective Work, disposal of materials or
equipment wrongly supplied and making good any damage to
property. Other overhead or general expense costs of any kind and
the costs of any item not specifically and expressly included in
paragraph 11.1.
11.1.3 The CONTRACTOR's fee allowed to CONTRACTOR for
overhead and profit shall be determined as follows:
11.1.3. l a fixed fee of ten percent (10%); or
11.1.3.2 for costs incurred under paragraph 11.1.1.1, the
CONTRACTOR's fee shall be five percent (5%);
11.1.3.3 where one or more tiers of subcontracts are on the basis of
Cost of the Work plus a fee and no fixed fee is agreed upon, the
intent of paragraphs II.I.I.I, 11.1.1.2, and 11.1.1.3 is that the
Subcontractor who actually performs or furnishes the Work, at
whatever tier, will be paid a fee of ten percent (10%) of the costs
incurred by such Subcontractor under paragraphs II.I.I.I and
11.1.1.2 and that any higher tier Subcontractor and CONTRACTOR
will each be paid a fee of five percent (5%) of the amount paid to the
next lower tier Subcontractor;
11.1.3.4. no fee shall be payable on the basis of costs itemized under
paragraphs 11.1.1.4, 11.1.1.5 and 11.1.2;
11.1.3.5 the amount of credit to be allowed by CONTRACTOR to
OWNER for any change which results in a net decrease in cost will
be the amount of the actual net decrease in cost plus a deduction in
CONTRACTOR's fee by an amount equal to five percent (5°/u) of
such net decrease; and
11.1.3.6 when both additions and credits are involved in any one
change, the adjustment in CONTRACTOR's fee shall be computed
on the basis of the net change in accordance with paragraphs 11.3.1
through 11.3.5, inclusive.
11.1.4 Whenever the cost of any Work is to be determined pursuant
to paragraphs 11.1.2 and 11.1.3, CONTRACTOR will establish and
maintain records thereof in accordance with generally accepted
accounting practices and submit in forth acceptable to ENGINEER
an itemized cost breakdown together with supporting data.
GC-23 (Quote Form)
11.2 Allowances
11.2.1 It is understood that CONTRACTOR has included in the
Contract Price all allowances so named in the Contract Documents
and shall cause the Work so covered to be furnished and performed
for such sums as may be acceptable to OWNER and ENGINEER.
11.2.2 CONTRACTOR agrees that:
11.2.2.1 Cash allowances include the cost to CONTRACTOR (less
any applicable trade discounts) of materials and equipment required
by the allowances to be delivered at the site, and all applicable taxes;
and
11.2.2.2 CONTRACTOR's costs for unloading and handling on the
site, labor, installation costs, overhead, profit and other expenses
contemplated for the allowances have been included in the Contract
Price and not in the allowances and no demand for additional
payment on account of any of the foregoing will be valid.
11.2.3 Prior to final payment, an appropriate Change Order will be
issued as recommended by ENGINEER to reflect actual amounts due
CONTRACTOR on account of Work covered by allowances, and the
Contract Price shall be correspondingly adjusted.
11.3 Unit Price Work
11.3.1. Where the Contract Documents provide that all or part of the
Work is to be Unit Price Work, initially the Contract Price will be
deemed to include for all Unit Price Work an amount equal to the
sum of the established unit price for each separately identified item of
Unit Price Work times the estimated quantity of each item as
indicated in the Agreement.
11.3.2 The estimated quantities of items of Unit Price Work are not
guaranteed and are solely for the purpose of comparison of Quotes
and determining an initial Contract Price. Determinations of the
actual quantities and classifications of Unit Price Work performed by
CONTRACTOR will be made by ENGINEER in accordance with
paragraph 9.7.
11.3.3 Each unit price will be deemed to include an amount
considered by CONTRACTOR to be adequate to cover
CONTRACTOR's overhead and profit for each separately identified
item.
11.1.3.4 The unit price of an item of Unit Price Work shall be subject
to reevaluation and adjustment under the following conditions:
11.3.4.1 If the total cost of a particular item of Unit Price Work
amounts to five percent (5%) or more of the Contract Price and the
variation in the quantity of that particular item of Unit Price Work
performed by CONTRACTOR differs by more than twenty percent
(20%) from the estimated quantity of such item indicated in the
Agreement; and
11.3.4.2 If there is no corresponding adjustment with respect to any
other item of Work; and
11.3.3.3 If CONTRACTOR believes that CONTRACTOR has
incurred additional expense as a result thereof; or if OWNER
believes that the quantity variation entitles OWNER to an adjustment
in the unit price, either OWNER or CONTRACTOR may make a
claim for an adjustment in the Contract Price in accordance with
Article 12 if the parties are unable to agree as to the effect of and
such variation in the quantity of Unit Price Work performed.
ARTICLE 12
CHANGES OF CONTRACT PRICE AND TIMES
12.1 Chanee of Contract Price
12.1.1 The Contract Price constitutes the total compensation (subject
to authorized adjustments) payable to CONTRACTOR for
performing the Work. All duties, responsibilities and obligations
assigned to or undertaken by CONTRACTOR shall be at
CONTRACTOR's expense without change in the Contract Price.
12.1.2 The Contract Price may only be changed by a Change Order or
by a Written Amendment. Any claim for an adjustment in the
Contract Price shall be based on written notice delivered by the party
making the claim to the other party and to ENGINEER promptly (but
in no event later than thirty (30) days) after the start of the occurrence
or event giving rise to the claim and stating the general nature of the
claim. Notice of the amount of the claim with supporting data shall
be delivered within sixty (60) days after the start of such occurrence
or event or thirty (30) days after the required Notice, (unless
ENGINEER allows additional time for claimant to submit additional
or more accurate data in support of the claim) and shall be
accompanied by claimant's written statement that the adjustment
claimed covers all known amounts to which the claimant is entitled
as a result of said occurrence or event. All claims for adjustment in
the Contract Price shall be determined by ENGINEER in accordance
with paragraph 9.11 if OWNER and CONTRACTOR cannot
otherwise agree on the amount involved. No claim for an adjustment
in the Contract Price will be valid if not submitted in accordance with
this paragraph 12.1.2.
12.2 The value of any work covered by a Change Order, any claim
for an adjustment in the Contract Price, or any claim for damages
shall be determined in one of the following ways:
12.2.1 where the Work involved is covered by Unit Prices contained
in the Contract Documents, by application of such Unit Prices to the
quantities of the items involved (subject to the provisions of
paragraphs 11.3;
12.2.2 where the Work involved is not covered by Unit Prices
contained in the Contract Documents, by a mutually agreed lump
sum (which may include an allowance for overhead and profit not
necessarily in accordance with paragraph 11.3);
12.2.3 where the Work involved is not covered by Unit Prices
contained in the Contract Documents and agreement to a lump sum is
not reached under paragraph 12.2.1, on the basis of the Cost of the
Work (determined as provided in paragraphs I1.1 and 11.2) plus a
CONTRACTOR's fee for overhead and profit of ten percent (10%)
total (determined as provided in paragraph 11.3).
12.2 Chanaes of Contract Time
12.2.1 The Contract Times (or Milestones) may only be changed by a
Change Order or a Written Amendment. Any claim for an adjustment
of the Contract Times (or Milestones) shall be based on written
notice delivered by the party making the claim to the other party and
to ENGINEER promptly (but in no event later than thirty (30) days)
after the occurrence of the event giving rise to the claim and stating
the general nature of the claim. Notice of the extent of the claim with
supporting data shall be delivered within sixty (60) days after such
occurrence or not later than thirty (30) days from the required Notice
(unless, ENGINEER allows an additional period of time to ascertain
more accurate data in support of the claim) and shall be accompanied
by the claimant's written statement that the adjustment claimed is the
entire adjustment to which the claimant has reason to believe it is
entitled as a result of the occurrence of said event.
12.2.2 All claims for adjustment in the Contract Times (or
Milestones) shall he determined by ENGINEER in accordance with
paragraph 9.8 if OWNER and CONTRACTOR cannot otherwise
agree. No claim for an adjustment in the Contract Times (or
GC-24 (Quote Form)
Milestones) will be valid if not submitted in accordance with the
requirements of this paragraph.
12.3 Delays
12.3.1 All Contract Times (or Milestone) stated in the Contract
Documents are of the essence of the Agreement.
12.3.2 Where CONTRACTOR is prevented from completing any part
of the Work within the Contract Times (or Milestones) due to delay
beyond the control of CONTRACTOR, the Contract Times (or
Milestones) will be extended in an amount equal to the time lost due
to such delay if a claim is made as provided in paragraph 12.L
Delays beyond the control of CONTRACTOR shall include, but not
be limited to, acts or neglect by OWNER, acts or neglect of utility
owners or other CONTRACTORS performing other work as
contemplated by Article 7, fires, floods, epidemics, abnormal weather
conditions or acts of God. Delays attributable to and within the
control of a CONTRACTOR's Subcontractor(s) or Supplier(s) shall
be deemed to be delays within the control of CONTRACTOR.
12.3.3 Where CONTRACTOR is prevented from completing any part
of the Work within the Contract Times (or Milestones) due to delay
beyond the control of both OWNER and CONTRACTOR, an
extension of the Contract Times (or Milestones) in an amount equal
to the time lost due to such delay shall be CONTRACTOR's sole and
exclusive remedy for such delay. In no event shall OWNER be liable
to CONTRACTOR, any Subcontractor, any Supplier, any other
person or organization, or to any surety for or employee or agent of
any of them, for damages arising out of or resulting from (i) delays
caused by or within the control of CONTRACTOR, (ii) delays
caused by or within the control of OWNER or (iii) delays beyond the
control of both parties including but not limited to fires, floods,
epidemics, abnormal weather conditions, acts of God or acts or
neglect by utility owners or other CONTRACTORS performing other
work as contemplated by Article 7.
ARTICLE-13 — -
TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR
ACCEPTANCE OF DEFECTIVE WORK
13.1 Notice of Defects
13.1.1 Prompt notice of all defective Work of which OWNER or
ENGINEER have actual knowledge will be given to
CONTRACTOR. All defective Work may be rejected, oomected or
accepted as provided in this Article 13.
13.2 Access to Work
13.2.1 OWNER, ENGINEER, ENGINEER's Consultants, other
representatives and personnel of OWNER, independent testing
laboratories and governmental agencies with jurisdictional interests
will have access to the Work at reasonable times for their
observation, inspecting and testing. CONTRACTOR shall provide
them proper and safe conditions for such access and advise them of
CONTRACTOR's site safety procedures and programs so that they
may comply therewith as applicable.
13.3 Tests and Inspections
13.3.1 CONTRACTOR shall give ENGINEER timely notice of
readiness of the Work for all required inspections, tests or approvals,
and shall cooperate with inspection and testing personnel to facilitate
required inspections or tests.
13.3.2 OWNER shall employ and pay for the services of an
independent testing laboratory to perform all inspections, tests, or
approvals required by the Contract Documents except:
13.3.2.1. for inspections, tests or approvals covered by paragraphs
13.3.3 and 13.3.4 below;
13.3.2.2 that costs incurred in connection with tests or inspections
conducted pursuant to paragraph 13.4 below shall be paid as provided
in said paragraph 13.4; and
13.3.2.3 as otherwise specifically provided in the Contract
Documents.
13.3.3. If Laws or Regulations of any public body having jurisdiction
require any Work (or part thereof) specifically to be inspected, tested
or approved by an employee or other representative of such public
body, CONTRACTOR shall assume full responsibility for arranging
and obtaining such inspections, tests or approvals, pay all costs in
connection therewith, and famish ENGINEER the required
certificates of inspection; or approval.
13.3.4 CONTRACTOR shall also be responsible for arranging and
obtaining and shall pay all costs in connection with any inspections,
tests, or approvals required for OWNER's and ENGINEER's
acceptance of materials or equipment to be incorporated in the Work,
or of materials, mix designs, or equipment submitted for approval
prior to CONTRACTOR's purchase thereof for incorporation in the
Work.
13.3.5 If any Work (or the work of others) that is to be inspected,
tested or approved is covered by CONTRACTOR without written
concurrence of ENGINEER, it must, if requested by ENGINEER, be
uncovered for observation.
13.3.6 Uncovering Work as provided in paragraph 13.3.5 shall be at
CONTRACTOR's expense unless CONTRACTOR has given
ENGINEER timely notice of CONTRACTOR's intention to cover the
same and ENGINEER has not acted with reasonable promptness in
response to such notice.
13.4 Uncovering Work
13.4.1 if any Work is covered contrary to the written request of
ENGINEER, it must, if requested, by ENGINEER, be uncovered for
ENGINEER's observation and replaced at CONTRACTOR's
expense.
13.4.2 If ENGINEER considers it necessary or advisable that covered
Work be observed by ENGINEER or inspected or tested by others,
CONTRACTOR, at ENGINEER's request, shall uncover, expose or
otherwise make available for observation, inspection or testing as
ENGINEER may require, that portion of the Work in question,
furnishing all necessary labor, material and equipment.
13.4.3 If it is found that such Work is defective, CONTRACTOR
shall pay all claims, costs, losses and damages caused by, arising out
of or resulting from such uncovering, exposure, observation,
inspection and testing and of satisfactory replacement or
reconstruction (including but not limited to all costs of repair or
replacement of work of others and attorneys' fees); and OWNER
shall be entitled to an appropriate decrease in the Contract Price, and,
if the parties are unable to agree as to the amount thereof, may make
a claim therefor as provided in Article 12.
13.4.4 If, however, such Work is not found to be defective,
CONTRACTOR shall be allowed an increase in the Contract Price or
an extension of the Contract Times (or Milestones), or both, directly
attributable to such uncovering, exposure, observation, inspection,
testing, replacement and reconstruction; and, if the parties are unable
to agree as to the amount or extent thereof, CONTRACTOR may
make a claim therefor as provided in Article12.
13.5 OWNER May Stoo the Work
GC-25 (Quote Form)
13.5.1 If the Work is defective, or CONTRACTOR fails to supply
sufficient skilled workers or suitable materials or equipment, or fails
to furnish or perform the Work in such a way that the completed
Work will conform to the Contract Documents, OWNER may order
CONTRACTOR to stop the Work, or any portion thereof, until the
cause for such order has been eliminated; however, this right of
OWNER to stop the Work shall not give rise to any duty on the part
of OWNER to exercise this right for the benefit of CONTRACTOR
or any surety or other party.
13.6 Correction or Removal of Defective Work
13.6.1 If required by ENGINEER, CONTRACTOR shall promptly,
as directed, either correct all defective Work, whether or not
fabricated, installed or completed, or, if the Work has been rejected
by ENGINEER, remove it from the site and replace it with Work that
is not defective. CONTRACTOR shall pay all claims, costs, losses
and damages caused by or resulting from such correction or removal
(including but not limited to all costs of repair or replacement of
work of others and attorneys' fees).
13.7 Correction Period
13.7.1. If within three (3) years after the date of Substantial
Completion or such longer period of time as may be prescribed by
Laws or Regulations or by the terms of any applicable special
guarantee required by the Contract Documents or by any specific
provision of the Contract Documents, any Work is found to be
defective, CONTRACTOR shall promptly, without cost to OWNER
and in accordance with OWNER's written instructions:
13.7.1.1 correct such defective Work, or, if it has been rejected by
OWNER, remove it from the site and replace it with Work that is not
defective, and
13.7.1.2 satisfactorily correct or remove and replace any damage to
other Work or the work of others resulting therefrom.
13.7.2 If CONTRACTOR does not promptly comply with the terms
of such instructions, or in an emergency where delay would cause
serious risk of loss or damage, OWNER may have the defective
Work corrected or the rejected Work removed and replaced, and all
claims, costs, losses and damages caused by or resulting from such
removal and replacement (including but not limited to all costs of
repair or replacement of work of others and attorneys' fees) will be
paid by CONTRACTOR.
13.7.3 In special circumstances where a particular item of equipment
is placed in continuous service before Substantial Completion of all
the Work, the correction period for that item may start to run from an
earlier date if so provided in the Specifications or by Written
Amendment.
13.7.4 Where defective Work (and damage to other Work resulting
therefrom) has been corrected, removed or replaced under this
paragraph 13.7, the correction period hereunder with respect to such
Work will be extended for an additional period of one (1) year after
such correction or removal and replacement has been satisfactorily
completed. If the defective work is completed or repaired in the third
year.
13.8 Acceptance of Defective Work
13.8.1 If, instead of requiring correction or removal and replacement
of defective Work, OWNER (and, prior to ENGINEER's
recommendation of final payment) prefers to accept it, OWNER may
do so: CONTRACTOR shall pay all claims, costs, losses and
damages attributable to OWNER's evaluation of and determination to
accept such defective Work (such costs to be approved by
ENGINEER as to reasonableness). If any such acceptance occurs
prior to ENGINEER's recommendation of final payment, a Change
Order will be issued incorporating the necessary revisions in the
Contract Documents with respect to the Work; and OWNER shall be
entitled to an appropriate decrease in the Contract Price, and, if the
parties are unable to agree as to the amount thereof, OWNER may
make a claim therefor as provided in Article 12. If the acceptance
occurs after such recommendation, an appropriate amount will he
paid by CONTRACTOR to OWNER.
13.9 OWNER May Correct Defective Work
13.9.1 If CONTRACTOR fails within seven (7) days after written
notice from ENGINEER to correct defective Work or to remove and
replace rejected Work as required by ENGINEER in accordance with
paragraph 13.6, or if CONTRACTOR fails to perform the Work in
accordance with the Contract Documents, or if CONTRACTOR fails
to comply with any other provision of the Contract Documents,
OWNER may correct and remedy any such deficiency.
13.9.2 In exercising the rights and remedies under this paragraph
OWNER shall proceed expeditiously. In connection with such
corrective and remedial action, OWNER may exclude
CONTRACTOR from all or part of the site, take possession of all or
part of the Work, and suspend CONTRACTOR's services related
thereto, take possession of CONTRACTOR's tools, appliances,
construction equipment and machinery at the site and incorporate in
The Work all materials and equipment stored at the site or for which
OWNER has paid CONTRACTOR but which are stored elsewhere.
CONTRACTOR shall allow OWNER, OWNER's representatives,
agents and employees, OWNER's other CONTRACTORS and
ENGINEER and ENGINEER's Consultants access to the site to
enable OWNER to exercise the rights and remedies under this
paragraph.
13.9.3 All claims, costs, losses and damages including attorneys' fees
incurred or sustained by OWNER in exercising such rights and
remedies will be charged against CONTRACTOR and a Change
Order will be issued incorporating the necessary revisions in the
Contract Documents with respect to the Work; and OWNER shall be
entitled to an appropriate decrease in the Contract Price, and, if the
parties are unable to agree as to the amount thereof, OWNER may
make a claim therefor as provided in Article 12. Such claims, costs,
losses and damages will include but not be limited to all costs of
repair or replacement of work of others destroyed or damaged by
correction, removal or replacement of CONTRACTOR's defective
Work including attorneys' fees.
13.9.4 CONTRACTOR shall not be allowed an extension of the
Contract Times (or Milestones) because of any delay in the
performance of the Work attributable to the exercise by OWNER of
OWNER's rights and remedies hereunder.
ARTICLE 14
PAYMENTS TO CONTRACTOR AND COMPLETION
14.1 Schedule of Values
14.1. The schedule of values established as provided in paragraph 2.7
will serve as the basis for progress payments and will be incorporated
into a form of Application for Payment acceptable to ENGINEER.
Progress payments on account of Unit Price Work will be based on
the number of units completed.
14.2 Application for Progress Payment
14.2.1 At least twenty (20) days before the date established for each
progress payment (but not more often than once a month),
CONTRACTOR shall submit to ENGINEER for review an
GC-26 (Quote Form)
covering the Work completed as of the date of the Application and
accompanied by such supporting documentation as is required by the
Contract Documents. If payment is requested on the basis of
materials and equipment not incorporated in the Work but delivered
and suitably stored at the site or at another location agreed to in
writing, the Application for Payment shall also be accompanied by a
bill of sale, invoice or other documentation warranting that OWNER
has received the materials and equipment free and clear of all Liens
and evidence that the materials and equipment are covered by
appropriate property insurance and other arrangements to protect
OWNER's interest therein, all of which will be satisfactory to
OWNER.
14.2.2 Beginning with the second Application for Payment, each
Application shall include an affidavit of CONTRACTOR stating that
all previous progress payments received on account of the Work have
been applied on account to discharge CONTRACTOR's legitimate
obligations associated with prior Applications for Payment.
14.2.3 The amount of retainage with respect to progress payments
will be as stipulated in the Agreement. As a requisite for payment of
any current estimate, the CONTRACTOR will be required to execute
the CONTRACTOR's Progress Affidavit or Waiver - on Exhibit E
attached to the Agreement, and have the same properly notarized.
14.2.2 Review of Applications for Progress Payment
14.2.2.1 ENGINEER will, within ten (10) days after receipt of each
Application for Payment, either indicate in writing a recommendation
of payment and present the Application to OWNER, or return the
Application to CONTRACTOR indicating in writing ENGINEER's
reasons for refusing to recommend payment. In the latter case,
CONTRACTOR may make the necessary corrections and resubmit
the Application. Thirty (30) days after presentation of the Application
for Payment to OWNER with ENGINEER's recommendation, the
amount recommended will, subject to the provisions of paragraph
14.2.2.5, become due and paid by OWNER to CONTRACTOR.
14.2.2.2 ENGINEER's recommendation of any payment requested in
an Application for Payment will constitute a representation by
ENGINEER to OWNER, based on ENGINEER's on -site
observations of the executed Work as an experienced and qualified
design professional and on ENGINEER's review of the Application
for Payment and the accompanying data and schedules, that to the
best of ENGINEER's knowledge, information and belief:
14.2.2.2.1 the Work has progressed to the point indicated,
14.2.2.2.2 the quality of the Work is generally in accordance with the
Contract Documents (subject to an evaluation of the Work as a
functioning whole prior to or upon Substantial Completion, to the
results of any subsequent tests called for in the Contract Documents,
to a final determination of quantities and classifications for Unit Price
Work under paragraph 9.7, and to any other qualifications stated in
the recommendation), and
14.2.2.2.3 the conditions precedent to CONTRACTOR's being
entitled to such payment appear to have been fulfilled in so far as it is
ENGINEER's responsibility to observe the Work.
14.2.2.3 however, by recommending any such payment ENGINEER
will not thereby be deemed to have represented that: (i) exhaustive or
continuous on -site inspections have been made to check the quality or
the quantity of the Work beyond the responsibilities specifically
assigned to ENGINEER in -the Contract Documents or (ii) that there
may not be other matters or issues between the parties that might
entitle CONTRACTOR to he paid additionally by OWNER or entitle
OWNER to withhold payment to CONTRACTOR.
14.2.2.4 ENGINEER's recommendation of any payment, including
final payment, shall not mean that ENGINEER is responsible for
CONTRACTOR's means, methods, techniques, sequences or
procedures of construction, or the safety precautions and programs
incident thereto, or for any failure of CONTRACTOR to comply with
Laws and Regulations applicable to the furnishing or performance of
Work, or for any failure of CONTRACTOR to perform or famish
Work in accordance with the Contract Documents.
14.2.2.5 ENGINEER may refuse to recommend the whole or any part
of any payment if, in ENGINEER's opinion, it would be incorrect to
make the representations to OWNER referred to in paragraph
14.2.2.2. ENGINEER may also refuse to recommend any such
payment, or, because of subsequently discovered evidence or the
results of subsequent inspections or tests, nullify any such payment
previously recommended, to such extent as may be necessary in
ENGINEER's opinion to protect OWNER from loss because:
14.2.2.5.1 the Work is defective; or completed Work has been
damaged requiring correction or replacement,
14.2.2.5.2 the Contract Price has been reduced by Written
Amendment or Change Order,
14.2.2.5.3 OWNER has been required to correct defective Work or
complete Work in accordance with paragraph 13.9, or
14.2.2.5.4 ENGINEER has actual knowledge of the occurrence of
any of the events enumerated in paragraph 15.2.1.1.
14.2.2.6 OWNER may refuse to make payment of the full amount
recommended by ENGINEER because:
14.2.2.6.1 claims have been made against OWNER on account of
CONTRACTORS performance or furnishing of the Work,
14.2.2.6.2 Liens or claims have been filed in connection with the
Work,
14.2.2.6.3 there are other items entitling OWNER to a set-off against
the amount recommended, or
14.2.2.6.4 OWNER has actual knowledge of the occurrence of any of
the events enumerated in paragraphs 14.2.2.5.1 through 14.2.2.5.3 or
paragraphs 15.2.1.1 through 15.2.1.4 inclusive;
14.2.2.7 OWNER must give CONTRACTOR immediate written
notice (with a copy to ENGINEER) stating the reasons for such
action and promptly pay CONTRACTOR the amount so withheld, or
any adjustment thereto agreed to by OWNER and CONTRACTOR,
when CONTRACTOR corrects to OWNER's satisfaction the reasons
for such action.
14.3 CONTRACTOR's Warranty of Title
14.3. CONTRACTOR warrants and guarantees that title to all Work,
materials and equipment covered by any Application for Payment,
whether incorporated in the Project or not, will pass to OWNER no
later than the time of payment free and clear of all Liens.
14.4 Substantial Completion
14.4.1 When CONTRACTOR considers the entire Work ready for its
intended use, CONTRACTOR shall notify OWNER and ENGINEER
in writing that the entire Work is substantially complete (except for
items specifically listed by CONTRACTOR as incomplete) and
request that ENGINEER issue a certificate of Substantial
Completion.
14.4.2 Within a reasonable time thereafter, OWNER,
CONTRACTOR and ENGINEER shall make an inspection of the
Work to determine the status of comnletion. If ENGINEER does nor
GC-27 (Quote Form)
consider the Work substantially complete, ENGINEER will notify
CONTRACTOR in writing giving the reasons therefor.
14.4.3 If ENGINEER considers the Work substantially complete,
ENGINEER will prepare and deliver to OWNER a tentative
certificate of Substantial Completion which shall fix the date of
Substantial Completion. There shall be attached to the certificate a
tentative list of items to be completed or corrected before final
payment. OWNER shall have seven (7) days after receipt of the
tentative certificate during which to make written objection to
ENGINEER as to any provisions of the certificate or attached list. If,
after considering such objections, ENGINEER concludes that the
Work is not substantially complete, ENGINEER will within fourteen
(14) days after submission of the tentative certificate to OWNER
notify CONTRACTOR in writing, stating the reasons therefor. If,
after consideration of OWNER's objections, ENGINEER considers
the Work substantially complete, ENGINEER will within said
fourteen (14) days execute and deliver to OWNER and
CONTRACTOR a definitive certificate of Substantial Completion
(with a revised tentative list of items to be completed or corrected)
reflecting such changes from the tentative certificate as ENGINEER
believes justified after consideration of any objections from
OWNER.
14.4.4 At the time of delivery of the tentative certificate of
Substantial Completion ENGINEER will deliver to OWNER and
CONTRACTOR a written recommendation as to division of
responsibilities pending final payment between OWNER and
CONTRACTOR with respect to security, operation, safety,
maintenance, heat, utilities, insurance and warranties and guarantees.
Unless OWNER and CONTRACTOR agree otherwise in writing and
so inform ENGINEER in writing prior to ENGINEER's issuing the
definitive certificate of Substantial Completion, ENGINEER's
aforesaid recommendation will be binding on. OWNER and
CONTRACTOR until final payment.
14.4.5 OWNER shall have the right to exclude CONTRACTOR from
the Work after the date of Substantial Completion, but OWNER shall
allow CONTRACTOR reasonable access to complete or correct
items on the tentative list.
14.5 Partial Utilization
14.5.1 Use by OWNER at OWNER's option of any substantially
completed part of the Work which: (i) has specifically been identified
in the Contract Documents, or (ill OWNER, ENGINEER and
CONTRACTOR agree constitutes a separately functioning and
usable part of the Work that can be used by OWNER for its intended
purpose without significant interference with CONTRACTOR's
performance of the remainder of the Work, may be accomplished
prior to Substantial Completion of all the Work subject to the
following:
14.5.1.1 OWNER at any time may request CONTRACTOR in
writing to permit OWNER to use any such part of the Work which
OWNER believes to be ready for its intended use and substantially
complete. If CONTRACTOR agrees that such part of the Work is
substantially complete, CONTRACTOR will certify to OWNER and
ENGINEER that such part of the Work is substantially complete and
request ENGINEER to issue a certificate of Substantial Completion
for that part of the Work.
14.5.1.2 CONTRACTOR at any time may notify OWNER and
ENGINEER in writing that CONTRACTOR considers any such part
of the Work ready for its intended use and substantially complete and
request ENGINEER to issue a certificate of Substantial Completion
for that part of the Work.
14.5.1.3 Within a reasonable time after either such request, OWNER,
CONTRACTOR and ENGINEER shall make an inspection of that
part of the Work to determine its status of completion. If ENGINEER
does not consider that part of the Work to be substantially complete,
ENGINEER will notify OWNER and CONTRACTOR in writing
giving the reasons therefor. If ENGINEER considers that part of the
Work to be substantially complete, the provisions of paragraphs 14.4
will apply with respect to certification of Substantial Completion of
that part of the Work and the division of responsibility in respect
thereof and access thereto.
14.5.1.4 OWNER may at any time request CONTRACTOR in
writing to permit OWNER to take over operation of any such part of
the Work although it is not substantially complete. A copy of such
request will be sent to ENGINEER and within a reasonable time
thereafter OWNER, CONTRACTOR and ENGINEER shall make an
inspection of that part of the Work to determine its status of
completion and will prepare a list of the items remaining to be
completed or corrected thereon before final payment. If
CONTRACTOR does not object in writing to OWNER and
ENGINEER that such part of the Work is not ready for separate
operation by OWNER, ENGINEER will finalize the list of items to
be completed or corrected and will deliver such lists to OWNER and
CONTRACTOR together with a written recommendation as to the
division of responsibilities pending final payment between OWNER
and CONTRACTOR with respect to security, operation, safety,
maintenance, utilities, insurance, warranties and guarantees for that
part of the Work which will become binding upon OWNER and
CONTRACTOR at the time when OWNER takes over such
operation (unless they shall have otherwise agreed in writing and so
informed ENGINEER). During such operation and prior to
Substantial Completion of such part of the Work, OWNER shall
allow CONTRACTOR reasonable access to complete or correct
items on said list and to complete other related Work.
14.6 Final Inspection
14.6.1 Upon written notice from CONTRACTOR that the entire
Work or an agreed portion thereof is complete, ENGINEER will
make a final inspection with OWNER and CONTRACTOR and will
notify CONTRACTOR in writing of all particulars in which this
inspection reveals that the Work is incomplete or defective.
CONTRACTOR shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
14.7 Final Payment
14.7.1 Application for Payment
14.7.1.1 After CONTRACTOR has completed all such corrections to
the satisfaction of ENGINEER and delivered in accordance with the
Contract Documents all maintenance and operating instructions,
schedules, guarantees, Bonds, certificates or other evidence of
insurance required by paragraph 5.4, certificates of inspection,
marked -up record documents (as provided in paragraph 6.12) and
other documents; CONTRACTOR may make application for final
payment following the procedure for progress payments.
14.7.1.2 The final Application for Payment shall be accompanied
(except as previously delivered) by: Ill all documentation called for
in the Contract Documents including but not limited to the evidence
of insurance required by subparagraph 5.4.13, (if) consent of the
surety, if any, to final payment, and (ill) complete and legally
effective releases or waivers (satisfactory to OWNER) of all Liens
arising out of or filed in connection with the Work, as attached.
14.7.1.3 In lieu of such releases or waivers of Liens and as approved
by OWNER, CONTRACTOR may famish receipts or releases in full
GC-28 (Quote Form)
include all labor, services, material and equipment for which a Lien
could be filed, and (ii) all payrolls, material and equipment bills and
other indebtedness connected with the Work for which OWNER or
OWNER's property in any way be responsible have been paid or
otherwise satisfied. (if any Subcontractor or Supplier fails to furnish
such, a release or receipt in full, CONTRACTOR may furnish a Bond
or other Collateral satisfactory to OWNER to indemnify OWNER
against any Lien. As a requisite for payment of the final estimate, the
CONTRACTOR will be required to sign the CONTRACTOR's
Affidavit on the form attached herein, and have the same properly
notarized.
14.7.2 -Final Payment and Acceptance
14.7.2.1 If, on the basis of ENGINEER's observation of the Work
during construction and final inspection, and ENGINEER's review of
the final Application for Payment and accompanying documentation
as required by the Contract Documents, ENGINEER is satisfied that
the Work has been completed and CONTRACTOR's other
obligations under the Contract Documents, have been fulfilled,
ENGINEER will within ten (10) days after receipt of the final
Application of Payment, indicate in writing ENGINEER's
recommendation of payment and present the Application to OWNER
for payment. At the same time ENGINEER will also give written
notice to OWNER and CONTRACTOR that the Work is acceptable
subject to the provisions of paragraph 14.9. Otherwise, ENGINEER
will return the Application to CONTRACTOR, indicating in writing
the reasons for refusing to recommend final payment, in which case
CONTRACTOR shall make the necessary corrections and resubmit
the Application
14.7.3 Thirty (30) days after the presentation to OWNER of the
Application and accompanying documentation, in appropriate form
and substance and with ENGINEER's recommendation and notice of
acceptability the amount recommended by ENGINEER will become
due and will be paid by OWNER to CONTRACTOR.
14.8 Final Completion Delayed
14.8.1 If, through no fault of CONTRACTOR. final completion of
the Work is significantly delayed and if ENGINEER so confirms,
OWNER shall, upon receipt of CONTRACTOR's final Application
for Payment and recommendation of ENGINEER, and without
terminating the Agreement, make payment of the balance due for that
portion of the Work fully completed and accepted. If the remaining
balance to be held by OWNER for Work not fully completed or
corrected is less than the retainage stipulated in the Agreement, and if
Bonds have been furnished as required in paragraph 5.1 the written
consent of the surety to the payment of the balance due for that
portion of the Work fully completed and accepted shall be submitted
by CONTRACTOR to ENGINEER with the Application for such
payment. Such payment shall, be made under the terms and
conditions governing final, payment, except that it shall; not
constitute a waiver of claims.
14.9 Waiver of Claims
14.9.1 The making and acceptance of final payment will constitute
14.9.1.1 a waiver of all claims by OWNER against CONTRACTOR,
except claims arising from unsettled Liens, from defective Work
appearing after final inspection pursuant to paragraph 14.6 from
failure to comply with the Contract Documents or the terms of any
special guarantees specified therein, or from CONTRACTOR's
continuing obligations under the Contract Documents; and
14.9.1.2 a waiver of all claims by CONTRACTOR against OWNER
other than those previously made, in writing and still unsettled.
SUSPENSION OF WORK AND TERMINATION
15.1 OWNER May Suspend Work
15.1.1 At any time and without cause, OWNER may suspend the
Work or any portion thereof for a period of not more than ninety (90)
consecutive days by notice in writing to CONTRACTOR and
ENGINEER which will fix the date on which Work will be resumed.
CONTRACTOR shall resume the Work on the date so fixed.
CONTRACTOR shall be allowed an extension of the Contract Times
directly attributable to any such suspension if CONTRACTOR makes
an approved claim therefor as provided in Article 12.
15.2 OWNER's Right to Terminate for Cause
15.2.1 The occurrence of anyone or more of the following events will
justify termination for cause:
15.2.1.1 if CONTRACTOR persistently fails to perform the Work in
accordance with the Contract Documents (including, but not limited
to, failure to supply sufficient skilled workers or suitable materials or
equipment or failure to adhere to the progress schedule established
under paragraph 2.7 as adjusted from time to time pursuant to
paragraph 6.4);
15.2.1.2 if CONTRACTOR disregards Laws or Regulations of any
public body having jurisdiction;
15.2.1.3 if CONTRACTOR disregards the authority of ENGINEER;
or
15.2.1.4 if CONTRACTOR otherwise violates in any substantial way
any provisions of the Contract Documents;
15.2.2 If any of the events identified in 15.2.1 exist, OWNER may,
after giving CONTRACTOR (and the surety, if any,) seven (7) days
written notice and to the extent permitted by Laws and Regulations,
terminate the services of CONTRACTOR,
15.2.2.1 exclude CONTRACTORfromthe site and take possession
of the Work and of all CONTRACTOR's tools, appliances,
construction equipment and machinery at the site and use the same to
the full extent they could be used by CONTRACTOR (without
liability to CONTRACTOR for trespass or conversion),
15.2.2.2 incorporate in the Work all materials and equipment stored
at the site or for which OWNER has paid CONTRACTOR but which
are stored elsewhere, and
15.2.2.3 finish the Work as OWNER may deem expedient.
15.2.3 In such case, CONTRACTOR shall not be entitled to receive
any further payment until the Work is finished. If the unpaid balance
of the Contract Price exceeds all claims, costs, losses, damages and
attorney's fees sustained by OWNER arising out of or resulting from
completing the Work such excess will be paid to CONTRACTOR. If
such claims, costs, losses and damages exceed such unpaid balance,
CONTRACTOR shall pay the difference to OWNER. Such claims,
costs, losses, attorneys fees and damages incurred by OWNER will
be reviewed by ENGINEER as to their reasonableness and when so
approved by ENGINEER incorporated in a Change Order, provided
that when exercising any rights or remedies under this paragraph
OWNER shall not be required to obtain the lowest price for the Work
performed.
15.2.4 Where CONTRACTOR's services have been so terminated by
OWNER, the termination will not affect any rights or remedies of
OWNER against CONTRACTOR then existing or which may
thereafter accrue. Any retention or payment of moneys due
CONTRACTOR by OWNER will not release CONTRACTOR from
liability.
GC-29 (Quote Form)
15.3 OWNER'S Right to Terminate for Convenience
15.3.1 Upon seven (7) days written notice to CONTRACTOR and
ENGINEER, OWNER may, without cause and for OWNER'S sole
convenience and without prejudice to any other right or remedy of
OWNER, elect to terminate the Agreement for its sole convenience
and benefit. In such case, CONTRACTOR shall be paid (without
duplication of any items):
15.3.1.1 for completed and acceptable Work executed in accordance
with the Contract Documents prior to the effective date of
termination, including fair and reasonable sums for overhead and
profit on such completed and accepted Work, only;
15.3.1.2 for expenses sustained prior to the effective date of
termination in performing services and furnishing labor, materials or
equipment as required by the Contract Documents, plus fair and
reasonable sums for overhead and profit on such expenses;
15.3.1.3 for all claims, costs, losses and damages incurred in
settlement of terminated contracts with Subcontractors, Suppliers and
others; and
15.3.1.4 CONTRACTOR shall not be paid on account of loss of
anticipated profits of revenue or other economic loss or other
consequential damages arising out of or resulting from such
termination.
15.4 CONTRACTOR May Stop Work or Terminate
15.4.1 If, through no act or fault of CONTRACTOR, (i) the Work is
suspended for a period of more than ninety (90) consecutive days by
OWNER or under an order of court or other public authority, or (ii)
ENGINEER fails to act on any Application for Payment within thirty
(30) days after it is submitted or (iii) OWNER fails for thirty (30)
days to pay CONTRACTOR any sum finally determined to be due,
then CONTRACTOR may, upon seven (7) days' written notice to
OWNER and ENGINEER, and provided OWNER or ENGINEER do
not remedy such suspension or failure within that time, stop the Work
until payment of all such amounts due CONTRACTOR. The
provisions of this paragraph are not intended to preclude
CONTRACTOR from making claim under Article 12 for an increase
in Contract Price or Contract Times or otherwise for expenses or
damage directly attributable to CONTRACTOR'S stopping Work as
permitted by this paragraph.
ARTICLE 16
DISPUTE RESOLUTION
ARTICLE 17
MISCELLANEOUS
17.1 Giving Notice
17.1.1 Whenever any provision of the Contract Documents requires
the giving of written notice, it will be deemed to have been validly
given if delivered in person to the individual or to a member of the
firm or to an officer of the corporation for whom it is intended or if
delivered at or sent by registered or certified mail, postage prepaid, to
the last business address known to the giver of the notice.
17.2 Computation of Times
17.2.1. When any period of time is referred to in the Contract
Documents by days, it will be computed to exclude the first and
include the last day of such period. If the last day of any such period
falls on a Saturday or Sunday or on a day made a legal holiday by the
law of the applicable jurisdiction, such day will be omitted from the
computation.
17.2.2. A calendar day of twenty-four hours measured from midnight
to the next midnight will constitute a day.
17.3 Notice of Claim
17.3.1 Should OWNER or CONTRACTOR suffer injury or damage
to person or property because of any error or omission or act of the
other party or of any of the other party's employees or agents or
others for whose acts the other party is legally liable, claim will be
made in writing to the other party within a reasonable time of the first
observance of such injury or damage. The provisions of this
paragraph 17.3 shall not be construed as a substitute for or a waiver
of the provisions of any applicable statute of limitations or repose.
17.4 Cumulative Remedies
17.4.1 The duties and obligations imposed by these General
Conditions and the rights and remedies available hereunder to the
parties hereto, and, in particular but without limitation, the
warranties, guarantees and obligations imposed upon
CONTRACTOR and all of the rights and remedies available to
OWNER and ENGINEER thereunder, are in addition to, and are not
to be construed in any way as a limitation of, any rights and remedies
available to any or all of them which are otherwise imposed or
available by Laws or Regulations, by special warranty or guarantee
or by other provisions of the Contract Documents, and the provisions
of this paragraph will be as effective as if repeated specifically in the
Contract Documents in connection with each particular duty,
obligation, right and remedy to which they apply.
17.5 Professional Fees and Court Costs Included
17.5.1 Whenever reference is made to claims, costs, losses and
damages, it shall include in each case, but not he limited to, all fees
and charges of engineers, architects, attorneys and other professionals
and all court or arbitration or other dispute resolution costs.
[The remainder of this page was left. blank intentionally.]
1652259
GC-30 (Quote Form)
GC-31
PART C
TECHNICAL SPECIFICATIONS
SECTION 01010
DEFINITION OF CONTRACT ITEMS
PART 1 GENERAL
1.01 FOREWORD
A. This Section describes the various Contract Items listed in the Bid.
1.02 WORK INCLUDED
A. Under each Item, the Contractor shall furnish all labor, materials, tools, plant
equipment, supplies, maintenance of equipment, heating, lighting and power, insurance
and bonds, coordination, and all work that may be specifically described and included
under the respective Items and necessary to complete the work in accordance with the
obvious or expressed intent of the Contract Documents.
1.03 WORKMANSHIP AND MATERIALS
A. The quality of workmanship and materials entering into any and all of the Items and the
work included shall conform to pertinent sections, paragraphs, sentences, and clauses,
both directly and indirectly applicable thereto, contained in the Contract Documents,
whether or not direct reference to such occurs under each Item in this Section.
1.04 PAYMENT
A. The lump sum and unit prices stated in the Bid shall be payment in full for the
completion of all work specified and described or required to be included in the
Contract, complete, and ready for use.
PART 2 PRODUCTS
None.
PART EXECUTION
None.
PART 4 SPECIAL PROVISIONS
4.01 CONTRACT ITEMS
A. The contract items are defined on the following pages.
2022 36-Inch Sewer Lining Section 01010 - 1 Definition of Contract Items
1.01
iXr➢]
2.01
2.02
3.01
A.
3.02
B.
ITEM 1
MOBILIZATION, DEMOBILIZATION, ADMINISTRATION, MISC.
DESCRIPTION
A. This Item shall include anything necessary to perform the Work that is not included in
other bid items including, but not limited to, administration costs, insurance, permits,
moving equipment in and out, utility connection costs, cleanup, submittals, etc.
PAYMENT
A. Item 1 shall be paid on a lump sum basis.
ITEM 2
36-INCH SEWER LINER
DESCRIPTION
A. This Item includes furnishing and installing CIPP liner in a 36-Inch sewer, generally as
described in Section 02766 and elsewhere.
B. Each lineal foot of liner shall also include the following items, which will not constitute
any extra cost to the Owner:
1. Furnishing and installing a pre -liner, spot lining, and/or any other steps
necessary to mitigate existing leaks prior to lining.
2. Sewer cleaning (up to three passes with a high-pressure hydro -jetting system).
3. Bypass pumping, dewatering, and/or plugging necessary to line the sewer.
4. Any other ancillary items necessary for complete and satisfactory sewer lining.
2.03 PAYMENT
A. The prices shall be for each linear foot of sewer lined.
ITEM 3
ALLOWANCE — RESTORATION
DESCRIPTION
This item consists of a $10,000 allowance to be used for site restoration as described in Section
01021 and elsewhere.
PAYMENT
Payment of the allowance shall be documented cost of labor and materials for the Work
described in Section 01021. Overhead, profit, and other expenses shall not be included in the
allowance.
END OF SECTION
Definition of Contract Items Section 01010 - 2
2022 36-Inch Sewer Lining
City of Carmel, Indiana
2022 36-inch Sewer Lining
SECTION 01021
ALLOWANCES
PART 1 GENERAL
541.7700.002
July 2022
1.01 SCOPE
A. This Section includes the allowances which are to be furnished by the Contractor.
B. These allowances shall cover the documented cost of labor, materials, and equipment
used for the items specified. The Contractor's overhead, profit, and other expenses shall
be included in the Contract Price and not in the allowance.
C. If the cost, when determined, less than the allowance, the Contract Price shall be
adjusted accordingly by Change Order.
1.02 SUBMITTALS
A. Upon request, the Contractor shall furnish sufficient invoices and other documentation
so that the Owner may verify the cost of the Work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
PART 4 SPECIAL PROVISIONS
4.01 LIST OF ALLOWANCES
A. Restoration $10,000
4.02 DEFINITION OF ALLOWANCE
A. This allowance shall be used for restoration of grass, landscaping, and roadways
disturbed during the Work.
END OF SECTION
Allowances
01021-1
SECTION 01043
COORDINATION AND CONTROL OF THE WORK
PART 1 GENERAL
1.01 SCOPE
A. This Section includes coordination and control of the Work.
1.02 SUBMITTALS
A. Submittals shall be in accordance with all requirements of Section 01300 and shall
include:
1. Information for the Record:
a. Bypass Pumping plan and procedures.
b. Coordination drawings shall include, but not be limited to, all process
piping including, but not limited to, bill of material, laying length,
embedded conduit runs, and embedded plumbing lines.
1.03 LINES AND GRADES
A. All work under this Contract shall be built in accordance with the lines and grades shown
on the Drawings or as altered or modified by authority of the Owner and Engineer.
1.04 EXISTING STRUCTURES SHOWN ON DRAWINGS
A. Where underground and surface structures are shown on the Drawings, the location,
depth, and dimensions of such structures are believed to be reasonably correct but are
not guaranteed.
B. Such structures are shown for the information of the Contractor, but information so
given is not to be construed as a representation that such structures will in all cases be
found or encountered just where shown, or that they represent all the structures which
may be encountered.
1.05 COOPERATION OF CONTRACTOR
A. The Contractor shall conduct his operations so as to interfere as little as possible with
those of the Owner, other contractors, utilities, or any public authority on or near the
Work.
B. The Owner reserves the right to perform other work by contract or otherwise, and to
permit other public bodies, public utility companies, and others to do work on or near
the project during progress of the Work. If a conflict arises, the Owner will determine
when and how the work shall proceed.
C. Claims for delay or inconvenience due to operations of such other parties on work
specified, shown on the Drawings, as directed or which can be reasonably expected to
be encountered by the nature and location of the Work will not be considered.
1.06 MAINTENANCE OF SANITARY SYSTEM DURING CONSTRUCTION
A. All construction which requires interruption of existing sanitary system flow shall be
executed during periods designated by the Owner.
B. Bypassing of untreated sanitary wastewater to any stream or body of water is
prohibited.
2022 36-Inch Sewer Lining Section 01043 - 1 Coordination and Control of the Work
1.07 PERMANENT PAVEMENT AND FINAL RESTORATION
A. Permanent pavement and final restoration shall be completed prior to the close of the
last paving season prior to the Contract's final completion.
1.09 TEMPORARY PARKING FACILITIES
A. Parking spaces for the Contractor's personnel shall be provided and maintained in
usable condition by the Contractor at all times. Provisions shall be made so that
sediment is not tracked onto paved roadways from the vehicles operated by the
Contractor's personnel. The parking areas shall consist of temporary parking areas or
new permanent parking areas shown on the Drawings. Temporary parking areas are to
be located in the area designated by the Owner and Engineer. At the completion of the
project, temporary parking areas shall be removed and the surface restored as specified,
shown on the Drawings, as directed or to its original condition.
B. The Contractor's personnel shall not utilize existing permanent parking areas unless
specifically noted otherwise on the Drawings.
1.11 DISPOSAL OF DEBRIS
A. All debris resulting from construction operations, i.e., packaging, waste materials,
damaged equipment, etc., shall be trucked from the site by the Contractor and disposed
of at spoil sites.
B. The Contractor shall police the hauling of debris to ensure that all spillage from haul
trucks is promptly and completely removed from public or private rights -of -way.
C. All debris shall be disposed of in accordance with federal, state, and local laws and
regulations.
1.12 CONTROL OF NOISE
A. The Contractor shall eliminate noise to as great an extent as possible at all times. Air
compressors shall be equipped with silencers and the exhaust of all gasoline motors and
other power equipment shall be provided with mufflers. In the vicinity of hospitals,
libraries, and schools, precautions shall be taken to avoid noise and other nuisance, and
the Contractor shall require strict observances of all pertinent ordinances and
regulations. Any blasting permitted in such locations shall be done with reduced
charges.
1.13 SMOKE PREVENTION
A. Strict compliance with all ordinances regulating the production and emission of smoke
will be required, and the Contractor shall accept full responsibility for all damage that
may occur to property as a result of negligence in providing required control.
1.14 SANITARY REGULATIONS
A. The Contractor shall provide all necessary housing accommodations for the workers for
changing clothes and for protection during inclement weather. Toilet accommodations
shall also be maintained for the use of the employees on the Work. The
accommodations shall be in approved locations, properly screened from public
observance and shall be maintained in a strictly sanitary manner. The Contractor shall
obey and enforce all other sanitary regulations and orders; shall take precautions
against infectious diseases and the spread of same; and shall maintain at all times
satisfactory sanitary conditions around all shanties, tool and supply houses, and on all
other parts of the Work.
Coordinatlon and Control of the Work Section 01043 - 2 2022 36-Inch Sewer Lining
1.15 EMERGENCY MAINTENANCE SUPERVISOR
A. The Contractor shall submit to the Engineer the names, addresses, and telephone
numbers of two employees responsible for performing emergency maintenance and
repairs when the Contractor is not working. These employees shall be designated in
writing by the Contractor to act as his representative and shall have full authority to act
on his behalf as specified in GC 6.2 of the General Conditions.
B. Contractor shall post at job site, in a conspicuous location, the emergency numbers for
the project.
C. Contractor shall be responsible for contacting the local fire, police, and emergency
response personnel and organizations in advance of the work. The Contractor shall be
responsible for the coordination and compliance with emergency response plans,
whether developed by the governing agency, laws, or the Contractor for the project.
D. At least one of the designated employees shall be available for a telephone call any time
an emergency arises.
1.16 PUBLIC SERVICE STRUCTURES
A. Public service structures shall be understood to include all poles, tracks, pipes, wires,
conduits, house -service connections, vaults, manholes, and other appurtenances,
whether owned or controlled by the Owner or other public bodies or by privately -
owned corporations, used to supply the public with transportation, heating, electric,
telephone, gas, water, sewer, or other services.
B. At least a week in advance of breaking ground, the Contractor shall notify the registered
underground protection service, all public bodies, and other owners of such facilities of
the proposed location of his operations, advising them that their property may be
affected and that such measures as they may deem necessary should be promptly taken
to protect, adjust, remove, or build them.
C. House service connections for water and sewer may not be marked in the field as a part
of the protection measure for public utilities. In developed residential and commercial
areas, the Contractor shall assume each building and dwelling has water and sewer
services and that they shall be protected and repaired as needed as part of the pipeline
installation. No additional payment will be made for work associated with supporting or
repairs of such services.
D. Three conditions which may be encountered will be dealt with as follows:
1. Structures which are adjacent to but not included within the limits of an
excavation required for performance of the Work shall be protected, supported,
and maintained in service by the Contractor at his expense.
2. Structures within the limits of the Work which can be satisfactorily supported
and maintained in service and which do not require removal and rebuilding in
the judgment of the Engineer shall be thus supported by the Contractor at his
expense, including cost of repair of damage incident to his operations.
a. Supports for water and gas mains, sewers, conduits, and similar
structures shall be constructed of timber or other acceptable materials;
shall be supported from undisturbed foundations, and shall be
sufficiently substantial to ensure against settlement when pipe trenches
or other excavations are backfilled. In all cases where permits or
inspection fees are required by utilities in connection with changes to or
temporary support of their conduits, the Contractor shall secure such
2022 36-Inch Sewer Lining Section 01043 - 3 Coordination and Control of the Work
permits and pay all permit and inspection fees.
b. The Contractor shall assume full responsibility for maintaining all public
service structures in service and shall support and protect, or remove
and rebuild them at his own expense. Such services shall not be
interrupted without permission of the owner of the public service
structure.
3. In case relocation of pipelines or other utility structures is required because of
direct interference, as determined jointly by the Owner, Engineer, and
Contractor, with the installation of the Work, the Contractor shall notify the
Owners of the utility structure involved.
a. The Contractor will not be reimbursed for the cost of the relocation if
the interference is shown on the Drawings, described in the
Specifications, apparent on visual inspection, or specifically included in
the Work to be performed by the Contractor.
b. The Contractor will not be paid for time lost because of such direct
interference. Where it is the policy of any utility owner to perform such
work with his own forces, the Contractor shall cooperate to the fullest
extent with such utility owner.
1.17 UNAUTHORIZED WORK
A. Work done beyond the lines shown on the Drawings or ordered, work done without
required inspection, except as herein provided, or any Extra Work done without
authority will be considered as unauthorized and will not be paid for under the
provisions of the Contract. Work so done may be ordered removed at the Contractor's
expense. Work done without lines and grades being given shall be considered as
unauthorized and subject to rejection.
PART 2 PRODUCTS
None.
PART 3 EXECUTION
None.
PART 4 SPECIAL PROVISIONS
4.01 SCHEDULING OF WORK
A. We anticipate that the Work will require bypass pumping.
B. We anticipate that the sewer has a peak wet weather flow of 20-mgd.
C. Contractor needs to demonstrate to the City inspector that their bypass pumping is
sufficient and capable of bypassing all the sewer flow for a given section prior to
executing bypass plan.
4.02 POTENTIALLY HAZARDOUS ENVIRONMENT
A. The environment in portions of the project site is rated as Class I Division 1 or 2 or some
areas of the project site are designated as permitted Confined Spaces. As a minimum,
whenever the Contractor is performing work in these areas, the Contractor shall provide
Factory Mutual- and UL-approved continuous monitoring of the atmosphere for the
presence of hydrogen sulfides, of low oxygen concentration, and of explosive gases
(both lighter and heavier than air). The Contractor shall evacuate all personnel from the
areas whenever the detection system registers hydrogen sulfide levels of greater than
Coordination and Control of the Work Section 01043-4 202236-Inch Sewer Lining
20 ppm, oxygen levels less than 19.5% or combustible gas levels of greater than 10% of
the LEL. In addition, whenever the Contractor is using tools producing open flames or
sparks, such as cutting torches, saws, and grinders, the Contractor shall provide for the
forced air exhaust ducted from the immediate area of the work.
4.03 REQUIRED SAFETY DOCUMENTATION TO BE SUBMITTED
A. On all projects that require the Contractor's or subcontractor's personnel to occupy
permitted confined spaces and/or hazardous atmospheres on the project site, the
Contractor shall submit to the Owner, a written proposed safety program. The safety
program shall comply with all Federal, State, and local requirements. If the Owner has a
safety plan that is more stringent than the Federal and State requirements, it will be
made available to the Contractor for review. The submittal of the proposed safety
program to the Owner shall be made well in advance of the start of construction at the
project site. The submittal shall include a written Safety Management Plan including
Confined Space Entry procedures. The Contractor shall be responsible to maintain
documentation that anyone employed by the Contractor, subcontractors, or suppliers of
any tier to the Contractor occupying such hazardous locations has received the
appropriate confined space entry training and other applicable training. The Contractor
is also responsible to maintain completed confined space entry permits.
END OF SECTION
2022 36-Inch Sewer Lining Section 01043 -5 Coordination and Control of the Work
SECTION 01090
REFERENCE STANDARDS
PART 1 GENERAL
1.01 SCOPE
A. This Section includes reference standards.
1.02 DESIGNATION OF ASSOCIATIONS, INSTITUTIONS, SOCIETIES & STANDARDS
A. Whenever in these Specifications reference is made to Associations, Institutions,
Societies, or Standards, they will be designated as follows:
AA
Aluminum Association
AAMA
Architectural Aluminum Manufacturers Association
AASHTO
American Association of State Highway and Transportation
Officials
ACI
American Concrete Institute
ADAAG
Americans with Disabilities Act Accessibility Guidelines
AFBMA
Anti -Friction Bearing Manufacturers Association
AFI
Air Filter Institute
AGA
American Gas Association
AGMA
American Gear Manufacturers Association
AIHA
American Industrial Hygiene Association
AISC
American Institute of Steel Construction
AISI -
American Iron & Steel Institute
AITC -
American Institute of Timber Construction
AMCA -
Air Moving and Conditioning Association
ANSI -
American National Standards Institute
API -
_American Petroleum Institute
ARI -
Air Conditioning and Refrigeration Institute
ASA -
American Standards Association
ASHRAE -
American Society of Heating, Refrigerating, and Air
Conditioning Engineers
ASME -
American Society of Mechanical Engineers
ASTM -
American Society for Testing Materials
AWS -
American Welding Society
AWWA -
American Water Works Association
BLS -
Bureau of Labor Standards
CISPI -
Cast Iron Soil Pipe Institute
FS -
Federal Specifications
IBR -
Institute of Boiler and Radiator Manufacturers
IEEE -
Institute of Electrical and Electronic Engineers
ISA -
Instrument Society of America
JIC -
Joint Industrial Council
INDOT -
Indiana Department of Transportation
NBS -
National Bureau of Standards
NEC -
National Electrical Code
NEMA
National Electrical Manufacturers Association
NFPA
National Fire Protection Association
NSF -
National Sanitation Foundation
OSHA -
Occupational Safety and Health Act
SMACNA -
Sheet Metal and Air Conditioning Contractors National
SSPC -
Association, Inc.
Steel Structures Paint!ng Council
2022 36-Inch Sewer Lining
Section 01090 - I Reference Standards
INBC
Indiana Building Code
IBC
- International Building Code
UBC
- Uniform Building Code
UL
- Underwriters Laboratories, Inc.
USBM
- United States Bureau of Mines
B. Wherever specific standard numbers are indicated, i.e., ASTM C 150, it shall be
understood to mean the latest revision thereof.
PART 2 PRODUCTS
None.
PART 3 EXECUTION
None.
PART 4 SPECIAL PROVISIONS
None.
END OF SECTION
Reference Standards Section 01090 - 2 2022 36-Inch Sewer Lining2022 36-Inch Sewer Lining
SECTION 01300
SUBMITTALS
PART 1 GENERAL
1.01 SCOPE
A. This Section includes requirements for submittals.
B. Contractor shall adhere to the submittal schedule as submitted under the provisions of the
General Conditions. Contractor shall modify the schedule as required to allow sufficient
time for submittal review based on current construction schedule.
1.02 COORDINATION OF SUBMITTALS
A. The Contractor shall be responsible for the coordination of submittals and field
verifications as required for the various parts of the work.
B. All submittals to the Engineer, unless otherwise specified, shall be made only by the
Contractor. Direct submittals from subcontractors or suppliers will not be accepted.
C. All submittals shall reference the Specification item that it covers, the Contractor's name,
the Contract title and location, and the date of submission. Submittal shall also indicate
whether the information is for the Engineer's review and approval, for record purposes,
or for the fulfillment of the operation and maintenance requirements.
PART 2 PRODUCTS
2.01 GENERAL
A. Two Categories of Information are Normally Required:
I . Shop drawings for Review.
2. Information for Record.
2.02 SHOP DRAWINGS FOR REVIEW
A. Shop Drawings:
1. The Contractor shall submit shop drawings in accordance with the General
Conditions, as required by individual Sections, shown on the Drawings or as
directed.
2. The Contractor shall indicate all variances from the requirements of the Contract
Documents in accordance with the General Conditions.
3. The Contractor shall clearly indicate the exact intended use of the equipment or
material contained in the submittal.
4. Color charts or samples shall be included for all submittals where a color
selection by the Owner is required.
B. Samples shall be provided as required in the individual Sections. Samples shall be of the
precise material proposed to be furnished. The number of samples and sample size shall
be the industry standard unless otherwise stated in the individual Sections.
2.03 INFORMATION FOR RECORD
A. Material certificates shall be submitted for materials as indicated in the individual
Sections. The certificate shall state that the products have been sampled and tested in
accordance with the proper industrial and governmental standards and meet the
requirements of the Specifications. Certificates shall be signed by an authorized agent of
the manufacturer.
2022 36-Inch Sewer Lining Section 01300 - 1 Submittals
2.04
B. Licenses and Permits - The Contractor shall submit copies of all licenses and permits
required by Local, State, and Federal laws to the Engineer.
C. Installation and calibration certificates shall be submitted for equipment as indicated in
the individual Sections. These certificates shall indicate manufacturer's satisfaction with
the installation, the accuracy of calibration and alignment, and the operation of the
equipment. Such certificates must be signed by an authorized agent of the manufacturer.
D. Progress Schedules shall be submitted in accordance with the General Conditions and
Section 01310.
E. Schedule of Shop Drawings and Sample Submittals shall be submitted in accordance with
the General Conditions.
F. Schedule of Values shall be submitted in accordance with the General Conditions.
OPERATION AND MAINTENANCE INFORMATION
A. Operation and Maintenance manuals shall be submitted as information for the record.
B. This information will be reviewed only if properly identified with Contract Section
Numbers and only after revised, where necessary, to conform to the Engineer's notes on
previous submittals that have been marked "Make Corrections Noted." Manuals shall be
tailored to suit the specific equipment provided.
C. Submittals Shall Include But Not Limited to the Following:
I . Descriptive literature, bulletins, or other data covering equipment or system.
2. Complete list of equipment and appurtenances included with system, complete
with manufacturer serial number and model number.
3. Utility requirements.
4. General arrangement drawing.
5. Sectional assembly.
6. Dimension print.
7. Materials of construction.
8. Certified performance curve.
9. Parts list with assembly drawings.
10. Recommended spare parts list with part and catalog number.
if. Lubrication recommendations and instructions.
12. Schematic wiring diagrams.
13. Schematic piping diagrams.
14. Description of associated instrumentation.
15. Drive dimensions and data.
16. Operating instructions.
17. Maintenance instructions including trouble -shooting guidelines, lubrication, and
preventive maintenance instructions with task schedule.
18. Special tools and equipment required for operation and maintenance.
19. Description of equipment controls.
20. Pump seal data.
21. Assembly, installation, alignment, adjustment, and checking instructions.
Submittals Section 01300 - 2 2022 36-Inch Sewer Lining
22. Confirmation of all corrections noted on shop drawings marked "Make
Corrections Noted."
23. Manufacturer's name, address, and telephone number along with manufacturers
job number and Purchase Order number.
24. Manufacturer's local sales representative, address, telephone number.
25. All installation instructions that were provided to Contractor for use to install
equipment.
D. All manuals shall be tailored to the project by high -lighting appropriate information and
deleting or crossing out nonapplicable information or the Contractor shall provide a data
sheet with all necessary information to correctly identify the applicable Sections of the
manuals for the actual equipment furnished. All options furnished shall be indicated.
E. Manuals shall be printed on 8-1/2 by 11 inch size with standard three hole punching.
Large manuals shall be submitted in three-ring binders. Small manuals shall be submitted
in folders with metal fasteners. Index tabs shall be furnished for all manuals containing
data for three or more items of equipment. All manuals shall have a title label on the
cover stating the specification item number and item name. A table of contents shall be
included in all manuals.
F. Drawings shall be reduced to 8-1/2 by 11 inch or 11 by 17 inch. Where reduction is not
possible, larger drawings shall be folded separately and placed in envelopes which are
bound into the manual.
G. Equipment installations shall not be considered substantially complete until all associated
O&M submittals are accepted by the Engineer.
H. Field modifications to equipment during installation shall be included in the manual so
that the manual reflects as -built conditions. Revisions to the manual may be submitted for
incorporation into the manual where appropriate. However, the Engineer reserves the
right to return all six manuals for revision to reflect as -built conditions.
PART 3 EXECUTION
3.01 IDENTIFICATION OF SUBMITTALS
A. All submittals shall be numbered in consecutive order.
B. Resubmittals shall carry the same number as that of the original submittal and shall be
further identified in consecutive order by alphabetical letters (i.e., 1, IA, Ib, etc.).
C. Submittals to satisfy the Operation and Maintenance information requirements shall be
numbered as resubmittals along with the prefix "O&M" (i.e. Submittal O&M 113).
3.02 DISTRIBUTION
A. Distribution of submittals shall be as follows unless otherwise directed in Part 4 or the
individual Sections:
Shop Drawings for Review:
a. The Contractor shall submit to the Engineer six copies of all documents
requiring the Engineer's review and approval.
b. If the submittals are found insufficient, three copies will be returned to
the Contractor for correction. The Contractor shall then make corrections
and resubmit six new copies of the entire submittal.
C. Upon acceptance, the Engineer will distribute marked copies via
construction bulletins as follows:
One Copy - Owner
2022 36-Inch Sewer Lining Section 01300 - 3 Submittals
One Copy - Resident Project Representative
Three Copies - Contractor
One Copy - Engineer
2. Information for the Record:
a. The Contractor shall submit three copies of all test certificates, licenses,
permits, and installation and calibration certificates directly to the
Engineer for distribution to Owner, Resident Project Representative and
Engineer.
3. Operation and Maintenance Information:
a. The Contractor shall submit to the Engineer six copies of information for
all equipment requiring maintenance.
b. Upon acceptance, the Engineer will distribute copies via construction
bulletins as follows:
1) Four Copies - Owner
2) One Copy - Resident Project Representative
3) One Copy - Engineer
PART 4 SPECIAL PROVISIONS
None.
END OF SECTION
Submittals Section 01300 - 4 2022 36-Inch Sewer Lining
SECTION 01350
COMMON PRODUCT REQUIREMENTS
PART 1 GENERAL
1.01 SCOPE
A. This Section includes general requirements for all materials, equipment and systems
furnished or installed under this project.
B. Additional specific requirements included under a particular Section shall take precedence.
C. This Section includes, but is not limited to, the following procedural and administrative
requirements:
I. Product Delivery Storage and Handling
2. Warranties
3. Quality Assurance and Control
1.02 SUBMITTALS
A. Submittals shall be in accordance with section 01300 and related specification sections.
B. The specification Sections and Drawings contain the specific submittal requirements.
1.03 QUALITY ASSURANCE
A. Where Contractor is required to provide design services or certification of the design, the
specified product, equipment or system shall comply with the specified criteria.
I. Contractor shall submit a written request for clarification when specified criteria
is incomplete or insufficient.
B. Manufacturer's name, make, model number and other designations provided in the contract
documents are to establish the significant characteristics, including but not limited to, type,
function, dimensions and physical properties, performance, and appearance for the purpose
of evaluating comparable products. Contractor shall verify product, equipment or system
proposed meets or exceeds the requirements as specified or shown on the Drawings.
1.04 PRODUCT HANDLING
A. Schedule delivery to minimize the time goods are kept in storage.
B. Deliver goods to project site in manufacturer's original packaging.
C. Inspect the goods to determine if there is visible damage to the packaging.
l . The packaging shall be removed in a manner that will allow resealing for storage.
2. If packaging can not be removed and reused, the goods shall be repackaged per the
manufacturer's recommendations.
D. Goods that are susceptible to damage by the environmental or project conditions, including
but not limited to, switchgear, motor control centers, panelboards, instrument control
panels, fixtures shall be stored in a controlled environment per the manufacturer's
recommendations. If no such area is available at the time such equipment is received, such
space shall be provided by the Contractor at no expense to the Owner.
E. Where construction is in roads or streets, that portion of the right-of-way not required for
public travel may be used for temporary storage purposes unless otherwise prohibited.
Materials shall not be stored in areas where such storage creates a hazard. Any other
additional space required for construction or storage of materials and equipment shall be
obtained by the Contractor at his expense.
2022 36-Inch Sewer Lining Section 01350 - I Common Product Requirements
The Contractor shall confine his equipment, the storage of materials and equipment, and
the operations of his workers to areas permitted by law, ordinances, permits, and the
requirements of the Contract Documents, and shall not unreasonably encumber the
premises with materials or equipment.
1.05 WARRANTY
A. Manufacturer's warranty, extending beyond one-year after substantial completion for the
specified product, equipment or system shall be provided to the Owner and endorsed by
the manufacturer.
B. Requirements for warranties extending beyond one-year after substantial completion are
described in individual Sections of these specifications.
C. Manufacturer's limitations and disclaimers shall not relieve the Contractor from warranty
obligations under the Contract Documents.
PART 2 PRODUCTS
2.01 REGULATORY REQUIREMENTS
A. Materials, equipment, coatings, and chemicals in contact with potable water or water being
treated for potable water use shall be approved by NSF International standard 60/61.
PART 3 EXECUTION
3.01 INSTALLATION
A. Products shall be installed in accordance with the manufacturer's instructions and Contract
Documents.
B. Required appurtenances including but not limited to, anchors, grout, and leveling shims,
shall be provided.
PART 4 SPECIAL PROVISIONS
None.
END OF SECTION
SECTION 01568
POLLUTION CONTROL
PART IGENERAL
1.01 SCOPE
A. This Section includes the requirements for pollution control.
PART 2 PRODUCTS
N/A
PART 3 EXECUTION
3.01 GENERAL REQUIREMENTS
A. It shall be the responsibility of the Contractor to prevent or limit pollution of air and water
resulting from his operations.
B. The Contractor shall perform work required to prevent soil from eroding or otherwise
entering onto all paved areas and into natural watercourses, ditches, and public sewer
systems, and to prevent dust attributable to his operations from entering the atmosphere.
C. Water containing suspended material from any part of the Contractor's operations shall be
clarified before discharging to drains.
3.01 STREETS, SIDEWALKS, AND DRIVEWAYS
A. Streets, haul roads, and detours and bypass roads shall be swept by automatic self-
contained sweepers.
B. Excessive dirt on pavements shall be removed by means of hand shoveling or appropriate
mechanical equipment and the area swept as directed above.
C. Sidewalks and driveways shall be cleaned by means of shovels and hand brooms or
appropriate mechanical equipment.
D. Dust on unsurfaced streets or parking areas and any remaining dust on surfaced streets shall
be controlled with calcium chloride dust palliative.
E. The Contractor shall comply with the above requirements on a daily basis. If the Contractor
fails to perform the above work in a satisfactory manner, all work, except cleanup
operations, shall be stopped until the Contractor has complied with the above requirement.
3.02 EROSION AND SEDIMENT CONTROL
A. The Contractor shall initiate appropriate vegetative practices on all distributed areas to
remain dormant (undisturbed) for more than 15 days within seven days.
1. Such practices may include: temporary seeding, permanent seeding, mulching,
matting sod stabilization, vegetative buffer strips, phasing and protection of trees.
B. Permanent or temporary soil stabilization shall be applied to disturbed areas within seven
(7) days after final grade is reached on any portion of the site.
C. When seasonal conditions prohibit the application of temporary or permanent seeding, non -
vegetative soil stabilization practices, such as mulching and matting, shall be used.
D. The paved street adjacent to the site entrance shall be swept a minimum of daily, or as
needed, to remove any excess mud, dirt, or rock being tracked from the site.
1. Dust and sediment along any street due to construction on this site is to be swept a
minimum of once at the end of the day or as necessary to prevent a build-up of
dust and soil on the pavement surface.
2022 36-Inch Sewer Lining Section 01568 - 1 Pollution Control
E. Dump trucks hauling from the construction site shall be covered with a tarpaulin.
F. No more than 200-feet of trench shall be open at any given time. Trench opening, laying
of pipe, and backfilling should occur so as to minimize the amount of disturbed area.
G. The Contractor shall minimize the width of his work area.
H. Existing trees, shrubs, and other ground cover vegetation shall be preserved where possible.
Tree removal will be limited to that necessary for construction and will be limited further
to the permanent easement wherever possible. No tree removal will be permitted outside
the temporary easement.
1. Storm water runoff and natural stream flow shall be intercepted or diverted when
originating upgrade away from the construction site so as to minimize the amount of flow
over the construction site.
J. All dewatering flows are to be settled in siltation basins or directed through filters before
discharge to stabilized sites, such as stream or storm sewers, and not onto exposed soils,
stream banks, or any other sites where the flow could cause erosion.
K. When construction occurs near storm sewer inlets, erosion control measures such as inlet
filters or hay bales shall be used to prevent silt from entering the storm sewers.
L. The clean-up and disposal of excess excavated material shall be done as soon as practical
after laying of the pipe. However, clean-up work shall not fall behind the pipe laying more
than 800-feet. Should the Contractor not keep his clean-up within the aforementioned
distance, work shall stop until the clean-up work is accomplished.
3.03 SEDIMENT CONTROL
A. Contractor shall control erosion and trap sediment from all sites remaining disturbed for
more than 14 days. Such practices shall include among others, sediment traps, sediment
basins, silt fences, and storm drain inlet protection.
B. Timing - Sediment control structures shall be functional throughout earth -disturbing
activity. Sediment ponds and perimeter sediment barriers shall be implemented as the first
step of grading and within seven days from the start of grubbing. They shall continue to
function until the upslope development area is restabilized.
C. Settling Ponds — Concentrated storm water runoff from disturbed areas flowing at rates
which exceed the design capacity of sediment barriers shall pass through a sediment
settling pond. The facility's storage capacity shall be 67 cubic yards per acre of drainage
area.
D. Sediment Barriers — Sheet flow from runoff from denuded area shall be intercepted by
sediment barriers. Sediment barriers, such as sediment fences or diversions directing runoff
to settling facilities, shall protect adjacent properties and water resources from sediment
transported by sheet flow.
E. Other erosion and sediment control practices shall prevent sediment -laden water from
entering drain systems. Unless the storm drain system drains to a settling pond. These
practices shall divert runoff from distributed areas and steep slopes where practicable and
stabilize channels and outfalls from erosive flows.
3.04 CONSTRUCTION ON SLOPES
A. The Contractor shall comply with the following requirements when working on slopes
exceeding 4:1.
1. The pipeline shall be constructed during dry weather, low flow periods as
determined by the Engineer. The construction time for this work shall be limited
to the shortest time possible in order to minimize environmental impacts.
Pollution Control Section 01568 - 2 2022 36-Inch Sewer Lining
3.05
2. Construction equipment shall be limited to trenching equipment or rubber tired
backhoes in order to prevent soil erosion and maintain slope stabilization.
3. Biodegradable mesh shall be used for slope stabilization. The mesh shall cover the
entire width of disturbed ground.
4. The trench shall be backfilled immediately after installation of the pipe. The
disturbed areas shall be graded, seeded, and mulched within 24 hours after
backfilling. The Contractor shall maintain all seeded and mulched areas in
accordance with the specifications until final acceptance of the work.
5. The Contractor shall place straw or hay bales at the base of the slopes for
sedimentation control. The bales shall be placed prior to construction of the
pipeline and shall remain until final seeding has germinated and become
established.
STREAM CROSSINGS
A.
B.
C.
D.
Construction of the stream crossings shall occur only during dry weather low -flow periods.
Wherever possible, use of heavy equipment during crossing construction is to be restricted
to the stream bank and is not to be permitted in the stream channel.
The width of stream banks disturbed in constructing a stream crossing shall be limited to
the width of the trenching machine.
Immediately after the conduit and any required concrete encasement is in place, the re-
establishment of channel contours and bank stabilization shall commence. The stream
crossing and associated restoration shall be completed within 48 hours of initiation.
To minimize erosion, the work of clearing, grading, excavation, pipe installation,
backfilling, erosion protection, final cleanup and all other work within 50-feet of the stream
shall be performed without interruption and within the shortest time practical.
PART 4 SPECIAL PROVISIONS
None.
END OF SECTION
2022 36-Inch Sewer Lining Section 01568 - 3
Pollution Control
This page was intentionally left blank.
Pollution Control Section 01568 - 4 2022 36-Inch Sewer Lining
SECTION 02766
SEWER LINING
PART 1 GENERAL
1.01 SCOPE
A. Under this Section the Contractor shall furnish all labor, materials, and equipment
necessary to rehabilitate by means of a lining process, deteriorated sections of sewers.
B. This Section shall include diverting sewer flow around work areas as needed, cleaning and
video-taped inspection of the existing sewers, clearing obstructions including root cutting,
rehabilitation of the sewer by the lining process, cutting of the new pipe liner to reestablish
lateral connections without excavation, re -televising the completed sewer line sections, and
other work incidental to the lining operation.
1.02 SUBMITTALS
A. Submittals shall be in accordance with the requirements of Section 01300 and shall include:
1. Shop Drawings for Review:
a.
Manufacturer's product literature for each product used.
b.
Technical Data sheet for each product used.
C.
Verification of compliance with reference standards.
d.
Verification of compliance with the specified requirements including but
not limited to independent testing reports.
2. Information for the Record:
a.
Field Measured Pipe Inside Diameters.
b.
Pre -lining (optional) and post lining video inspection.
C.
Bypass pumping plan.
d.
Design calculations including but not limited to, wall thickness, and
structural capacity, signed and sealed by a licensed Engineer in the state
of the project.
e.
Cleaning procedures including the water pressure.
f.
Installation procedures and sequence of cleaning and installation
operation.
g.
Upon request, qualifications of installing contractors, including
experience and references.
h.
Manufacturer's current certification of installing contactor.
i.
Recommended installation procedures.
1.03 QUALITY ASSURANCE
A. The manufacturer of the products specified herein shall have a minimum of 10 years'
experience in the research, development and production of the products specified.
B. The installing contractor shall have a minimum of 5 years of experience working with and
installing the specified products and shall be certified by the manufacturer.
C. The installing contractor shall be responsible for the liner system, including but not limited
2022 36-Inch Sewer Lining Section 02766 - 1 Sewer Lining
D. The products specified herein shall comply with the listed ASTM standards.
PART 2 PRODUCTS
2.01 MATERIALS
A. Liner:
1. The liner shall be a resin impregnated flexible felt tube which, when cured, will be
abrasion resistant and chemically resistant to withstand internal exposure to
sewage gases containing normal levels for domestic sewage of hydrogen sulfide,
carbon monoxide, carbon dioxide, methane, traces of mercaptans, saturation with
moisture, dilute sulfuric acid, and external exposure to soil bacteria.
2. The liner shall be designed by the manufacturer to provide full pipe strength for
the rehabilitated section using, as a basis of design, the existing field conditions
and assuming no strength imparted by the existing pipe. The basis of design shall
be in accordance with ASTM F1216.
3. The liner shall be properly sized to the diameter of the host pipe and the length of
to be rehabilitated and be able to stretch to fit irregular pipe sections.
4. The reinforcing material of the liner shall be a needle interlocked terylene felt
formed into sheets of required thickness. Thickness of the cured liner shall be
within plus 10 percent and minus 5 percent of the required thickness determined
by the manufacturer and shall not include the thickness of the polyurethane inner
liner.
5. The liner shall be fabricated to a size that when installed will neatly fit the internal
circumference of the conduit to be lined. Allowance for longitudinal and
circumferential stretching of the liner during insertion shall be made by the
manufacturer. The length of the liner shall be that deemed necessary by the
manufacturer to effectively carry out the insertion and seal the liner at the inlet and
outlet of the respective manholes or chambers, unless it is a spot repair. The
Contractor shall verify the lengths in the field before cutting the liner to length.
B. Resin:
The resin shall be a polyester or vinyl ester resin system, including but not limited
to all catalysts initiators required for curing within the liner. The resin content of
the impregnated liner shall have a volume ratio with the felt of 85 percent resin to
15 percent felt.
2. The resin must be able to cure in the presence of water and the initialization
temperature for cure shall be less than 180 degrees F (82.2 degrees Q.
C. The lining system shall be continuous over the entire length of an insertion run between
two or more manholes, unless it is a spot repair. The liner end, at each manhole, shall be
sealed.
D. Liner system shall be free from visual defects such as foreign inclusions, dry spots,
pinholes, and delamination. The lining shall be impervious and free of any infiltration or
exfiltration.
The inner surface shall be free of cracks and crazing with smooth finish and with
an average of not over two pits per square foot and all pits shall be less than 3
millimeter diameter and not over l millimeter deep and are covered with sufficient
resin to avoid exposure to the inner fabric.
Sewer Lining Section 02766 - 2 2022 36-Inch Sewer Lining
E. The materials for the liner system shall be as manufactured by:
1. Insituform of North America
2. National Liner
3. In -Liner
2.02 PERFORMANCE REQUIREMENTS
A. The liner system shall provide a uniform smooth, interior wall surface and will have at least
100% of the flow capacity of the original pipe before rehabilitation. In lieu of
measurements, calculated capacities may be derived using a Manning "n" coefficient of
0.013 for the original pipe material and a Manning on" coefficient of 0.010 for ajoint-less
smooth wall cured -in -place pipe liner.
B. The structural performance of the cured -in -place pipe liner system must be adequate to
accommodate all internal and external loads (live and dead) over its service life. Unless
otherwise approved by the Engineer in writing, the liner system shall be designed
considering the host pipe is fully deteriorated, a prism loading, and meeting the following:
Loading
120 cf, w/2.0 factor of safety
2 %
n
5 %, maximum
of Soil Reaction
WStrength.
1,000 psi
Stren th
4,500 si
hancement Factor K
7 maximum
ds
H-20
Reduction Factor Lon -Term
50 %
Hydrostatic Load
Beginning at the surface
Factor of Safety
2.0
Design Life
50-year service life under continuous
loading conditions
Soil Load
Maximum depth from surface to
crown of pipe along a segment length
Other Design Considerations
The Bidder/Contractor may request
additional information from the
Pnorinee, as needed
C. Calculations performed in accordance with the above verifying the required wall thickness
requirements of the liner to be used shall be submitted to the Engineer for approval prior
to fabrication of the tube.
D. Liner system shall meet the requirements of the following ASTM:
ASTM F1216
2. ASTM F1743
ASTM D5813
E. The chemical corrosion resistance of the actual resin system (neat plus modifications)
selected shall be tested by the resin manufacturer in accordance with ASTM 1216.
2022 36-Inch Sewer Lining Section 02766 - 3 Sewer Lining
F. The cured polyester impregnated liner shall meet the following minimum strength
requirements.
Pro ert
Test Method
Value
Ultimate Elon ation at Yield:
ASTM D 638
2 %
Flexural Stren the
ASTM D 790
4,500 si
Flexural Modulus:
ASTM D 790
250,000 si short term
Hardness:
ASTM D 2583
Barcol 22
Heat Distortion Tem erature:
ASTM D 648
70 de rees C
2.03 HYDROPHILIC SEALS
A. The termination of all liners must end with the installation of a hydrophilic seal.
The main lines shall have "End Seals" installed at both ends of the liner.
B. The hydrophilic seals at the ends of mainline liners shall be full -circle O-Ring
compression seals at the ends of a pipe rehabilitated by lining. This hydrophilic
sealing product is intended for use in conjunction with all pipe rehabilitation
systems. After the seals haves been placed into the ends of the pipe, a rehabilitative
liner product shall be installed into the pipe.
C. A mechanical fastener is provided with the tubular sleeve that is specifically
designed to hold the tubular sleeve in place during installation of a pipe liner. The
mechanical fastener may utilize a double -sided adhesive to ensure that neither the
tubular sleeve nor the fastener shift during installation.
D. The member that creates the end seal is a hydrophilic neoprene rubber of
approximately 50 Shore A durometer. The tubular sleeve has a uniform wall
thickness of approximately 2 mm, a length of approximately 3.5 inches, and a
diameter slightly less than the interior pipe diameter. The hydrophilic neoprene
rubber has the following characteristics:
Characteristic
Test Method
Shore A Hardness
ASTMD2240
Tensile Strength
Wpoint50
ASTMD412
Elongation at Break
ASTMD412
Specific GravityASTMD297
Swell Capacity in
Water Contact
%
200
GRCSC
E. The hydrophilic seals shall be InsigniaTM Connection Hat, InsigniaTM End Seal
by LMK Technologies, or equal
PART 3 EXECUTION
3.01 COORDINATION
A. Contractor shall coordinate liner system installation with Owner's operation of the
collection system.
D. Contractor shall be responsible for coordinating the manhole coating system with the liner
system.
Sewer Lining Section 02766 -4 2022 36-Inch Sewer Lining
3.02 PREPARATION
A. Prior to lining of a sewer or lateral, it shall be the responsibility of the Contractor to clean
debris out of the sewer line in accordance with National Association of Sewer Service
Companies (NASSCO) Specifications for Sewer Collection System Rehabilitation Section
III "Sewer Line Cleaning".
B. The Contractor shall field verify the inside diameter of all sewers to be relined at both the
upstream and downstream manholes prior to fabricating liner tubes. The records of this
inspection shall be submitted to the Engineer.
C. The Contractor shall inspect by closed circuit TV the section of sewer to be lined and shall
record the location of all obstructions and service taps. Th
frmasthe -------- --- -- --rc u .+...,,.. »:.._ if n.., lateral is ,,..a,.,..:..,. b_-.__., the ,__�o _vthe lawal eanneetien liner.
1. Note, Carmel Utilities recently performed a video inspection of the sewer to be
lined. The Contractor may use that video in leu of the typical pre -lining inspection.
2. It is believed that there are no laterals in the sewer to be lined. There are laterals in
the upstream and downstream manholes.
D. It shall be the responsibility of the Contractor to clear the line of obstructions, solids,
dropped joints, protruding services, or collapsed pipe that will prevent the insertion of the
liner. If inspection reveals an obstruction that cannot be repaired without excavation, the
Owner and Engineer shall be notified to make the final determination. Excavation to repair
a sewer is not included in this Section.
Contractor shall be responsible for disposal of all debris removed from the cleaning
operation in accordance with the specifications, local, state and federal regulations.
2. Contactor may separate the solids and liquid contents from the cleaning and the
liquids may be discharge into the sanitary sewer, in a controlled rate, with Owner's
approval.
E. The Contractor shall provide for the flow of sewage around the sections of line that are to
be lined. This includes any pumping that may be required. Pumps and bypass lines shall be
of adequate capacity and size to handle the flow.
Peak wet weather flows are believed to be 20 mgd.
F. The lateral inspection camera shall be capable of color closed circuit TV recording and be
launched from the mainline camera.
G. Active leaks of ground water into the pipe shall be sealed to prevent the development of
heat sinks while the liner is being cured.
H. Debris, scale roots lateral cutting debris or other materials that will prevent the proper
installation and inversion of the liner shall be removed from the sewer to be lined.
Break-in connections (hammer taps) and or pipe protruding into the main shall be ground
back flush to the sewer main inside diameter.
3.03 SEWER CLEANING
A. The Contractor is expected to review the video records of the sewer laterals to gain an
understanding of the scope of work required for cleaning ahead of cured in place lateral
installation.
B. Cleaning shall constitute removal of all loose debris, solids, and protruding obstructions
which inhibit, television inspection, or the liner installation. Mineral deposits or debris shall
2022 36-Inch Sewer Lining Section 02766 - 5 Sewer Lining
be removed as necessary to permit the installation of liners and testing and grouting of
sewers.
C. If cleaning, protruding obstruction removal or root removal efforts were not performed by
the Contractor to a level to permit the installation of grout repairs or liners, the Contractor
shall repeat or complete the cleaning, protruding obstruction or root removal to a degree
necessary to permit the work to be completed at no additional compensation to the
Contractor.
D. The Contractor shall note any areas with pipe defects such as dropped joints, egg shaped
pipe, protrusions, broken or missing pipe sections that will prevent proper the installation
CIPP liner repairs to the Engineer. The Engineer will provide direction to the Contractor
regarding the use of the Bid Items to excavate and repair the damaged pipe sections.
E. Root cutting may be required to complete the initial television inspection of lateral
connections to building foundations. This shall be incidental and will not constitute an extra
cost to the Owner.
3.04 ROOT CUTTING
A. Root cutting in area(s) designated shall be performed by means of a Skid Style Root and
Grease Cutter with a power motor and thruster assembly capable of being launched from a
manhole or cleanout.
B. The cutting head shall be a concave circular saw designed to keep the teeth off the pipe
surface. The cutting head shall have a diameter of 1-in. less than the interior diameter of
the sewer.
C. The skid assembly shall position the root cutter head in the middle of the sewer line thereby
minimizing damage to the sewer pipe.
D. Multiple passes shall be made in areas of dense root intrusion.
3.05 LATERAL CONNECTIONS
A. It is believed that there are no laterals in the sewer to be lined. There are laterals in the
upstream and downstream manholes.
3.06 HYDROPHILIC SEALS
A. The installation of the hydrophilic seals shall be in conformance with the manufacturer's
recommendations and NASSCO Standards.
B. The installation of the hydrophilic seals shall provide a water tight joint between the pipe
and the linier.
3.07 INSTALLATION
For Full Line segment reconstruction, M.H. To M.H.
a. The installation shall be done in accordance with ASTM F 1216 and F 1743
and in accordance with the lining manufacturer's recommended
procedure.
b. Resin impregnation shall be in a quantity sufficient to fill the volume of
air voids in the liner material with allowances for shrinkage and loss of
resin.
C. The resin impregnated liner shall be inserted into position in the host pipe
using the inversion method of pull -in method per the manufacturer's
recommendations and as defined by the relevant ASTM sections. Care
shall be exercised so as to not damage the Owner's infrastructure and the
liner system during the installation.
Sewer Lining Section 02766 - 6 2022 36-Inch Sewer Lining
d. Curing shall utilize hot water under pressure or steam pressure in
accordance with the manufacturer's recommendations and relevant
ASTM.
1) The temperature of the incoming and outgoing water used for
curing shall be monitored. A temperature gauge shall be placed
between the host pipe and the liner, at the invert, at both ends of
the section being lined, to monitor the temperature during the
curing.
2) Curing water temperature shall be between 150 degrees F and no
more than 200 degrees F, measured at the return.
e. Cool down shall be in accordance with the manufacturer's
recommendations. The liner shall be cooled to 100 degrees F before
relieving the pressure. Care shall be taken to prevent a vacuum on the
newly installed liner.
3.08 INSPECTION
A. After the work is completed, the Contractor shall supply the Owner with video showing
the lined sections including service connections. The Video shall follow the PACP format
for pipeline defect identification and assessment.
B. The water tightness of the liner shall be gauged while curing and under a positive head.
The minimum test head shall be fifteen feet. The maximum allowable leakage shall be 200
gallons per inch pipe diameter per mile of pipe in 24 hours.
PART 4 SPECIAL PROVISIONS
4.01 REHABILITATION PRODUCTS OR PROCESSES
A. Rehabilitation products or processes that will be considered shall meet the following
requirements:-
1. The process must have a minimum of five years commercial experience in like
projects in the USA.
B. The Contractor shalt submit product test data supporting the long term strength, corrosion
resistance and 50-year design life. These tests shall be based on the following standards:
1. Material tested shall be identical to those proposed for the installation and shall be
from samples of materials in final place after the trauma of installation and/or
reforming of the product. Testing shall be in accordance with applicable ASTM
Standards. Laboratory samples will not be acceptable.
2. Short tern tests can be extrapolated using actual short test data and applicable
ASTM Standards for plastic pipe.
3. All test data whether theoretically extrapolated or actual must be validated by an
independent third party qualified in these testing procedures.
C. The product must have a minimum of 15,000 lineal feet of wastewater collection system
installations in the US documented to assure commercial viability of the process.
D. The Contractor shall submit all ASTM Standards for installation and/or materials on their
product. Foreign standards will not be acceptable.
E. The Contractor must submit engineering design guide and quality control procedures for
product manufacturer and for product installation, including detailed inspection, testing of
physical properties, retention of production samples, and taking of and testing of field
samples.
2022 36-Inch Sewer Lining Section 02766 - 7 Sewer Lining
F. The Contractor shall submit statement as to country of manufacture of all major
components used to produce the final installed product.
G. The Contractor shall submit evidence of installer training, testing and/or certification of
being trained to install the product by the manufacturer of the process.
4.02 LEAKAGE TESTING
A. All rehabilitated sewers shall be visually inspected for leakage during the television
inspection. All visible leakage in the rehabilitated sewer shall be repaired and retested at
no additional cost to the Owner.
4.03 WARRANTY AND ACCEPTANCE
A. The Contractor shall warrant all work to be free of defects in workmanship or materials for
a period of one [1] year from the date of final acceptance of the final video tapes of the
rehabilitated sewer.
4.04 ANTICIPATED SEQUENCE OF WORK
A. The chronological sequence of work is expected to be as follows:
1. Clean and televise main line and laterals
2. Installation of the liner in the main line
3. Post Video Inspection
B. Audio -video tapes of all sewer line television inspections shall be delivered to Owner prior
to substantial completion at no additional cost to the Owner. The Video shall follow the
PACP format for pipeline defect identification and assessment. Any additional television
inspections required by unacceptable leakage tests or additional debris/cleaning required
prior to insertion shall be included in the audio -video tapes in the appropriate chronological
sequence.
4.05 SCHEDULE OF WORK
A. The sewer to be lined is between manholes SMH-52-62 and SMH-52-63 as marked in
purple on the image below.
B. The original contractor drawings state that the sewer is lineal 455-feet (or 470-feet based
on station numbering). Carmel's GIS system states that the sewer is 506.4-feet. The
Contractor shall be required to field measure the actual length of the sewer prior to liner
fabrication.
Sewer Lining Section 02766 - 8 2022 36-Inch Sewer Lining
I
f
to
g
41
Sewer segment to be lined.
f�4 r
J,
SECTION 02800
SODDING, SEEDING, AND MULCHING
PART 1 GENERAL
1.01 SCOPE
A. This Section includes fine grading, placing sod, and seeding and mulching areas
designated on the Drawings, specified, or ordered.
B. The work consists of fine grading, furnishing and placing topsoil, sod, seed, mulching
material, and fertilizer, and watering until growth is assured.
C. The Contractor shall restore all grass areas damaged by his operations in construction of
facilities included in the Contract.
D. Unless otherwise specified herein or directed, work shall be in conformance with INDOT
Item 621 Seeding and Sodding.
1.02 SUBMITTALS
A. Submittals shall be in accordance with the requirements of Section 01300 and shall
include:
1. Shop Drawings for Review:
a. Manufacturer's project information for materials.
2. Information for the Record:
a. Submit to Resident Project Representative:
1) Invoices indicating the weight, brand, and composite analysis of
fertilizer used on the project.
2) Bag tickets indicating weight and composition of all seed used
on the project.
B. The operation of finish grading and sowing shall not be performed when the ground is
frozen or muddy.
PART 2 PRODUCTS
2.01 SOD
A. Sod shall conform to INDOT Item 914.07, unless otherwise specified in Special
Provisions.
2.02 SEED
A. Seed mixtures shall be in conformance with the requirements of INDOT Items 621.06
and 914.04. The mixtures to be used shall be as specified in Part 4 of this Section.
2.03 FERTILIZER
A. Commercial fertilizers shall be from a dealer or manufacturer whose brands and grades
are registered or licensed by the Indiana State Seed Commissioner. The content of
nutrient shall be 12-12-12, unless otherwise approved by Engineer.
2.04 MULCHING MATERIAL
A. Mulching material shall be straw, wood fiber or compost reasonably free of weed seed,
and other foreign materials as specified in INDOT Item 914.05.
2.05 MATTING MATERIAL
A. Matting material shall be in conformance with the requirements of INDOT Items 914.05
(a)3 or 5.
2022 364nch Sewer Lining Section 02800 - I Sodding, Seeding, end Mulching
2.06 TOPSOIL
A. Topsoil furnished by the Contractor shall be as specified in Section 02200.
PART 3 EXECUTION
3.01 FURNISHING AND PLACING TOPSOIL
A. Areas from which topsoil has been removed shall be recovered with a minimum of 4
inches of re -compacted topsoil in conformance with the pertinent parts of INDOT Item
621.03.
3.02 PREPARATION
A. Areas to be Sodded:
1. Preparation of areas to be sodded shall be in conformance with INDOT Item
621.08.
B. Areas to be Seeded:
1. Unless otherwise shown on the Drawings or specified in Part 4 all areas of
disturbed soil on the project site shall be seeded.
2. The area to be seeded shall be disked and harrowed and all depressions filled in
accordance with INDOT Item 621.03.
3. Fertilizer shall be applied at a rate which will provide 240 pounds per acre of
chemical fertilizer nutrients in equal proportions of Nitrogen, Phosphoric Acid,
and Potash. Either dry or liquid fertilizer may be used and shall be distributed in
an even pattern over the specified area, then thoroughly disked, harrowed, or
raked into the soil to a depth of not less than 1 inch.
4. All clods, rubbish, and stones greater than 1 inch in any dimension shall be
removed and the area graded to a smooth surface. Hand raking will be required in
areas inaccessible to machines and may be required in areas of urban character
and in front of residences where machines do not provide results equivalent to
hand raking.
3.03 INSTALLATION
A. Sodding:
1. Sod shall be placed in conformance with INDOT Item 621.09.
2. No sod shall be placed when the temperature is below 32 degree F. No frozen sod
shall be placed nor shall any sod be placed upon frozen soil. When sod is placed
between the dates of June 1 to October 15 it shall be covered immediately with
straw mulch 1 inch thick, loose measurement.
B. Seeding:
1. The seed shall be mixed thoroughly and sown evenly at a rate specified by
INDOT Item 621.05 (b). The seed mixture may be sown dry or hydraulically.
2. The seed mixture shall be applied when the soil is in a workable condition and
shall be raked into a depth of approximately 1/4 inch.
3. Seed shall be sown only between the dates of May 1 and October 15, unless
otherwise permitted by the Engineer.
C. Mulching:
1. Within 24 hours after an area has been seeded it shall be mulched in conformance
with one of the following specified methods as designated in Part 4:
2. Mulch:
Sodding, Seeding, and Mulching Section 02800 - 2 2022 36-Inch Sewer Lining
a. Mulching with hay or straw shall be in conformance with mulching
requirements of INDOT Item 621.05 (c), except that in front of
residences the mulching material shall be kept in place by an approved
nontracking adhesive or other approved method in lieu of the specified
asphalt emulsion.
b. Straw matting used for mulching shall be placed in conformance with
INDOT Item 621.05 (f).
C. Matting shall be used on all slopes greater than 3:1. Excelsior blankets
used for mulching shall be placed in conformance with INDOT Item
621.05 (d).
D. Seeded and sodded areas shall be watered and maintained as specified below until they
are established.
1. The seed bed shall be thoroughly watered, as soon as the seed is covered.
2. Water shall be applied by a hydro -seeder or water tank under pressure with a
nozzle producing a spray that will not dislodge the mulching material.
3. Water applications shall be made at least once a week, provided significant
rainfall has not occurred within the weekly period.
4. The rate of application shall be 120 gallons per 1,000 square feet.
5. The Contractor shall keep all sodded areas, including the subgrade, thoroughly
moist for two weeks after sodding. After the two -week period, the Contractor
shall water the sod as specified for seeded areas.
6. Matting areas shall be maintained until all work on the Contract has been
completed and accepted.
7. The seeded areas shall be mowed once at an approximate height of 6 inches as
directed by the Engineer to control excess growth, including weeds.
8. Maintenance shall consist of the repair of areas damaged by erosion, wind, fire,
or other causes. The soil in these damaged seeded areas shall be restored to the
condition of grade existing prior to application of matting, and restored areas
shall be relimed, refertilized, and reseeded. Where necessary, the matting shall be
completely replaced. Damaged sod shall be replaced with new sod.
PART 4 SPECIAL PROVISIONS
4.01 INSTALLATION
A. The Owner may choose to discuss landscaping restoration preferences with impacted
property owners. The Contractor shall comply with any reasonable divergences from this
section directly requested by the Owner or Engineer in deference to any such preferences.
B. The mixture to be used on various areas shall be as follows:
Seed Mixture U INDOT Item 621.06(b)
(Specific Areas - Lawns and well -kept areas
Seed Mixture P INDOT Item 621.06(c)
Shoulder and median areas - Grading contracts only)
Seed Mixture D INDOT Item 621.06(e)
Chronic saturated soils
END OF SECTION
2022 36-Inch Sewer Lining Section 02800 - 3 Sodding, Seeding, and Mulching
A , Jones & Henry
F ENCINFFas. iro.
City of Carmel, Indiana
2022 36-Inch Sewer Lining
ADDENDUM1
August 1, 2022
Planholders on the City of Carmel 2022 36-Inch Sewer Lining are hereby notified of the following
amendments to the Contract Documents. This Addendum is hereby made a part of the Contract
Documents.
SPECIFICATIONS
Replace the "Notice to Proceed" with the attached.
A , Jones & Henry
F ENGINEERS. LTD.
City of Carmel, Indiana
2022 36-Inch Sewer Lining
ADDENDUM
August 3, 2022
Planholders on the City of Carmel 2022 36-Inch Sewer Lining are hereby notified of the following
amendments to the Contract Documents. This Addendum is hereby made a part of the Contract
Documents.
GENERAL COMMENTARY
Although this statement is non -binding, a notice of award is anticipated for this project by August 8
This project is for an Indiana local government entity and as such is generally exempt from sales tax
Contractors will be solely responsible for facilitating vehicle access, such as by placing stone or mats.
Contactors will be responsible for restoring the site back to original condition, such as removing stone or
filling in ruts. These statements replace and supersede verbal comments made during the site
walkthrough.
SPECIFICATIONS
Replace the Quote Summary page with the attached. The new version clarifies that the estimated time
of completion does not include site restoration or demobilization.
Replace the Agreement with the attached version. The new version removes a placeholder statement of
completion time. A reasonable completion time based on the contractors proposed schedule will be
inserted into the final agreement prior to signing.
Replace the SRF requirements package with the attached. The new version strikes out requirements for
to DBE, MBE, and WBE good faith efforts, which the SRF has stated are not requires for this project. The
new version also includes Davis Bacon wage rate determinations.
Replace Section 02766 with the attached. The new version deletes a reference to TV inspection of
laterals; inspection and lining laterals are not required for this project. The new version also has
modified language related to bypass pumping.
City of Carmel, Indiana
OkCCity`mel
Utilities
2022 36-Inch Sewer Lining
Request for Quotes
July 2022
CARMEL BOARD OF PUBLIC WORKS AND SAFETY
Mayor James Brainard, Presiding Officer
Mary Ann Burke, Board Member
Lori Watson, Board Member
CARMEL UTILITIES
John Duffy, Utility Director
Mike Hendricks, Assistant Utility Director
Ben Donald, Operations Manager
5E
Jones & Henry Engineers, Ltd.
Carmel, Indiana
TABLE OF CONTENTS
PART A
Table of Contents
1 page
Request for Quotes Letter
2 pages
Quote Summary Form
1 page
Agreement
Agreement Exhibit D — Contractor's Waiver Liens and Claims
16 pages
2 pages
Agreement Exhibit E — Subcontractor's Waiver of Liens and Claims
2 pages
Agreement Exhibit F — Change Order Form
1 page
Agreement Exhibit G — Confined Space
1 page
Verification of Work Eligibility (E-Verify)
1 page
Notice to Proceed Form
1 page
SRF Requirement Package
21 pages
PART B
General Conditions
31 pages
PART C
Section 01010 — Definition of Contract Items
2 pages
Section 01021 —Allowances
1 page
Section 01043 — Coordination and Control of the Work
5 pages
Section 01090 — Reference Standards
2 pages
Section 01300 — Submittals
4 pages
Section 01350 — Common Product Requirements
2 pages
Section 01568 — Pollution Control
4 pages
Section 02766 — Sewer Lining
9 pages
Section 02800 — Sodding, Seeding, and Mulching
3 pages
IF ANY OF THE PAGES LISTED ABOVE ARE NOT INCLUDED IN THESE CONTRACT
DOCUMENTS, PLEASE ADVISE.
2022 36-inch Sewer Lining City of Carmel
Table of Contents
tJones & Henry
ENGINEERS, LTD.
July 29, 2022
Subject: Request for Quote
2022 36-inch Sewer Lining
City of Carmel, Indiana
Fluid thinking®
1980 East I I6th Street, Suite 260, Cannel, IN 46032
Phone: 317.818.1805 JllEng.wm
The City of Carmel is requesting price quotes to line a 36-inch concrete gravity sewer approximately 507-feet in
length.
The scope of work shall be as in the following attached documents:
1) This Request for Quotes Letter
2) Quote Price Form
3) Agreement, incorporating Exhibits D through H
4) SRF Requirement Packet
5) General Conditions
6) Technical Specifications
7) Reference Drawings
Any questions prior to the quote submission can be directed to the engineer:
Philip Teague, PE
pteague@jheng.com
419-277-6039
Quotes should be emailed to BOTH of the following:
Mr. John Duffy, Carmel Utility Director
jduffy@carmel.in.gov
Mr. Mike Hendricks, Carmel Assistant Utility Director
mhendricks@carmel.in.gov
Quotes will be accepted until August 5, 2022, at 3:00 PM local time. The email subject line should be "36-Inch
Sewer Lining Quote" Your email should include a completed "Price Quote Form" saved as a PDF.
The lowest and best quote will be selected at the sole discretion of Carmel Utilities based on price and proposed
schedule.
This project may receive funding from the SRF. As such, the selected Contractor will be required to comply all
SRF requirements, including Davis -Bacon wage rates and submission of the following forms:
1) Certification of Non -segregated Facilities
2) Non-discrimination In Employment Form
Camtel, IN I Cincinnati, OH I Fort Wayne, IN I Kalamazoo, MI I Toledo, OH
Request for Quotes
36-Inch Sewer Lining Jones &Henry
City of Carmel, Indiana MJNV
ENGINEERS. LTD.
Page 2 of 2
3) Bidder's DBE Status Form
After selection, the successful contractor will be required to provide a completed Agreement with all Exhibits
and insurance certificates as described in the General Conditions.
Bid, payment, and performance bonds are not required for this project. The Contractor will not be required to
obtain permits for the Work. The Contactor may, at their discretion, use Carmel Utility's recent video of the
sewer in leu of the typical per -lining inspection video. The Contractor shall be responsible for modifications to,
and restoration of, manholes as required for completion of the work; however, the Contractor will not be
responsible for re -lining the manhole.
Sincerely,
JONES & HENRY ENGINEERS, LTD.
Philip Teaguor
e, PE
Principal Engineer
o v
o
v
a
a E
Y
o n
O
O
�
E «
O
O h
r
y�J
N
N
o �
`
N
O
_
0
O
p
C
F
Z
O
J O
U lL
~
C U
C
C
J
C ll
=
Z 4
Y
j
W N
C (n
J �
xy
UI
~
W Z
H J
O
d W
w
p
� W
O N
�
ii
z
LL
p
O
O
Ln
Q
rn
o
Z
Z
n
N
W
u
V
A
CI
ena
N
N
�
O
N
Y
LL
J
J
O
Y �
W �
7
a
C
0
C
Y
N
C
O
-_
O
G
S
O m
W
C
Y
`o
`u
E
c
«o
Y Y
VI
U
U Y
N
a E
c
3
Q
M
W O
0
A
U