HomeMy WebLinkAboutChange Order 1; United Construction Services; ($197,413.68); 18-ENG-06 - Walnut Street and Range Line Road Roundabout; CO #1, Final; Engineering DocuSign Envelope ID:5642928D-5E46-45C0-98D6-83D681323032 City of Carmel Project 18-ENG-06 Walnut Street and Rangeline Road RAB (APPROVED CHANGE ORDER #1, FINAL ar �.cre .,at e�,Sep,..zozz Balancing/Reconciliation for Pay Items 1 through 179 Contract Price prior to this Change Order $2,517,000.00 Contract Price will be increased/decreased by this Change Order $197,413.68 New Contract Price including this Change Order $2,714,413.68 Amount Adjusted Contract Cumulative Price Change from Original Contract Original Contract $2,517,000.00 $0.00 N/A COI, Final $197,413.68 $2,714,413.68 7.8% DocuSign Envelope ID:5642928D-5E46-45C0-98D6-83D681323032 CITY OF CARMEL TO: United Construction Services CONTRACT CHANGE ORDER FINAL 347 5 Broadway St DATE:08/24/2022 Pendleton IN 46064 PROJECT NAME: 18-ENG-06 Intersection Improvements Rangeline Rd and Walnut CITY REQ.NO.:N/A CITY PO NO.: 104350 CITY PO DATE: 10/14/2021 I. You are directed to make the following changes in this Contract: Add additional items due to modifications in the field and requests from Carmel Utility Departments. SCHEDULED ADJUSTMENT ITEM AMOUNT f+1 OR(-)DAYS *See detail of items and summary of changed costs in attached Table TOTAL OF CHANGE ORDER ITEMS $197,413.68 0 Days 11. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order:R.F P.: -n/a W.D.C.NO.:, n/a Other:_By Request from the City of Carmel per proposals included herein The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $2,517,000.00 Contract Price will be increased by this Change Order $ 197,413.68 New Contract Price including this Change Order $2.714 413.68 Contract Time prior to this Change Order 125 Days July 15 2021 Completion Date Net increased resulting from this Change Order 371 Days Current Contract Time including this Change Order July 20 2022 Completion Date This Change Order is for full and final settlement of all direct,indirect,impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are Recommended The Above Changes Are Accepted Approved rTi000Sig„ed by: CROSSROAD ENGINEERS United Construction Services ArrralreallYalit r ENGINEER CONTRACTOR 115 North 17th Ave 347 S Broadway St Jere Kas an,City ngineer Do gn tl by: Address Address Beech Grove,IN 46107 - dleton IN46064 , 0,t10ke,Member City/State/Zip City/S e/Zt �p 4 .� Lo ' 4Mermber By: 1GgC4ete gefeezdaes y, i. ATTE DocuSigned by: Fitto s wog Phone: 317-780-1555 765-729-1013. Sue 1215 rer Date: 09/02/2022 Date: Q�/t /j7f}.,?r� Date: IYL� DocuSign Envelope ID:5642928D-5E46-45C0-98D6-83D681323032 18-ENG-06 Intersection Improvements Rangeline Rd and Walnut St CHANGE ORDER#1 TABLE Item Original Original Final Na Description Unit Unit Price Quantity Amount Quantify Final Amount Overt(Under) 1 Construction Engineering LS 516.500,00 1 $ 16,500.00 0 S - S (16,500.00) 2 Mobilization and Demobilization LS S81,81210 1 $ 81.312.10 0 $ - $ (81.312.10) 3 Clearing of Right of Way LS $14,134,00 I $ 14,134.00 1 S 14,134.00 5 - 4 Houses and Buildings,Parcel No. I,Remove LS $28,165.00 1 $ 28,165.00 1 S 28.165.00 5 - 5 Relocate Archway LS 5181,889.00 1 $ 181,889.00 1 $ 181,889.00 S • 6 Excavation.Common CYS S60.70 2465 5 149,625.50 3916.7 $ 237,743.69 S 88,118,19_ 7 Borrow CYS $14.20 1255 S 17,821.00 1870 $ 26,554.00 $ 8,733.00 8 Pavement Removal(Undistributed) SYS $10.15 1761 S 17,874.45 1919.54 $ 19,483.33 5 1,609.18 N 9 Storm Water Quality Management Budget .DOL 51.00 13048 $ 13,048.00 11164,15 $ 11,164,15 $ (1,883.85) 10 SWQCP Preparation and implementation,Level 1 LS S 17,182.00 1 $ 17,182.00 1 $ 17,182.00 5 - 11 Subgrade Treatment,Type lc SYS 522.85 236 5 5 392.60 1991.3 $ 45,501 21 $ 40,108.61 12 Subgrade Treatment.Type II SYS S14.45 779 $ 11,256.55 1294.4 $ 18,794.08 $ 7,447.53 13 Subgrade Treatment,Type(BC SYS S17.90 4084 $ 73.103.60 3418.7 $ 61,194.73 $ (11,908,87) 14 Structure Backfill,Type 2 CYD 545.40 188 $ 8,535.20 198.19 $ 8,995.56 S 460,36 15 Compacted Aggregate,No.53,Base CYS S50.65 44 $ 2,228.60 303.6 $ 15,377.34 $ 13,148.74 16 Widening with HMA,Type C TON $273.40 42 $ 11,482.80 0 S - $ (11,482.80) 17 Widening with PCC Base,6 IN SYS 542.95 176 $ 7,559,20 249.3 $ 10,707.44 5 3,148.24 18 Milling,Asphalt 1.5" SYS $2.50 4,086 S 10,215.00 0 $ -_ 5 (10.215.00) 19 QC/QA-1-1MA,3,70,Surface,9.5 aim TON 5115.50 633 S 73,11 L50 606.77 $ 70,081.94 $ (3,029.56) 20 QC/QA-HMA,3,64,Intermediate.19.0 mm TON 599.00 465 $ 46,035,00 465.68 S 46,10232 S 67.32 21 QC/QA-HMA,3.64.Base,25.0 rum TON S93.50 1,139 5 106.496.50 1174.25 $ 1119.792.33 $ 3,295.88 22 QC/QA-FIMA,3,76,Intermediate,GO 19.0 mm TON $90.20 955 $ 41.041.1)0 464.91 $ 41,934.88 $ 893.88 23 Joint Adhesive,Surface LFT $0,55 1972 S 1,084.60 267 5 146.85 5 (937.75) 24 Joint Adhesive,Intermediate LFT_ $0.55 943 $ 518.65 249 $ €36.95 $ (381.70) 25 Liquid Asphalt Sealent LET $0.15 1,972 $ 295.80 267 $ 40.05 $ (255.75) 26 HMA For Temporary Pavement,Type B TON $239,45 67 5 16,043.15 0 $ - 5 (16,043.15) 27 Asphalt for Tack Coat TON $605.00 5 , $ 3,025 00 1.9 S 1,149.50 5 (1,875,50) 28 Base Seal TON S1,100.00 l $ 1,100.00 0 $ - S (1,100.00) 29 Colored and Jointed Concrete.7" SYS $129.35 157 S 20,307.95 156.7 5 20,269.15 $ (38.80) 30 Sidewalk,Concrete SYS $60.50 1277 $ 77.258.50 838.8 $ 50,747.40 S (26.511.10) 31 Curb Ramp,Concrete SYS 5161.70 153 $ 24,740.10 195.8 $ 31,660.86 5 6,920.76 32 Detectable Warning Surfaces SYS 5462.00 49 5 22,638.00 50.1 $ 23,146.20 $ 508.20 33 Straight Concrete Curb LET $30.55 1,107 $ 33.818,85 1131.4 S 34 564.27 $ 745,42 34 Roll Curb for Truck Apron LET 528.15 2,007 $ 56,497.05 1973.5 S 55,554.03 5 (943.02) 35 Curb and Gutter,Concrete,Type II LFT $29.35 1454 $ 42,674.90 2521.3 S 74,000,16 S 31,325.26 36 Concrete Center Curb,D SYS $425.30 2 $ 850.60 4 5 1,701.20 $ 850.60 37 PCCP for Approaches 9 is SYS 5105.15 191 5 20.083.65 720.3 5 75,739.55 $ 55,655.90 38 Concrete,A.Stmetures CYS $0.00 6 5 - 0 5 - 5 - 39 Concrete,B.Footings CYS $0.00 6 $ - 0 5 - S - 40 Reinforcing Bars.Epoxy Coated LBS 50.00 551 $ - 0 $ - S - 41 Surface Seal LS 50.00 1 S - 0 S - 5 - 42 Anti-Graffiti Coat LS $0.00 1 $ - 0 S - $ - 43 Field Office.B MOS $1,467.00 6 $ 8,802.00 0 S - $ (8,802.00) 44 Computer System Equipment EA_ 5550.00 2 S l,100.00 0 5 - 5 (1,100.09) 45 Computer System EA $550.00 2 S 1,100.00 0 $ - S (1.100,00) 46 Mobilization And Demobilization For Seeding EA $550.00 2 $ 1,100.00 2 5 1,100.00 5 - 47 Sodding,Nursery SYS S5.65 662 $ 3.740.30 1010.6 $ 5,709.89 5 1,969.59 48 Pipe,Type 4,Circular,6" LET $7.30 1.468 $ 10.716.40 0 $ - S (10.716.40) 49 Pipe.Underdrain Outlet,6" LET 522.90 72 $ 1,648.80 109.2 $ 2,500.68 S 851.88 50 Pipe,Type 2,Circular.12" LFT $39.15 617 S 24,155.55 552.9 5 21,646.04 $ (2,509.51) 51 Pipe,Type 2,Circular,18" LFT $54.70 65 $ 3,555,50 74,12 S 4,054.34 5 498.86 52 Video Inspection for Pipe LET $2.20 628 $ 1.381.60 0 S - $ (1,381.60) 53 Video Inspection for Underdrain LFT $1.20 1,468 S 1,761.60 1163.48 $ 1,396.18 S (365.421 54 Geotextile for Underdrain,Type IA SYS $1.35 1,224 S 1,652.40 1523.9 5 2,057.27 $ 404.87 55 Aggegate for Underdrain CYS S72.55 127 $ 9,213.85 125.06 $ 9.073.10 S (140.75) 56 Casting,Adjust to Grade,Sanitary EA $618.25 2 5 1.236.50 2 $ 1,236.50 S - 57 Casting,Adjust to Grade,Storm EA $477,45 7 $ 3,342.15 6 5 2,864.70 S (477.45) 58 Manhole,C-4 EA 53,545.05 5 S 17,725.25 5 $ 17.725.25 $ - 59 Inlet,B-15 EA $2,800,70 7 $ 19,604.90 7 -$ 19,604.90 $ - 60 Inlet,C-15 EA $2.889.45 11 $ 31,783.95 11 $ 31,783,95 $ - 61 Road Closure Sign Assembly EA S412.50 5 S 2,062.50 5 S 2,062.50 $ - 62 Detour Route Sip Assembly EA $181.50 18 5 3,267.00 18 $ 3,267.00 $ - 63 Construction Sign.A EA S330,00 21 5 6,930.00 9 $ 2.970,00 S (3,960.00) 64 Construction Sign,B EA 5137.50 2 5 275,00 16 $ 2,200,00 $ 1,925.00 65 Maintaining Traffic IS $21,555.85 I 5 21,555.85 0 $ - 5 (21,555.85) 66 Barricade,I11-B LFT $33,00 96 5 3,168.00 152 S 5,016.00 S 1,848.00 67 Sign Post,Square,Type 1,Reinforced Anchor Base LET $20.10 281 5 5,648.10 251.2 $ 5,049.12 5 (598.98) 68 Decorative Street Sign Assembly EA 52,220.00 4 $ 8,880.00 4 S 8,880.00 $ - 69 Sign.Sheet,with Legend 0.080"thiclamess SFT $21,55 €25 S 2,693.75 122.25 I S 2,634.49 $ (59.26) DocuSign Envelope ID:5642928D-5E46-45C0-98D6-83D681 323032 18-ENG-06 Intersection Improvements Rangeline Rd and Walnut St CHANGE ORDER H1 TABLE Item Description Unit Unit Price Original Original Final Final Amount Overf(Under) No. Quantity Amount Quantity 70 Sign,Sheet,with Legend 0,100"thickness SET S23.50 53 S 1,245.50 49.68 $ 1,167.48 S (78.02) 71 Controller and Cabinet,PI EA $6,678.00 I $ 6,678.00 1 $ 6,678.00 5 - 72 Controller Cabinet Fowsdation,PI EA $1453.00 1 $ 1,453.00 1 $ 1.453.00 $ - 73 Conduit-PVC,2 IN.Schedule 40 LET S8.90 961 $ 8,55290 0 $ - S (8,552.90) 74 Conduit,PVC,2 IN.Schedule 80 LFT $10.05 568 $ 5,708.40 0 S - 5 (5,708.40) 75 Conduit,PVC,4 IN,Schedule 40 LFT $12.20 777 $ 9.479.40 0 S - $ (9.479.40) 76 Conduit,PVC,4 IN.Schedule 40,with 3-1.25 IN Innerducts LFT $24.30 777 S 18,881.10 0 $ - $ (18,88110) 77 Conduit,PVC,4 IN,Schedule 80 LFT $14.40 1501 $ 21,614.40 0 $ - S (21,614.40) 78 Conduit,PVC.4 IN,Schedule 80 with 3-1.25 IN Innerducts LFT S27.60 879 S 24,260.40 0 _ S - S (24,260,40) 79 Handhole,Lighting EA $840.50 5 $ 4,202.50 12 S 10,086.00 S 5,883.50 80 Handhole,Communications EA $1,546.45 12 S 18.557,40 6 5 9,276.70 S (9.278.70) 81 Service Point,II Modified _ EA $1,177.30 1 S 1,177.30 I $ 1,177.30 S _ 82 Wire,XHHW.Na.4 Copper,in plastic Duct 4-l!c LET 512.10 2377 $ 28,761 J0 0 $ - $ (28,761 70) 83 Luminaire,Ornamental,70 watt LED EA 53.312.90 6 S 19.877.40 5 5 16,564.50 $ (3,312.90) 84 Luminaire,Ornamental,185 watt LED EA S4,133.60 9 $ 37,202.40 9 5 37,202,40 $ - 85 Light Polc,Ornamental,15 FT EA S3,697.90 6 5 22,187.40 5 S 18,489.50 S (3,697.90) 86 Light Pole,Ornamental,30 FT Pole with 8 FT Mast Arm EA^ 54,848.60 9 $ 43,637.40 9 $ 43.637.40 $ _ 87 Conduit.Steel.Galvenized,2" LFT S29.05 181 $ 5,258.05 167 $ 4,851.35 S (406.70) 88 Lighting Foundation,Concrete with Grounding,18 IN Dia x 72 IN EA $1,250.40 6 $ 7,502.40 5 S 6,252.00 S (1,250.401 89 Lighting Foundation,Concrete with Grounding,30 IN Dia x 96 IN EA $1,383,60 9 $ 12.452.40 11 $ 15,219.60 $ 2,767.20 90 Transverse Mesg Mkg,Multi-Component,Pedestrian Crossing EA S275.00 8 S 2,200.00 8 S 2,200.00 S - 9l Transverse Marking,Thermoplastic,Stop Bar,24 Inches LFT S22.00 I 1 $ 242.00 0 S - $ (242.00) 92 Transverse Marking,Thermoplastic,Solid White,Crosswalk,24 Inches LFT S22.00 [10 S 2420.00 0 $ - S (2.420.00) 93 Line.Thermopostic,Solid White.4 Inches LFT S2.20 330 S 726.00 0 $ - S (726.00) 94 Line,Thermoplastic.Solid White,6 Inches LET_ S6.60 801 $ 5,286.60 0 $ - S (5,286.60) 95 Line,Thermoplastic,Dotted White,8 Inches(2'Line,2'Gap) LFT $11,00 96 $ 1,056,00 0 $ - $ (1,056,00) 96 Line,Thermoplastic.Dotted White,4 Inches(2'Line,2'Gap) LET S5.50 41 S 225.50 0 $ - S (225.50) 97 Line,Thermoplastic.Dotted Yellow.4 Inches(3'Line,9'Gap) LFT $5.50 244 S 1,342.00 0 S - S (1,342.00) 98 Transverse Marking,Thermoplastic,White Yield Line,36 in LET $44.00 63 $ 2,772.00 63 S 2,772.00 5 99 Grooving for Pavement Markings LFT $4.40 1905 S 8.382.00 0 $ - 5 (8,382.00) 100 Line,Thermoplastic,Solid Yellow,4 Inches LFT $2.20 3591 $ 7,900.20 0 $ - S (7,900,20) [01 Snowplowable Raised Pavement Marker EA $ 357,50 5 S 1.787,50 0 $ - S (1,787_50) [02 Pavement Marking,Green Cycle Track SYS S 217.80 536 S 116.740.80 0 $ - $ ([16,740.801 103 Pavement Message Marking,Thermoplastic,Bike Symbol EA $ 440.00 2 S 380.00 0 $ - S (860.00) 104 Pavement Message Marking,Thermoplastic,Lane Indication Arrow EA S 330.00 2 $ 660.00 0 S - $ (660.00) 105 Business Sign Installation EA S 8.361.30 1 S 8.361.30 1 S 8.361.30 $ - 106 12"Ductile Iron Water Main LFT $ 108.05 709 $ 76.607.45 0 S - $ (76,607.45) 107 Structure Backfill for Water Main CYS S 47,45 650 $ 36 842.50 560,5 $ 26,595,73 $ (4,246.77) 108 12"Gate Valve EA $ 3,280.15 3 $ 9 ,40.45 4 S 13,120.60 5 3,280.15 109 Complete Hydrant Assembly EA $ 5.411.50 I $ 5,41150 I _$ 5,411.50 S - 110 12"Connection EA $ 4,371.55 3 $ 13.114.65 5 S 21.857,75 $ 8,743.10 Ill 6"Connection EA $ 3073.30 I S 3.073.30 0 S - $ (3,073.30) 112 Service Line for Irrigation EA S 6,136.60 1 S 6,136.60 I $ 6,136.60 $ - 113 Adjust to Grade,Water Valve EA S 408.55 3; $ 1,225.65 2 $ 817.10 S (408.55) 114 Sanitary Sewer Service Adjustment(Undistributed) LFT $ 127.45 50 $ 6,372.50 32 $ 4,078,40 S (2,294.10) 115 Long&Short Side Services(Undistributed) EA $ 4,123.75 5 5 20.618.75 0 S - $ (20,618.75) 1 16 Structural Soil CYS S 169.80 450 $ 76,410.00 0 $ - $ (76,410,00) 117 Planting Soil Mix CYS $ 99.55 336 $ 33,448.80 0 $ - $ (33,448.80) 118 Shredded Hardwood Mulch CYS S 84.25 126 $ 10,615.50 101.9 $ 8,585.06 S (2,030.42) 119 irrigation System LS S 96.556 20 1 S 98,556.20 1 _$ 98,556.20 S - 120 Lasvn Seed SFT S 0.25 11327 $ 2,831.75 29533 $ 7,383,25 $ 4,551.50 121 Deciduous Shade Tree.3 IN Caliper EA $ 662.10 37 S 24.497.70 37 $ 24.497.70 $ - 122 Deciduous Shade Tree,2 IN Caliper EA $ 491.05 l l S 5,401.55 8 S 3,928.40 $ (1,473.15) 123 Deciduous Shade Tree,2.5 IN Caliper EA 5 643.20 15 $ 9.648.00 11 $ 7 075,20 $ (2.572.80) 124 Evergreen Shrub.No 3 Container £A S 61.25 107 S 6,553.75 135 $ 8,268.75 S 1,715.00 125 Deciduous Shrub,No 3 Container EA S 53.60 19 S 1,018.40 19 $ 1,016 40 $ - 126 Ornamental Grass.No 1 Container EA $ 18.40 319 $ 5.869.60 362 $ 6,660,80 $ 791.20 127 Perrenial,No 1 Container EA $ 16.45 355 S 5,839.75 313 5 5,148.85 $ (690.90) 128 Perennial,4 IN Pot EA 5 7.25 958 S 6,945.50 1192 S 8,642.00 $ 1,696.50 129 Evergreen Shrub,48 IN Height EA $ 238.15 48 S 11.431.20 48 S 11,431.20 S - 130 Decorative Roadside Planter EA $ 465.25 95 S 44,198,75 0 $ - $ (44,198.75) 131 Contaminated Soil.Remove(Undistributed) CYS $ 98.95 100 $ 9.895.00 0 $ - 5 (9,895.00) 132 Raised Crosswalks EA $ 9,569.10 8 $ 76,552.80 8 S 76,552.80 S - 133 Testing for Asbestos EA $ 825.00 1 S 825.00 I S 825.00 S - 134 Subgrade Treatment,Type III SYS $ 3.97 $ - 1082 93 S 4,299.23 S 4,299.23 135 Milling,Asphalt,Variable Depth SYS S 6.45 S - 0 S - S - 136 HMA Wedge and Level.Type C TON S 273.17 S - 0 5 - 5 - 137 HMA for Sidewalk TON S 217,10 $ - 218,8 S 47,501.48 S 47,501.48 138 HMA for Structure Installation,Type C TON S 201.40 S - 0 S - $ - 139 Manhole.110 EA $ 5,459.60 $ - 2 S 10,919.20 S 10,919.20 DocuSign Envelope ID:5642928D-5E46-45C0-98D6-83D681323032 18-ENG-06 Intersection Improvements Rangeline Rd and Walnut St CHANGE ORDER tt]TABLE Item Original Original Final No. Description Unit Unit Price Final Amount OverkUnder) Quantity Amount Quantity 140 Inlet,110 EA $ 3,670.13 S - 4 $ 14,680.52 5 14.680.52 I41 Inlet,R13 EA $ 3,403.40 S - l $ 3.403.40 $ 3,403.40 [42 Light Standard Relocate EA S 2,690.28 S - 2 5 5 380.56 S 5.380.56 [43 Deciduous Shade Tree.6'Height EA $ 491.05 S - 3 $ 1.473_)5 S 1,473.15 144 Concrete Curb Removal LFT $ 11.33 S - 1291 S 14,627.03 $ 14,627.03 145 Concrete Sidewalk Removal SYS $ 14.74 $ - 492.8 5 7,263.87 S 7.263.87 146 Concrete Approach Removal SYS 5 13.67 $ - 358.2 S 4,896.59 $ 4,896,59 147 Added MOT for Moron Square LS S 2,123.00 $ - 0 $ - $ - 148 Duke Tranformer Pad T&M LS S 8,498.61 S - I S 8,498.61 5 8,498.61 149 Pipe Removal LFT 5 36.48 S 476 5 17,364.48 $ 17,364.48 150 Construction Engineering LS 5 23,250.00 S - I S 23,250.00 S 23,250.00 151 Mobilization and Demobilization LS 5 88,179.90 5 - 1 5 88,179.90 S 88.179.90 152 Milling,Asphalt 1.5" SYS S 3.23 $ - 3880.2 $ 12,533.05 S 12.533.05 153 Pipe,Type 4,Circular,6" LFT $ 8.48 S - 1862.4 S 15.793.15 $ 15,793.15 154 Maintaining Traffic LS $32.258.07 S - 1 $ 32.258.07 S 32 258.07 155 Conduit,PVC,2 IN,Schedule 40 LFT $ 9.43 $ - 1385 $ 13.060_55 $ 13,060.55 156 Conduit,PVC,2[N,Schedule 80 LFT $ 12.18 $ - 340 $ 4,14L20 5 4,141.20 157 Conduit,PVC,4 IN.Schedule 40 LFT $ 14.61 S - 450 S 6,574.50 5 6.574.50 158 Conduit,PVC,4 IN,Schedule 40,with 3-1.25 IN Innerducts LET $ 27.60 $ - 595 S 16,422.00 S 16 422,00 159 Conduit,PVC,4[N,Schedule 80 LFT S 19.86 5 - 1166 S 23.156.76 $ 23.156,76 160 Conduit.PVC.4 IN.Schedule 80 with 3.1.25 IN Innerducts LFT S 31.99 5 - 425 S 13,595.75 S 13,595.75 161 Wire,XHHW,No.4 Copper,in plastic Duct,4-l!c LFT S 13.75 S - 1715 $ 23,581.25 S 23.581.25 162 Transverse Marking,Thermoplastic,Stop Bar,24 inches LET S 28.60 $ - 33.5 5 958.10 S 958.10 163 Transverse Marking,Thermoplastic,Solid White,Crosswalk,24 Inches LET 5 27.53 S - 255.6 $ 7,036.67 S 7,036.67 164 Line,Thennopostic.Solid White,4 Inches LET $ 3.52 $ - 0 I. - S - 165 Line,Thermoplastic,Solid White,6 Inches LET S 10.23 5 - 306 5 3,130.38 S 3,130.38 166 Line,Thermoplastic,Dotted White,8 Inches(2'Line,2'Gap) LET $ 19.64 $ - 88 $ 1,728.32 S [,72832 167 Line,Thermoplastic,Dotted White.4 Inches(2'Line.2'Gap) LET $ 6.i 7 $ - 0 $ - S - 168 Line,Thermoplastic.Solid Yellow.4 Inches LFT $ 3.51 5 - 3399.4 $ 11.931.89 $ 11,931,89 169 12"Ductile Iron Water Main LET S 1[8.73 S - 836.7 5 99,341.39 5 99.341.39 170 Planting Soil Mix CYS 5 92.75 5 - 1240 S i 15,010.00 S 115,010.00 171 Additional Detour Route COI l EA S 2,123.00 5 - 1 S 2,123.00 S 2,123.00 172 Relocate Hydrant CO83 EA S 3,475.45 5 - l $ 3,475 45 $ 3,475,45 173 96th Street Storm Work C004 EA $ 15,729.16 S - I 5 15,729.16 S 15,729.16 174 Field Order Work CO85-6 CA $ 3,793.75 $ - I S 3,793.75 $ 3.793.75 175 Additional Roudcbush Plantings C0a2 EA $ 1,052.78 S - I S 1,052.78 $ 1,052.78 176 T&M Irrigation Repairs COd7 LS S 4,446.75 5 - 1 S 4,446.75 S 4,446.75 177 T&M Morphey Conduit Street Crossing LS $ 8,467.29 $ - 1 S 8,467.29 $ 8,467.29 178 T&M UCS Utility Cleanup and Cannel Welding Drive LS 5 3,977.2E $ • 1 S 3,077.21 $ 3,077.21 179 T&M Additional Landscape and Irrigation Repairs LS 5 1,880.19 S - 1 S 1,880.19_5 1,880.19 TOTAL OF CHANGE ORDER ITEMS I S 197,413,68 CONTRACT PRICE PRIOR TO CHANGE ORDER $ 2,517,000,00 CHANGE ORDER Final 5 197,413.68 NEW CONTRACT AMOUNT INCLUDING APPROVED CHANGE ORDERS $ 2,714,413.68 DocuSign Envelope ID:5642928D-5E46-45C0-98D6-83D681 323032 I8-ENG-06 Intersection Improvements Rangeline Rd and Walnut St EXHIBIT A You have been directed to make the following changes in this Contract: Item No. Description Reason For Change Walnut St and Rangeline Rd 1 Construction Engineering CO Item added because of unit cost change 2 Mobilization and Demobilization CO Item added because of unit cost change 3 Clearing of Right of Way N/A 4 Houses and Buildings,Parcel No.I.Remove N/A 5 Relocate Archway N/A 6 Excavation,Common Over because of redesign 7 Borrow Over because ofredesien 8 Pavement Removal(Undistributed) More pavement under road than expected 9 Storm Water Quality Management Budget Under planned quantity 10 SWQCP Preparation and implementation,Level 1 N/A 11 Subgsade Treatment,Type lc Over because of redesign/West leg subgrade treatment 12 Subgrade Treatment,Type II Over because of redesign 13 Subgrade Treatment,Type IBC Under because of using Type Ic on west leg 14 Structure Backfill,Type 2 Over because of added pipe 15 Compacted Aggregate,No.53,Base Over because of redesign 16 Widening with HMA,Type C Under because of redesign 17 Widening with PCC Base,6 IN Over because of redesign 18 Milling,Asphalt 15" CO Item added because of unit cost change 19 QC/QA-HMA,3,70,Surface,9.5 mm Under because of redesign 20 QCIQA-HMA,3,64,Intermediate,19.0 mm Over because of redesign 21 QC/QA-I MA,3,64.Base,25.0 mm Over because of redesign 22 QC/QA-HMA,3,76,Intermediate.OG 19.0 mm Over because of redesign 23 Joint Adhesive,Surface Under planned quantity 24 Joint Adhesive,Intermediate Under planned quantity 25 Liquid Asphalt Sealent Under planned quantity 26 HMA For Temporary Pavement.Type B Did not use 27 Asphalt for Tack Coat Under planned quantity 28 Base Seal Did not use 2-n 29 Colored and Jointed Concrete,7" Under planned quantity 30 Sidewalk,Concrete Sections of sidewalk were removed from the job 31 Curb Ramp,Concrete Curb ramps added to the job 32 Detectable Warning Surfaces Curb ramps added to the job 33 Straight Concrete Curb Over because of redesign 34 Roll Curb for Truck Apron Under planned quantity 35 Curb and Gutter,Concrete,Type 11 Over because of redesign 36 Concrete Center Curb,D Under planned quantity 37 PCCP for Approaches 9 in. Over because of redesi n 38 Concrete,A,Structures Removed from the job 39 Concrete.B,Footings Removed from the job 40 Reinforcing Bars,Epoxy Coated Removed from the job 41 Surface Seal Removed from the job 42 Anti-Graffiti Coat Removed from the job 43 Field Office,B Paid under a different contract 44 Computer System Equipment Paid under a different contract 45 Computer System Paid under a different contract 46 Mobilization And Demobilization For Seeding N/A 47 Sodding,Nursery Over due to redesign 48 Pipe,Type 4,Circular,6" CO Item added because of unit cost change 49 Pipe,Underdrain Outlet,6" Over because of unknown pipes 50 Pipe,Type 2,Circular,12" Under planned quantity 51 Pipe,Type 2,Circular,18" Addedpipe area 52 Video Inspection for Pipe _ Did not do 53 Video Inspection for Underdrain Did not do the west leg 54 Geotextile for Underdrain,Type 1 A Added pipe area 55 Aggregate for Underdrain Under planned quantity 56 Casting,Adjust to Grade,Sanitary N/A 57 Casting,Adjust to Grade,Storm Under planned quantity 58 Manhole.C-4 _ N/A DocuSign Envelope ID:5642928D-5E46-45C0-98D6-83D681 323032 18-ENG-06 Intersection Improvements Rangeline Rd and Walnut St EXHIBIT A You have been directed to make the following changes in this Contract: ffetn Description Reason For Change No. 59 Inlet,B-15 N/A 60 Inlet,C-15 N/A 61 Road Closure Sign Assembly n 62 Detour Route Sign Assembly m 63 Construction Sign.A Used more Type B signs 64 Construction Sign,B Used instead of Type A 65 Maintaining Traffic CO Item added because of unit cost change 66 Barricade,I1I-B Added MOT 67 Sign Post.Square,Type I.Reinforced Anchor Base Under planned quantity 68 Decorative Street Sign Assembly N/A 69 Sign,Sheet,with Legend 0.080"thickness Under planned quantity 70 Sign,Sheet,with Legend 0.100"thickness Under planned quantity 71 Controller and Cabinet,PI N/A 72 Controller Cabinet Foundation,P1 N/A 73 Conduit.PVC.2 IN,Schedule 40 CO Item added because of unit cost change 74 Conduit,PVC,2 IN,Schedule 80 CO Item added because of unit cost change 75 Conduit,PVC,4 IN,Schedule 40 CO Item added because of unit cost change 76 Conduit,PVC,4 fN,Schedule 40,with 3-1.25 IN Trine CO Item added because of unit cost change 77 Conduit,PVC,4 IN,Schedule 80 CO Item added because of unit cost change 78 Conduit,PVC,4 IN,Schedule 80 with 3-1,25 IN Inner CO Item added because of unit cost change 79 Handhole,Lighting More added after redesign 80 Handhole.Communications Under because of redesign 81 Service Point.[I Modified N/A 82 Wire.3BIHW.No.4 Copper,in plastic Duct.4-1/c CO Item added because of unit cost change 83 Luminaire,Ornamental,70 watt LED Over because of redesign 84 Luminaire,Ornamental,185 watt LED N/A 85 Light Pole,Ornamental,15 FT Over because of redesign 86 Light Pole,Ornamental,30 FT Pole with 8 FT Mast At IA 87 Conduit,Steel,Galvenized,2" Under planned quantity 88 Lighting Foundation,Concrete with Grounding,18 IN Removed due to conflict 89 Lighting Foundation,Concrete with Grounding,30 IN Over because of redesign 90 Transverse Mesg Mkg,Multi-Component,Pedestrian(N/A 91 Transverse Marking,Thermoplastic,Stop Bar,24 Inch CO Item added because of unit cost change 92 Transverse Marking,Thermoplastic,Solid White,Cros CO Item added because of unit cost change 93 Line,Thermopostic,Solid White,4 Inches CO item added because of unit cost change 94 Line,Thermoplastic,Solid White,6 Inches CO Item added because of unit cost change 95 Line,Thermoplastic,Dotted White,8 Inches(2'Line,:CO Item added because of unit cost change 96 Line,Thermoplastic,Dotted White,4 Inches(2'Line,:CO Item added because of unit cost change 97 Line,Thermoplastic,Dotted Yellow,4 Inches(3'Line,CO Item added because of unit cost change 98 Transverse Marking,Thermoplastic,White Yield Line CO Item added because of unit cost change 99 Grooving for Pavement Markings Removed from the job 100 Line,Thermoplastic,Solid Yellow,4 Inches CO Item added because of unit cost change 101 Snowplowable Raised Pavement Marker Removed from the job 102 Pavement Marking,Green Cycle Track Removed from the job 103 Pavement Message Marking,Thermoplastic,Bike Syrr Removed from the job 104 Pavement Message Marking,Thermoplastic.Lane Inch Removed from the job 105 Business Sign Installation N/A 106 12"Ductile Iron Water Main CO Item added because of unit cost change 107 Structure Backfill for Water Main Under planned quantity 108 I2"Gate Valve Overdue to redesign 109 Complete Hydrant Assembly N/A 110 12"Connection Paid instead of 6" 111 6"Connection No 6"pipe on the lob 112 Service Line for Irrigation N/A 113 Adjust to Grade,Water Valve Under planned quantity 114 Sanitary Sewer Service Adjustment(Undistributed) Under planned quantity 115 Long&Short Side Services(Undistributed) Not used 116 Structural Soil Removed from the job 117 Planting Soil Mix CO Item added because of unit cost change 118 Shredded Hardwood Mulch Under planned quantity 119 Irrigation System WA DocuSign Envelope ID:5642928D-5E46-45C0-98D6-83D681 323032 18-ENG-06 Intersection Improvements Rangeline Rd and Walnut St EXHIBIT A You have been directed to make the following changes in this Contract: Item Description Reason For Change No. 120 Lawn Seed Added space from the building demo 121 Deciduous Shade Tree,3 IN Caliper N/A 122 Deciduous Shade Tree,2 IN Caliper Under due to plans 123 Deciduous Shade Tree,2.5 IN Caliper Under due to plans 124 Evergreen Shrub,No 3 Container Over because of redesign 125 Deciduous Shrub,No 3 Container N/A 126 Ornamental Grass,No 1 Container Over because of redesi 127 Perrenial.No 1 Container r 128 Perennial,4 IN Pot Over because of redesign 129 Evergreen Shrub,48 IN Height N/A 130 Decorative Roadside Planter Removed from the job 131 Contaminated Soil,Remove(Undistributed) Did not remove any 132 Raised Crosswalks N/A 133 Testing for Asbestos N/A 134 Subgrade Treatment,Type III Added to redesign 135 Milling,Asphalt,Variable Depth Did not use 136 HMA Wedge and Level,Type C Did not use 137 HMA for Sidewalk Added to redesign l38 HMA for Structure Installation,Type C Not used 139 Manhole,110 Added to redesign 140 Inlet,J10 Added to redesign 141 Inlet,R13 Added to redesign 142 Light Standard Relocate Added to redesign l43 Deciduous Shade Tree,6'Height Added to redesign 144 Concrete Curb Removal Added to redesign 145 Concrete Sidewalk Removal Added to redesign 146 Concrete Approach Removal Added to redesign 147 Added MOT for Monon Square Paid under different number 148 Duke Trani-turner Pad T&M Added to redesign 149 Pipe Removal Added to redesign 150 Construction Engineering Added to redesign 151 Mobilization and Demobilization Added to redesign 152 Milling,Asphalt 1.5" Added to redesign 153 Pipe,Type 4,Circular,6" Added to redesign 154 Maintaining Traffic Added to redesign 155 Conduit.PVC,2 IN,Schedule 40 Added to redesign 156 Conduit,PVC,2 IN,Schedule 80 Added to redesign 157 Conduit,PVC,4 IN,Schedule 40 Added to redesign 158 Conduit,PVC,4 IN,Schedule 40,with 3-1.25 IN line Added to redesign !59 Conduit,PVC,4 IN,Schedule 80 Added to redesign 160 Conduit,PVC.4 IN,Schedule 80 with 3-1.25IN Inner Added to redesign 161 Wire.JO-IHW,No.4 Copper,in plastic Duct.4-1/c Added to redesign l62 Transverse Marking,Thermoplastic,Stop Bar,24 Inch Added to redesign 163 Transverse Marking,Thermoplastic,Solid White,Cros Added to redesign l64 Line.Thermopostic,Solid White,4 Inches None in the plans 165 Line,Thermoplastic,Solid White,6 Inches Added to redesign 166 Line,Thermoplastic,Dotted White,8 Inches(2'Line,:Added to redesign 167 Line,Thermoplastic,Dotted White,4 Inches(2'Line,:None in the plans l68 Line,Thermoplastic,Solid Yellow,4 Inches Added to redesign 169 !2"Ductile Iron Water Main Added to redesign 170 Planting Soil Mix Added to redesign 171 Additional Detour Route COS l Added to redesign 172 Relocate Hydrant CO#3 Added to redesign 173 96th Street Storm Work CO#4 Added to redesign 374 Field Order Work CO45-6 Added to redesign 175 Additional Roudebush Plantings COrl2 Added to redesign 176 T&M Irrigation Repairs CO87 Damaged by Traffic 177 T&M Morphey Conduit Sueet Crossing Added for connection front existing Carmel Comm handhole across Walnut and Veterans Way 178 T&M UCS Utility Cleanup and Carmel Welding Drive A stone driveway was added on the back of Carmel Welding and Utility holes were filled in 179 T&M Additional Landscape and Irrigation Repairs Damaged by Traffic