HomeMy WebLinkAboutG002 - GENERAL-CONSTRUCTION NOTES#1
of
15
Date:
5.17.22
Sheet:
Revision:
www.caseindy.com
99 E. Carmel Drive, Suite 100
Carmel, Indiana 46032
317.846.2600 317.846.2601(f)
These drawings have been
prepared by Case Design &
Remodeling solely for its use andshould not be reproduced or relied
upon by any other parties.
Dimensions shown or scaled are
subject to change per actual job
condition and must be verified.
Materials are to be supplied as
specified as equal or standard
when not uniquely specified.Installed materials may vary in
appearance from drawings.
Reference manufacturer's product
data for actual appearance and
specifications.Studer ResidenceMorgan and Chris5643 Blackfoot TrailCarmel, Indiana 46033Approved By:
Date:
G002
PERMIT
Maggie Smith
Designer
msmith@caseindy.com
Amanda Chapman
Project Developer
achapman@caseindy.com
GENERAL / CONSTRUCTION NOTES
DDEEMMOOLLIITTIIOONN NNOOTTEESS PPRROOPPOOSSEEDD NNOOTTEESS
#2 6.8.22
#3 7.22.22
#4 10.7.22
KITCHEN:KITCHEN:
REMOVE AND HAUL KITCHEN TILE BACKSPLASH
REMOVE AND HAUL COUNTERTOPS, SINK AND FAUCETS
SALVAGE GARBAGE DISPOSAL FOR REINSTALLATION
REMOVE AND HAUL CABINETRY AND CABINET HARDWARE
DEMO PANTRY WALLS AND REMOVE DOOR, CASINGS, AND HARDWARE
REMOVE AND HAUL CAN LIGHTS IN KITCHEN CEILING
REMOVE AND SALVAGE REFRIGERATOR
REMOVE AND HAUL RANGE, MW, DISHWASHER; VERIFY IF TEMPORARY SALVAGING NEEDED
EXISTING FLOORINGS TO REMAIN
MASTER BATH:MASTER BATH:
REMOVE AND HAUL SHOWER ENCLOSURE, SHOWER PAN, AND SHOWER PLUMBING FIXTURES
REMOVE AND SALVAGE TOILET FOR REINSTALLATION
REMOVE AND HAUL TUB DECK, TUB, AND TUB FAUCET
REMOVE AND HAUL VANITY TOPS, SINKS AND FAUCET
REMOVE AND HAUL MIRRORS AND ACCESSORIES
REMOVE AND HAUL VANITY CABINETS AND HARDWARE
REMOVE AND HAUL TILE FLOOR
REMOVE AND HAUL DOOR TO CLOSET 2
DEMO WALL BETWEEN CLOSET 1 AND 2 FOR NEW DOORWAY
REMOVE AND HAUL BASE/SHOE AS NEEDED
REMOVE AND HAUL CAN LIGHT OVER TUB
REMOVE AND HAUL FAN/LIGHT IN TOILET ROOM
KITCHEN:KITCHEN:
PATCH AND REPAIR DRYWALL WALLS AND CEILINGS FROM DEMOLITION AND GENERAL ROUGH IN; MATCH
TEXTURE CEILING
FURNISH AND INSTALL NEW DUCT WORK FOR ENW HOOD BLOWER UNIT; DUCT TO EXTERIOR WITH NEW
DAMPER
FURNISH AND INSTALL NEW CABINETRY PER PLANS; THIS INCLUDES WOOD HOOD WITH EXHAUST INSERT;
AND ACCESSORIES; SEE LOCATIONS IN PLAN
FURNISH AND INSTALL NEW CABINETRY TRIMS TO MATCH CABINET FINISHES
FURNISH AND INSTALL NEW CABINETRY HARDWARE
FURNISH AND INSTALL NEW COUNTERTOPS
FURNISH AND INSTALL NEW MOSIAC PICKET TILE BACKSPLASH THROUGHOUT; INSTALL SHLUTER TRIM FOR
EXPOSED EDGES
PAINT WALLS AND CEILINGS; BASE/SHOE TOUCH UP AS NEEDED
PAINT CASINGS ON KITCHEN SIDE OF BACKDOOR, FAMILY ROOM DOOR, DINING DOORWAY, AND DOORWAY
TO ENTRY
MASTER BATH:MASTER BATH:
FRAME NEW SHOWER THRESHOLD AND NEW SHOWER NICHE
FRAME FOR NEW CLOSET DOORWAY BETWEEN CLOSET 1 AND 2; DOORWAY TO BE DRYWALL WRAPPED
FRAME IN WHERE CLOSET 1 DOOR WAS REMOVED
PATCH AND REPAIR DRYWALL WALLS AND CEILING FROM DEMOLITION AND GENERAL ROUGH IN AND
FRAMING
FURNISH AND INSTALL NEW VANITY CABINETRY
FURNISH AND INSTALL NEW 8X20 SHOWER WALL TILE ON HORIZONTAL BRICK LAY; INSTALL 3X8 ACCENT
BAND ON VERTICAL STRAIGHT LAY; INSTALL SHLUTER TRIM FOR EXPOSED EDGES
FURNISH AND INSTALL NEW PENNY SHOWER FLOOR TILE
FURNISH AND INSTALL NEW 12X24 ROOM FLOOR TILE ON 1/3 BRICK LAY PERPENDICULAR WITH VANITY
CABINETS
FURNISH AND INSTALL NEW VANITY COUNTERTOPS WITH 4" SPLASH; INCLUDES SHOWER PARTS TO MATCH
(THRESHOLD PIECES AND NICHE CAP)
FURNISH AND INSTALL 1 NEW GLASS SHELF ON CLIPS IN NICHE
FURNISH AND INSTALL NEW CLEAR GLASS SHOWER ENCLOSURE WITH BRUSHED NICKEL HARDWARE
FURNISH AND INSTALL NEW MIRRORS AT VANITY
FURNISH AND INSTALL NEW ACCESSORIES PER PLANS; FIELD VERIFY INSTALL HEIGHT LOCATIONS WITH
H.O.
FURNISH AND INSTALL NEW BASE AND SHOW TO MATCH EXISTING IN BATHROOM AND CLOSET
TUCK CARPET IN CLOSET AND INSTALL WOOD THRESHOLD BETWEEN CLOSETS WHERE WALL WAS
REMOVED; PAINT THRESHOLD TO MATCH TRIM
PAINT WALLS AND CEILINGS IN MASTER BATHROOM AND TOILET ROOM
PAINT BOTH MODIFIED WALLS IN CLOSETS; INCLUDES BOTH SIDES OF NEW WALL WITH DOORWAY
PAINT BASE/SHOE IN BATHROOM AND TOILET ROOM; INCLUDES PATCHING IN NEW BASE ON BOTH SIDES OF
MODIFIED CLOSET WALL AND WHERE DOORWAY WAS FRAMED IN
FURNISH AND INSTALL BATHROOM ACCESSORIES PER PLANS; FIELD VERIFY INSTALL HEIGHTS WITH H.O.
10/13/22